SUBJECT:

CLINTON POWER STATION - SECURITY BASELINE INSPECTION REPORT 05000461/2023420

Dear David P. Rhoades:

On July 20, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Clinton Power Station and discussed the results of this inspection with John Kowalski, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Jefferson K. Clark, Chief Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response Docket No. 05000461 License No. NPF-62

Enclosure:

As stated

Inspection Report

Docket Number:

05000461

License Number:

NPF-62

Report Number:

05000461/2023420

Enterprise Identifier:

I-2023-420-0006

Licensee:

Constellation Nuclear

Facility:

Clinton Power Station

Location:

Clinton, IL

Inspection Dates:

March 27, 2023 to July 20, 2023

Inspectors:

J. Berry, Team Leader

P. Coughlin, Senior Physical Security Inspector, NSIR

A. Woyansky, Physical Security Inspector, NSIR

M. Ziolkowski, Senior Physical Security Inspector, RIII

Approved By:

Jefferson K. Clark, Chief

Security Performance Evaluation Branch

Division of Security Operations

Office of Nuclear Security and Incident Response

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Clinton Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

SAFEGUARDS

71130.03 - Contingency Response - Force-On-Force Testing

Contingency Response - Force-On-Force Testing (1 Sample)

(1) NRC inspectors completed the Contingency Response - Force-on-Force (FOF)

Testing inspection procedure by evaluating the licensees performance in implementing the physical protection program to detect, assess, interdict, and neutralize threats up to, and including, the design basis threat of radiological sabotage. Two NRC-evaluated FOF exercises were conducted for the evaluation.

REPORT ATTACHMENTS

Supplemental Information for the report is considered Safeguards Information and is located separately within the NRCs Safeguards Information Local Area Network and Electronic Safe database SLES, under NS125958.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On July 20, 2023, the inspectors presented the security baseline inspection results to John Kowalski, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

IR 04688461

Two Dress Rehearsal Exercises Followed with LSTRDs -

Lessons Learned

IR 4504295

FOF Related Benchmark Visits (Ginna, Byron, Dresden)

IR 4504724

FOF Related Benchmark Visits (Ginna, Byron, Dresden)

Corrective Action

Documents

IR 4565170

NEI Force on Force Conference

AR 04691467

FOF Observations

AR 04691576

FOF Observations

AR 04692127

Triennial FOF Management Critique

IR 04691467

Results of Exercise One

IR 04691576

Results of Exercise Two

Corrective Action

Documents

Resulting from

Inspection

IR 4514975

Contingency Response - FOF Testing

Engineering

Evaluations

SY-CL-101-502

Clinton Power Station, Security Target Sets

Rev 8

2/14/2022

Millstone Site North Access Point First Floor Plan

Critical Task 12

Lesson Plan, Perform Testing of Intrusion Detection

Equipment and Special Purpose Detectors

Rev 2

Critical Task 13

Lesson Plan, Provide Compensatory Measures

Rev 3

Critical Task 3

Lesson Plan, Control Personnel Access to Protected and

Vital Areas

Rev 4

Miscellaneous

Critical Task 8

Lesson Plan, Conduct Security Patrols

Rev 0

Clinton Power Station, Protective Strategy Brief 2023

01/2023

Clinton Power Station, Security Plan, Training and

Qualification Plan, Safeguards Contingency Plan

Rev 21,

08/16/2021

SY-AA -150-101-

F-29, Revision 0

Exelon Generation, Security Lesson Plan

Rev 0

SY-AA-101-122

Exelon Generation, Testing Security Equipment

Rev 22

71130.03

Procedures

SY-AA-101-122-

1001, Revision 13

Exelon Generation, Performance of Security System Tests

Rev 13

SY-AA-101-130

Exelon Generation, Security Responsibilities for Station

Personnel

Rev 25

SY-AA-101-133,

Revision 16

Exelon Generation, Integrated Response Plan with Off-Site

Response Agencies

Rev 16

71130.03

Procedures

SY-AA-101-145

Exelon Generation, Security Standards of Conduct

Rev 13

SY-AA-116

Maintenance, Testing, and Calibration

Rev 6

SY-AA-120

Operability Testing

Rev 12

SY-AA-150-1006

Exelon Generation, Timelines

Rev 3

SY-AA-150-1006-

F-01

Exelon Generation, Responder Timeline Worksheet

Rev 2

SY-AA-150-1006-

F-02

Exelon Generation, Adversary Timeline Worksheet

Rev 2

SY-AA-150-101-

F48

Exelon Generation, Security Drill and Exercise Controller

Training

Rev 9

03/27/2018

SY-AA-150-102,

Revision 0

Exelon Generation, Security Drills and Exercises

Rev 0

SY-AA-150-105-

F-05

Exelon Generation, Clinton Physical Fitness Test

Rev 0

SY-CL-101-122,

Revision 10

Clinton Power Station Site Specific Equipment Testing

Rev 10

71130.03

Procedures

SY-CL-101-501

Clinton Power Station, Site Specific Defensive Strategy

Rev 12,

2/28/2022

5