IR 05000321/2008004
ML083020164 | |
Person / Time | |
---|---|
Site: | Hatch, 07200036 |
Issue date: | 10/28/2008 |
From: | Shaeffer S M NRC/RGN-II/DRP/RPB2 |
To: | Madison D R Southern Nuclear Operating Co |
References | |
IR-08-004, IR-08-501 | |
Download: ML083020164 (28) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 October 28, 2008 Mr. Dennis Vice President - Hatch Southern Nuclear Operating Company, Inc. Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513
SUBJECT: EDWIN I. HATCH NUCLEAR PLANT - NRC INTEGRATED INSPECTION REPORT 05000321/2008004, 05000366/2008004, 05000321/2008501 AND, 05000366/2008501
Dear Mr. Madison:
On September 30, 2008, U. S. Nuclear Regulatory Commission (NRC) completed an inspection at your Edwin I. Hatch Nuclear Plant, Units 1 and 2. The enclosed integrated inspection report documents the inspection results, which were discussed on October 20, 2008, with you and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings of significance were identified. However, licensee-identified violations, which were determined to be of very low safety significance, are listed in this report. The NRC is treating these violations as a non-cited violations (NCVs) consistent with Section VI.A.1 of the NRC Enforcement Policy because of the very low safety significance of the violations and because they were entered into your corrective action program. If you contest these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC resident inspector at the Edwin I. Hatch Nuclear Plant.
SNC 2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosures, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,/RA/ Scott M. Shaeffer, Chief Reactor Projects Branch 2 Division of Reactor Projects
Docket Nos.: 50-321, 50-366, 72-36 License Nos.: DPR-57, NPF-5
Enclosures:
Inspection Report 05000321/2008004, 05000366/2008004, 05000321/2008501, 05000366/2008501
w/Attachment:
Supplemental Information cc w/encl: (See page 3)
_________________________ X SUNSI REVIEW COMPLETE CWR OFFICE RII:DRP RII:DRP RII:DRP RII:DRP RII:DRS RII:DRS RII:DRS RII:DRS SIGNATURE CWR /RA for/ via email via telecom via email via email via email ECM /RA/ PGC /RA/ NAME TLighty ARao JHickey PNiebaum LMiller BCaballero EMichel PCapehart DATE 10/20/2008 10/16/2008 10/20/2008 10/16/2008 10/16/2008 10/15/2008 10/21/2008 10/20/2008 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO SNC 3 cc w/encl: Jeffrey T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Raymond D. Baker Licensing Manager Licensing-Hatch Southern Nuclear Operating Company, Inc. Electronic Mail Distribution L. Mike Stinson Vice President Fleet Operations Support Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution David H. Jones Vice President Engineering Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Moanica Caston Vice President and General Counsel Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Steven B. Tipps Hatch Principal Engineer - Licensing Edwin I. Hatch Nuclear Plant Electronic Mail Distribution Mr. K. Rosanski Resident Manager Oglethorpe Power Corporation Electronic Mail Distribution Laurence Bergen Oglethorpe Power Corporation Electronic Mail Distribution
Bob Masse Resident Manager Vogtle Electric Generating Plant Oglethorpe Power Corporation Electronic Mail Distribution Arthur H. Domby, Esq. Troutman Sanders Electronic Mail Distribution
Dr. Carol Couch Director Environmental Protection Department of Natural Resources Electronic Mail Distribution
Cynthia Sanders Program Manager Radioactive Materials Program Department of Natural Resources Electronic Mail Distribution
Jim Sommerville (Acting) Chief Environmental Protection Division Department of Natural Resources Electronic Mail Distribution
Mr. Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia Electronic Mail Distribution
Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Electronic Mail Distribution
Chairman Appling County Commissioners County Courthouse 69 Tippins Street, Suite 201 Baxley, GA 31513
SNC 4 Letter to Dennis from Scott M. Shaeffer dated October 28, 2008
SUBJECT: EDWIN I. HATCH NUCLEAR PLANT - NRC INTEGRATED INSPECTION REPORT 05000321/2008004, 05000366/2008004, 05000321/2008501 AND, 05000366/2008501 Distribution w/encl:
C. Evans, RII L. Slack, RII OE Mail RIDSNRRDIRS PUBLIC R. Martin, NRR
Enclosure U. S. NUCLEAR REGULATORY COMMISSION REGION II
Docket Nos.: 50-321, 50-366,72-036 License Nos.: DPR-57 and NPF-5
Report Nos.: 05000321/2008004, 05000366/2008004 05000321/2008501, 05000366/2008501
Licensee: Southern Nuclear Operating Company, Inc.
Facility: Edwin I. Hatch Nuclear Plant Location: Baxley, Georgia 31513
Dates: July 1 - September 30, 2008
Inspectors: J. Hickey, Senior Resident Inspector P. Niebaum, Resident Inspector A. Rao, Reactor Inspector B. Caballero, Operations Engineer (Section 1R11) P. Capehart, Operations Engineer (Section 1R11) L Miller, Senior Emergency Preparedness Inspector, (Sections 1EP2, 1EP3, 1EP4, 1EP5, 4OA1, and 4OA5) E. Michel, Senior Reactor Inspector (Section 4OA5)
Approved by: Scott M. Shaeffer, Chief Reactor Projects Branch 2 Division of Reactor Projects
Enclosure
SUMMARY OF FINDINGS
IR 05000321/2008-004, 05000366/2008-004; 05000321/2008501, 05000366/2008501; 07/01/2008-09/30/2008; Edwin I. Hatch Nuclear Plant, Units 1 and 2, Routine integrated report The report covered a three-month period of inspection by resident inspectors, two reactor inspectors, two operations engineers, and a senior emergency preparedness inspector. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process (ROP), Revision 4, dated December 2006.
A.
NRC-Identified and Self-Revealing Findings
No findings of significance were identified.
B. Licensee-Identified Violations
A violation of very low safety significance, which was identified by the licensee, has been reviewed by the inspectors. Corrective actions taken or planned by the licensee have been entered into the licensee's corrective action program. This violation and corrective actions are listed in Section 4OA7 of this report.
