Triennial Fire Protection Inspection Report 05000461/2023010
ML23146A129
Person / Time
Site: Clinton Constellation icon.png
Issue date: 05/26/2023
From: Catherine Nolan
NRC/RGN-III/DORS/EB2
To: Rhoades D
NRC/RGN-III
References
IR 2023010
Download: ML23146A129 (1)


Text

SUBJECT:

CLINTON POWER STATION -TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000461/2023010

Dear David Rhoades:

On April 26, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Clinton Power Station and discussed the results of this inspection with Thomas Chalmers, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Caty E. Nolan, Acting Chief Engineering Branch 2 Division of Operating Reactor Safety Docket No. 05000461 License No. NPF-62

Enclosure:

As stated

Inspection Report

Docket Number:

05000461

License Number:

NPF-62

Report Number:

05000461/2023010

Enterprise Identifier:

I-2023-010-0047

Licensee:

Constellation Nuclear

Facility:

Clinton Power Station

Location:

Clinton, IL

Inspection Dates:

March 13, 2023 to April 26, 2023

Inspectors:

K. Barclay, Senior Reactor Inspector

K. Fay, Reactor Inspector

A. Shaikh, Senior Reactor Inspector

M. Siddiqui, Reactor Inspector

Approved By:

Caty E. Nolan, Acting Chief

Engineering Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Clinton Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.05 -Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)

The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).

(1) Fire Protection Pumps / Hydraulic Calculations (Suppression)
(2) Halon-Main Control Room & Auxiliary Electric Equipment Room (Suppression)
(3) Low Pressure Core Spray (LPCS) System (Post-Fire Safe Shutdown)

Fire Protection Program (FPP) Administrative Controls (IP Section 03.02) (1 Sample)

The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensured that the licensees FPP contains adequate procedures to implement the selected administrative control. Verified that the selected administrative control meets the requirements of all committed industry standards.

(1) Hot Work Controls

Fire Protection Program Changes/Modifications (IP Section 03.03) (2 Samples)

The inspectors verified the following:

a.

Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown.

b.

The adequacy of the design modification, if applicable.

c.

Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications.

d.

The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, FHA, and SSA were updated consistent with the FPP or design change.

e.

Post-fire Safe Shutdown operating procedures, such as abnormal operating procedures, affected by the modification were updated.

(1) EC 636661 / EC 638677: GL 86-10 Evaluation for Fire Pump A Impairment Exceeding 90 Days
(2) EC 627073: Update and Issue Calculation IP-M-0177-CT; EC 626754: Containment Airlock Door Evaluation - Elimination of Containment Airlock Doors 1MC02W & 1MC03W as Transient Combustible Free Zones

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public disclosure.

On April 26, 2023, the inspectors presented the triennial fire protection inspection results to Thomas Chalmers, Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

01FP12

Leakage Paths for Underfloor Halon System AEER

26073

Update and Issue Calculation IP-M-0177-CT

2/19/2019

INSFP007

Pressure Drop for WS System

IP-M-0177-CT

Fire Loads in CPS Fire Zones Containment Building

IP-M-0471

CPS Post Fire Safe Shutdown Criteria

Calculations

IP-M-0532

Appendix R Safe Shutdown Assessment

4A

01437330

Possible Delay in Fire Fighting Efforts

11/08/2012

04067179

Fire Protection Maintenance Program Not Updated

10/26/2017

234238

NEIL PM Frequencies Do Not Have Grace

03/29/2019

234272

Performance Based Monitoring

03/29/2019

04315501

MCR Halon 1H13U707 Trouble Silence Rocker Switch

Light out

2/05/2020

04342235

Trouble Alarm on MCR Halon Panel 1H13-U709

05/09/2020

04356978

Fire Pump B 9071.02 Capacity Test Trending

07/15/2020

04367364

MCR FP XL-3 1H13P841 Trouble 23-18 EOF Halon

09/03/2020

04409606

LPCS Ammeter 1E21-N558 Current Readings OOS

03/17/2021

04419735

MCR Received FP Alarm Device 23-18 EOF Halon

System

04/28/2021

04420408

Accessible Fire Seal

04/30/2021

04434031

Halon Suppression for MCR Sub-Floor

07/08/2021

04455419

0FP01PB Fire Pump B Fuel Level Below 9071.01B Limit

10/24/2021

04477785

Fire Protection Impairment Greater than 180 Days

2/13/2022

04483898

FP A Diesel Engine HMI Failure on Power Up

03/09/2022

04491054

0FP01PB Battery Out of Spec

04/07/2022

04502327

Benchmark: MCR Halon Panel Backup Batteries Voltage

Trend Low

05/18/2022

04524848

Delay in Halon Swap Puts TT Mod on Hold

09/27/2022

04524977

Battery Voltage is Low on 1H13U703 Halon Panel

09/27/2022

04526776

Unexpected Auto-Start of 0FP01PA Fire Pump 'A'

