LICENSEE:
CONSTELLATION ENERGY GENERATION, LLC FACILITIES:
CLINTON POWER STATION, UNIT 1
SUBJECT:
SUMMARY
OF THE JUNE 14, 2023, PUBLIC OUTREACH TO DISCUSS THE NRC 2022 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF CLINTON POWER STATION, UNIT 1 On June 14, 2023, from 5:00 p.m. to 6:00 p.m. (CDT), an information meeting (open house) with question-and-answer session was held by representatives of the U. S. Nuclear Regulatory Commission (NRC) to provide the public with information on the 2022 end-of-cycle plant performance assessment of Clinton Power Station, Unit 1, along with general information on the NRC. The NRC representatives discussed plant performance with members of the public.
A representative from Constellation Nuclear was also in attendance.
The NRC discussed their assessment of Clintons performance as documented in the March 1, 2023, end-of-cycle assessment letter (ADAMS Accession No. ML23055A166). During the question-and-answer session of the open house, representatives from the NRC discussed various topics of public interest.
Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket No. 50-461 License No. NPF-62 cc: Distribution via LISTSERV June 22, 2023 Signed by Ruiz, Robert on 06/22/23
SUBJECT:
SUMMARY
OF THE JUNE 14, 2023, PUBLIC OUTREACH TO DISCUSS THE NRC 2022 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF CLINTON POWER STATION, UNIT 1 DISTRIBUTION:
Paul Zurawski RidsNrrDorlLpl3 RidsNrrPMClinton Resource RidsNrrDroIrib Resource John Giessner Mohammed Shuaibi Diana Betancourt-Roldan Allan Barker R3-DORS ROPassessment.Resource@nrc.gov ADAMS Accession Number:ML23173A014 OFFICE RIII RIII NAME NShah:mb RRuiz DATE 06/22/2023 06/22/2023 OFFICIAL RECORD COPY
Enclosure PUBLIC MEETING ATTENDEES June 14, 2023 U. S. Nuclear Regulatory Commission V. Mitlyng, Senior Public Affairs Officer A. Muneeruddin, Resident Inspector, Clinton A. Panter, Co-op Student R. Ruiz, Chief, Branch 1, DORS J. Steward, Senior Resident Inspector, Clinton Constellation Nuclear B. Nauman Members of the Public B. Ragu J. Rossler, Pantagraph D. Zimmerman, Pantagraph