REPORT DETAILS
Summary of Plant Status
Unit 1 began the period at 100% Rated Thermal Power (RTP). On July 4, a reactor scram occurred during testing of the hydraulic system that controls the main turbine control valves. Unit 1 was returned to 100% RTP on July 11. On September 6, reactor power was reduced to 13% RTP while the main generator was taken off line for stator cooling water system repairs. Unit 1 was returned to 100% RTP on September 11 and remained there through the end of the reporting period.
Unit 2 began the inspection period at full RTP and remained at or near 100% for the remainder of the inspection period.
REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
1R01 Adverse Weather
a. Inspection Scope
External Flooding. The inspectors performed a review of the licensee's readiness to cope with external flooding and performed walk downs of the intake structure to verify that equipment was in place to mitigate the potential impacts from external flooding. The inspectors reviewed licensee procedure 34AB-Y22-002-0, Naturally Occurring Phenomena, to verify guidance existed to cope with an external flood. Additionally, the inspectors reviewed licensee documentation that shows design flood levels for area containing safety-related equipment. Documents reviewed are listed in the Attachment.
Imminent Weather Conditions. The inspectors performed a review of the licensee's readiness to cope with the following two adverse weather events. The inspectors performed walk downs to verify that equipment and materials stored on the site were properly secured. The inspectors responded to the control room during the tornado warning event to verify implementation of station adverse weather procedures. Additionally, the inspectors reviewed licensee procedure 34AB-Y22-002-0, Naturally Occurring Phenomena to verify guidance existed to cope with impending adverse weather. Documents reviewed are listed in the Attachment.
- Tropical Storm Fay preparations, August 19-20
- Tornado Warning for Toombs County, August 22
b. Findings
No findings of significance were identified.
41R04 Equipment Alignment
a. Inspection Scope
Partial Walkdowns. The inspectors performed partial walkdowns of the following three systems when the opposite trains were removed from service or after completing maintenance. The inspectors checked system valve positions, electrical breaker positions, and operating switch positions to evaluate the operability of the opposite trains or components by comparing the position listed in the system operating procedure to the actual position. Documents reviewed are listed in the Attachment.
- Unit 2 B train of the Residual Heat Removal (RHR) system
- Unit 2 A train of the Core Spray (CS) system
- Unit 2 B train of the CS system Complete System Walkdown. The inspectors performed a complete walkdown of the following system. The inspectors performed a detailed check of electrical breaker positions, and operating switch positions to evaluate the operability of the system or components by comparing the required position in the system operating procedure to the actual position. The inspectors also interviewed personnel and reviewed control room logs to verify that alignment and equipment discrepancies were being identified and appropriately resolved. Documents reviewed are listed in the Attachment.
- Unit 1 600 volt Safety Related Buses C and D.
b. Findings
No findings of significance were identified.
1R05 Fire Protection
a. Inspection Scope
Fire Area Tours. The inspectors toured the following four risk significant plant areas to assess the material condition of the fire protection and detection equipment, verify fire protection equipment was not obstructed and that transient combustibles were properly controlled. The inspectors reviewed the Fire Hazards Analysis drawings H-11846 and H-11847 to verify that the necessary fire fighting equipment, such as fire extinguishers, hose stations, ladders, and communications equipment, was in place. Documents reviewed are listed in the Attachment.
- Unit 1 Emergency Diesel Generator (EDG) Rooms
- Unit 1 Vital Area Switchgear Rooms
- Unit 2 EDG Rooms
- Unit 2 Vital Area Switchgear Rooms 5Fire Drill Observation. The inspectors observed a fire drill conducted on August 28. The inspectors reviewed licensee procedure 34AB-X43-001-1, Fire Procedure, and the drill scenario to verify proper response of the on-shift fire brigade to a simulated fire. The inspectors checked proper use of protective clothing, self contained breathing apparatus, fire fighting equipment, fire pre-plans, proper fire fighting strategy including smoke removal and fire propagation checks, communications, command and control, and coordination with offsite fire company support. In addition, the inspectors attended the post-drill critique to assess if the licensee identified performance issues were comparable to those identified by the inspectors.
b. Findings
No findings of significance were identified.
1R11 Licensed Operator Requalification
a. Inspection Scope
Resident Quarterly Observation. The inspectors observed the performance of licensee simulator scenario LT-SG-51083-05, which included a recirculation pump speed decrease, a Main Steam Line break resulting in a Group 1 isolation and reactor scram, an inadvertent start signal to the High Pressure Coolant Injection (HPCI) system; and an unisolable HPCI steam leak requiring an emergency depressurization of the reactor vessel. The inspectors reviewed licensee procedures 10AC-MGR-019-0, Procedure Use and Adherence, and DI-OPS-59-0896, Operations Management Expectations, to verify formality of communication, procedure usage, alarm response, control board manipulations, group dynamics, and supervisory oversight. The inspectors attended the post-exercise critique of operator performance to assess if the licensee identified performance issues were comparable to those identified by the inspectors. In addition, the inspectors reviewed the critique results from previous training sessions to assess performance improvement.
Licensed Operator Requalification. The inspectors reviewed documentation, interviewed licensee personnel, and observed the administration of operating tests associated with the licensee's operator requalification program to assess the effectiveness of the licensee in implementing requalification requirements identified in 10 CFR Part 55, Operators' Licenses. The evaluations were also performed to determine if the licensee effectively implemented operator requalification guidelines established in NUREG-1021, Operator Licensing Examination Standards for Power Reactors. The inspectors also evaluated the licensee's simulation facility for adequacy for use in operator licensing examinations using ANSI/ANS-3.5-1985, American National Standard for Nuclear Power Plant Simulators for use in Operator Training and Examination. The inspectors observed four crews during the performance of the operating tests. Documentation reviewed included written examinations, job performance measures, simulator scenarios, licensee procedures, on-shift records, simulator change request records and performance test records, the feedback process, licensed operator qualification records, remediation plans, watch standing records, and medical records. The records were 6inspected using the criteria listed in Inspection Procedure 71111.11. Documents reviewed are listed in the Attachment.
b. Findings
No findings of significance were identified.
1R12 Maintenance Effectiveness
a. Inspection Scope
The inspectors reviewed the following two samples associated with structures, systems, and components to assess the licensee's implementation of the Maintenance Rule (10 CFR 50.65) with respect to the characterization of failures and the appropriateness of the associated (a) (1) or (a) (2) classification. The inspectors reviewed operator logs, associated CRs, Maintenance Work Orders (MWO), and the licensee's procedures for implementing the Maintenance Rule to determine if equipment failures were being identified, properly assessed, and corrective actions established to return the equipment to a satisfactory condition. Documents reviewed are listed in the Attachment.
