ML092240471

From kanterella
Jump to navigation Jump to search
IR 05000382-09-003; 4/7/09 - 7/7/09; Waterford Steam Electric Station, Unit 3; Problem Identification and Resolution: Exercise Evaluation, Identification and Resolution of Problems the Report Covered a 3-month Period of Inspection by Reside
ML092240471
Person / Time
Site: Waterford Entergy icon.png
Issue date: 08/12/2009
From: Clark J
NRC/RGN-IV/DRP/RPB-E
To: Kowalewski J
Entergy Operations
References
IR-09-003
Download: ML092240471 (43)


See also: IR 05000382/2009003

Text

UNITED STATES

NUC LE AR RE G UL AT O RY C O M M I S S I O N

R E GI ON I V

612 EAST LAMAR BLVD , SU I TE 400

AR LI N GTON , TEXAS 76011-4125

August 12, 2009

Joseph Kowalewski, Vice President, Operations

Entergy Operations, Inc.

Waterford Steam Electric Station, Unit 3

17265 River Road

Killona, LA 70057-3093

Subject: WATERFORD STEAM ELECTRIC STATION, UNIT 3 - NRC INTEGRATED

INSPECTION REPORT 05000382/2009-003

Dear Mr. Kowalewski:

On July 7, 2009, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

your Waterford Steam Electric Station, Unit 3. The enclosed integrated inspection report

documents the inspection findings, which were discussed on August 11, 2009, with you and

other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

This report documents three NRC identified findings of very low safety significance (Green). All

of these findings involved violations of NRC requirements. However, because of the very low

safety significance and because they are entered into your corrective action program, the NRC

is treating these findings as noncited violations, consistent with Section VI.A.1 of the NRC

Enforcement Policy. If you contest the violations or the significance of the noncited violations,

you should provide a response within 30 days of the date of this inspection report, with the basis

for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, D.C. 20555-0001, with copies to the Regional Administrator, U.S. Nuclear

Regulatory Commission, Region IV, 612 E. Lamar Blvd, Suite 400, Arlington, Texas,

76011-4125; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission,

Washington, D.C. 20555-0001; and the NRC Resident Inspector at the Waterford Steam Electric

Station, Unit 3 facility. In addition, if you disagree with the characterization of any finding in this

report, you should provide a response within 30 days of the date of this inspection report, with

the basis for your disagreement, to the Regional Administrator, Region IV, and the NRC

Resident Inspector at Waterford Steam Electric Station, Unit 3. The information you provide will

be considered in accordance with Inspection Manual Chapter 0305.

Entergy Operations, Inc. -2-

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter, and its

enclosure, will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records component of NRCs document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

Sincerely,

/RA/

Jeffrey A. Clark, P.E.

Project Branch E

Division of Reactor Projects

Docket: 50-382

License: NPF-38

Enclosure:

NRC Inspection Report 05000382/2009003

w/Attachment: Supplemental Information

cc: w/Enclosure Site Vice President

Senior Vice President Waterford Steam Electric Station, Unit 3

Entergy Nuclear Operations Entergy Operations, Inc.

P. O. Box 31995 17265 River Road

Jackson, MS 39286-1995 Killona, LA 70057-0751

Director

Senior Vice President and Nuclear Safety Assurance

Chief Operating Officer Entergy Operations, Inc.

Entergy Operations, Inc. 17265 River Road

P. O. Box 31995 Killona, LA 70057-0751

Jackson, MS 39286-1995

General Manager, Plant Operations

Vice President, Operations Support Waterford 3 SES

Entergy Services, Inc. Entergy Operations, Inc.

P. O. Box 31995 17265 River Road

Jackson, MS 39286-1995 Killona, LA 70057-0751

Senior Manager, Nuclear Safety Manager, Licensing

and Licensing Entergy Operations, Inc.

Entergy Services, Inc. 17265 River Road

P. O. Box 31995 Killona, LA 70057-3093

Jackson, MS 39286-1995

Chairman

Louisiana Public Service Commission

P. O. Box 91154

Baton Rouge, LA 70821-9154

Entergy Operations, Inc. -3-

Parish President Council Chief, Technological Hazards

St. Charles Parish Branch

P. O. Box 302 FEMA Region VI

Hahnville, LA 70057 800 North Loop 288

Federal Regional Center

Director, Nuclear Safety & Licensing Denton, TX 76209

Entergy, Operations, Inc.

440 Hamilton Avenue Chairperson, Radiological Assistance

White Plains, NY 10601 Committee

Region VI

Louisiana Department of Environmental Federal Emergency Management Agency

Quality, Radiological Emergency Planning Department of Homeland Security

and Response Division 800 North Loop 288

P. O. Box 4312 Federal Regional Center

Baton Rouge, LA 70821-4312 Denton, TX 76201-3698

Entergy Operations, Inc. -4-

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Chuck.Casto@nrc.gov)

DRP Director (Dwight.Chamberlain@nrc.gov)

DRP Deputy Director (Anton.Vegel@nrc.gov)

DRS Director (Roy.Caniano@nrc.gov)

DRS Deputy Director (Troy.Pruett@nrc.gov)

Senior Resident Inspector (Ray.Azua@nrc.gov)

Resident Inspector (Dean.Overland@nrc.gov)

Branch Chief, DRP/E (Jeff.Clark@nrc.gov)

Senior Project Engineer, DRP/E (George.Replogle@nrc.gov)

WAT Site Secretary (Linda.Dufrene@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource

Regional State Liaison Officer (Bill.Maier@nrc.gov)

NSIR/DPR/EP (Steve.LaVie@nrc.gov)

Only inspection reports to the following:

DRS STA (Dale.Powers@nrc.gov)

OEDO RIV Coordinator (Leigh.Trocine@nrc.gov)

ROPreports

File located: R:\_REACTORS\_WAT\2009\WAT 2009003 RP-DHOAdams.doc ML092240471

SUNSI Rev Compl. :Yes No ADAMS :Yes No Reviewer Initials GDR

Publicly Avail  : Yes No Sensitive Yes : No Sens. Type Initials GDR

RIV:SRI:DRP/E SPE/DRP/E C:DRS/EB1 C:DRS/EB2 C:DRs/OB

DHOverland GDReplogle TRFarnholtz NFOKeefe RELantz

/RA/-E /RA/ /RA/ /RA/ /RA/

8/4/09 8/5/09 8/5/09 8/5/09 8/5/09

C:DRS/PSB C:DRS/OSB2 C:DRP/E

MPShannon GEWerner JAClark

/RA/ /RA/ /RA/

8/ /09 8/8/09 8/11/09

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 05000382

License: NFP-38

Report: 05000382/2009003

Licensee: Entergy Operations, Inc.

Facility: Waterford Steam Electric Station, Unit 3

Location: Hwy. 18

Killona, LA

Dates: April 7 through July 7, 2009

Inspectors: D. Overland, Senior Resident Inspector

Paul J. Elkmann, Senior Emergency Preparedness Inspector

Gilbert L. Guerra, CHP, Emergency Preparedness Inspector

Approved By: Jeff Clark, Chief, Project Branch E

Division of Reactor Projects

-1- Enclosure

SUMMARY OF FINDINGS

IR 05000382/2009003; 4/7/09 - 7/7/09; Waterford Steam Electric Station, Unit 3; Problem

Identification and Resolution: Exercise Evaluation, Identification and Resolution of Problems

The report covered a 3-month period of inspection by resident inspectors and an announced

baseline inspection by regional based inspectors. Three Green noncited violations of

significance were identified. The significance of most findings is indicated by their color (Green,

White, Yellow, or Red) using Inspection Manual Chapter 0609, Significance Determination

Process. Findings for which the significance determination process does not apply may be

Green or be assigned a severity level after NRC management review. The NRC's program for

overseeing the safe operation of commercial nuclear power reactors is described in

NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.

A. NRC-Identified Findings and Self-Revealing Findings

Cornerstone: Mitigating Systems

Appendix B, Criterion VXI (Corrective Actions), because the licensee failed to

identify the cause for a significant condition adverse to quality. The Train B 125

Vdc battery bank failed to pass a technical specification surveillance requirement

discharge test during a Spring 2008 outage. The root cause procedure required

that the licensee sequester the battery in a controlled area so that vital

information related to the failure could be obtained. However, the licensee

disposed of the battery instead. When questions arose concerning the specified

failure cause (impurities in the battery materials), the licensee was unable to

provide objective evidence to support the conclusion. Had the licensee obtained

objective evidence to support their conclusion that impurities caused the battery

failure, a 10 CFR Part 21 report may have been required. The licensee replaced

the battery and planned to replace similar batteries in the other two trains during

the next refueling outage. The licensee entered this finding in their corrective

action program as Condition Report CR-WF3-2009-2846.

The finding was more than minor because, if left uncorrected, it could lead to a

more significant safety concern. Specifically, since the cause of the battery

failure was not definitively found, the licensee may not have taken corrective

actions to prevent other battery failures. Using the Inspection Manual

Chapter 0609, Significance Determination Process, Phase 1 Screening

Worksheet, the finding was of very low risk significance because it did not

actually cause the loss of operability or functionality of another 125 Vdc battery at

the time of the inspection. This finding had a crosscutting aspect in the area of

Problem Identification and Resolution (Corrective Action Program Component)

because the licensee failed to thoroughly evaluate the need to keep the battery

prior to disposal P.1(c) (Section 4OA2).

