IR 05000321/2021001

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000321/2021001 and 05000366/2021001
ML21126A020
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 05/06/2021
From: Alan Blamey
NRC/RGN-II/DRP/RPB2
To: Gayheart C
Southern Nuclear Operating Co
References
IR 2021001
Download: ML21126A020 (33)


Text

May 6, 2021

SUBJECT:

EDWIN I. HATCH NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000321/2021001 AND 05000366/2021001

Dear Ms. Gayheart:

On March 31, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Edwin I. Hatch Nuclear Plant. On April 22, 2021, the NRC inspectors discussed the results of this inspection with Sonny Dean and other members of your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealing findings were identified during this inspection.

A licensee-identified violation which was determined to be of very low safety significance is documented in this report. We are treating this violation as a non-cited violation (NCV)

consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Edwin I. Hatch Nuclear Plant.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Alan J. Blamey, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos. 05000321 and 05000366 License Nos. DPR-57 and NPF-5

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000321 and 05000366

License Numbers:

DPR-57 and NPF-5

Report Numbers:

05000321/2021001 and 05000366/2021001

Enterprise Identifier: I-2021-001-0067

Licensee:

Southern Nuclear Operating Co., Inc.

Facility:

Edwin I. Hatch Nuclear Plant

Location:

Baxley, GA

Inspection Dates:

January 01, 2021 to March 31, 2021

Inspectors:

J. Hickman, Resident Inspector

B. Kellner, Senior Health Physicist

M. Magyar, Reactor Inspector

A. Nielsen, Senior Health Physicist

W. Pursley, Health Physicist

D. Simpkins, Senior Technical Training Program Specialist

R. Smith, Senior Resident Inspector

N. Staples, Senior Project Engineer

Approved By:

Alan J. Blamey, Chief

Reactor Projects Branch 2

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Edwin I. Hatch Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report Section: 71124.0

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000321/2020-001-00 LER 2020-001-00 for Edwin I. Hatch Nuclear Plant Unit 1, 1A EDG Inoperable Due to Water in the Day Tank 71153 Closed

PLANT STATUS

Unit 1 began the inspection period at 100 percent rated thermal power (RTP). On January 9, 2021, the unit was down powered to 70 percent RTP to perform a sequence exchange and turbine valve testing and on January 10, 2021, the unit was returned to 100 percent RTP. On March 20, 2021, the unit was down powered to 70 percent RTP to perform a sequence exchange, scram time testing, turbine valve testing and attempted to repair a steam leak in the condenser bay and on March 21, 2021, the unit was returned to 100 percent RTP. On March 22, 2021, the unit was down powered to 93.5 percent RTP for rod pattern adjustment and was retuned to 100 percent RTP on the same day and operated there for the remainder of the inspection period.

Unit 2 began the inspection period at 91 percent RTP in its end cycle coast down for the winter refueling outage. On January 7, 2021, the unit was down powered to 70 percent RTP to remove the fourth stage feed water heaters from service, this was to achieve an increase in RTP due to removing feed water heating. On January 7, 2021, the Unit returned to 97 percent RTP and continued the end cycle coast down to the refueling outage. On February 8, 2021, the operators shut down the unit for the scheduled refueling outage. The unit was restarted on March 7, 2021 and reached approximately 100 percent RTP on March 13, 2021. On March 19, 2021, the unit was down powered to 98 percent RTP to perform the final rod pattern adjustment after startup was returned to 100 percent RTP on the same day. On March 26, 2021, the unit was down powered to 93 percent RTP due to isolation of the fourth stage B high pressure feed water heater and was returned to 100 percent RTP on March 29, 2021 and operated there for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the Coronavirus Disease 2019 (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week; conducted plant status activities as described in IMC 2515, Appendix D, Plant Status; observed risk-significant activities; and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portions of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather for a tornado watch in the area on February 15 and 18, 2021.

External Flooding Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated that flood protection barriers, mitigation plans, procedures, and equipment are consistent with the licensees design requirements and risk analysis assumptions for coping with external flooding on February 23, 2021.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Alignment of 2C Emergency Diesel Generator (EDG) following 34SV-R43-003-2 Diesel Generator 2C Monthly Test, 34SO-R43-001-2, Diesel Generator Standby AC System, Attachments 2 and 3, Version 30.8 on January 19, 2021.
(2) Alignment of 2B Core Spray (CS) during refueling outage, the system was relied on for Emergency Reactor Pressure Vessel inventory control on 02/10/2021.
(3) Alignment of 2A CS during refueling outage, the system was relied on for emergency reactor pressure vessel inventory control on 02/10/2021.
(4) Alignment of 1A EDG following 34SV-R43-001-1 Diesel Generator 1A Monthly Test, 34SO R43-001-1, Diesel Generator Standby AC System, Attachments 1, 2 and 3, Version 29.4, on March 11, 2021.