- Unit 1 Reactor Core Isolation Cooling System
- Unit 2 Train A RHR System
b. Findings
No findings of significance were identified.
1R13 Maintenance Risk Assessments and Emergent Work Evaluation
a. Inspection Scope
The inspectors reviewed the following Plan of the Day documents listed below to verify that risk assessments were performed prior to components being removed from service. The inspectors reviewed the risk assessment and risk management controls implemented for these activities to verify they were completed in accordance with licensee procedure 90AC-OAM-002-0, Scheduling Maintenance, and 10 CFR 50.65 (a)(4). For emergent work, the inspectors assessed whether any increase in risk was promptly assessed and that appropriate risk management actions were implemented.
- July 26 through August 1, 1B Reactor Building Closed Cooling Water (RBCCW) Heat Exchanger maintenance, 2B RBCCW Heat Exchanger maintenance, Low River Level Intake plugging risk, Unit-1 RCIC Outage
b. Findings
No findings of significance were identified.
71R15 Operability Evaluations
a. Inspection Scope
The inspectors reviewed the following five operability evaluations and compared the evaluations to the system requirements identified in the Technical Specification (TS) and the Final Safety Analysis Report to ensure operability was adequately assessed and the system or component remained available to perform its intended function. Also, the inspectors assessed the adequacy of compensatory measures implemented as a result of the condition. Documents reviewed are listed in the Attachment.
- Unit 2 HPCI room cooler accumulated dust in discharge
- Unit 2 B EDG sequencer timing card failure
- Unit 2 A RHR Pump degraded flow
- Unit 1 Control room Air Handling Unit 1Z41B003C blown fuse
- EDG speed droop set at 50 during testing
b. Findings
No findings of significance were identified.
1R18 Plant Modifications
a. Inspection Scope
The inspectors reviewed the following three plant modifications to ensure that safety functions of important safety systems have not been affected. Also, the inspectors verified that the design bases, licensing bases and performance capability of risk significant structures, systems and components have not been degraded through modifications. The inspectors verified that any modifications performed during increased risk-significant configurations did not place the plant in an unsafe condition. Documents reviewed are listed in the Attachment.
Permanent Plant Modification
- ED 2081618501, Replacement Bus Bars and Insulators For RHR Service Water (RHRSW) Pump Motor Surgepack Temporary Plant Modifications
- 2-08-003, Non-standard lifting lug baseplate dimensions due to rebar interference to support lifting the 2A EDG inner cooler covers
- 1-08-016, 1E11F031A 1A RHR Pump Discharge Check Valve disc modification
b. Findings
No findings of significance were identified.
81R19 Post Maintenance Testing
a. Inspection Scope
For the following six post maintenance tests, the inspectors reviewed the test scope to verify the test demonstrated the work performed was completed correctly and the affected equipment was functional and operable in accordance with TS requirements. The inspectors also reviewed equipment status and alignment to verify the system or component was available to perform the required safety function. Documents reviewed are listed in the Attachment.
- 1B21F022D, Main Steam Isolation Valve hydraulic accumulator repair
- 2P41F036B, RHR/CS Room Cooler Plant Service Water Supply Valve replacement
- 2E11N007B, RHRSW Heat Exchanger B Inlet Flow Transmitter replacement
- 1C11D001-126, Scram Valve Seat replacement
- 2E11F005C, RHRSW Pump Discharge Check Valve inspection
- 2P41F339A, 2A EDG PSW Supply Valve rebuild
b. Findings
No findings of significance were identified.
1R20 Refueling and Outage Activities
a. Inspection Scope
On July 4, a Unit 1 reactor scram occurred during turbine hydraulic control system testing. The inspectors reviewed the licensee's forced outage plan, monitored shutdown activities, licensee control of outage activities, and monitored the activities listed below. Documents reviewed are listed in the Attachment.
- Reactor Coolant System cooldown following shutdown to verify the cooldown rate did not exceed TS limits
- TS and licensee procedures to verify mode change requirements were met
- Plant startup, heatup, and power ascension
- Licensee identification and resolution of problems related to outage activities
b. Findings
No findings of significance were identified.
1R22 Surveillance Testing
a. Inspection Scope
The inspectors reviewed licensee surveillance test procedures and either witnessed the test or reviewed test records for the following five surveillances to determine if the scope 9of the test adequately demonstrated the affected equipment was operable. The inspectors reviewed these activities to assess for preconditioning of equipment, procedure adherence, and equipment alignment following completion of the surveillance. The inspectors reviewed licensee procedure AG-MGR-21-0386, Evolution and Pre-and Post-Job Brief Guidance, and attended selected briefings to determine if procedure requirements were met. Documents reviewed are listed in the Attachment.
Surveillance Tests
- 34SV-E41-002-2, Unit-2 HPCI Pump Operability Test
- 34SV-E11-001-2, Unit-2 B Loop RHR Pump Operability Test
- 34SV-C11-006-1S, Control Rod Drive (CRD) Withdraw Stall Flow Test In-Service Test
- 34SV-E41-002-1, Unit-1 HPCI Pump Operability Test Reactor Coolant Leakage Test
- 34SV-SUV-019-2, Drywell Floor-drain Leakage Surveillance Checks
b. Findings
No findings of significance were identified.
Cornerstone:
Emergency Preparedness 1EP2 Alert and Notification System Testing
a. Inspection Scope
The inspector evaluated the adequacy of licensee
=s methods for testing the alert and notification system in accordance with NRC Inspection Procedure 71114, Attachment 02, AAlert and Notification System Evaluation
@. The applicable planning standard 10 CFR Part 50.47(b)(5) and its related 10 CFR Part 50, Appendix E, Section IV.D requirements were used as reference criteria. The criteria contained in NUREG-0654, Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants, Revision 1, was also used as a reference. Documents reviewed are listed in the Attachment. This inspection activity satisfied one inspection sample for the alert and notification system on a biennial basis.
b. Findings
No findings of significance were identified.
