IR 05000327/2024001

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000327/2024001 and 05000328/2024001
ML24106A181
Person / Time
Site: Sequoyah  
Issue date: 04/17/2024
From: Louis Mckown
Division Reactor Projects II
To: Jim Barstow
Tennessee Valley Authority
References
IR 2024001
Download: ML24106A181 (12)


Text

SUBJECT:

SEQUOYAH, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000327/2024001 AND 05000328/2024001

Dear Jim Barstow:

On March 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Sequoyah, Units 1 and 2. On April 9, 2024, the NRC inspectors discussed the results of this inspection with Tom Marshall, site vice president, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Louis J. McKown, II, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Nos. 05000327 and 05000328 License Nos. DPR-77 and DPR-79

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000327 and 05000328

License Numbers:

DPR-77 and DPR-79

Report Numbers:

05000327/2024001 and 05000328/2024001

Enterprise Identifier:

I-2024-001-0027

Licensee:

Tennessee Valley Authority

Facility:

Sequoyah, Units 1 and 2

Location:

Soddy Daisy, TN 37379

Inspection Dates:

January 1, 2024 to March 31, 2024

Inspectors:

D. Hardage, Senior Resident Inspector

A. Price, Resident Inspector

Approved By:

Louis J. McKown, II, Chief

Reactor Projects Branch 5

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Sequoyah, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at rated thermal power (RTP). On March 3, 2024, the unit began end-of-life coast down. On March 22, 2024, the unit was at 85 percent RTP and shutdown for refueling outage 1R26. The unit remained shutdown for refueling the remainder of the inspection period.

Unit 2 operated at or near RTP for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather due to impending freezing temperatures on January 11, 2024.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Spare 2-S 125-volt (V) vital battery charger alignment to vital battery board IV during scheduled preventative maintenance on vital battery charger IV on January 24, 2024.
(2) Unit 2 A train component cooling water system (CCS) alignment following restoration of 2A2 CCS heat exchanger from cleaning on March 10, 2024.
(3) Safety injection system alignment for low temperature overpressure protection in Mode 5 with the reactor coolant system (RCS) in a solid water configuration on March 23, 2024.
(4) Unit 1 residual heat removal system (RHR) aligned for RCS cooldown in Mode 6 with RCS level below the flange on March 27, 2024.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Units 1 and 2 auxiliary building, elevation 653 on January 3, 2024.
(2) Units 1 and 2 auxiliary building, elevation 690 on January 31, 2024.
(3) Units 1 and 2 auxiliary building, elevation 669 on February 29, 2024.
(4) Units 1 and 2 auxiliary building, elevation 749, electrical board, battery, and transformer rooms on March 6, 2024.
(5) Units 1 and 2 auxiliary building, elevation 759 on March 21, 2024.

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill on January 31, 2024.

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections in the unit 1 and unit 2 auxiliary building, elevation 749, electrical board, battery, and transformer rooms on March 4, 2024.

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) 2A1 CCS heat exchanger on February 12, 2024.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (2 Samples)

(1) The inspectors observed and evaluated a simulator training scenario focused on refueling outage RHR operations including a loss of RHR while in mid-loop operations due to loss of offsite power with a diesel generator failure on February 27, 2024.
(2) The inspectors observed and evaluated licensed operator performance in the main control room during shutdown and cooldown for refueling outage 1R26 on March 22, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Maintenance rule preventable functional failure of 2-FCO-030-246B, 480V transformer room ventilation supply damper operator due to the connecting rod separating from the damper, cause determination and evaluation (CDE) 3198, on January 25, 2024.
(2) Maintenance rule CDE 3235 for the B electric board room chiller failure to start following maintenance on March 29, 2024.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 1 and 2, week of January 21 thru 28, including protected equipment reviews for scheduled maintenance on 120V vital battery charger IV and 1B emergency diesel generator (EDG).
(2) Week of January 29, including protected equipment review for repairs to the 2A safety injection pump (SIP) and review of the associated risk-informed-completion-time requirements on February 1, 2024.
(3) Unit 1 and 2, week of February 25 thru March 1, including protected equipment review for scheduled maintenance on the unit 1 steam-driven auxiliary feedwater pump, cleaning of the 2A2 CCS heat exchanger and the A main control room chiller.
(4) Unit 1, Yellow shutdown risk week of March 25-29, while RCS level was below the reactor flange level for reactor disassembly, including review of defense-in-depth protected equipment for 1R26.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)1A and 2A EDG battery rack each have a tie rod completely corroded through on January 2, 2024.