Appendix B, Criterion XVI (Corrective Action), for the failure to promptly correct

-2- Enclosure

conditions adverse to quality. The licensee had documented several conditions

adverse to quality and then transferred the concerns to other condition reports.

Then, the licensee closed those condition reports without addressing the

concerns. Identified conditions included (1) the Train B 125 Vac discharge test

data indicated a loose battery connection but the battery was permitted to pass

the test anyway; (2) the root cause determination for the failed battery was

focused on the statements of one person and failed to address other information;

(3) the root cause determination failed to address conflicting information;

and (4) the root cause determination failed to properly address other potential

causes for the inoperable battery, such as tampering. Plant personnel had failed

to accurately translate the issues when transferring information from one

condition report to another. The licensee entered this finding into their corrective

action program as Condition Report CR-WF3-2009-1177.

The finding was more than minor because, if left uncorrected, it would become a

more significant safety concern. For example, the failure to include acceptance

criteria in the battery discharge test (intended to identify and correct loose battery

connections) could result in another inoperable 125 Vdc battery for an extended

period. The inspectors evaluated the finding using Inspection Manual

Chapter 609, Significance Determination Process, Phase 1 Screening Worksheet

and determined that the finding was of very low risk significance because it did

not result in another battery becoming inoperable or nonfunctional. This finding

had a crosscutting aspect in the area of Human Performance (Work Practices

Component) because plant personnel failed to effectively use human error

prevention techniques, such as self and peer checking, when transferring

concerns between condition reports H.4(a) (Section 4OA2).

Cornerstone: Emergency Preparedness

the licensees failure to develop and have in place guidelines for the choice of

protective actions during an emergency that were consistent with federal

guidance. Specifically, the licensees guidelines for extending existing protective

action recommendations into additional geographical areas of the emergency

planning zone under conditions of changing wind vectors were not consistent

with the guidance of EPA-400-R-92-001, AManual of Protective Action Guides

and Protective Actions for Nuclear Incidents.@ The licensees practices resulted

in unnecessary recommendations for protective actions in areas where valid

dose projections show federal protective action guides are not exceeded, and

may expose members of the public to unjustified risks. The licensee has entered

this issue into their corrective action system as Condition

Report CR-WF3-2009-03256.

This finding was more than minor because it was not similar to the examples of

Manual Chapter 0612, Appendix E, and affected the emergency preparedness

cornerstone objective because unnecessary protective actions may expose

members of the public to an unjustified risk. The finding was associated with the

-3- Enclosure

emergency response organization attributes of 50.47(b) planning standards and

training. This finding was of very low safety significance because it was not a

risk significant planning standard functional failure or degraded function because

licensee protective action recommendations would be issued in accordance with

federal guidance for all areas of the emergency planning zone where Protective

Action Guides are exceeded. This finding was evaluated as not having a

crosscutting aspect because the finding was not indicative of current licensee

performance (Section 1EP1).

B. Licensee-Identified Violations

None

-4- Enclosure

REPORT DETAILS

Summary of Plant Status

The plant began the inspection period on April 7, 2009, at 100 percent power and remained at

approximately 100 percent power for the rest of the inspection period.

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and

Emergency Preparedness

1R01 Adverse Weather Protection (71111.01)

.1 Summer Readiness for Offsite and Alternate-ac Power

a. Inspection Scope

The inspectors performed a review of the licensees preparations for summer weather for

selected systems, including conditions that could lead to loss-of-offsite power and

conditions that could result from high temperatures. The inspectors reviewed the

licensees procedures affecting these areas and the communications protocols between

the transmission system operator and the plant to verify that the appropriate information

was being exchanged when issues arose that could affect the offsite power system.

Examples of aspects considered in the inspectors review included:

  • The coordination between the transmission system operator and the plant during

off-normal or emergency events

  • The explanations for the events
  • The estimates of when the offsite power system would be returned to a normal

state

  • The notifications from the transmission system operator to the plant when the

offsite power system was returned to normal

During the inspection, the inspectors focused on plant-specific design features and the

licensees procedures used to mitigate or respond to adverse weather conditions.

Additionally, the inspectors reviewed the Final Safety Analysis Report and performance

requirements for systems selected for inspection, and verified that operator actions were

appropriate as specified by plant-specific procedures. Specific documents reviewed

during this inspection are listed in the attachment. The inspectors also reviewed

corrective action program items to verify that the licensee was identifying adverse

weather issues at an appropriate threshold and entering them into their corrective action

program in accordance with station corrective action procedures. The inspectors

reviews focused specifically on the following plant systems:

-5- Enclosure

  • Station startup transformers
  • Uninterruptible power supplies

These activities constitute completion of one readiness for summer weather affect on

offsite and alternate ac power sample as defined in Inspection Procedure 71111.01-05.

b. Findings

No findings of significance were identified.

1R04 Equipment Alignments (71111.04)

.1 Partial Walkdown

a. Inspection Scope

The inspectors a performed partial system walkdown of the following risk-significant

system:

The inspectors selected this system based on its risk significance relative to the reactor

safety cornerstones at the time it was inspected. The inspectors attempted to identify

any discrepancies that could affect the function of the system and, therefore, potentially

increase risk. The inspectors reviewed applicable operating procedures, system

diagrams, Final Safety Analysis Report, technical specification requirements,

administrative technical specifications, outstanding work orders, condition reports, and

the impact of ongoing work activities on redundant trains of equipment in order to identify

conditions that could have rendered the system incapable of performing their intended

functions. The inspectors also walked down accessible portions of the system to verify

system components and support equipment were aligned correctly and operable. The

inspectors examined the material condition of the components and observed operating

parameters of equipment to verify that there were no obvious deficiencies. The

inspectors also verified that the licensee had properly identified and resolved equipment

alignment problems that could cause initiating events or impact the capability of

mitigating systems or barriers and entered them into the corrective action program with

the appropriate significance characterization. Specific documents reviewed during this

inspection are listed in the attachment.

These activities constitute completion of one partial system walkdown sample as defined

in Inspection Procedure 71111.04-05.

b. Findings

No findings of significance were identified.

-6- Enclosure

.2 Complete Walkdown

a. Inspection Scope

On June 3, 2009, the inspectors performed a complete system alignment inspection of

the containment spray system Train B to verify the functional capability of the system.

The inspectors selected this system because it was considered both safety-significant

and risk-significant in the licensees probabilistic risk assessment. The inspectors

walked down the system to review mechanical and electrical equipment line ups,

electrical power availability, system pressure and temperature indications, as

appropriate, component labeling, component lubrication, component and equipment

cooling, hangers and supports, operability of support systems, and to ensure that

ancillary equipment or debris did not interfere with equipment operation. The inspectors

reviewed a sample of past and outstanding work orders to determine whether any

deficiencies significantly affected the system function. In addition, the inspectors

reviewed the corrective action program database to ensure that system

equipment-alignment problems were being identified and appropriately resolved.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one complete system walkdown sample as

defined in Inspection Procedure 71111.04-05

b. Findings

No findings of significance were identified.

1R05 Fire Protection (71111.05)

.1 Quarterly Fire Inspection Tours

a. Inspection Scope

The inspectors conducted fire protection walkdowns that were focused on availability,

accessibility, and the condition of firefighting equipment in the following risk-significant

plant areas:

  • April 28, 2009, reactor auxiliary building fire Zones 33, 35, and 36
  • May 11, 2009, reactor auxiliary building fire Zones 2, 15, 16, and 23
  • May 27, 2009, reactor auxiliary building fire Zones 17, 18, and 19
  • May 27, 2009, reactor auxiliary building fire Zones 20, and 21

The inspectors reviewed areas to assess if licensee personnel had implemented a fire

protection program that adequately controlled combustibles and ignition sources within

the plant; effectively maintained fire detection and suppression capability; maintained

passive fire protection features in good material condition; and had implemented

adequate compensatory measures for out of service, degraded or inoperable fire

protection equipment, systems, or features, in accordance with the licensees fire plan.

The inspectors selected fire areas based on their overall contribution to internal fire risk

-7- Enclosure

as documented in the plants Individual Plant Examination of External Events with later

additional insights, their potential to affect equipment that could initiate or mitigate a plant

transient, or their impact on the plants ability to respond to a security event. Using the

documents listed in the attachment, the inspectors verified that fire hoses and

extinguishers were in their designated locations and available for immediate use; that

fire detectors and sprinklers were unobstructed, that transient material loading was

within the analyzed limits; and fire doors, dampers, and penetration seals appeared to

be in satisfactory condition. The inspectors also verified that minor issues identified

during the inspection were entered into the licensees corrective action program.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of four quarterly fire-protection inspection samples

as defined in Inspection Procedure 71111.05-05.

b. Findings

No findings of significance were identified.

1R06 Flood Protection Measures (71111.06)

a. Inspection Scope

The inspectors reviewed the Final Safety Analysis Report, the flooding analysis, and

plant procedures to assess susceptibilities involving internal flooding; reviewed the

corrective action program to determine if licensee personnel identified and corrected

flooding problems; inspected underground bunkers/manholes to verify the adequacy of

sump pumps, level alarm circuits, cable splices subject to submergence, and drainage

for bunkers/manholes; and verified that operator actions for coping with flooding can

reasonably achieve the desired outcomes. The inspectors also walked down the area

listed below to verify the adequacy of equipment seals located below the flood line, floor

and wall penetration seals, watertight door seals, common drain lines and sumps, sump

pumps, level alarms, and control circuits, and temporary or removable flood barriers.

