Tennessee Valley Authority, Sequoyah Nuclear Plant, P.O. Box 2000, Soddy Daisy, Tennessee 37384

July 29, 2024 10 CFR 50.54(q) 10 CFR 72.44(f)

ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001

Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327, 50-328, and 72-034

Subject:

Emergency Plan Implementing Procedure Revision

In accordance with the requirements of 10 CFR 50.54(q) and 10 CFR 72.44(f), the Tennessee Valley Authority is submitting a description of changes to the Sequoyah Nuclear Plant (SQN)

Radiological Emergency Plan. The affected document, and current revision level, is the SQN Emergency Plan Implementing Procedure (EPIP) listed below.

EPIP Revision Title Effective Date(s) 7 39 Activation and Operation of the Operations Support Center (OSC) July 8, 2024

The above referenced revision was evaluated in accordance with 10 CFR 50.54(q)(3) and 10 CFR 72.44(f) and determined that the change does not reduce the effectiveness of the Emergency Plan. Details of the revision are included in the enclosure.

There are no new regulatory commitments contained in this letter. Should you have any questions concerning this submittal, please contact Mr. Paul Gain, Site Emergency Preparedness Manager, at (423) 843-7088.

Respectfully,

Thomas B. Marshall Site Vice President Sequoyah Nuclear Plant

U.S. Nuclear Regulatory Commission Page 2 July 29, 2024

Enclosure:

SQN Units 1 & 2 Description of Revision/Change

cc: NRC Regional Administrator Region II NRC Senior Resident Inspector Sequoyah Nuclear Plant NRC Director Division of Fuel Management, NMSS

ENCLOSURE: SQN UNITS 1 & 2 DESCRIPTION OF REVISION/CHANGE

EPIP-7, Revision 39 Updated Attachment 18 OSC [Operations Support Center] Team Briefing/Debriefing Form to allow OSC Radiation Protection (RP) personnel to sign off on RP Briefing.