101EP3 Emergency Response Organization Augmentation
a. Inspection Scope
The inspector reviewed the licensee
=s Emergency Response Organization (ERO) augmentation staffing requirements and process for notifying the ERO to ensure the readiness of key staff for responding to an event and timely facility activation. The qualification records of key position ERO personnel were reviewed to ensure all ERO qualifications were current. A sample of problems identified from augmentation drills or system tests performed since the last inspection were reviewed to assess the effectiveness of corrective actions. Documents reviewed are listed in the Attachment.
The inspection was conducted in accordance with NRC Inspection Procedure 71114, Attachment 03, Emergency Response Organization Staffing and Augmentation System. The applicable planning standard (PS), 10 CFR 50.47(b)(2) and its related 10 CFR 50, Appendix E requirements were used as reference criteria. This inspection activity satisfied one inspection sample for the ERO staffing and augmentation system on a biennial basis.
b. Findings
No findings of significance were identified.
1EP4 Emergency Action Level and Emergency Plan Changes
a. Inspection Scope
Since the last NRC inspection of this program area, Revision 27 of the Hatch Emergency Plan was implemented based on the licensee's determination, in accordance with 10 CFR 50.54(q), that the changes resulted in no decrease in the effectiveness of the Plan, and that the revised Plan continued to meet the requirements of 10 CFR 50.47(b) and Appendix E to 10 CFR Part 50. The inspector conducted a sampling review of the Plan changes and implementing procedure changes made between September 2007 and June 2008 to evaluate for potential decreases in effectiveness of the Plan. However, this review was not documented in a Safety Evaluation Report and does not constitute formal NRC approval of the changes. Therefore, these changes remain subject to future NRC inspection in their entirety. Documents reviewed are listed in the Attachment.
The inspection was conducted in accordance with NRC Inspection Procedure 71114, Attachment 04, Emergency Action Level and Emergency Plan Changes. The applicable PS, 10 CFR 50.47(b)(4) and its related 10 CFR 50, Appendix E requirements were used as reference criteria. This inspection activity satisfied one inspection sample for the emergency action level and emergency plan changes on an annual basis.
b. Findings
No findings of significance were identified.
111EP5 Correction of Emergency Preparedness Weaknesses and Deficiencies
a. Inspection Scope
The inspector reviewed the corrective actions identified through the Emergency Preparedness program to determine the significance of the issues and to determine if repeat problems were occurring. The facility
=s self-assessments and audits were reviewed to assess the licensee
=s ability to be self-critical, thus avoiding complacency and degradation of their emergency preparedness program. In addition, inspector reviewed licensee
=s self-assessments and audits to assess the completeness and effectiveness of all emergency preparedness related corrective actions. Documents reviewed are listed in the Attachment.
The inspection was conducted in accordance with NRC Inspection Procedure 71114, Attachment 05, Correction of Emergency Preparedness Weaknesses. The applicable planning standard, 10 CFR 50.47(b)(14) and its related 10 CFR 50, Appendix E requirements were used as reference criteria. This inspection activity satisfied one inspection sample for the correction of emergency preparedness weaknesses on a biennial basis.
b. Findings
No findings of significance were identified.
1EP6 Drill Evaluation
a. Inspection Scope
During the following drill, the inspectors observed licensee activities in the simulator, Technical Support Center and Operations Support Center to verify implementation of licensee procedure 10AC-MGR-006-0, Hatch Emergency Plan. The inspectors reviewed the classification of the simulated events and the development of protective action recommendations to verify these activities were conducted in accordance with licensee procedure 73EP-EIP-001-0, Emergency Classification and Initial Actions. The inspectors also reviewed licensee procedure 73EP-EIP-073-0, Onsite Emergency Notification, to verify the proper offsite notifications were made. The inspectors attended the post-exercise critique to assess the licensee's effectiveness in identifying areas of improvement. Documents reviewed are listed in the Attachment.
- Emergency Plan Drill conducted on July 23, 2008
b. Findings
No findings of significance were identified.
OTHER ACTIVITIES
4OA1 Performance Indicator Verification
a. Inspection Scope
The inspectors reviewed a sample of the licensee submittals for the performance indicators (PIs) listed below to verify the accuracy of the data reported. The PI definitions and the guidance contained in NEI 99-02, Regulatory Assessment Indicator Guideline, Rev. 2 and licensee procedure 00AC-REG-005-0S, Preparation and Reporting of NRC PI Data, were used to verify procedure and reporting requirements were met.
Cornerstone:
- Unplanned Scrams per 7000 Critical Hours
- Unplanned Scrams with Complications
- Unplanned Transients per 7000 Critical Hours
Cornerstone:
- Reactor Coolant System Leakage
- Reactor Coolant System Activity The inspectors reviewed raw PI data collected since September 2007 for the Initiating Events and Barrier Integrity indicators identified. The inspectors compared graphical representations from the most recent PI report to the raw data to verify the data was included in the report. The inspectors also examined a sampling of operations logs and procedures to verify the PI data was appropriately captured for inclusion into the PI report, and the individual PIs were calculated correctly. The inspectors observed a chemistry technician perform a sample of the reactor coolant system and a portion of the analysis in accordance with licensee procedure 64CH-SAM-025-0, Reactor Coolant Sampling and
Analysis.
Documents reviewed are listed in the Attachment.
Cornerstone:
- Emergency Response Organization Drill/Exercise Performance
- Emergency Response Organization Readiness
- Alert and Notification System Reliability The inspectors reviewed portions of the raw PI data developed from monthly performance indicator reports and discussed the methods for compiling and reporting the PIs with cognizant emergency preparedness personnel. The inspector also independently screened drill and exercise opportunity evaluations, drill participation reports, and drill evaluations. Selected reported values were calculated to verify their accuracy. The inspectors compared graphical representations from the most recent PI report to the raw data to verify that the data was correctly reflected in the report.
Documents reviewed are listed in the Attachment to this report.
134OA2 Identification and Resolution of Problems
.1 Daily Screening of Corrective Action Items
As required by Inspection Procedure 71152, Identification and Resolution of Problems, and in order to help identify repetitive equipment failures or specific human performance issues for follow-up, the inspectors performed a daily screening of items entered into the licensee's corrective action program. This review was accomplished by either attending daily screening meetings that briefly discussed major Condition Reports (CR), or accessing the licensee's computerized corrective action database and reviewing each CR that was initiated.