Specific documents reviewed during this inspection are listed in the attachment.

  • July 1, 2009, review of Operating Experience Smart Sample OpESS FY2007-02,

Flooding Vulnerabilities Due to Inadequate Design and Conduit / Hydrostatic

Seal Barrier Concerns, in the switchgear Train B room

These activities constitute completion of one flood protection measure inspection sample

as defined in Inspection Procedure 71111.06-05.

b. Findings

No findings of significance were identified.

-8- Enclosure

1R11 Licensed Operator Requalification Program (71111.11)

a. Inspection Scope

On May 28, 2009, the inspectors observed a crew of licensed operators in the plants

simulator to verify that operator performance was adequate, evaluators were identifying

and documenting crew performance problems, and training was being conducted in

accordance with licensee procedures. The inspectors evaluated the following areas:

  • Licensed operator performance
  • Crews clarity and formality of communications
  • Crews ability to take timely actions in the conservative direction
  • Crews prioritization, interpretation, and verification of annunciator alarms
  • Crews correct use and implementation of abnormal and emergency procedures
  • Control board manipulations
  • Oversight and direction from supervisors
  • Crews ability to identify and implement appropriate technical specification

actions and emergency plan actions and notifications

The inspectors compared the crews performance in these areas to pre-stablished

operator action expectations and successful critical task completion requirements.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one quarterly licensed-operator requalification

program sample as defined in Inspection Procedure 71111.11.

b. Findings

No findings of significance were identified.

1R12 Maintenance Effectiveness (71111.12Q)

a. Inspection Scope

The inspectors evaluated degraded performance issues involving the following risk

significant systems:

  • June 29, 2009, review of Operating Experience Smart

Sample OpESS FY2008-01, Negative trend and Recurring Events Involving

Emergency Diesel Generators

-9- Enclosure

The inspectors reviewed events such as where ineffective equipment maintenance has

resulted in valid or invalid automatic actuations of engineered safeguards systems and

independently verified the licensee's actions to address system performance or condition

problems in terms of the following:

  • Implementing appropriate work practices
  • Identifying and addressing common cause failures
  • Characterizing system reliability issues for performance
  • Charging unavailability for performance
  • Trending key parameters for condition monitoring
  • Verifying appropriate performance criteria for structures, systems, and

components classified as having an adequate demonstration of performance

through preventive maintenance, as described in 10 CFR 50.65(a)(2), or as

requiring the establishment of appropriate and adequate goals and corrective

actions for systems classified as not having adequate performance, as described

in 10 CFR 50.65(a)(1)

The inspectors assessed performance issues with respect to the reliability, availability,

and condition monitoring of the system. In addition, the inspectors verified maintenance

effectiveness issues were entered into the corrective action program with the appropriate

significance characterization. Specific documents reviewed during this inspection are

listed in the attachment.

These activities constitute completion of two quarterly maintenance effectiveness

samples as defined in Inspection Procedure 71111.12-05.

b. Findings

No findings of significance were identified.

1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13)

a. Inspection Scope

The inspectors reviewed licensee personnel's evaluation and management of plant risk

for the maintenance and emergent work activities affecting risk-significant and

safety-related equipment listed below to verify that the appropriate risk assessments

were performed prior to removing equipment for work:

- 10 - Enclosure

  • April 17, 2009, replacement and calibration of power Supply 37-H for PPS

Channel B

  • April 21, 2009, planned maintenance outage of Train B emergency core cooling

systems

  • May 6, 2009, scheduled maintenance outage of high pressure safety injection

Train A

  • June 17, 2009, corrective maintenance to replace station Battery 3AB-S Cell 31

due to low individual cell voltage

The inspectors selected these activities based on potential risk significance relative to

the reactor safety cornerstones. As applicable for each activity, the inspectors verified

that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4)

and that the assessments were accurate and complete. When licensee personnel

performed emergent work, the inspectors verified that the licensee personnel promptly

assessed and managed plant risk. The inspectors reviewed the scope of maintenance

work, discussed the results of the assessment with the licensee's probabilistic risk

analyst or shift technical advisor, and verified plant conditions were consistent with the

risk assessment. The inspectors also reviewed the technical specification requirements

and inspected portions of redundant safety systems, when applicable, to verify risk

analysis assumptions were valid and applicable requirements were met. Specific

documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of four maintenance risk assessments and

emergent work control inspection samples as defined in Inspection

Procedure 71111.13-05.

b. Findings

No findings of significance were identified.

1R15 Operability Evaluations (71111.15)

a. Inspection Scope

The inspectors reviewed the following issues:

  • May 12, 2009, voiding discovered at low pressure safety injection Pump A

discharge to reactor coolant Loop 2B vent

  • May 13, 2009, multiple trips of control room emergency filtration unit Train A

percent design basis load during scheduled surveillance run

- 11 - Enclosure

The inspectors selected these potential operability issues based on the risk-significance

of the associated components and systems. The inspectors evaluated the technical

adequacy of the evaluations to ensure that technical specification operability was

properly justified and the subject component or system remained available such that no

unrecognized increase in risk occurred. The inspectors compared the operability and

design criteria in the appropriate sections of the technical specifications and Final Safety

Analysis Report to the licensees evaluations, to determine whether the components or

systems were operable. Where compensatory measures were required to maintain

operability, the inspectors determined whether the measures in place would function as

intended and were properly controlled. The inspectors determined, where appropriate,

compliance with bounding limitations associated with the evaluations. Additionally, the

inspectors also reviewed a sampling of corrective action documents to verify that the

licensee was identifying and correcting any deficiencies associated with operability

evaluations. Specific documents reviewed during this inspection are listed in the

attachment.

These activities constitute completion of three operability evaluations inspection

sample(s) as defined in Inspection Procedure 71111.15-05

b. Findings

No findings of significance were identified.

1R19 Postmaintenance Testing (71111.19)

a. Inspection Scope

The inspectors reviewed the following postmaintenance activities to verify that

procedures and test activities were adequate to ensure system operability and functional

capability:

  • April 20, 2009, replacement and calibration of power Supply 37-H for PPS

Channel B

  • April 22, 2009, replacement of diesel generator sequencer

Relay EG EREL2392-N following Part 21 recall

  • May 7, 2009, breaker and motor maintenance and relay replacement on high

pressure safety injection Pump A

  • May 13, 2009, leak test and adjustment for control room outside air intake

Valve HVC-102 following multiple trips of control room emergency filtration unit

Train A

  • May 15, 2009, replacement of a motor-operated potentiometer and adjustment of

the mechanical governor following a failed emergency diesel generator Train A

surveillance run

- 12 - Enclosure

Pump A

  • June 12, 2009, corrective maintenance to replace pump plungers and packing to

correct leaking seals on charging Pump AB in an attempt to reduce reactor

coolant system leakage

  • June 16, 2009, corrective maintenance to replace pump plungers and packing to

correct leaking seals on charging Pump B in an attempt to reduce reactor coolant

system leakage

The inspectors selected these activities based upon the structure, system, or

component's ability to affect risk. The inspectors evaluated these activities for the

following (as applicable):

  • The effect of testing on the plant had been adequately addressed; testing was

adequate for the maintenance performed

  • Acceptance criteria were clear and demonstrated operational readiness; test

instrumentation was appropriate

The inspectors evaluated the activities against the technical specifications, the Final

Safety Analysis Report, 10 CFR Part 50 requirements, licensee procedures, and various

NRC generic communications to ensure that the test results adequately ensured that the

equipment met the licensing basis and design requirements. In addition, the inspectors

reviewed corrective action documents associated with postmaintenance tests to

determine whether the licensee was identifying problems and entering them in the

corrective action program and that the problems were being corrected commensurate

with their importance to safety. Specific documents reviewed during this inspection are

listed in the attachment.

These activities constitute completion of eight postmaintenance testing inspection

samples as defined in Inspection Procedure 71111.19-05.

b. Findings

No findings of significance were identified.

1R22 Surveillance Testing (71111.22)

a. Inspection Scope

The inspectors reviewed the Final Safety Analysis Report, procedure requirements, and

technical specifications to ensure that the five surveillance activities listed below

demonstrated that the systems, structures, and/or components tested were capable of

performing their intended safety functions. The inspectors either witnessed or reviewed

- 13 - Enclosure

test data to verify that the significant surveillance test attributes were adequate to

address the following:

  • Preconditioning
  • Evaluation of testing impact on the plant
  • Acceptance criteria
  • Test equipment
  • Procedures
  • Jumper/lifted lead controls
  • Test data
  • Testing frequency and method demonstrated technical specification operability
  • Test equipment removal
  • Restoration of plant systems
  • Fulfillment of ASME Code requirements
  • Updating of performance indicator data
  • Engineering evaluations, root causes, and bases for returning tested systems,

structures, and components not meeting the test acceptance criteria were correct

  • Reference setting data

The inspectors also verified that licensee personnel identified and implemented any

needed corrective actions associated with the surveillance testing.

  • April 23, 2009, low pressure safety injection Pump B operability check
  • April 27, 2009, component cooling water in-service valve testing
  • May 8, 2009, emergency feedwater Pump A operability check

- 14 - Enclosure

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of five surveillance testing inspection sample(s) as

defined in Inspection Procedure 71111.22-05.

b. Findings

No findings of significance were identified.