(2)2A SIP oil analysis indicates an increase in metals, specifically chromium and nickel on January 30, 2024.

(3) Unit 2 turbine-driven auxiliary feedwater pump had an unknown substance in the catch basin of the outboard pump bearing on February 1, 2024.
(4) Scaffold supported by CCS piping above the 2B centrifugal charging pump on February 29, 2024.
(5) Loss of backup containment penetration conductor overcurrent protective device for reactor coolant pump 1-2 on February 29, 2024.
(6) Pressurizer power operated relief valve 1-PCV-68-340 failed initial close valve stroke time on March 23, 2024.

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Design equivalent change package SQN-24-001. Change normal configuration of auxiliary feedwater LCVs to open on February 15, 2024.

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1)

(Partial)

The inspectors evaluated unit 1 refueling outage 1R26 activities from March 22 thru March 31, 2024.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (4 Samples)

(1) WO (work order) 123554426. 1A SIP oil cooler inspection on January 31, 2024.
(2) WO 119348977. Implement ECP 23886 (rev. 1) to replace QA essential raw cooling water pump packing on February 2, 2024.
(3) WO 124228677. Replace 2A SIP pump shaft and bearings on February 4, 2024.
(4) WO 124306595. Replace pressurizer pressure transmitter SQN-2-PT-068-0323 on March 18, 2024.

Surveillance Testing (IP Section 03.01) (3 Samples)

(1)2-PI-OPS-047-002.0, Steam Inlet Valve Testing on March 6, 2024.

(2)1-SI-OPS-088-001.0, Phase A Isolation Test on March 24, 2024.

(3)1-SI-OPS-082-026.B, Loss of Offsite Power with Safety Injection - D/G 1B-B Test on March 26, 2024.

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1)1-SI-SXP-003-202.A, Motor Driven Auxiliary Feedwater Pump 1A-A Comprehensive Performance Test on March 22, 2024.

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Sample)

(1) Emergency preparedness training drill including a general emergency resulting from a loss of coolant accident with fuel failure and containment failure conducted on February 14,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10)===

(1) Unit 1 (January 1, 2023 through December 31, 2023).
(2) Unit 2 (January 1, 2023 through December 31, 2023).

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1) Unit 1 (January 1, 2023 through December 31, 2023).
(2) Unit 2 (January 1, 2023 through December 31, 2023).

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Condition report (CR) 1697913. Low margin for motor-driven auxiliary feedwater pump 1B-B.
(2) CR 1916599. Technical Requirement (TR) 7.5.3 assessment on nonfunctional seismic monitors 0-XT-52-75A and 0-XT-52-75B.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 9, 2024, the inspectors presented the integrated inspection results to Tom Marshall, site vice president, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

CR 1902428

Freeze Protection Issue 0-PI-OPS-000-006.0

01/11/2024

71111.01

Procedures

0-PI-OPS-000-

006.0

Freeze Protection

Revision 74

0-SO-250-1

25 Volt DC Vital Power System

Revision 88

1-SI-OPS-068-

001.1

Low Temperature Overpressure Protection

Revision 13

2-SO-62-5

Emergency Core Cooling System

Revision 70

71111.04

Procedures

2-SO-70-1,

Component Cooling Water System "A" Train Valve Checklist

10/17/2021

Corrective Action

Documents

Resulting from

Inspection

CR 1913750

Scaffold in contact with piping for shutdown board room air

handling units

2/29/2024

AUX-0-653-00

Fire Protection Pre Fire Plans Auxiliary Building - El. 653

Revision 9

AUX-0-690-01

Fire Protection Pre Fire Plans Auxiliary Building (El. 690 Unit

Side)

Revision 9

AUX-0-690-02

Fire Protection Pre Fire Plans Auxiliary Building (El. 690 Unit

Side)

Revision 9

AUX-0-749-01

Fire Protection Pre Fire Plans Auxiliary Building (El. 749 Unit

Side)

Revision 13

AUX-0-749-02

Fire Protection Pre Fire Plans Auxiliary Building (El. 749 Unit

Side)