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 2 Primary Containment Purge & Inerting System on March 23, 2021.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1/2 Station Battery Rooms, Drawing A-43965 Sheets 011, 012, 017, and 018 on January 14, 2021.
(2) Unit 1 EDG 1C and Switchgear Room 1G, drawings A43966 Sheets 8A, 8B, 9A and 9B on January 20, 2021.
(3) Unit 2 600V Switchgear Rooms 2C and 2D Drawing A-43956 Sheets 37A and 38A, on January 27, 2021.
(4) Unit 1 Northeast Residual Heat Removal (RHR) and CS pump room, and the control rod drive (CRD) and the High Pressure Coolant Injection (HPCI) Pump room Drawing A-43965 Sheets 53A, 54A, 55A, 53B, 54B and 55B, on February 3, 2021.
(5) Unit 1 Reactor Core Isolation Cooling (RCIC) Pump and Turbine Room, and the Southeast RHR and CS pump room, Drawings A43965 Sheets 51A, 52A, 51B and 52B on February 3, 2021.
(6) Unit 1 Reactor Building (RB) 130 foot elevation including CRD Hydraulic Units, various switchgears, drawing 43965 Sheets 51A, 51B, 52A, 52A, 53A, 53B, 54A, 54B, 55A and 55B on February 2, 2021.

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protection in the:

(1) Unit 2, RCIC and HPCI rooms on March 19, 2021.

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) 1A EDG associated heat exchangers: jacket water cooler, lube oil cooler and scavenger air cooler.

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

(1) The inspectors evaluated BWR Non-destructive Testing by reviewing the following examinations from February 22 - 26, 2021:
  • Ultrasonic Testing (UT)a. 2B11/2N8A, A Loop JP INSTR Nozzle to Shell, ASME Class 1 (reviewed)b. 2B11/2N8A (IR), A Loop JP INSTR Nozzle IR, ASME Class 1 (reviewed)

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during plant shutdown, they observed power decrease by reducing Reactor Recirculation Flow to minimum, inserting control rods to 20 percent RTP, followed by a Main Turbine trip, and the insertion of a Manual Reactor SCRAM to complete the shutdown. They then observed the operating crew establish a controlled cooldown rate within Technical Specification (TS) limits, for the Unit 2 Refueling Outage, on February 7 and 8, 2021.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated License Operator Requalification Program (LORP) Scenario H-LTC-SE-50322, "Shutdown Cooling (SDC) Operation / Loss of SDC / SOER 09-1," for one team during simulator training on January 12, 2020.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Review of the Unit 2 Drywell Chillers system 2P64 due to unplanned trips during 2020, on March 24, 2021.
(2) Review of the Unit 1 and 2 FLEX Equipment due to Operating Experience Smart Sample 2020/01, Flex Equipment Design Control, Maintenance and Testing, on March 31, 2021.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 2 elevated risk due to the HPCI system outage on January 13, 2021.
(2) Unit 1 elevated risk due RHR Loop A out of service to perform a repair on 2E11-F047A heat exchanger inlet valve, on January 27, 2021.
(3) Unit 2 elevated risk as the unit entered refueling outage 26, on February 7, 2021
(4) Unit 1 and Unit 2 evaluated risk due to the Plant Service Water (PSW) underground pipe leak and repairs which resulted in 2C EDG inoperability, on March 1, 2021.
(5) Unit 1 elevated risk due to the liner replacement on 1A EDG on March 22, 2020.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (7 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 2 HPCI Pump inoperable due to high Comprehensive Pump Test (CPT)differential pressure ratio on January 6, 2021.
(2) Unit 2 Main Turbine Emergency Overspeed Trip Protection loss of ability to test the sensors on June 6, 2020.
(3) Unit 1 EDG 1A, scavenging air is leaking from the air receiver covers 2C and 3C due to missing gasket material on January 25, 2021.
(4) Unit 1 Scaffold Impact on SCRAM Discharge Volume Drain Isolation Line and Scaffold over High Energy Line Break (HELB) grating on February 4, 2021.
(5) Unit 2 Drywell Air Lock and Equipment Hatches Seal Grease on the Sealing Surfaces Potential Effect on Local Leak Rate Test Results, on February 12, 2021.
(6) Unit 2 EDG 2C trip during monthly testing, on March 11, 2021.
(7) Unit 2 NE Diagonal room coolers after 2T41B003A room cooler fan rotor assembly catastrophically failed, on March 15, 2021.

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) SNC632608, Unit 2 Main Control Room Feedwater Controller replacement due to current controllers being obsolete.
(2) SNC1010116CCP, Unit 2, Change Power Supply Breaker Micro Versa Trip settings due to breaker coordination issues associated with National Fire Protection Association (NFPA) 805 requirements.

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (10 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1)34SV-P41-001-1, Plant Service Water Operability, Version 15.2 following replacement of the 1C Plant Service Water Pump Motor, Work Order SNC556025, on January 10, 2021.

(2)34SV-R43-001-2, Diesel Generator 2A Monthly Test, Version 29.4 following the replacement of expansion joint 2P41D002D, Work Order SNC1139786, on January 29, 2021.