Cornerstone: Emergency Preparedness

1EP1 Exercise Evaluation (71114.01)

a. Inspection Scope

The inspectors reviewed the objectives and scenario for the 2009 biennial emergency

plan exercise to determine if the exercise would acceptably test major elements of the

emergency plan. The scenario simulated a tornado touchdown on site that damaged the

turbine building, a failure of a liquid radiological waste tank, a main generator trip leading

to damage in the station switchyard causing a loss of offsite power, failures of both

emergency diesel generators leading to station blackout conditions, a large reactor

coolant system break inside containment, fission product barrier failures, core damage

from fuel overheating, a filtered and monitored radiological release to the environment

via a containment penetration failure and annulus ventilation, and a change in the

direction of the radiological release to demonstrate the licensee emergency response

organizations capability to implement their emergency plan.

The inspectors evaluated exercise performance by focusing on the risk-significant

activities of event classification, offsite notification, recognition of offsite dose

consequences, and development of protective action recommendations, in the control

room simulator and the following dedicated emergency response facilities:

  • Operations Support Center
  • Emergency Operations Facility

The inspectors also assessed recognition of, and response to, abnormal and emergency

plant conditions, the transfer of decision making authority and emergency function

responsibilities between facilities, onsite and offsite communications, protection of

emergency workers, emergency repair evaluation and capability, and the overall

implementation of the emergency plan to protect public health and safety and the

environment. The inspectors reviewed the current revision of the facility emergency

plan, emergency plan implementing procedures associated with operation of the

licensees emergency response facilities, procedures for the performance of associated

emergency functions, and other documents as listed in the attachment to this report.

- 15 - Enclosure

The inspectors compared the observed exercise performance with the requirements in

the facility emergency plan, 10 CFR 50.47(b), 10 CFR Part 50, Appendix E, and with the

guidance in the emergency plan implementing procedures and other federal guidance.

The inspectors attended the postexercise critiques in each emergency response facility

to evaluate the initial licensee self-assessment of exercise performance. The inspectors

also attended a subsequent formal presentation of critique items to plant management.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one sample as defined in Inspection

Procedure 71114.01-05.

b. Findings

Introduction. The inspectors identified a noncited violation of 10 CFR 50.47(b)(10) for

the licensees failure to develop and have in place guidelines for the choice of protective

actions during an emergency that were consistent with federal guidance. Specifically,

the licensees guidelines for extending existing protective action recommendations into

additional geographical areas of the emergency planning zone under conditions of

changing wind vectors were not consistent with the guidance of EPA-400-R-92-001,

AManual of Protective Action Guides and Protective Actions for Nuclear Incidents.@

Description. The inspectors identified that Procedure EP-2-052, AProtective Action

Guidelines,@ Revision 20, allows the licensee to generate evacuation protective action

recommendations for members of the general public in areas of the emergency planning

zone where radiological protective action guides are not exceeded. Specifically,

inspectors determined that, with an existing initial protective action recommendation

based on plant conditions, the licensee's practice when changes occur in the wind

direction vector were to recommend to offsite authorities in any circumstance additional

protective actions to the same downwind distance for every geographical area traversed

by the wind as previously recommended. The recommendations would be done without

considering in the decision process whether EPA protective action guides were

exceeded in the newly-affected areas. The licensees practices result in unnecessary

recommendations for protective actions in areas where valid dose projections show

federal protective action guides are not exceeded, and may expose members of the

public to unjustified risks.

The inspectors determined the licensee has adopted a prompt protective action scheme

based on EPA-400-R-92-001, AManual of Protective Action Guides and Protective

Actions for Nuclear Incidents,@ as described by:

Section 6.6.1.2, Offsite Protective Action Recommendations, states, in part, the

set of guidelines, based on dose projections, is consistent with both EPA

protective action guidelines and with the protective action guidelines of the State

of Louisiana Peacetime Radiological Response Plan, that guidelines will be used

to minimize risks for an accident and that, when total effective dose equivalent

- 16 - Enclosure

projected dose is less than 1 rem or to the projected committed dose equivalent

thyroid is less than 5 rem, no immediate actions are necessary.

  • Procedure EP-2-052, AProtective Action Guidelines,@ Revision 20, states in

Section 1.0 the purpose is to provide guidance for protective action

decisionmaking with respect to the EPA Protective Action Guidelines, and in

Section 5.2.1.3, that if dose projection information is available, then use

Attachment 7.2 or equivalent computerized methods which assess the projected

radiation dose to modify the initial General Emergency protective actions as

necessary.

The inspectors reviewed the licensees Emergency Plan and emergency plan

implementing procedure for making protective action recommendations to offsite

authorities, and discussed with licensee emergency preparedness staff the licensees

expectations and practices for making protective action recommendations under

conditions of changing wind direction and radiological severity. The inspectors were

informed by the licensees emergency preparedness management that their practice

with regard to changing wind direction was to always recommend extending existing

protective actions to adjacent geographical areas affected by the new wind vector(s) to

the same downwind distance as in previously-affected areas. The licensee would make

this automatic extension of existing protective action recommendations without

considering dose projection results, even when valid dose projections were available

that showed protective action guides were not exceeded along the new wind vector(s).

The inspectors concluded that the licensees practice of always recommending to offsite

authorities the extension of protective actions to the same downwind distance as existing

recommendations was not in accordance with the guidance of EPA-400-R-92-001,

because the licensee did not modify initial General Emergency protective actions based

on EPA protective action guides when valid dose projection information was available.

The inspectors determined that the licensee performed periodic dose assessments to

assess the impact of a radiological release on the emergency planning zone as

meteorological and radiological conditions change. The inspectors determined the

licensee's practices under conditions of changing wind direction and release severity

would always result in appropriate protective action recommendations to offsite

authorities for geographical areas in the emergency planning zone where radiological

risk to the public exists (that is, where protective action guides are exceeded), but also

could result in recommendations to evacuate geographical areas where radiological risk

is determined not to exist (that is, where protective guides are not exceeded).

Analysis. Licensee practices resulting in recommending to offsite authorities protective

actions for the public in geographical areas of the emergency planning zone where valid

dose assessment has not identified that protective action guides are projected to be

exceeded was a performance deficiency, and it was within the licensees ability to

foresee and correct, and could have been prevented. The finding was more than minor

because it was not similar to the examples of Manual Chapter 0612, Appendix E, and

has the potential to impact public safety because unnecessary protective actions may

expose members of the public to an unjustified risk. The finding was associated with the

- 17 - Enclosure

emergency response organization attributes of 50.47(b) planning standards and training.

The finding affects the emergency preparedness cornerstone objective because

recommendations to offsite authorities to take protective actions in areas where

protective action guides were not exceeded affects the offsite authoritys ability to protect

the health and safety of the public, and may have resulted in unnecessary risk to the

public. This finding was evaluated using the emergency preparedness significance

determination process and was determined to have very low safety significance (Green)

because it was a failure to comply with NRC requirements, was associated with

emergency preparedness planning standard 50.47(b)(10), was associated with a risk

significant planning standard as defined in Manual Chapter 0609, Appendix B,

Section 2.0, and was not a risk significant planning standard functional failure or a risk

significant planning standard degraded function because appropriate protective action

recommendations would be issued for all geographical areas of the plume phase

emergency planning zone where protective action guides are exceeded. The finding

was evaluated as not having a crosscutting aspect.

Enforcement. Title 10 of the Code of Federal Regulations, 50.47(b)(10) states, in part,

that guidelines for the licensees choice of protective actions during an emergency,

consistent with federal guidance, are developed and in place.Section IV(B) of Part 50,

Appendix E, requires, in part, that a licensee describe the basis for determining when

and what type of protective measures should be considered outside the site boundary.

Federal guidance for the choice of protective actions during an emergency is described

in EPA-400-R-92-001. Section 1.4 of EPA-400-R-92-001 states that protective action

guides are the approximate levels at which protective measures are justified.

Section 2.3.1 of EPA-400-R-92-001 states that evacuation is seldom justified at

projected radiation doses less than one rem of total effective dose equivalent.

Contrary to the above, the licensee did not develop and have in place guidelines for the

choice of protective actions during an emergency that were consistent with federal

guidance. The licensees guidelines for extending initial General Emergency protective

action recommendations under conditions of changing wind direction vectors were not

consistent with EPA-400-R-92-001 guidance. Specifically, the licensees process of

automatically extending existing offsite protective action recommendations without

evaluating dose assessment information did not provide justification for recommending

protective actions in geographical areas where valid dose projections show federal

protective action guides are not exceeded. Because this failure was of very low safety

significance and has been entered into the licensee=s corrective action system

(Condition Report CR-WF3-2009-03256), this violation is being treated as a noncited

violation, consistent with Section VI.A of the NRC Enforcement Policy:

NCV 05000382/2009003-1, Licensee Practices Result in Protective Action

Recommendations for Areas Where Protective Action Guides Are Not Exceeded.

- 18 - Enclosure

Cornerstone: Emergency Preparedness

1EP4 Emergency Action Level and Emergency Plan Changes (71114.04)

a. Inspection Scope

The inspector performed an in-office review of Revision 37 to the Waterford 3 Steam

Electric Station Emergency Plan submitted May 12, 2009. This revision added security

threats to the bases of the four emergency classifications, revised the [offsite]

Notification Message Form to characterize radiological releases as being below or above

federally-approved operating limits, added detail about the functions of the Reactor

Auxiliary Building instrumentation laboratory, increased the number of available voice

communications channels from 5 to 23, increased the number of offsite emergency

warning sirens from 72 to 73, revised definitions used in the emergency plan, updated

station position titles and service vendors, and made minor editorial changes.