Revision 14

AUX-0-759-01

Fire Protection Pre-Fire Plans

Auxiliary Building (El. 759 Unit 1 Side)

Revision 6

AUX-0-759-02

Fire Protection Pre-Fire Plans

Auxiliary Building (El. 759 Unit 2 Side)

Revision 7

71111.05

Fire Plans

PFP NO: FPH

Fire Protection Pre-Fire Plans

Fire Pump House

Revision 1

Calculations

MDN-000-000-

2010-0203

SQN Probabilistic Risk Assessment - Internal Flooding

Analysis

Revision 6

71111.06

Procedures

AOP-M.08

Internal Flooding

Revision 8

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.07A

Work Orders

WO 12379629

2A1 CCS heat exchanger clam and mic inspection

2/20/2024

CR 1819324

Operator connecting rod separated from dampers

11/26/2022

CR 1909937

"B" Electric Board Room Chiller failed to startup during PMT

run

2/14/2024

Corrective Action

Documents

WO 124198051

Remove/Replace B-B EBR Chiller Compressor Motor Starter

2/12/2024

NPG-SPP-03.4

Maintenance Rule Performance Indicator Monitoring,

Trending and Reporting - 10CFR50.65

Revision 5

Procedures

TI-4

Maintenance Rule Performance Indicator Monitoring

Trending, and Reporting - 10CFR50.65

Revision 39

71111.12

Work Orders

WO 124302610

B Electric Board Room Chiller failed to startup during PMT

03/05/2024

CR 1906501

NRC identified boric acid build up on 2BB safety injection

casing flange and vent valve

01/29/2024

Corrective Action

Documents

Resulting from

Inspection

CR 1920063

NRC identified protected equipment barrier missing and

scaffold touching flex conduit in 1A RHR pump room

03/27/2024

71111.13

Procedures

0-GO-16

System Operability Checklists

Revision 36

CR 1900954

2AA SIP oil analysis

01/03/2024

CR 1913939

1B 6.9KV unit board control power auto transferred to

alternate

2/29/2024

Corrective Action

Documents

CR 1914385

TR 3.7.5 condition report - 1B 6.9KV Unit Board BD control

power transfer

03/01/2024

CR 1900168

Significant Corrosion on EDG battery rack tie rods

2/27/2023

CR 1907411

NRC identified unknown substance U2 TDAFW stuffing box

gland

2/01/2024

Corrective Action

Documents

Resulting from

Inspection

CR 1913856

Scaffold attached to safety related piping

2/29/2024

71111.15

Work Orders

WO 124221101

Perform flush and CUNO inspection

01/30/2024

CR 1919426

White powder (boric acid or sodium tetraborate) behind the

base of pressurizer

03/25/2024

Corrective Action

Documents

Resulting from

Inspection

CR 1919430

Leak on component cooling water line to RCP 1-2 thermal

barrier

03/25/2024

71111.20

Procedures

0-SI-SXX-068-

27.0

RCS and Pressurizer Temperature and Pressure Limits

Revision 17

CR 1918307

MFP speed probe deviation alarms during AFW

comprehensive test

03/20/2024

71111.24

Corrective Action

Documents

CR 1918999

Procedure change request - AFW Pump Comprehensive

03/23/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Tests

CR 1919433

ERCW pump L-B would not start manually as directed 1-SI-

OSP-082-026.B

03/26/2024

2-SI-ICC-068-

23.3

Channel Calibration of Pressurizer Pressure Channel III,

Rack 9, Loop 2-P-68-323

Revision 21

2-SI-SXP-063-

201.A

Safety Injection Pump 2A-A Performance Test

Revision 29

Procedures

MI-6.9

Safety Injection Pump Inspection and Rebuild

Revision 23

71151

Corrective Action

Documents

CR 1851189

Unit 2 SI-137.0 unidentified leakage at Action Level II

04/19/2023

CR 1697633

1B MDAFW Pump DP below acceptance criteria

05/29/2021

Corrective Action

Documents

CR 1697806

MDAFW critical spare exhibited marginal performance

05/31/2021

EWR 21-DEM-

003-076

MDAFWP pump curve (generic location)

Revision 2

71152A

Engineering

Evaluations

SQN-0-24-017

PRA Evaluation for seismic monitors nonfunctionality

03/12/2024