(3)34SV-R43-003-1, Diesel Generator 1C Monthly Test, Version 20.2 following repair of a lube oil leak, Work Order SNC137368, on February 5, 2021.

(4)42SV-TET-001-2, Primary Containment Periodic Type B & C Leakage Test, Version 37.2 following the replacement of 2T48-F320 containment vent and purge valve, on February 26. 2021.

(5)34SV-B21-011-2, Automatic Depressurization System Logic System Functional Test, Version 1.1 following safety relief valve maintenance, on February 26, 2021.

(6) NMP-ES-024, Nondestructive Examination and Certification Processes, Version 7.0 following 2C EDG Plant Service Water pipe repairs, on March 2, 2021.

(7)57CP-C51-002-0, Intermediate Range Monitor (IRM) Detector Testing, Version 3.3 following the installation of new IRM E detector, on February 26, 2021.

(8)42SV-C11-003-0, Control Rod SCRAM Timing, Version 11.1, following the replacement of 20 control rod drive mechanisms, on March 2, 2021.

(9)34SO-C51-001-0, Tip System Operation and Local Power Range Monitor (LPRM)

Calibration, Version 19.4, following the replacement of three LPRM strings during the Unit 2 refueling outage, on March 10 and 16, 2021.

(10)52SV-R43-001-0, Diesel, Alternator, and Accessories Inspection, Version 31.21, following the liner replacement on 1A EDG on March 28, 2021.

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated Unit 2 refueling outage 26 activities from February 7, 2020 to March 9, 2021.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1)34SV-R43-003-1, Diesel Generator 1C Monthly Test, Ver. 20.2 on January 13, 2021.

(2)34SV-E21-001-1, Core Spray Pump 1A Pump Operability, Version 24.2, January 26, 2021.

(3)34SV-E11-004-1, RHR Service Water Pump Operability, Version 22.1, on February 4, 2021.

(4)34SV-E41-010-2, HPCI Logic Function System Test, Version 1.2, on February 10, 2021 and March 5, 2021.

(5)34SV-E51-010-2, RCIC Logic Function System Test, Version 1.5, on February 10, 2021.

(6)34SV-R43-020-2, Diesel Generator 2A Loss of Coolant Accident/Loss of Offsite Power (LOCA/LOSP) Logic Function System Test, Version 4.0, on February 12, 2021.

(7)34SV-T48-002-2, Suppression Chamber to Drywell Vacuum Breaker Operability And Containment Purge/Vent Valve Position Check, Version 5.8, on March 4, 2021.

Inservice Testing (IP Section 03.01) (1 Sample)

(1) 34SV-E41-002-2, HPCI Pump Operability CPT, Version 39.1 on January 6, 2021.

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1)42SV-TET-001-0, Local leak Rate Testing (LLRT) Testing Methodology, Version 13.0, on 2E11-F016B RHR Containment Spray Outboard Isolation Valve on February 17, 2021.

FLEX Testing (IP Section 03.02) (1 Sample)

(1) SNC1060565, Mode 5 Core Cooling Pump Functional Test on January 11,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

The inspectors evaluated instructions to workers including radiation work permits used to access high radiation areas.

(1)

  • RWP 21-2014, Torus Diving
  • RWP 21-2205, Vessel Disassembly/Reassembly
  • Radioactive Material Labels in the U2 Reactor Building, Refueling Floor, and Turbine Building

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) Personnel and equipment released from the Radiation Controlled Area (RCA)
(2) Excavated earth released from the protected area (PA)

Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.

(1) Drywell Head Lift
(2) Reactor Head Lift
(3) Fuel Movement

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (2 Samples)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:

(1) U2 Reactor Building
(2) Turbine Building Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.02 - Occupational ALARA Planning and Controls

Radiological Work Planning (RWP) (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensees radiological work planning for the following:

(1) ALARA Plan for RWP 21-2205, U2 Reactor Disassembly/Reassembly
(2) ALARA Plan for RWP 20-1602, Repair 1E11F050A
(3) ALARA Plan for RWP 20-1620, U1 Drywell Scaffolding Work (4)2021 Annual Site ALARA Goal Estimate

Verification of Dose Estimates and Exposure Tracking Systems (IP Section 03.02) (4 Samples)

The inspectors reviewed the following as low as reasonably achievable evaluations of radiological outcomes:

(1) RWP 20-1620 Post Job Review - Drywell/Steam Chase Install/Remove-Shielding, Tents & Scaffolds & Support Activities
(2) RWP 20-1205 Post Job Review - Refuel Floor Vessel Disassembly/Reassembly, Cavity/Dryer Separator Work & Support
(3) Unit One H1R29 Outage ALARA Summary Report (4)2019 Plant Hatch Annual ALARA Report

Implementation of ALARA and Radiological Work Controls (IP Section 03.03) (3 Samples)

The inspectors reviewed as low as reasonably achievable practices and radiological work controls for the following work activities:

(1) RWP 21-2014, Torus Diving
(2) RWP 21-2205, Vessel Disassembly/Reassembly
(3) RWP 21-2608, CRD Exchange

Radiation Worker Performance (IP Section 03.04) (1 Sample)

The inspectors evaluated radiation worker and radiation protection technician performance during:

(1) Torus Diving Vessel Disassembly/Reassembly CRD Exchange

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Permanent Ventilation Systems (IP Section 03.01) (1 Sample)

The inspectors evaluated the configuration of the following permanently installed ventilation systems:

(1) Main Control Room Habitability Filter Train

Temporary Ventilation Systems (IP Section 03.02) (1 Sample)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1) HEPA filtration systems used on the refuel floor

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) Observed use of powered air-purifying respirators during drywell head lift

Self-Contained Breathing Apparatus (SCBA) for Emergency Use (IP Section 03.04) (1 Sample)

(1) Observed storage of SCBA designated for emergency use and discussed preventative maintenance with licensee technicians. Reviewed breathing air testing records.

71124.04 - Occupational Dose Assessment

Source Term Characterization (IP Section 03.01)

The inspectors evaluated licensee performance as it pertains to radioactive source term characterization.

External Dosimetry (IP Section 03.02)

The inspectors evaluated licensee's external dosimetry program

Internal Dosimetry (IP Section 03.03) (3 Samples)

The inspectors evaluated the internal dosimetry program implementation as follows:

(1) In-vivo analysis results for worker ID#22939 Dated 02/27/2019.
(2) Reviewed licensee position paper for exemption from in-vitro urinalysis in cases where tritium concentrations in the water in the torus is below 1E-2 microcuries per milliliter.
(3) In-vivo analysis results for worker ID#19564 Dated 06/21/2020.

Special Dosimetric Situations (IP Section 03.04) (3 Samples)

The inspectors evaluated the following special dosimetric situation:

(1) Licensees records for two declared pregnant workers.
(2) Licensees implementation of extremity monitoring for "under vessel" work for two workers.
(3) Licensees implementation of requirements for monitoring EDE with multiple dosimeters during diving activities in the unit 2 spent fuel storage area for two workers.

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (7 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Portable survey instruments (ion chamber, friskers, telepoles) ready for use located at the RP counting lab.
(2) Tennelec and Sodium Iodide (NaI) scaler low background counter located at the RP counting lab.
(3) Argos-5AB and Gem-5 personnel contamination monitors located at the main radiologically controlled area exit and the protected area exit.
(4) Gamma spectroscopy units located in the Chemistry counting room.
(5) Whole body counting system located in the dosimetry office.
(6) SAM-12 small article monitors located at the RCA exit.
(7) Area Radiation Monitors (ARMs) located in various areas throughout the RCA.

Calibration and Testing Program (IP Section 03.02) (11 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Serial Number (S/N) 322210, MPL #: D21-N1960, Ludlum Model 2200 Scaler with NaI detector, 12/2/2020
(2) S/N 268, MPL #: D21-N1931, Thermo-Eberline SAM-12, 12/12/2021
(3) S/N 718A, MPL #: D21-N1487, Thermo-Eberline Model RM-25 countrate meter, 5/10/2019
(4) S/N 706, MPL #: D21-N1514, Thermo-Eberline Model RM-25 countrate meter, 6/3/2019
(5) S/N 1483/725680, MPL #: D21-N1646, Thermo-Eberline Model ASP-2E with NRD HD neutron detector, 11/3/2019 and 12/9/2020
(6) S/N 3569, MPL #: D21-N1633, Bicron Electra 1B/AP5BD alpha countrate meter, 1/17/2018 and 2/18/2019
(7) S/N 7108, MPL #: D21-N180, Eberline Model E-120 countrate meter, 12/2/2019 and 12/4/2020
(8) S/N 709, MPL #: D21-N1137, Eberline Model RO-20 Ion Chamber, 7/2/2020
(9) S/N 5681, MPL #: D21-N1733, Eberline Model RO-20 Ion Chamber, 7/2/2020
(10) S/N 42123-2, MPL #: D21-N1380, automatic Tennelec low background counter, 7/1/2020
(11) S/N 1301-003, MPL #: D21-N1905, Canberra ARGOS-5AB personnel contamination monitor, 11/24/2020

Effluent Monitoring Calibration and Testing Program Sample (IP Sample 03.03) (3 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Work Order (W/O) SNC968111, Unit 1 Drywell High Range Radiation Monitors 1D11-K621A & B Calibration [24 month calibration - electronics only], 03/12/2020
(2) W/O SNC821119, Unit 1 Drywell High Range Radiation Monitors 1D11-K621A & B Calibration [24 month calibration - electronics only], 09/27/2017
(3) W/O SNC1014242, Unit 2 Reactor Building Vent Stack D11-K636A, repair and perform Functional Test and Calibration, 4/27/2019

71124.07 - Radiological Environmental Monitoring Program

GPI Implementation (IP Section 03.03) (1 Partial)

(1)

(Partial)