This revision was compared to its previous revision, to the criteria of NUREG-0654,

Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and

Preparedness in Support of Nuclear Power Plants, Revision 1, and to the standards in

10 CFR 50.47(b), to determine if the revision adequately implemented the requirements

of 10 CFR 50.54(q). This review was not documented in a safety evaluation report and

did not constitute approval of the licensees changes; therefore, this revision is subject to

future inspection.

These activities constitute completion of one sample as defined in Inspection

Procedure 71114.04-05.

b. Findings

No findings of significance were identified.

4. OTHER ACTIVITIES

4OA1 Performance Indicator Verification (71151)

.1 Data Submission Issue

a. Inspection Scope

The inspectors performed a review of the data submitted by the licensee for the first

quarter 2009 performance indicators for any obvious inconsistencies prior to its public

release in accordance with Inspection Manual Chapter 0608, Performance Indicator

Program.

This review was performed as part of the inspectors normal plant status activities and,

as such, did not constitute a separate inspection sample.

- 19 - Enclosure

b. Findings

No findings of significance were identified.

.2 Safety System Functional Failures

a. Inspection Scope

The inspectors sampled licensee submittals for the safety system functional failures

performance indicator for the period from the first quarter 2008 through the first

quarter 2009. To determine the accuracy of the performance indicator data reported

during those periods, performance indicator definitions and guidance contained in NEI

Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 5,

and NUREG-1022, Event Reporting Guidelines 10 CFR 50.72 and 50.73, definitions

and guidance were used. The inspectors reviewed the licensees operator narrative

logs, operability assessments, maintenance rule records, maintenance work orders,

issue reports, event reports, and NRC integrated inspection reports for the period of

March 2008 through March 2009 to validate the accuracy of the submittals. The

inspectors also reviewed the licensees issue report database to determine if any

problems had been identified with the performance indicator data collected or

transmitted for this indicator and none were identified. Specific documents reviewed are

described in the attachment to this report.

These activities constitute completion of one safety system functional failures sample as

defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

.3 Mitigating Systems Performance Index - Emergency ac Power System

a. Inspection Scope

The inspectors sampled licensee submittals for the mitigating systems performance

index - emergency ac power system performance indicator for the period from the first

quarter 2008 through the first quarter 2009. To determine the accuracy of the

performance indicator data reported during those periods, performance indicator

definitions and guidance contained in NEI Document 99-02, Regulatory Assessment

Performance Indicator Guideline, Revision 5, was used. The inspectors reviewed the

licensees operator narrative logs, mitigating systems performance index derivation

reports, issue reports, event reports, and NRC integrated inspection reports for the

period of March 2008 through March 2009 to validate the accuracy of the submittals.

The inspectors reviewed the mitigating systems performance index component risk

coefficient to determine if it had changed by more than 25 percent in value since the

previous inspection, and if so, that the change was in accordance with applicable NEI

guidance. The inspectors also reviewed the licensees issue report database to

determine if any problems had been identified with the performance indicator data

- 20 - Enclosure

collected or transmitted for this indicator and none were identified. Specific documents

reviewed are described in the attachment to this report.

These activities constitute completion of one safety system functional failures sample as

defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

.4 Mitigating Systems Performance Index - High Pressure Injection Systems

a. Inspection Scope

The inspectors sampled licensee submittals for the mitigating systems performance

index - high pressure injection systems performance indicator for the period from the first

quarter 2008 through the first quarter 2009. To determine the accuracy of the

performance indicator data reported during those periods, performance indicator

definitions and guidance contained in NEI Document 99-02, Regulatory Assessment

Performance Indicator Guideline, Revision 5, was used. The inspectors reviewed the

licensees operator narrative logs, issue reports, mitigating systems performance index

derivation reports, event reports, and NRC integrated inspection reports for the period of

March 2008 through March 2009 to validate the accuracy of the submittals. The

inspectors reviewed the mitigating systems performance index component risk

coefficient to determine if it had changed by more than 25 percent in value since the

previous inspection, and if so, that the change was in accordance with applicable NEI

guidance. The inspectors also reviewed the licensees issue report database to

determine if any problems had been identified with the performance indicator data

collected or transmitted for this indicator and none were identified. Specific documents

reviewed are described in the attachment to this report.

These activities constitute completion of one safety system functional failures sample as

defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

.5 Drill/Exercise Performance (EP01)

a. Inspection Scope

The inspectors sampled licensee submittals for the Drill and Exercise Performance,

performance indicator for the period from July 2008 through March 2009. To determine

the accuracy of the performance indicator data reported during those periods,

performance indicator definitions and guidance contained in Nuclear Energy Institute

Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 5,

was used. The inspectors reviewed the licensees records associated with the

- 21 - Enclosure

performance indicator to verify that the licensee accurately reported the indicator in

accordance with relevant procedures and the Nuclear Energy Institute guidance.

Specifically, the inspectors reviewed licensee records and processes including

procedural guidance on assessing opportunities for the performance indicator;

assessments of performance indicator opportunities during predesignated control room

simulator training sessions, performance during the 2007 biennial exercise, and

performance during other drills. Specific documents reviewed are described in the

attachment to this report.

These activities constitute completion of the drill/exercise performance sample as

defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

.6 Emergency Response Organization Drill Participation (EP02)

a. Inspection Scope

The inspectors sampled licensee submittals for the Emergency Response Organization

Drill Participation performance indicator for the period from July 2008 through March

2009. To determine the accuracy of the performance indicator data reported during

those periods, performance indicator definitions and guidance contained in Nuclear

Energy Institute Document 99-02, Regulatory Assessment Performance Indicator

Guideline, Revision 5, was used. The inspectors reviewed the licensees records

associated with the performance indicator to verify that the licensee accurately reported

the indicator in accordance with relevant procedures and the Nuclear Energy Institute

guidance. Specifically, the inspectors reviewed licensee records and processes

including procedural guidance on assessing opportunities for the performance indicator,

rosters of personnel assigned to key emergency response organization positions, twelve

selected emergency responder training records, and a sample of eight exercise

participation records. Specific documents reviewed are described in the attachment to

this report.

These activities constitute completion of the emergency response organization drill

participation sample as defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

- 22 - Enclosure

.7 Alert and Notification System (EP03)

a. Inspection Scope

The inspectors sampled licensee submittals for the Alert and Notification System

performance indicator for the period from July 2008 through March 2009. To determine

the accuracy of the performance indicator data reported during those periods,

performance indicator definitions and guidance contained in Nuclear Energy Institute

Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 5,

was used. The inspectors reviewed the licensees records associated with the

performance indicator to verify that the licensee accurately reported the indicator in

accordance with relevant procedures and the Nuclear Energy Institute guidance.

Specifically, the inspectors reviewed licensee records and processes including

procedural guidance on assessing opportunities for the performance indicator and the

results of bimonthly alert notification system operability tests. Specific documents

reviewed are described in the attachment to this report.

These activities constitute completion of the alert and notification system sample as

defined in Inspection Procedure 71151-05.

b. Findings

No findings of significance were identified.

4OA2 Identification and Resolution of Problems (71152)

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency

Preparedness, Public Radiation Safety, Occupational Radiation Safety, and

Physical Protection

.1 Routine Review of Identification and Resolution of Problems

a. Inspection Scope

As part of the various baseline inspection procedures discussed in previous sections of

this report, the inspectors routinely reviewed issues during baseline inspection activities

and plant status reviews to verify that they were being entered into the licensees

corrective action program at an appropriate threshold, that adequate attention was being

given to timely corrective actions, and that adverse trends were identified and

addressed. The inspectors reviewed attributes that included: the complete and

accurate identification of the problem; the timely correction, commensurate with the

safety significance; the evaluation and disposition of performance issues, generic

implications, common causes, contributing factors, root causes, extent of condition

reviews, and previous occurrences reviews; and the classification, prioritization, focus,

and timeliness of corrective. Minor issues entered into the licensees corrective action

program because of the inspectors observations are included in the attached list of

documents reviewed.

- 23 - Enclosure

These routine reviews for the identification and resolution of problems did not constitute

any additional inspection samples. Instead, by procedure, they were considered an

integral part of the inspections performed during the quarter and documented in

Section 1 of this report.

b. Findings

No findings of significance were identified.

.2 Daily Corrective Action Program Reviews

a. Inspection Scope

In order to assist with the identification of repetitive equipment failures and specific

human performance issues for follow-up, the inspectors performed a daily screening of

items entered into the licensees corrective action program. The inspectors

accomplished this through review of the stations daily corrective action documents.

The inspectors performed these daily reviews as part of their daily plant status

monitoring activities and, as such, did not constitute any separate inspection samples.

b. Findings

No findings of significance were identified.

.3 Semi-Annual Trend Review

a. Inspection Scope

The inspectors performed a review of the licensees corrective action program and

associated documents to identify trends that could indicate the existence of a more

significant safety issue. The inspectors focused their review on repetitive equipment

issues, but also considered the results of daily corrective action item screening

discussed in Section 4OA2.2, above, licensee trending efforts, and licensee human

performance results. The inspectors nominally considered the period from October 2008

through June 2009, although some examples expanded beyond those dates where the

scope of the trend warranted.

The inspectors also included issues documented outside the normal corrective action

program in major equipment problem lists, repetitive and/or rework maintenance lists,

departmental problem/challenges lists, system health reports, quality assurance

audit/surveillance reports, self-assessment reports, and maintenance rule assessments.