.2 Annual Sample
a. Inspection Scope
The inspectors performed a detailed review of the following CR to verify the full extent of the issue was identified, an appropriate evaluation was performed, and appropriate corrective actions were specified and prioritized. The inspectors evaluated the CR against the licensee's corrective action program as delineated in licensee procedure NMP-GM-002, Corrective Action Program, and 10 CFR 50, Appendix B. Documents reviewed are listed in the Attachment.
- CR 2008105108 2A RHRSW Pump degraded flow on two separate occasions due to a snake becoming entangled in the pump impeller.
b. Findings and Observations
No findings of significance were identified. The root cause was comprehensive and thorough. Six causes were identified and six corrective actions have either been taken or are planned. The extent of condition review included previous events related to river debris and other foreign material being ingested into the RHRSW Pumps.
4OA3 Event Follow-up
.1 (Closed) Licensee Event Report (LER) 05000366/2007-003 Excessive Leakage on Secondary containment Bypass Valves Due to Foreign Material
On March 1, 2007 both the inboard and outboard drywell floor drain sump isolation valves failed local leakrate testing (LLRT). This resulted in a bypass of the secondary containment boundary. The cause of the LLRT failure was foreign material intrusion into the valves. This condition was documented in CR 2007102669. A licensee-identified violation is described in Section 4OA7.
14.2 (Closed) LER 05000366/2008-002 Reactor Scram on Low Water Level due to loss of Condensate System The contents of this LER have been withheld from disclosure in accordance with 10 CFR 2.390(d). The residents reviewed this LER and no findings of significance were identified.
.3 Unit 2 Reactor Scram during testing of the hydraulic turbine control system
a. Inspection Scope
The inspectors responded to the site on July 4, 2008, and verified the licensee actions in response to the reactor scram were in accordance with Emergency, Abnormal, and Normal Operating Procedures. The inspectors verified the cause of the scram was understood, reviewed chart recorders, operating logs and attended event response meetings.
b. Findings
No findings of significance were identified.
4OA5 Other Activities
.1 Quarterly Resident Inspector Observations of Security Personnel and Activities
a. Inspection Scope
During the inspection period, the inspectors conducted observations of security force personnel and activities to ensure that the activities were consistent with licensee security procedures and regulatory requirements relating to nuclear plant security. These observations took place during both normal and off-normal plant working hours.
b. Findings
No findings of significance were identified.
.2 Operation of an Independent Spent Fuel Storage Installation (ISFSI)
a. Inspection Scope
The inspectors reviewed selected ISFSI operations to verify that the licensee performed ISFSI activities safely and in compliance with approved procedures. The inspectors reviewed records to verify that the licensee had properly identified the parameter of each fuel assembly loaded, and that a physical inventory had been performed on all spent fuel in the ISFSI on a frequency of at least every 12 months. The inspectors also reviewed the TS to verify that the fuel placed in these casks met the requirements. The inspectors walked down the ISFSI pads to assess the material condition of the casks, the installation of security equipment, and the performance of monitoring systems. The 15inspectors also reviewed ISFSI document control practices to verify that any changes to the required ISFSI procedures were performed in accordance with guidelines established in local procedures and 10CFR72.48. Documents reviewed are listed in the Attachment.
- Licensing Document Change Request 2008-022 DC, Dry Cask Storage - 10 CFR 72.212 Report - Revision for 2008 Loading Campaign
b. Findings
No findings of significance were identified.
.3 (Discussed) Temporary Instruction (TI) 2515/176, Emergency Diesel Generator Technical Specification Surveillance Requirements Regarding Endurance and Margin Testing
a. Inspection Scope
The objective of this TI was to gather information to assess the adequacy of nuclear power plant emergency diesel generator (EDG) endurance and margin testing as prescribed by plant-specific technical specifications (TS). The inspector interfaced with the appropriate station staff to obtain the information specified in Attachment 1 of the TI Worksheet. The TI applies to all operating nuclear power reactor licensees that use EDGs as the onsite standby power supply. The inspector verified the accuracy of the information by review of TS, EDG Design Basis Event (DBE) loading calculations, EDG endurance run test procedures, test data from the last three endurance tests performed on each EDG, EDG ratings, and EDG operating history. The information gathered will be forwarded to Nuclear Reactor Regulation/Division of Engineering/Electrical Engineering Branch (NRR/DE/EEEB) for further review to assess the adequacy and consistency of EDG testing at nuclear stations.
b. Findings and Observations
The TI is presently scheduled to be open until August 31, 2009, pending completion of the NRR/DE/EEEB review.
.4 (Closed) Temporary Instruction (TI) 2515/175, Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review
The inspector completed Temporary Instruction TI 2515/175, Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review. Appropriate documentation of the results was provided to the NRC, as required by the TI.
.5 (Closed) Unresolved Item (URI)05000321/2008002-01, RHRSW Hanger Failures
The inspectors reviewed the licensee's Root Cause Evaluation as documented in CR2008102081, RCCA Version 1.0, 03-31-08; and the Failure Analysis Report for 16RHRSW hangers H98 and H291 as documented in Log Number 08-MR-023. The regulatory aspects are dispositioned in Section 4OA7.
4OA6 Meetings, Including Exit
On October 20, 2008, the inspectors presented the inspection results to Mr. Dennis Madison and the other members of his staff who acknowledged the observations. The inspectors confirmed proprietary information was not provided or examined during the inspection.
4OA7 Licensee-Identified Violations
The following violations of very low safety significance (Green) were identified by the licensee and are violations of NRC requirements which meet the criteria of Section VI of the NRC Enforcement Policy, NUREG-1600, for being dispositioned as NCVs.
- 10 CFR 50 Appendix B Criterion V, Instructions, Procedures, and Drawings states in part that "Activities affecting quality shall be prescribed by documented instructions, procedures, -.. appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures,-" Contrary to this on March 1, 2007, the licensee determined both the inboard and outboard drywell floordrain sump isolation valves failed their LLRT due to foreign material intrusion. This finding is of very low safety significance because the overall penetration leakage was small compared to the primary containment volume. This finding was entered in the licensee's corrective action program under CR 2007102669.
- 10 CFR 50, Appendix B, Criterion III, Design Control states, in part, that the design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternate or simplified calculation methods, or by the performance of a suitable testing program. Contrary to the above, the licensee did not adequately evaluate, or use other means to demonstrate, that the RHRSW flow control valves operating in the normal flow regimes would not cause cavitation and subsequent vibration such that the RHRSW piping hangers would remain functional. This finding is of very low safety significance because a subsequent operability determination demonstrated that there was no loss of RHRSW system safety function capability. This finding was entered into the licensee's corrective action program as CR2008101568.