The inspectors evaluated a reported leak of tritium from the unit two condensate storage tank pump moat.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 03.01)===

(1) Unit 1 (January 1, 2020 to December 31, 2020)
(2) Unit 2 (January 1, 2020 to December 31, 2020)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 03.02) (2 Samples)

(1) Unit 1 (January 1, 2020 to December 31, 2020)
(2) Unit 2 (January 1, 2020 to December 31, 2020)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 03.03) (2 Samples)

(1) Unit 1 (January 1, 2020 to December 31, 2020)
(2) Unit 2 (January 1, 2020 to December 31, 2020)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 03.15) (1 Sample)

(1) January 1, 2020 through January 31, 2021

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 03.16) (1 Sample)

(1) November 30, 2020 through January 31, 2021

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Root Cause Determination Report 278526, Unplanned Power Changes Performance Indicator Low Margin Hatch Unit 1 during 2020, was reviewed by inspectors, on March 15, 2020.

71153 - Follow-up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000321/2020-001-00, 1A EDG Inoperable due to water in day tank (ADAMS Accession No. ML20345A083) on December 10, 2020. The inspection conclusions associated with this LER are documented in Inspection Report 05000321/2020002 under Inspection Results Section

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71124.07 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: 10CFR20 1406(c) requires in part, that licensees, to the extent practical, conduct operations to minimize the introduction of residual radioactivity into the site, including the subsurface. Contrary to this requirement, on February 1, 2021, as the result of the licensee's failure to perform, to the extent practical, maintenance activities on the unit two condensate storage tank transfer pump moat to minimize the introduction of residual radioactivity to the site subsurface, leakage of elevated tritium activity from the moat was detected in an adjacent ground water monitoring well.

Significance/Severity: Green.

Corrective Action References: CR

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 22, 2021, the inspectors presented the integrated inspection results to Sonny Dean and other members of the licensee staff.
  • On February 26, 2021, the inspectors presented the ISI Baseline Inspection and HP Occupational Baseline Inspection results to Sonny Dean, Site VP and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Calculations