The inspectors compared and contrasted their results with the results contained in the

licensees corrective action program trending reports. Corrective actions associated with

a sample of the issues identified in the licensees trending reports were reviewed for

adequacy.

These activities constitute completion of one single semi-annual trend inspection sample

as defined in Inspection Procedure 71152-05.

- 24 - Enclosure

b. Findings

Introduction. The inspectors identified a noncited violation of 10 CFR Part 50,

Appendix B, Criterion XVI (Corrective Action), for the failure to promptly correct

conditions adverse to quality. The licensee had documented several conditions adverse

to quality and then transferred the concerns to other condition reports. Then, the

licensee closed those condition reports without addressing the concerns. Identified

conditions included (1) the Train B 125 Vac discharge test data indicated a loose battery

connection but the battery was permitted to pass the test anyway; (2) the root cause

determination for the failed battery was focused on the statements of one person and

failed to address other information; (3) the root cause determination failed to address

conflicting information; and (4) the root cause determination failed to properly address

other potential causes for the inoperable battery, such as tampering.

Description. On December 17, 2008, the NRC described to the licensee several

concerns with a root cause analysis for a significant condition adverse to quality (Train B

125 Vdc battery failure identified on September 2, 2008). Specifically, the inspectors

identified that (1) the root cause determination for the failed battery was focused on the

statements of one person and failed to address other information; (2) the root cause

determination failed to address conflicting information from different individuals;

and (3) the root cause determination failed to properly address other potential causes for

the inoperable battery, such as tampering. These concerns were entered into the

corrective action process as Condition Report CR-WF3-2008-5852. This condition

report was closed out to Condition Report CR-WF3-2009-4179, Corrective Action CA-54,

which was intended to correct the conditions. However, this condition report was

subsequently closed without addressing the concerns.

On January 6, 2009, the licensee identified that the Train B 125 Vac discharge test data

(May 27, 2008) indicated a loose battery connection but the battery was permitted to

pass the test anyway. Several months later, the licensee found that the loose

connection had rendered the battery inoperable. That condition was documented in

Condition Report CR-WF3-2009-0069. This condition report was subsequently closed

out to Condition Report CR-WF3-2009-4179, Corrective Action CA-55, which was

intended to address the condition. However, the corrective action was closed without

addressing the concern.

NOTE: Additional NRC followup to the failed station battery will be documented

in NRC Inspection Report 05000382/2009008.

On February 9, 2009, the inspectors identified that the licensee had closed Condition

Report CR-WF3-2008-4179 but had not corrected the conditions that were transferred to

the document from Condition Reports CR-WF3-2008-5852 and CR-WF3-2009-0069.

The licensee entered this new finding into their corrective action process as Condition

Report CR-WF3-2009-0697.

- 25 - Enclosure

To determine the extent of condition, the licensee reviewed the corrective actions for

Condition Report CR-WF3-2008-4179 and determined that an additional seven

corrective actions had been closed out without fully being answered. These additional

examples were entered into the licensees corrective action program as Condition

Report CR-WF3-2009-1177. The licensee characterized the problem as a significant

condition adverse to quality. Subsequently, the licensees extent of condition review

identified an additional 30 examples where corrective actions were inappropriately

closed without correcting the identified conditions in the past 14 months.

Analysis. The failure to correct conditions adverse to quality was a performance

deficiency. The finding was more than minor because, if left uncorrected, it would

become a more significant safety concern. For example, the failure to include

acceptance criteria in the battery discharge test (intended to identify and correct loose

battery connections) could result in another inoperable 125 Vdc battery for an extended

period. The inspectors evaluated the finding using Inspection Manual Chapter 0609,

Significance Determination Process, Phase 1 Screening Worksheet and determined that

the finding was of very low risk significance because it did not result in another battery

becoming inoperable or nonfunctional. This finding had a crosscutting aspect in the area

of Human Performance (Work Practices Component) because plant personnel failed to

effectively use human error prevention techniques, such as self and peer checking,

when transferring concerns between condition reports H.4(a).

Enforcement. In accordance with 10 CFR Part 50, Appendix B, Criterion XVI,

Corrective Action, requires, in part, that measures be established to assure that

conditions adverse to quality are promptly identified and corrected. On December 17,

2008, and on January 6, 2009, four conditions adverse to quality were identified by the

inspectors and the licensee, as noted in the body of this report. Contrary to the above,

the licensee failed to correct the conditions adverse to quality, in that the concerns were

transferred to another condition report and then closed without action. Because this

violation was of very low safety significance and was entered in the corrective action

program as Condition Report CR-WF3-2009-0697, this violation is being treated as a

noncited violation, consistent with Section VI.A of the NRC Enforcement Policy:

NCV 05000382/2009002-02, Failure to Correct Several Conditions Adverse to Quality.

.4 Selected Issue Follow-up Inspection

a. Inspection Scope

During a review of items entered in the licensees corrective action program, the

inspectors reviewed operator workarounds and burdens and conducted a review of

conditions surrounding the premature failure of the Train B 125 Vdc station battery. The

inspectors considered the following during the review of the licensees actions:

(1) complete and accurate identification of problems in a timely manner; (2) evaluation

and disposition of operability/reportability issues; (3) consideration of extent of condition,

generic implications, common cause, and previous occurrences; (4) classification and

prioritization of the resolution of the problem; (5) identification of root and contributing

- 26 - Enclosure

causes of the problem; (6) identification of corrective actions; and (7) completion of

corrective actions in a timely manner.

These activities constitute completion of two in-depth problem identification and

resolution samples as defined in Inspection Procedure 71152-05.

b. Findings

Introduction. The inspectors identified a green noncited violation of 10 CFR Part 50,

Appendix B, Criterion XVI (Corrective Actions), because the licensee failed to identify the

cause for a significant condition adverse to quality. The Train B 125 Vdc battery bank

failed to pass a technical specification surveillance required discharge test during a

Spring 2008 outage. The root cause procedure required that the licensee sequester the

battery in a controlled area so that vital information related to the failure could be

obtained. However, the licensee disposed of the battery instead. When questions arose

concerning the specified failure cause (impurities in the battery materials), the licensee

was unable to provide objective evidence to support the conclusion. Had the licensee

obtained objective evidence to support their conclusion that impurities caused the

battery failure, a 10 CFR Part 21 report may have been required. The licensee replaced

the battery and planned to replace similar batteries in the other two trains during the next

refueling outage.

Description. On May 16, 2008, during a refueling outage, the licensee conducted a

technical specification required performance test of the safety-related Train B, 125 Vdc

station battery. The licensee determined that the battery capacity was 86.25 percent

from this test. This was an unexpected result, as the licensee had predicted a capacity

near 100 percent.

The licensee consulted with the battery vendor (C&D). The vendor advised the licensee

that the licensees testing method may be inappropriate and suggested changes. The

licensee performed a second test of the battery on May 22 and noted that the capacity

was 71.6 percent. Technical Specification Surveillance Requirement 4.8.2.1.d required

that the battery capacity be verified to be at least 80 percent of the manufacturers rating

every 60 months, when subjected to a discharge test. The failure to pass the technical

specification surveillance requirement rendered the battery inoperable. The battery had

a vendor specified 20- year service life but had only lasted a little more than 15 years.

The licensee promptly procured a new battery and replaced the failed Train B battery.

The only extent of condition review that the licensee performed was to verify that the

other station batteries were from different manufacturing lots. At the time of the

surveillance failure, the plant was in an outage and was relying on the other station

batteries to meet the requirements for the technical specification required minimum

equipment.

In response to the battery failure, the licensee performed a root cause analysis, as

documented in Condition Report WF3-2008-02431, dated August 12, 2008. The

licensee considered the battery failure a significant condition adverse to quality. The

licensee concluded that the battery had most likely failed the test because of impurities

- 27 - Enclosure

introduced during manufacturing. The licensee reached this conclusion based on the

elimination of other potential causes that they had considered. The inspectors

determined that the licensee did not obtain vendor assistance or input. The licensee did

not perform testing to verify that impurities were actually present in the battery. Then,

the licensee disposed of the battery. No cells from the defective battery train were

returned to the vendor for analysis.

On July 30, 2009, licensee senior management decided to reassess the root cause

because they no longer believed that it involved a manufacturing defect. The inspectors

identified that the licensee had failed to meet the requirements of 10 CFR Part 50,

Appendix B, Criterion XVI (Corrective Actions), for the battery failure. This requirement

specifies, in part, that the cause of significant conditions adverse to quality be

determined and corrective actions taken to preclude repetition. In this instance, since

the licensee disposed of the battery prior to performing a thorough analysis of the failed

components, the licensee could not adequately determine the cause.

The inspectors also noted that the licensee had failed to follow their root cause

procedure concerning analysis of failed components. Corporate Procedure EN-LI-118,

Root Cause Analysis Process, Revision 7, discusses actions to be performed during

the course of performing a root cause analysis. Section 5, step [3](a)(3) required the

licensee to initiate physical evidence collection and move items to a controlled area to

prevent tampering or loss. For the failed battery, the licensee did not complete these

actions.