ATTACHMENT:
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee personnel
- S. Bargeron, Plant Manager
G Brinson, Operations Manager
- J. Dixon, Health Physics Manager
- B. Goodwin, Design Manager
- S. Grantham, Operations Training Supervisor
- J. Hammond, Training Manager
- G. Johnson, Site Engineering Manager
- J. Lewis, Site Support Manager
- D. Madison, Hatch Vice President
- R. Ott, Emergency Preparedness Supervisor
- S. Soper, Engineering Support Manager
- J. Thompson, Nuclear Security Manager
- S. Tipps, Licensing Principal Engineer
- K. Underwood, Performance Improvement Supervisor
- R. Varnadore, Maintenance Manager
LIST OF ITEMS
DISCCUSED AND CLOSED
Discussed 2515/176 TI Emergency Diesel Generator Technical Specification Surveillance Requirements Regarding Endurance and Margin Testing (Section 4OA5.3)
Closed
- 05000366/LER-2007-003 LER Excessive Leakage on Secondary Containment Bypass Valves due to Foreign Material (Section 4OA3.1)
- 05000366/LER-2008-002 LER Reactor Scram on Low Water Level due to loss of Condensate System (Section 4OA3.2)
- 2515/175 TI Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review (Section 4OA5.4)
- 05000321/FIN-2008002-01 URI RHRSW Hanger Failures (Section 4OA5.5)
LIST OF DOCUMENTS REVIEWED
Section 1R01: Adverse Weather
- Procedures: 52PM-Y46-001-0, Inground Pullbox and Cable Duct Inspection for Water
- DI-OPS-75-0404, Inground Pullbox and Cable Duct Inspection 34AR-650-315-1, Annunciator Response for High Level in the Intake Structure Pump Drawings: H-13004, H-13322, H-21102 MWOs:
- 1071581301,
- 1072021501 CRs:
- 2005108764,
- 2005108902 AI:
- 2008202044
- 2
Section 1R04: Equipment Alignment
- Procedures:
- 34SO-E11-010-2 Residual Heat Removal System on Standby Mode
- 34SO-E21-001-2 Core Spray System
- 34SO-R23-001-1 600/480 Volt AC System Drawing:
- FSAR: 6.3 Emergency Core Cooling System, 8.3.1 Auxiliary Electrical Power System
Section 1R05: Fire Protection
- Drawings: A-43965 sheets 06B, 07B, 08B, 09B, 10B, 11B, 12B, 14B, 15B, 16B, 17B, 18B, 19B, 20B, 21B, 22B, 23B, 24B, 25B, 26B, H-11846 Plant Hatch Fire Hazards Analysis (FHA) Appendix E 34AB-X43-001-2, Fire Procedure
Section 1R11: Licensed Operator Requalification
- Procedures:
- 2TR-TRN-002-0, License Continuing Training Program, Rev. 14
- DI-TRN-37-0787, Simulator Configuration Control, Rev. 5
- DI-TRN-19-0785, Examination Control, Administration, and Documentation, Rev. 9.1
- DI-TRN-55-0601, Operations Personnel Qualification Instructions, Rev. 8
- LR-EG-00101-04, License Continuing Training Annual Exam Examiner's Guide, 8/7/08
- LR-EG-00102-08, License Continuing Training Biennial Written Exam Examiner's Guide, 8/1/08
- LR-EG-00104-06, Simulator Exam Evaluator Guide, 8/17/07
- Written Examinations Reviewed:
- All 2007 Biennial Written Examinations 2008 LOR Segment Exams License Continuing Training Program Master Plan Simulator Documents:
- Closed Simulator Change Reports (SCRs) since 2006
- All open SCRs Simulator Testing Schedule, 2004 to 2012
- Steady State Tests
- Test # 615-1, 35% Steady State Performance Unit 1: 7/9/07 and 2/18/08 Test # 615-2, 35% Steady State Performance Unit 2:
- 7/17/07 and 2/21/08
- Transient Tests (2007 & 2008)
- 706-0, Main Turbine Trip at Max Power Which Does Not Cause Rx Trip, 4/2/07 & 2/5/08 709-0, Maximum Size Main Steam Line Un isolable Steam Line Rupture, 4/2/07 & 2/6/08
- Malfunction Tests
- 525-0, Turbine Trip, 8/21/03 & 4/3/07 538-1, Unit 1 Rx Press Ctl System Failure Including Turb Bypass Failure, 9/2/03 & 9/13/07 538-2, Unit 2 Rx Press Ctl System Failure Including Turb Bypass Failure, 9/2/03 & 5/2/07 579-0, Loss of Normal FW or Normal FW System Failure, 5/8/06
- Core Cycle 20 Tests
- 3Test #1:
- Axial Power Profiles, Rev. 0 Test #2:
- Decay Heat, Rev. 0 Test #3:
- Criticality, Rev. 0
- Test #4:
- Core Heat Balance, Rev. 0 Test #5:
- SR-OJ-60104-09, Core Alterations/ Fuel Movements, 3/6/08
- LR-JP-45.33-07, Move a Fuel Assembly/Blade Guide Using the Main Fuel Grapple, 1/25/07
- Simulator Scenarios
- LR-SE-00021-14, 4160V Bus 2F Fault/ Stuck Open SRV/ Steam Leak in Drywell/ Drywell Spray
- LR-SE-00026-20, ATWS/ Torus Level Loss/ ED
- CRs:
- 2008109363,
- 2008109198,
- 2008109139,
- 2008109189,
- 2008109014,
- 2008107849,
- 2008106529,
- 2008105363,
- 2008105729,
- 2008103585,
- 2008100506,
- 2008100460,
- 2008100048,
- 2007110763,
- 2007108804,
- 2007106693,
- 2007100726
- Exam Security Agreements Reactivation Records (31) Medical Records (14) Attendance Records from 2006 thru 2008
- Feedback Comments from Licensed Operator Requal 2006 thru 2008 Remedial Training Plans-Written Exam Failures Remedial Training Plans-As Found Exam Crew Failure
Section 1R12: Maintenance Effectiveness
- 40AC-ENG-020-0, Maintenance Rule (10
- CFR 50.65) Implementation and Compliance 90AC-OAM-022-0, Scheduling Maintenance