SCNH-13-020

Hatch Probable Maximum Flood Hydraulics - Severe

Accident Management (SAM) for Fukushima Near-Term

Task Force (NTTF) Recommendation 2.1 Flooding

Reevaluation

1.0

71111.01

Calculations

SCNH-13-021

Evaluation of Plant Hatch Local Intense Precipitation -

Severe Accident Management (SAM) for Fukushima

Near-Term Task Force (NTTF) Recommendation 2.1

Flooding Evaluation

1.0

71111.01

Corrective Action

Documents

Resulting from

Inspection

10776017

2/18/2021

71111.01

Miscellaneous

HNP-2-FSAR-2

Hatch Nuclear Plant, Final Safety Analysis Reports

Updates, Chapter 2

71111.01

Miscellaneous

Natural Weather

Service Watch,

Warning & Advisories

Tornado Watch

2/15/2021

71111.01

Procedures

34AB-Y22-002-0

Naturally Occurring Phenomena

19.2

71111.01

Procedures

34AR-650-206-2

Plant Service Water Valve Pit Sumps Level High

1.2

71111.01

Procedures

NMP-OS-017

Severe Weather Attachments 1 through 8

2/15/2021

71111.01

Procedures

NMP-OS-017

Severe Weather Attachments 1 through 9

2/18/2021

71111.01

Procedures

NMP-OS-017

Severe Weather

3.0

71111.04

Corrective Action

Documents

Resulting from

Inspection

10773366

2/10/2021

71111.04

Corrective Action

Documents

Resulting from

Inspection

10784664

03/23/2021

71111.04

Drawings

H-26018

Unit 2 Core Spray System P&ID

40.0

71111.04

Drawings

H-26083

Hatch Unit 2 Nitrogen Inerting System P&ID

45.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Drawings

H-26084

Hatch Nuclear Plant Unit 2 Primary Containment Purge

and Inerting System P&ID

2.0

71111.04

Procedures

34SO-E21-001-2

Core Spray System operating procedure

26.5

71111.04

Procedures

34SO-R43-001-1

Diesel Generator Standby System

29.2

71111.04

Procedures

34SO-R43-001-2

Diesel Generator Standby AC System, Attachments 2

and 3

30.8

71111.04

Procedures

34SO-T48-002-2

Containment Atmospheric Control and Dilution Systems

29.7

71111.05

Corrective Action

Documents

Resulting from

Inspection

10768272

01/21/2021

71111.05

Corrective Action

Documents

Resulting from

Inspection

10769666

01/27/2021

71111.05

Corrective Action

Documents

Resulting from

Inspection

10770244

01/29/2021

71111.05

Corrective Action

Documents

Resulting from

Inspection

10771474

2/03/2021

71111.05

Corrective Action

Documents

Resulting from

Inspection

10771727

2/04/2021

71111.05

Corrective Action

Documents

Resulting from

Inspection

10771737

2/04/2021

71111.05

Drawings

A-43965 Sheets 53A

and 53B

NE RHR & Core Spray Room

2.0

71111.05

Drawings

A-43965 Sheets 011,

Unit 1/2 Station Battery Rooms

3.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2, 017, and 018

71111.05

Drawings

A-43965 Sheets 51A

and 51B

SE RHR & Core Spray Room

2.0

71111.05

Drawings

A-43965 Sheets 52A

and 52B

RCIC Pump and Turbine Room

2.0

71111.05

Drawings

A-43965 Sheets 54A

and 54B

CRD and DRW Sump Room

2.0

71111.05

Drawings

A-43965 Sheets 55A

and 55B

HPCI Pump Room

2.0

71111.05

Drawings

A-43966 8A, 8B, 9A

and 9B

PRE-Fire Plan Diesel Generator Room 1C

2.0

71111.05

Drawings

H11846

Fire Hazards Analysis Diesel Generator BLDG

3.0

71111.05

Fire Plans

A-43965 Sheet 37A

Pre-Fire Plan 600V Switchgear Room 2C

4.0

71111.05

Miscellaneous

Email from the Senior

Fire Protection

Engineer Plant Hatch

Update on CR 10769666

2/03/2021

71111.05

Miscellaneous

Evaluation of Fire

Barrier Degradation

2/10/2020

71111.05

Procedures

DI-OPS-72-1204

Fire Brigade Gear Restoration

15.2

71111.06

Calculations

H-RIE-IF-U00-001

Hatch Internal Flood Notebook - Tasks 1, 2, and 3

1.0

71111.06

Corrective Action

Documents

Resulting from

Inspection

10783738

03/19/2021

71111.06

Fire Plans

A-43965 Sheet 38A

Pre-Fire Plan 600V Switchgear Room 2D

71111.06

Procedures

34SO-G11-013-2

Drywell and Reactor Building Sump Systems

1.4

71111.06

Procedures

57IT-T45-002-2

Sump Isolation Valve Actuation Test

0.3

71111.07A

Procedures

2SV-R43-001-0

Diesel, Alternator, and Accessories Inspection

31.21

71111.07A

Procedures

NMP-ES-012-001

Inspection of Heat Exchangers

03/24/2021

71111.11Q Miscellaneous

H-LT-SG-50332

Shutdown Cooling (SDC) Operations / Loss of SDC /

SOER 09-1

29.4

71111.11Q Procedures

34GO-OPS-007-0

Shutdown/Refueling Mode Preparation Strategy For

Flex

1.2

71111.11Q Procedures

34GO-OPS-013-2

Normal Plant Shutdown

33.5

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.12

Corrective Action

Documents

10676552

01/09/2020

71111.12

Corrective Action

Documents

10702333

04/12/2020

71111.12

Corrective Action

Documents

10704587

04/23/2020

71111.12

Corrective Action

Documents

10744782

10/09/2020

71111.12

Corrective Action

Documents

10744782

10/09/2020

71111.12

Corrective Action

Documents

10753668

11/13/2020

71111.12

Corrective Action

Documents

10755578

11/21/2020

71111.12

Corrective Action

Documents

CAR278637

Unit 2A drywell Chiller Trip

2/29/2020

71111.12

Corrective Action

Documents

CAR278637

Unit 2A Drywell Chiller Trip

2/29/2020

71111.12

Corrective Action

Documents

Resulting from

Inspection

10786885

3/31/2021

71111.12

Engineering

Evaluations

EVAL-H-P64-05230

Applicable to Both 2P64B006A and 2P64B006B Drywell

Chillers a(1) Review

2/30/2020

71111.12

Engineering

Evaluations

TE1066690

05/22/2020

71111.12

Engineering

Evaluations

TE1068785

06/30/2020

71111.12

Engineering

Evaluations

TE1076069

11/05/2020

71111.12

Engineering

Evaluations

TE1078644

2/02/2020

71111.12

Engineering

Evaluations

TE4078088

2/08/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.12

Miscellaneous

Maintenance Rule

SSC Function

Consolidation and

Performance Criteria

Selection Form for P-

Primary

Containment Chilled

Water (Unit 2)