Additionally, had the licensee conclusively determined that battery failure was caused by

impurities introduced during the manufacturing process, a 10 CFR Part 21, Reporting of

Defects and Noncompliance, may have been required. This regulation requires

licensees and vendors to notify the NRC of defects in safety-related components that

could involve a substatial safety hazard. If the failure did involve a defect, the inspectors

believed that a subsafety hazard would exist due to the rapid degradation that occurred

within a single surveillane interval making the failure undetectable. The NRC would then

notify licensees that could be affected by the condition so that they could take

appropriate corrective measures. In this instance, however, since the cause of the

failure was not actually known, the NRC could not evaluate the condition or further

consider a generic communication.

Analysis. The failure to identify the cause for a significant condition adverse to quality

was a performance deficiency. The finding was more than minor because, if left

uncorrected, it could lead to a more significant safety concern. Specifically, since the

cause of the battery failure was not definitively found, the licensee may not have taken

corrective actions to prevent other battery failures. Using the Inspection Manual

Chapter 0609, Significance Determination Process, Phase 1 Screening Worksheet, the

finding was of very low risk significance because it did not actually cause the loss of

operability or functionality of another 125 Vdc battery at the time of the inspection. This

finding had a crosscutting aspect in the area of Problem Identification and Resolution

(Corrective Action Program Component) because the licensee failed to thoroughly

evaluate the need to keep the battery prior to disposal P.1(c).

- 28 - Enclosure

Enforcement. Title 10 CFR Part 50, Appendix B, Criterion XVI (Corrective Actions),

requires, in part, that Measures shall be established to assure that conditions adverse

to quality . . . are promptly identified and corrected. In the case of significant conditions

adverse to quality, the measures shall assure that the cause of the condition is

determined and corrective action taken to preclude repetition. Contrary to the above, as

of July 7, 2009, the licensee had identified a significant condition adverse to quality

(125 Vdc battery train failure on May 22, 2008) but had not determined the cause of the

condition and therefore could not specify actions to preclude repetition. Because this

violation was of very low safety significance and was entered in the corrective action

program as Condition Report CR-WF3-2009-2846, this violation is being treated as a

noncited violation, consistent with Section VI.A of the NRC Enforcement Policy:

NCV 05000382/2009003-03, Failure to Determine the Cause of a 125 Vdc Battery

Failure.

4OA5 Other Activities

.1 Quarterly Resident Inspector Observations of Security Personnel and Activities

a. Inspection Scope

During the inspection period, the inspectors performed observations of security force

personnel and activities to ensure that the activities were consistent with Waterford

Steam Electric Station security procedures and regulatory requirements relating to

nuclear plant security. These observations took place during both normal and off-normal

plant working hours.

These quarterly resident inspector observations of security force personnel and activities

did not constitute any additional inspection samples. Rather, they were considered an

integral part of the inspectors normal plant status review and inspection activities.

b. Findings

No findings of significance were identified.

4OA6 Meetings

Exit Meeting Summary

On May 27, 2009, the inspector conducted a telephonic exit meeting to present the results of

the in-office inspection of changes to the licensees emergency plan to Mr. J. Lewis, Manager,

Emergency Preparedness, and other members of the licensees staff. The licensee

acknowledged the issues presented.

On June 26, 2009, the inspectors presented the results of the inspection of the onsite

emergency preparedness exercise to Mr. J. Kowalewski, Site Vice President, and other

members of the licensees staff. The licensee acknowledged the issues presented. The

inspectors asked the licensee whether any materials examined during the inspection should be

- 29 - Enclosure

considered proprietary or sensitive. All identified proprietary or sensitive information examined

during the inspection had been returned to the licensee.

On June 30 and July 1, 2009, the inspectors discussed the technical and regulatory aspects of

the identified emergency preparedness noncited violation with Mr. J. Lewis, Manager,

Emergency Preparedness.

On July 20, 2009, the inspectors presented the inspection results to Mr. Joe Kowalewski, Site

Vice-President, and other members of the licensee staff. A followup telephonic exit was

conducted on August 10 with Mr. Joe Kowalewski and other members of the licensee staff. The

licensee acknowledged the issues presented. The inspector asked the licensee whether any

materials examined during the inspection should be considered proprietary. No proprietary

information was identified.

- 30 - Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

M. Adams, Supervisor, System Engineering

S. Anders, Manager, Plant Security

B. Briner, Technical Specialist IV, Componet Engineering

K. Christian, Director, Nuclear Safety Assurance

K. Cook, Manager, Operations

C. Fugate, Assistant Manager, Operations

M. Haydel, Supervisor, Programs and Components

J. Kowalewski, Vice President of Operations

J. Lewis, Manager, Emergency Preparedness

B. Lindsey, Manager, Maintenance

M. Mason, Senior Licensing Specialist, Licensing

W. McKinney, Manager, Corrective Action and Assessments

R. Murillo, Manager, Licensing

K. Nicholas, Director, Engineering

R. Putnam, Manager, Programs and Components

J. Williams, Senior Licensing Specialist, Licensing

LIST OF ITEMS OPENED AND CLOSED

Opened and Closed

05000382/2009003-01 NCV Licensee Practices Result in Protective Action

Recommendations for Areas Where Protective Action

Guides are Not Exceeded.(Section 1EP1)05000382/2009003-02 NCV Failure to Correct Several Conditions Adverse to Quality

(Section 4OA2)05000382/2009003-03 NCV Failure to Determine the Cause of a 125 Vdc Battery

Failure (Section 4OA2)