11/14/2022

04527702

FP A Achieved 200F+ Coolant Temp

10/07/2022

71111.21N.05

Corrective Action

Documents

04528744

FP "A" Pump Roll-Up Door

10/10/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

04529392

NOS ID: USFAR Change Action Not Completed

10/14/2022

04529881

Fire Pump A Coolant System Heating Up Faster Than

Expected

10/17/2022

04552992

Unexpected 5063-3G LPCS Pump Discharge Press

Abnormal

2/06/2023

04556428

0FP01PA Batteries Not Per Design

2/22/2023

1-89-03-177

1893.01 F.P. Program

03/29/1989

1-97-08-046

1FP035 USAR /M05 Discrepancy with CPS 3213.01

08/05/1997

04562137

23 NRC FP Triennial: WO Record Missing Completed

Procedure

03/15/2023

04562602

NRC ID: Fire Pump Log Entries

03/16/2023

04562638

NRCID Flex Conduit Peeling Off Flow Switch 0FSFP032

Cable

03/16/2023

04562875

23 NRC FP Triennial: 1893.01 Evaluations Not

Completed

03/17/2023

04563568

23 NRC Triennial: Non-Permanent Scaffold Installation

03/20/2023

04563586

23 NRC FP Triennial: RHR A HTX Bolt Corrosion

03/20/2023

04564350

NRC ID: Fire Impairment Record Could Not Be Produced

03/23/2023

04564603

23 NRC FP Triennial - FP B Controller Conduit Fitting

03/24/2023

04565470

NRCID: UFSAR Change Does Not Reflect Current Plant

Config

03/28/2023

04565494

NRC ID: Graffiti Inside MCR Panel Door for 1H13-U711

03/28/2023

04665742

Update NSED-P-NFPA for NFPA 51B Designated Hot

Work Areas

03/29/2023

04666148

Inconsistencies in LS-AA-128 Form for EC 630948

03/30/2023

04672317

NRC ID: OP-AA-201-004 Conflict with NFPA 51B USAR

9.5.1

04/23/2023

Corrective Action

Documents

Resulting from

Inspection

04672657

NRC ID: Fire Watch Training Deviation from NFPA 51B

04/24/2023

384214

Spurious Operation of SRVs

630948

Replace Fire Pump 'A' OFP01PA Including Pump, Right

Angle Geared Drive, Engine and Control Panel 0-2

Engineering

Changes

FP-39

Modification: Install Jockey Pump to Maintain Fire

Protection System Supply at the Required Pressure

08/13/1986

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PDR 99-0550

Temporary Change Approval Checklist: CPS No. 3213.01

05/04/1999

Engineering

Evaluations

EE-00-138

Evaluate MCR Halon System Inspection Frequency

1893.04M101

LPCS Pump Room Prefire Plan

5a

1893.04M351

Aux. Elect. Equip., Inverter & Battery Rooms Prefire Plan

7d

Fire Plans

1893.04M364

Main Control Room Prefire Plan

3a

Clinton Fire Impairment Log

2/10/2023

Clinton NFPA Code Conformance Evaluation with

Completed Checklists

Miscellaneous

19-AI-81

CPS Appendix R Safe Shutdown Component Circuit

Analysis

2761.02

Leak Rate Testing Equipment Operation

6a

CC-AA-402

Maintenance Specification: Installation of Temporary

Rigging

CC-AA-501-1027

Hot Work Precautions and Safety Practices

CPS 1893.01

Fire Protection Impairment Reporting

& 22b

CPS

1893.04M803

A Fire Pump Room Prefire Plan

6b

CPS 1893.06

Fire Protection Maintenance and Testing Program

13a

CPS 3213.01

Fire Detection and Protection

4, 12, 17, 18,

19, 19a, 24,

& 32c

MA-AA-716-025

Scaffold Installation, Modification, and Removal Request

Process

MA-AA-716-025-

F-1

Non-Permanent Scaffold Request Form

ME-06.00

Guidelines For Determining Fire Loads and Preparing

Fireload Calculations

9b

Procedures

OP-AA-201-007

Fire Protection System Impairment Control

Self-

Assessments

04513795

Clinton Power Station Pre-NRC Fire Protection Triennial

Inspection Self-Assessment

2/10/2023

01688710

LPCS Injection 1MC036 LLRT

09/25/2019

04946959

LPCS Pump Operability

10/22/2019

Work Orders

04961668

Replace Defective Sections of Piping

09/22/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

04987739

Leak Rate Testing of LPCS Injection

09/30/2021

05164485

9071.02 OP Fire Pump B Controls Test

05/24/2022

05172141

9071.19C001 Fire Protection Safety Related Valve Lineup

05/27/2022

05187254

9476.02U22 OP Halon Storage Tank Weight and

Pressure Verification

2/07/2023

219884

CPS 3822.05 Halon Functional

2/28/2022

05308043

Diesel Driven Fire Pump A Functionality Test

11/08/2022