11/12/2019

71111.12

Miscellaneous

PMCR99240

2P64-B006A/B Main Oil Pump Motor Starter

03/12/2021

71111.12

Procedures

FL600DG1Y-H

Flex 600V Diesel Generator Operational Inspection

Work Instructions

08/16/2018

71111.12

Procedures

FL600VDG1Y-H4

FLLEX 600V Stack Diesel Generator Performance Test

Work Instructions

01/07/2021

71111.12

Procedures

FL600VDG3Y-H

FLEX 600V Diesel Generator Performance Test Work

Instructions

08/16/2018

71111.12

Procedures

FL600VDG3Y-H4

FLEX 600V Stack Diesel Generator Performance Test

Work Instructions

01/07/2021

71111.12

Procedures

FL60KW3Y-H

FLEX 60KW Generator Performance Test Work

Instructions

8/16/2018

71111.12

Procedures

FL60KW6M-H

60KW Generator Operational Inspection Work

Insructions

08/16/2018

71111.12

Procedures

FLBSTRPMP3Y

FLEX Booster Pump Performance Test Work

Instructions

03/02/2021

71111.12

Procedures

FLBSTRPMP6M

Flex Booster Pump Functional Test and Inspection Work

Instructions

10/26/2020

71111.12

Procedures

NMP-)S-019-013-

GL02

Hatch BDB Equipment Unavailability Tracking Guideline

5.1

71111.12

Procedures

NMP-ES-002-006

System Vulnerability Review Process

3.4

71111.12

Procedures

NMP-ES-027

Maintenance Rule Program

9.0

71111.12

Procedures

NMP-GM-038

Diverse and Flexible Coping Strategies (FLEX) Program

4.0

71111.12

Procedures

NMP-OS-019

Beyond Design Basis Events

2.0

71111.12

Procedures

NMP-OS-019-013

Beyond Design Basis Equipment Unavailability Tracking

4.0

71111.12

Procedures

NMP-OS-019-291

FLEX Core Cooling Pump Operating Instruction

2.0

71111.12

Procedures

NMP-OS-019-292

FLEX Mode 4/5 Core Cooling Pump Operating

2.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Instruction

71111.12

Procedures

NMP-OS-019-293

FLEX 600V Diesel Generator Operating Instruction

1.1

71111.12

Procedures

NMP-OS-019-294

FLEX 60KW Diesel Generator Operating Instruction

1.0

71111.12

Procedures

NUMARC 93-01

Industry Guideline for Monitoring the Effectiveness of

Maintenance at Nuclear Power Plants

4A

71111.12

Work Orders

SNC1060565

Mode 5 Core Cooling Pump Functional Test

1/11/2021

71111.13

Corrective Action

Documents

Resulting from

Inspection

10784404

03/22/2021

71111.13

Miscellaneous

License Amendment Request to Revise the RAS of TS 3.8.1, AC Sources - Operating, for One-Time Extension