- NMP-DP-001, Operational Risk Awareness MWOs:
- 1050211401,
- 1061984601,
- 1061983801,
- 1070331901,
- 1061983901,
- 1070332501,
- 1071639701,
- 1070220401,
- 1072490601,
- 1080181601,
- 1071934901,
- 1072490701,
- 1061984501,
- 1070332101,
- 1061357101,
- 1071234201,
- 1072350601,
- 1070516001,
- 1070299501,
- 1070332601,
- 1072724901,
- 2040892301,
- 205086301,
- 2050856401,
- 2050856601,
- 2060296101,
- 2062012801,
- 2062012901,
- 2062013202,
- 2062014601,
- 2062015901,
- 2062016701,
- 2062017801, 2072262301
Section 1R13: Maintenance Risk Assessments and Emergent Work Evaluation
- NMP-DP-001, Operational Risk Awareness
- AG-OAM-02-0701, Work Scheduling Principles CRs:
- 2008107552,
- 2008105114, 2008100384
Section 1R15: Operability Evaluations
- CR:
- 2007105396,
- 2008107899,
- 2008107935,
- 2008107915,
- 2008107950,
- 2008104839,
- 2008104293,
- 2006105330
- 4MWO:
- 2071205501,
- 1080754901 Procedures: 34AR-650-902-2, Annunciator Response 34AB-R22-002-2, Loss of 4160 Emergency Bus 34AR-652-207-2, Diesel Gen B Loading Timer Failure 34SV-R43-001-1 Diesel Generator 1A Monthly Test 42IT-TET-014-2, Safeguard Equipment Room Coolers Data Collection Drawing:
- SX-23528, Operation and Maintenance Manual for the Reactor Building Safeguard System Cooling Units Action Item
- 2006202467 Unit-2 FSAR sections 6 and 9 Unit-2 Technical Specification Bases 3.8.1
- Unit-1 Technical Specifications Section 3.7.5 Control room logs Unit-2 Technical Specifications Section 3.7.2, 3.7.1
Section 1R18: Plant Modifications
- Procedures:
- NMP-ES-022, DCP Site Approval Implementation and Closure
- 34SV-E11-001-1, Residual Heat Removal Pump Operability MWOs:
- 2081616501,
- 1081269706
- DOEJ-HE2081618501-C001 Drawings: B-45379, CA93007
- CR 2007110724
Section 1R19: Post Maintenance Testing
- MWO:
- 1071167101,
- 2030038601,
- 2081312501,
- 1071384517,
- 2051734101,
- 2030173001,
- 1071624601 Procedures: 95IT-OTM-001-0, Maintenance Work Order Functional Test Guideline
- 34SV-B21-001-1, MSIV Exercise and 10% Closure Instrumentation Functional Test
- 34SV-B21-002-1, MSIV Trip Test completed sat.
- 2SV-B21-001-1, MSIV Limit Switch Response and Component Inspection/Repair 95IT-OTM-001-0, Maintenance Work Order Functional Test Guideline
- 2GM-MME-025-0, Removal of Pipe Hangers, Restraints, and Supports 52CM-MME-024-0, Fisher Type 657 Actuators Sizes 30-70 and 87 52CM-MME-017-0, Fisher Control Design ED, EAD, ES, EAS, ET, EAT, EWD,& EWT Valves 57CP-CAL-250-0, Flow Scanner Data Acquisition 57CP-CAL-097-2, Rosemount 1153 and 1154 Transmitters
- 51GM-MNT-002-0, Maintenance Housekeeping 52PM-C11-003-1, CRD SCRAM Valve Maintenance 51GM-MNT-033-0, Torque of Pressure Boundary Applications 42SV-SUV-040-2, Check Valve Internals Inspection 51GM-MNT-048-0, Bolted Bonnet Swing Check Valve Maintenance
- 2IT-TET-004-0, Operating Pressure Testing of Piping and Components 52CM-MNT-001-0, Minitork Valve Maintenance 42It-TET-012-2S, Plant Service Water and RHR Service Water Piping Inspection Procedure 52CM-MME-001-0, Packing Valves, Adjusting Packing, and Stroking Valves Drawing S-80175 - MSIV Instruction Manual
- 5Engineering Evaluation 747, 750,
- CR:2008102989,
- 2008103425,
- 2008102223, 2008100393
Section 1R20: Refueling and Outage Activities
- 34AB-C71-001-1 Reactor Scram Procedure 34-GO-OPS-001-1, Plant Startup
- CRs:
- 2008107160,
- 2008107168,
- 2008107170, 2008107175
Section 1R22: Surveillance Testing
- 31GO-INS-001-0, Pump and Valve Inservice Testing (IST) CRs:
- 2008109526,
- 2008109405,
- 2008108873,
- 2008108383,
- 2008108196, 2008108223
Section 1EP2: Alert and Notification System Testing
Procedures
and Documentation
- DI-TRN-49-0691N, Alert and Notification Radio Program, Rev. 3.0
- Records and Data Transient Sign Inspection Record, January 2006 - July 2008
- Tone Alert Radio Phone Survey Tabulation, February 20, 2008 2006 Annual Report of the Edwin I. Hatch Nuclear Plant EPZ Prompt Notification Program 2007 Annual Report of the Edwin I. Hatch Nuclear Plant EPZ Prompt Notification Program
- CR2008108978
Section 1EP3: Emergency Response Organization Augmentation
Procedures
- Severe Accident Management Training Plan, System Master Plan, Rev. 02 System Master Plan, Emergency Preparedness Training, Rev. 08
- Records and Data All Call Training Drill, May 22, 2008 at 8:31 pm Staff Augmentation Drill, June 17, 2008 at 7:30 pm Staff Augmentation Drill, August 12, 2008 at 7:40 pm Training records of selected key ERO personnel E.I. Hatch Nuclear Plant Emergency Call List, June 23, 2008
Section 1EP4: Emergency Action Level and Emergency Plan Changes
- Radiological Emergency Plan, Rev. 27 Change package for Radiological Emergency Plan, Rev. 27 Change package for 73EP-EIP-001-0, Emergency Classification and Initial Conditions, Rev. 16.0, 16.1 Change package for 73EP-EIP-004-0, Duties of Emergency Director, Rev. 9.4 Change package for 73EP-EIP-063-0, Technical Support Center Activation, Rev. 9.0
