Forwards Rev F to QA Program Manual.Historical Document Containing All Changes to QA Manual Since First Edition Issued in Aug 1973 Encl
ML20080Q829
Person / Time
Site: Millstone Dominion icon.png
Issue date: 09/30/1983
From: Counsil W
NORTHEAST UTILITIES, NORTHEAST UTILITIES SERVICE CO.
To: Murley T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20080Q833 List:
References
B10911, NUDOCS 8310170190
Download: ML20080Q829 (2)


Text

_ _ - - _ _ _

General Offices

  • Selden Street, Berlin, Connecticut tw cowcrcur ton as.o ma w" P.O. BOX 270 l

$$ ((""

umE.ir oau umacE cow-HARTFORD. CONNECTICUT 06141-0270 (203)666-6911 g ,

MWatast asuCLEAR EwmovCowassv 1

September 30,1983 Docket Nos.30-213 50-245 50-336  ;

50-423 I I

B10911 Dr. Thomas E. Murley  !

Regional Administrator Region I U. S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406

Reference:

(1) W. G. Counsil letter to T. E. Murley, " Final Rule, Reporting of Changes to the Quality Assurance Program", dated June 9, 1983.

Final Rule, " Reporting of Changes to the Quality Assurance Program" Submittal of Prir.cipal Contractor's Quality Assurance Program Millstone Nuclear Power Station, Unit 3

Dear Dr. Murley:

3 In Reference (1), we requested an extension for our principal contractor, Stone &

Webster Engineering Corporation (SWEC), for submittal of their most recent -

quality assurance program description as required by 10 CFR 50.54(a)(2) and/or 50.55(f)(2). Northeast Utilities utilizes principal contractor's quality assurance programs only for Millstone Unit 3 and these programs are referenced in Chapter 17 of the Millstone Unit 3 FSAR.

At this time, we are submitting the current description of the SWEC Quality Assurance Program Manual for the Millstone Nuclear Power Station, Unit 3, Table of Contents, Revision F, dated April 6,1981 (Attachment 1). This program was derived, without degradation, from the SWEC Topical Report, SWSQAP l-74, Revision N/A, as approved by the NRC on December 31,1974 (Attachment 2).

We have also included a historical document (Attachment 3), containing all of the changes te the SWEC Quality Assurance Program Manual for the Millstone Nuclear Power Station, Unit 3 since te first edition of the manual was issued in August 1973. For your convenience, a summarized listing of these changes is also included (Attachment 4).

8310170190 23 PDR ADOCK 0 PDR g Q f

6 As such, we consider this to fulfill the requirements of 10 CFR 50.55 (f)(2). 'If questions regarding this submittal, please contact Mr. Donald O.

you have any(203)

Nordquist at 666-6911, Ext. 5447.

r. Very truly yours,

~ NORTHEAST UTILITIES SERVICE COMPANY g-W. G. Counsil Senior Vice President cc:

NRC Region U. S. NRC IV Vendor Document Program Control Desk (15Branch copies (I cop)y)

T. Rebelowski - NRC Resident Inspector - Millstone Unit 3 (l' copy)

G. Napuda - NRC Region 1 (3 copies)

3. Shediosky - NRC Senior Resident Inspector - Millstone Station (1 copy)