LIST OF DOCUMENTS REVIEWED

Section 1R01: Adverse Weather Protection

CONDITION REPORTS

CR-WF3-2009-2229 CR-WF3-2009-2305 CR-WF3-2009-2306 CR-WF3-2009-2961

CR-WF3-2009-2413 CR-WF3-2009-2767 CR-WF3-2009-2307 CR-WF3-2009-2118

CR-WF3-2009-2414 CR-WF3-2009-2938 CR-WF3-2009-2326 CR-WF3-2009-0687

CR-WF3-2009-2415 CR-WF3-2009-2651 CR-WF3-2009-2343 CR-WF3-2009-0155

CR-WF3-2009-2440

A-1 Attachment

WORK ORDERS

51798176 51701184 194505 51088942

51697577 51680597 167665

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION

ENS-PL-159 Summer Reliability

OP-009-002 Emergency Diesel Generator 310

OP-006-001 Plant Distribution 305

OP-006-008 Transformer Operation 301

OP-006-009 Electrical Bus Outages 4

OP-006-005 Inverters and Distribution 302

OP-902-003 Loss of Offsite Power 6

Section 1R04: Equipment Alignment

WORK ORDERS

52021780 34838

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION

OP-009-002 Emergency Diesel Generator 308

OP-903-121 Safety Systems Quarterly IST Valve Tests 9

OP-009-001 Containment Spray 301

1R05: Fire Protection

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION

UNT-005-013 Fire Protection Program 10

OP-009-004 Fire Protecton 305

MM-004-424 Building fire Hose Station Inspection and Hose 10

Replacement

MM-007-010 Fire Extinguisher Inspection and Extinguisher 302

Replacement

FP-001-014 Duties of a Fire Watch 14

A-2 Attachment

FP-001-015 Fire Protection Impairments 302

DBD-018 Appendix R/fire Protection

Section 1R06: Flood Protection Measures

NUMBER TITLE REVISION

OP-901-521 Severe Weather and Flooding 4

OP-902-008 Functional Recovery Procedure 15

FSAR Section 3.6A.6 Flooding Analysis 14-A

FSAR Section 3.6A.6.4.1 Reactor Auxiliary Building - High Energy Pipe 14-A

Breaik

DWG - G173 Sheet 2 Sump Pump System - Reactor Auxiliary Bldg. 5

FSAR Figure 9.3-5 Reactor Auxiliary Building Drainage Sys. 4

Section 1R11: Licensed Operator Requalification Program

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION

E-68 Simulator Scenario 3

OP-901-202 Steam Generator Tube Leakage or High Activity 9

OP-901-212 Rapid Plant Power Reduction 3

OP-902-000 Standard Post Trip Actions 10

OP-902-008 Safety Function Recovery Procedure 15

Section 1R12: Maintenance Effectiveness

CONDITION REPORTS

CR-WF3-2009-2662 CR-WF3-2009-2384 CR-WF3-2009-2356 CR-WF3-2009-2355

CR-WF3-2009-2245 CR-WF3-2009-2223 CR-WF3-2009-2092 CR-WF3-2009-1356

CR-WF3-2009-1284 CR-WF3-2009-0205 CR-WF3-2009-0017 CR-WF3-2009-0016

CR-WF3-2008-5905 CR-WF3-2008-5669 CR-WF3-2008-4215 CR-WF3-2008-3210

CR-WF3-2008-3106 CR-WF3-2008-2957 CR-WF3-2008-2833 CR-WF3-2008-2756

CR-WF3-2008-2467 CR-WF3-2008-1315 CR-WF3-2008-0676 CR-WF3-2008-0613

CR-WF3-2007-0762 CR-WF3-2008-0037 CR-WF3-2008-5786 CR-WF3-2009-2321

CR-WF3-2007-0935 CR-WF3-2008-2352 CR-WF3-2009-0785 CR-WF3-2009-2337

CR-WF3-2007-1666 CR-WF3-2008-5115 CR-WF3-2009-1972 CR-WF3-2009-2343

CR-WF3-2007-2469 CR-WF3-2008-5258 CR-WF3-2009-2306 CR-WF3-2009-2861

CR-WF3-2007-4448 CR-WF3-2007-4280 CR-WF3-2007-4281 CR-WF3-2007-2610

A-3 Attachment

WORK ORDERS

117089 155100 172152 51562560

94701 94702 113371 132935

00085241 00140811 95498 51097820

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION

DC-121 Maintenance Rule 1

NUMARC 93-01 Industry Guideline for Monitoring the Effectiveness 3

of Maintenance at Nuclear Power Plants

Section 1R13: Maintenance Risk Assessment and Emergency Work Controls

CONDITION REPORTS

CR-WF3-2009-1706 CR-WF3-2009-1718 CR-WF3-2009-3023 CR-WF3-2009-2807

WORK ORDERS

00190937 186497 160282 51657973

186508 185547 185560 184949

173008 136785 116977 197599

197692

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION

EN-WEM-101 On-Line Work Management Process 1

OI-037-000 Operations Risk Assessment Guideline 2

OP-006-003 125 Vdc Electric Distribution 301

ME-007-002 Molded Case Circuit Breakers 15

ME-007-008 Motor-Operated Valves 16

ME-007-045 Motor-Operated Valve Motor Power Monitor 2

UNT-001-015 Equipment QAualification Program 7

ME-004-809 Low/Medium voltage Power & Control 302

Cable/Conductor Terminations and splices

ME-007-047 VOTES Testing of Motor-Operated Valves 5

OP-009-008 Safety Injection System 25

OP-009-001 Containment spray 301

MI-005-464 Plant Protection System Power Supply Calibration 303

OP-009-007 Plant Protection System 9

ME-007-005 Time Delay Relay Setting Check Adjustment 13

A-4 Attachment

ME-004-330 4KV Induction Motor Maintenance 300

ME-004-211 Station Battery (Quarterly) 7

ME-002-210 Station Battery Bank & Charger (Quarterly) 14

Section 1R15: Operability Evaluations

CONDITION REPORTS

CR-WF3-2009-2189 CR-WF3-2008-5867 CR-WF3-2008-5618 CR-WF3-2009-2253

CR-WF3-2009-2212 CR-WF3-2009-2226 CR-WF3-2009-2229 CR-WF3-2009-2253

WORK ORDERS

51646383 194110 164712 51701184

51695212 52033543 194505

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION

OP-903-026 Emergency Core Cooling System Valve Lineup 17

Verification

OP-009-008 Safety Injection 25

MM-007-038 Valves HVC-101 and HVC-102 Leak Test 300

OP-009-002 Emergency Diesel Generator 308

OP-903-068 Emergency Diesel Generator Operability and 302

Subgroup Relay Operability Verification

OP-903-15 Train A Integrated Emergency Diesel Generator / 10

Engineering Safety Features Test

Section 1R19: Postmaintenance Testing

CONDITION REPORTS

CR-WF3-2009-1706 CR-WF3-2009-1718 CR-WF3-2008-5786 CR-WF3-2008-4765

CR-WF3-2008-4304 CR-WF3-2008-4304 CR-WF3-2008-4765 CR-WF3-2009-2253

CR-WF3-2009-2212 CR-WF3-2009-2226 CR-WF3-2009-2229 CR-WF3-2009-225

WORK ORDERS

00190937 180143 46961 168290

173009 516557973 186508 185547

185560 184946 173008 52022649

52030855 52022009 51646383 194110

164712 51701184 51695212 52033543

34838 170228 52033835 52036094

194505 52034706 52031652 191225

197180

A-5 Attachment

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION

MI-005-464 Plant Protection System Power Supply Calibration 303

OP-009-007 Plant Protection System 9

MI-013-522 PPS Ground Detection Test 5

MI-005-293 Retest Procedure for Power Supplies 2

OP-903-107 Plant Protection System Channel A&B&C&D 303

Functional Test

ME-007-005 Time Delay Relay Setting Check Adjustment 13

OP-009-008 Safety Injection System 25

OP-903-030 Safety Injection Pump Operability Verification 15

OP-009-008 Safety Injection System 25

ME-007-002 Molded Case Circuit Breakers 15

ME-007-005 Time Delay Relay Setting Check Adjustment 13

ME-007-008 Motor Operated Valves 16

ME-007-045 Motor-Operated Valve Motor Power Monitor 2

ME-004-809 Low/Medium Voltage Power & Control 302

Cable/Conductor Terminations and Splices

ME-007-057 MCE/EMAX Data Acquisition 4

ME-004-330 4KV Induction Motor Maintenance 300

MM-007-038 Valves HVC-101 and HVC-102 Leak Test 300

OP-009-002 Emergency Diesel Generator 308

OP-903-068 Emergency Diesel Generator Operability and 302

Subgroup Relay Operability Verification

OP-903-115 Train A Integrated Emergency Diesel Generator / 10

Engineering Safety Features Test

OP-100-002 Leak Reduction 300

OP-903-003 Charging Pump Operability Check 301

OP-002-005 Chemical and Volume Control 28

OP-903-035 Containment Spray Pump Operability Check 13

OP-009-001 Containment Spray 301

MM-006-021 Charging Pump Maintenance 9

A-6 Attachment

Section 1R22: Surveillance Testing

WORK ORDERS

52033543 51794147 51797247 51695212

51795535 52034706 52031652

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION

OP-903-030 Safety Injection Pump Operability Verification 15

OP-009-008 Safety Injection System 25

OP-903-118 Primary Auxiliaries Quarterly IST Valve Test 16

OP-002-003 Component Cooling Water System 305

OP-009-003 Emergency Feedwater 301

OP-903-046 Emergency Feed Pump Operability Check 304

OP-002-005 Chemical and Volume Control 28

OP-100-002 Leak Reduction 300

OP-009-002 Emergency Diesel Generator 308

OP-903-068 Emergency Diesel Generator Operability and 302

Subgroup Relay Operability Verification

OP-903-115 Train A Integrated Emergency Diesel Generator / 10

Engineering Safety Features Test,

Section 1EP1: Exercise Evaluation

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION / DATE

EP-1-001 Recognition and Classification of Emergencies 22

EP-1-020 Actions for Alert 301

EP-1-030 Actions for Site Emergency 25-2

EP-1-040 Actions for General Emergency 26-2

EP-2-010 Notifications and Communications 303

EP-2-015 Emergency Responder Activation 8-1

EP-2-030 Emergency Radiation Exposure Guidelines and 9

Controls

EP-2-031 In-Plant Radiation Control during Emergencies 7-2

EP-2-033 KI Administration 301

EP-2-034 Onsite Surveys during Emergencies 5-1

EP-2-050 Offsite Dose Assessment 303

A-7 Attachment

NUMBER TITLE REVISION / DATE

EP-2-052 Protective Action Guidelines 20

EP-2-071 Site Protective Measures 18-2

EP-2-100 TSC Activation, Operation, and Deactivation 33

EP-2-101 OSC Activation, Operation, and Deactivation 302

EP-2-102 EOF Activation, Operation, and Deactivation 301

EP-2-130 Emergency Team Assignments 22

2007-03 2007 Green Team Site Drill February 18, 2008

2007-04 2007 Green Team Biennial Exercise March 10, 2008

2008-01 2008 Red Team Site Drill August 3, 2008

2008-03 2008 Blue Team Site Drill January 8, 2009

2008-04 2008 Orange Team Site Drill March 29, 2009

2009-01 2009 Green Team Site Drill June 19, 2009

2009-02 2009 Blue Team Site Drill June 21, 2009

WLP-EP-EDIR Emergency Preparedness Lesson Plan: Emergency 7

Director

WLP-EP-EC Emergency Preparedness Lesson Plan: Emergency 6

Coordinator

WLP-EP-RPC Emergency Preparedness Lesson Plan: Radiation 3

Protection Coordinator

WLP-OPS-EP02 Operations Lesson Plan: Emergency Plan Training for 8

Control Room Personnel, Training Personnel, and

Operations Coordinators

CORRECTIVE ACTION DOCUMENTS

2009-01101 2009-01184

Section 4OA1: Performance Indicator Verification

NUMBER TITLE REVISION

NEI 99-02 Regulatory Assessment Performance Indicator 5

Guideline

PROCEDURES

NUMBER TITLE REVISION

EP-1-001 Recognition and Classification of Emergencies 22

EP-2-010 Notifications and Communications 303

EP-2-052 Protective Action Guidelines 20

A-8 Attachment

EP-3-070 Emergency Communications Systems Routine 301

Testing

EN-EP-201 Emergency Planning Performance Indicators 8

EN-LI-114 Perofrmance Indicator Process 4

EPP-422 Siren and Helicopter Warning System Maintenance 4

EPP-424 Siren Testing and Siren Administrative Controls 12

MISCELLANEOUS DOCUMENTS

TITLE REVISION

Water3 Steam Electric Station Emergency Plan 37

Section 4OA2: Identification and Resolution of Problems

PROCEDURES

NUMBER TITLE REVISION

OI-002-000 Annunciator, Control Room Instrumentation and 301

Workaround Status Control

OI-034-000 Work Management Center 18

EN-LI-102 Corrective Action Process 11

ME-003-240 Battery Performance Test 13

EN-LI-118 Root Cause Analysis Process 7

CONDITION REPORTS

CR-WF3-2009-0069 CR-WF3-2009-1177 CR-WF3-2009-0697 CR-WF3-2008-4179

CR-WF3-2008-2431 CR-WF3-2008-2515 CR-WF3-2008-5852 CR-WF3-2009-2846

WORK ORDERS

155714 169263 168928 157646

156715 148345 152819

A-9 Attachment