Summary of Meeting with Union Electric Company for the Licensee to Present Its Application Dated September 17, 2004, to Replace the Steam Generators in the Fall of 2005
ML043130289
Person / Time
Site: Callaway Ameren icon.png
Issue date: 11/17/2004
From: Donohew J
NRC/NRR/DLPM/LPD4
To:
Donohew J N, NRR/DLPM,415-1307
Shared Package
ML List:
References
TAC MC4437
Download: ML043130289 (6)


Text

November 17, 2004 LICENSEE: Union Electric Company FACILITY: Callaway Plant

SUBJECT:

SUMMARY

OF MEETING WITH UNION ELECTRIC COMPANY -

PRESENTATION ON REPLACEMENT OF THE STEAM GENERATORS IN THE FALL OF 2005 (TAC NO. MC4437)

A meeting was held on Thursday, November 4, 2004, between the NRC staff and representatives of the Union Electric Company, the licensee for the Callaway Plant. The meeting was requested by the licensee to present the technical issues in its license amendment request application dated September 17, 2004, to support the replacement steam generators (RSGs) to be installed in Refueling Outage (Refuel) 14 in the Fall of 2005. is the list of attendees and Enclosure 2 is the handout from the licensee. There was no handout from the NRC staff.

The agenda (the first page of Enclosure 2) for the meeting was the following:

1. Introduction
2. General Description of RSG
3. Westinghouse Nuclear Steam Supply System (NSSS) RSG Analyses
4. RSG Licensing Activities
5. Application of Leak Before Break (LBB) to Pressurizer Surge Line
6. Other Refuel 14 Operating License (OL) Submittals
7. Adjourn Meeting In Item No. 2 above, the licensee explained the reasons for the steam generators (SGs) replacement at Callaway and provided a comparison between the current SGs and the RSGs and the special features of the RSGs.

In Items Nos. 3 and 4 above, the licensee explained the Technical Specification (TS) changes and the new methodologies being proposed for Callaway in the September 17, 2004, application. The NRC staff asked the licensee questions to clarify what is being proposed in the application.

In Item No. 5 above, the licensee presented the mitigative measures it is considering for its application of LBB for the pressurizer surge line. The licensee stated that its application is now expected to be submitted in January 2005, instead of the November 19, 2004, date given in its September 17, 2004, application. The NRC staff gave its views on the two different approaches shown on page 12 of Enclosure 2. The weld overlay approach would require a

relief request submittal from the licensee in addition to the application to apply LBB for the pressurizer surge line.

In Item No. 6 above, the licensee presented the two other license amendment requests for Refuel 14 that will propose changes to the TSs. These other amendment requests are described on page 11 of Enclosure 2.

The licensee completed its presentation and the meeting was adjourned. There were no decisions made by the NRC staff related to the licensees September 17, 2004, application, or the other applications to be made by the licensee for Refuel 14.

/RA/

Jack Donohew, Senior Project Manager, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-483

Enclosures:

1. List of Meeting Attendees
2. Licensee's Handout (ADAMS Accession No. ML043090388) cc w/encls: See next page

Callaway Plant, Unit 1 cc:

Professional Nuclear Consulting, Inc. Mr. Rick A. Muench 19041 Raines Drive President and Chief Executive Officer Derwood, MD 20855 Wolf Creek Nuclear Operating Corporation P.O. Box 411 John ONeill, Esq. Burlington, KA 66839 Shaw, Pittman, Potts & Trowbridge 2300 N. Street, N.W. Mr. Dan I. Bolef, President Washington, D.C. 20037 Kay Drey, Representative Board of Directors Coalition for the Mr. Mark A. Reidmeyer, Regional Environment Regulatory Affairs Supervisor 6267 Delmar Boulevard Regulatory Affairs University City, MO 63130 AmerenUE P.O. Box 620 Mr. Lee Fritz, Presiding Commissioner Fulton, MO 65251 Callaway County Court House 10 East Fifth Street U.S. Nuclear Regulatory Commission Fulton, MO 65151 Resident Inspector Office 8201 NRC Road Mr. David E. Shafer Steedman, MO 65077-1302 Superintendent, Licensing Regulatory Affairs Mr. Les H. Kanuckel AmerenUE Manager, Quality Assurance P.O. Box 66149, MC 470 AmerenUE St. Louis, MO 63166-6149 P.O. Box 620 Fulton, MO 65251 Mr. Keith D. Young Manager, Regulatory Affairs Missouri Public Service Commission AmerenUE Governor Office Building P.O. Box 620 200 Madison Street Fulton, MO 65251 Jefferson City, MO 65102-0360 Mr. Scott Clardy, Director Regional Administrator, Region IV Section for Environmental Public Health U.S. Nuclear Regulatory Commission P.O. Box 570 611 Ryan Plaza Drive, Suite 400 Jefferson City, MO 65102-0570 Arlington, TX 76011-4005 Certrec Corporation Mr. Ronald A. Kucera 4200 South Hulen, Suite 630 Deputy Director for Public Policy Fort Worth, TX 76109 Department of Natural Resources P.O. Box 176 Mr. Garry L. Randolph Jefferson City, Missouri 65102 Vice President and Chief Nuclear Officer Union Electric Company Post Office Box 620 Fulton, MO 65251

ML043090388) cc w/encls: See next page DISTRIBUTION:

PUBLIC JFair PDIV-2 Reading EMurphy RidsNrrDlpm (TMarsh/JLyons) MHart RidsNrrDlpmLpdiv (HBerkow) PPatnaik RidsNrrPMJDonohew JTsao RidsNrrLAEPeyton KWichman KDesai TMensah HLi RidsNrrDlpmPdiv2 (RGramm)

RHernandez RLobel RTjader RidsRgn4MailCenter (AHowell)

RidsOgcRp RidsAcrsAcnwMailCenter Package No.: ML043220634 Meeting Notice No.: ML042930481 ADAMS Accession No.: ML043130289 NRC-001 OFFICE PDIV-2/PM PDIV-2/LA PDIV-2/SC NAME JDonohew EPeyton RGramm DATE 11/16/04 11/15/04 11/17/04 DOCUMENT NAME: E:\Filenet\ML043130289.wpd MEETING WITH UNION ELECTRIC COMPANY NOVEMBER 4, 2004 LIST OF MEETING ATTENDEES NAME AFFILIATION J. Donohew NRC/NRR/PDIV-2 R. Tjader NRC/NRR/TSS R. Hernandez NRC/NRR/SPLB J. Fair NRC/NRR/EMEB K. Desai NRC/NRR/SRXB H. Li NRC/NRR/EEIB M. Hart NRC/NRR/SPSB R. Lobel NRC/NRR/SPSB E. Murphy NRC/NRR/EMCB J. Tsao NRC/NRR/EMCB P. Patnaik NRC/NRR/EMCB K. Wichman NRC/NRR/EMCB D. Shafer UE T. Herrmann UE B. Yates UE K. Mills UE B. Huhmann UE J. Andrachek Westinghouse M. Watson Westinghouse D. Horner McGraw Hill Where: NRC = Nuclear Regulatory Commission NRR = Office of Nuclear Reactor Regulation PDIV-2 = Project Directorate IV-Section 2 EEIB = Electrical and Instrumentation and Control Branch EMCB = Materials and Chemical Engineering Branch EMEB = Mechanical and Civil Engineering Branch SPLB = Plant Systems Branch SRXB = Reactor Systems Branch SPSB = Probabilistic Safety Assessment Branch UE = Union Electric Company Westinghouse = Westinghouse Electric Company ENCLOSURE 1

LICENSEE'S HANDOUT FOR NOVEMBER 4, 2004, MEETING ENCLOSURE 2