- NMP-EP-109, Protective Action Recommendations, Rev. 2.0
Section 1EP5: Correction of Emergency Preparedness Weaknesses and Deficiencies
- C-EP-2007, Quality Assurance Audit of Plants Farley, Hatch, Vogtle Offsite Emergency Preparedness Support, March 20, 2007
- 6H-EP-2007, QA Audi of Emergency Preparedness (EP), March 20, 2007 J-EP-2008, Joint Fleet Oversight Audit of Emergency Preparedness, March 27, 2008 C-EP-2008, Fleet Oversight Audit of Plants Farley, Hatch, Vogtle Offsite Emergency Preparedness Support, April 29, 2008 CR2007100162(CS), Fleet Emergency Preparedness Team Self Assessment,
- January 29-February 2, 2007
- Records and Data
- EP-0608-002, Documentation package for 2008 EP Exercise 02 conducted June 3, 2008
- EP-0408-001, Documentation package for 2008 EP Exercise 01 conducted March 25, 2008
- EP-0706-001, Documentation package for 2006 EP Exercise 01 conducted May 17, 2006
- EP-0706-002, Documentation package for 2006 EP Exercise 02 conducted June 14, 2006
- EP-0906-004, Documentation package for 2006 EP Exercise 03 conducted August 26, 2006
- EP-1006-003, Documentation package for 2006 EP Exercise 04 conducted October 18, 2006
- EP-0607-003, Documentation package for 2007 EP Exercise 01 conducted May 30, 2007
- EP-0807-003, Documentation package for 2007 EP Exercise 02 conducted July 11, 2007
- EP-0907-001, Documentation package for 2007 EP Exercise 03 conducted August 22, 2007
- EP-1207-001, Documentation package for 2007 EP Exercise 04 conducted November 14, 2007
- CRs:
- 2008100135,
- 2008100233,
- 2007103494,
- 2008100234,
- 2006109304,
- 2007104560,
- 2007106895,
- 2007107525,
- 2007107777,
- 2007107779,
- 2007108050,
- 2007108787,
- 2007108878,
- 2007109201,
- 2007109300,
- 2007109999,
- 2007110095,
- 2007110860,
- 2007110873,
- 2007111300,
- 2007111383,
- 2007111416,
- 2008100487,
- 2008101259,
- 2008101376,
- 2008102281,
- 2008103925,
- 2008104352,
- 2008104355,
- 2008105371,
- 2008106075,
- 2008106196,
- 2008107275, 2008107713
Section 1EP6: Drill Evaluation
- Drill scenario for HNP Emergency Preparedness 2008 Exercise 03 Southern Nuclear Emergency Notification Forms
Section 4OA1: Performance Indicator Verification
- LER
- 2-2008-002
- Hatch Key Performance Indicators 00AC-REG-005-0, Preparation and Reporting of NRC PI Data, Rev. 5.5
- DEP data from 3
rd Qtr 2007 to 2
nd Qtr 2008 ERO data from 3
rd Qtr 2007 to 2
nd Qtr 2008
Section 4OA2: Identification and Resolution of Problems
- NMP-AD-010, 10CFR 50.59 Screenings and Evaluations Apparent Cause Determination Grading Sheets Monthly CAP Performance Indicators Key Performance Indicators Trend Evaluation File Corrective Action Program Performance Indicators
Section 4OA5: Other Activities
- Applicability Determination, Dry Cask Storage - 10
- CFR 72.212 Report - Revision for 2008 Loading Campaign
- 710
- CFR 72.48 Screening/Evaluation, Dry Cask Storage - 10
- CFR 72.212 Report - Revision for 2008 Loading Campaign Radiological Cask Surveys # 44983, 44984, 45728, 45730 Fuel Assembly Certification Datasheets
- MPC-68 Loading Pattern Datasheets
- Loading Verification
- Datasheets
- 2FH-ENG-030-0 SNM Unit Physical Inventory dated 6/18/08 34FH-OPS-002-0, Dry Fuel Movement Prerequisites
- NMP-DP-001, Operational Risk Awareness 52PM-F18-003-0, Spent Fuel Dry Storage Transporting Equipment
- NMP-AD-006, Infrequently Performed Tests and Evolutions
- 51GM-MLH-004-0, NUREG 0612 Heavy Load Movement Design Calculation SENH 89-009, Steady State Loading On Emergency Buses 1E, 1F, & 1G During LOSP/LOCA/SBO Design Calculation SENH 89-015, Steady State Loading On Emergency Buses 2E, 2F, & 2G During LOSP/LOCA/SBO Technical Specifications/Bases Section 3.8.1 Unit-1 FSAR Section 8.4
- Unit-2 FSAR Section 8.3 Letter dated September 6, 1983 from Colt Industries detailing EDG capacities 34SV-R43-011-1, Diesel Generator 1A 24 Month Operability Test 34SV-R43-001-1, Diesel Generator 1A Monthly Test 34SV-R43-004-1, Diesel Generator 1A Semi-Annual Test
- 34SV-R43-013-1, Diesel Generator 1C 24 Month Operability Test 34SV-R43-003-1, Diesel Generator 1C Monthly Test 34SV-R43-006-1, Diesel Generator 1C Semi-Annual Test 34SV-R43-011-2, Diesel Generator 2A 24 Month Operability Test 34SV-R43-001-2, Diesel Generator 2A Monthly Test
- 34SV-R43-004-2, Diesel Generator 2A Semi-Annual Test 34SV-R43-013-2, Diesel Generator 2C 24 Month Operability Test 34SV-R43-003-2, Diesel Generator 2C Monthly Test 34SV-R43-006-2, Diesel Generator 2C Semi-Annual Test 34SV-R43-002-1, Diesel Generator 1B Monthly Test
- 34SV-R43-005-1, Diesel Generator 1B Semi-Annual Test 34SV-R43-012-2, Diesel Generator 1B 24 Month Operability Test 34SV-R43-002-2, Diesel Generator 1B Monthly Test 34SV-R43-005-2, Diesel Generator 1B Semi-Annual Test CRs:
- 2001010670,
- 2003002594, 2004111628