of Completion Time for Unit 1 and Swing EDGs SNC

Responses to NRC RAI, Attachments 5 and 6

71111.13

Procedures

34GO-OPS-007-0

Shutdown/Refueling Mode Preparation Strategy for Flex

1.2

71111.13

Procedures

NMP-GM-031-003

Risk Management Actions for 10 CFR 50.65(a)(4) and

the Risk Informed Completion Time Program

8.0

71111.13

Procedures

NMP-OS-010

Protected Train/Division and Protected Equipment

Program

8.1

71111.13

Procedures

NMP-OS-010-002

Hatch Protected Equipment Logs

11.1

71111.13

Procedures

NMP-OS-019-253

Hatch Unit C SIG-12, Mode 4/5 RPV Inventory Control

2.3

71111.15

Corrective Action

Documents

10714013

06/07/2020

71111.15

Corrective Action

Documents

10763139

2/28/2020

71111.15

Corrective Action

Documents

10763247

2/29/2020

71111.15

Corrective Action

Documents

10764816

01/06/2021

71111.15

Corrective Action

Documents

10769088

01/25/2021

71111.15

Corrective Action

Documents

107819557

03/11/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.15

Corrective Action

Documents

10782116

03/12/2020

71111.15

Corrective Action

Documents

10782586

03/15/2021

71111.15

Corrective Action

Documents

10783262

03/17/2021

71111.15

Corrective Action

Documents

10786180

03/29/2021

71111.15

Corrective Action

Documents

10786184

03/29/2021

71111.15

Corrective Action

Documents

Resulting from

Inspection

10771474

2/03/2021

71111.15

Corrective Action

Documents

Resulting from

Inspection

10783264

03/17/2021

71111.15

Drawings

H-21033

Unit 2 Turbine Building Service Water System

61.0

71111.15

Drawings

H-21704

Diesel Engine & Fuel Oil System

56.0

71111.15

Engineering

Changes

SNC1148794

Design Equivalent Change Package for 2T41-B003B

Cooler Fan Failure TCC

03/30/2021

71111.15

Engineering

Evaluations

NMP-AD-012-F01

Operability Determination Support Basis for

CR10764816

4.0

71111.15

Engineering

Evaluations

TE 313720

01/18/2012

71111.15

Engineering

Evaluations

TE457436

07/05/2012

71111.15

Miscellaneous

APC 2-20-024

Alarm 2N32-K4001A/B Monitoring Actions

06/08/2020

71111.15

Miscellaneous

Specification Sheet

Lube Oil Heat Exchanger Specification Sheet

1.0

71111.15

Operability

Evaluations

NMP-AD-012-F01

Operability Determination Support Basis for 2T41-

B003B

03/25/2021

71111.15

Procedures

2SV-TET-001-0

LLRT Testing Methodology

13.0

71111.15

Procedures

2SV-TET-001-2

Primary Containment Periodic Type B and Type C

37.2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Leakage Tests

71111.15

Procedures

NMP-AD-002-F04

Troubleshooting Log for the 2C EDG

1.1

71111.15

Procedures

NMP-AD-012-F01

Operability determination Support Basis for the 2C EDG

03/16/2021

71111.15

Work Orders

SNC1100180

71111.15

Work Orders

SNC1135192

71111.15

Work Orders

SNC865011

2/08/2021

71111.18

Calculations

MC-H-19-0020

Coordination Study for 600V and 208V Switchgear

Busses

05/04/2020

71111.18

Corrective Action

Documents

10771124

2/02/2021

71111.18

Corrective Action

Documents

10778925

2/25/2021

71111.18

Corrective Action

Documents

10780926

03/08/2021

71111.18

Engineering

Changes

SNC1010116

Commercial Change

Package

NFPA 805 - Coordination for Breakers 2R25-S021 &

2R25-S022

08/04/2020

71111.18

Miscellaneous

SNC1010116FPP5

Fire Protection Program Impact Screen of Commercial

Change Package SNC1010116

07/06/2020

71111.18

Procedures

2SP-10-30-20-RR-1-

Yokogawa YS1700 Reactor Feed Pump Controllers

2C32-R600, 2C32-R601A/B, 2C32-R619, and 2C32-

R609 FT for DECP SNC632608

1.1

71111.18

Procedures

NMP-AD-008

Applicability Determinations

2.0

71111.18

Procedures

NMP-AD-009

Licensing Document Change Requests

17.0

71111.18

Procedures

NMP-AD-010

CFR 50.59 Screenings and Evaluations

17.0

71111.18

Procedures

NMP-MA-014

Post Maintenance Testing/Post Modification Testing

2.2

71111.18

Shipping

Records

SNC 1107054

Revise the Micro Versa Trip Unit Setting on 2R23-S021

FR 4M

2/25/2021

71111.18

Work Orders

SNC1107044

Revise the Micro Versa Unit Setting on 2R23-S021 FR

4B

2/24/2021

71111.18

Work Orders

SNC632608

Main Control Room Feedwater Controller Replacement

06/18/2020

71111.18

Work Orders

SNC632608DLL

Critical Digital Asset (CDA) Screening

05/15/2020

71111.18

Work Orders

SNC632608DOEJJ001 EMI/RFI Evaluation of Equipment Added for

DCPSNC632608

03/17/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.18

Work Orders

SNC632608MAX1, 2

and 3

71111.18

Work Orders

SNC632608OE

Applicable Operating Experience Review

71111.18

Work Orders

SNC632608PE

71111.18

Work Orders

SNC632608REF

Walkdown Plan and Observations Record

2/24/2020

71111.18

Work Orders

SNC632608RF

05/06/2020

71111.18

Work Orders

SNC632608SCP

Software Quality Assurance Classification

05/14/2020

71111.19

Corrective Action

Documents

10776153

2/18/2021

71111.19

Corrective Action

Documents

10776156

2/18/2021

71111.19

Corrective Action

Documents

10776158

2/18/2021

71111.19

Corrective Action

Documents

10776420

2/19/2021

71111.19

Corrective Action

Documents

10776752

2/20/2021

71111.19

Corrective Action

Documents

10778039

2/25/2021

71111.19

Corrective Action

Documents

10781022

03/08/2021

71111.19

Corrective Action

Documents

Resulting from

Inspection

10771741

2/04/2021

71111.19

Engineering

Changes

SNC1142049

03/03/2021

71111.19

Procedures

34SO-C51-001-0

Tip Operation and LPRM Calibration

19.4

71111.19

Procedures

34SV-P41-001-1

Plant Service Water Operability

15.2

71111.19

Procedures

34SV-R43-001-2

Diesel Generator 2A Monthly Test

29.4

71111.19

Procedures

34SV-R43-003-1

Diesel Generator 1C Monthly Test

20.2

71111.19

Procedures

2FH-ENG-030

ICA Transfer Authorization for Nuclear Detector

Installation

5.0

71111.19

Procedures

2FH-ENG-030-0

ICA Transfer Authorization

5.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.19

Procedures

2SV-C11-003-0

U2C27 BOC Control Rod Scram Timing

11.1

71111.19

Procedures

2SV-TET-001-0

LLRT Testing Methodology

13.0

71111.19

Procedures

2SV-TET-001-0

Volumetric Leak Rate Monitor Local Leak Rate Test

Data Sheet for, 2T48-F319 & 2T48-F320

03/02/2021

71111.19

Procedures

2SV-TET-001-0

Unit 2 LLRT 2T48-F320 Shaft & Flange O-Rings

03/02/2021

71111.19

Procedures

2SV-TET-001-2

Primary Containment Periodic Type B & Type C

Leakage Tests

37.2

71111.19

Procedures

2GM-C51-001-0

LPRM Removal and Installation

17.3

71111.19

Procedures

2SV-R43-001-0

Diesel, Alternator, And Accessories Inspection, Section

7.9 Diesel Generator Run In

03/28/2021

71111.19

Procedures

2SV-R43-001-0

Diesel, Alternator, and Accessories Inspection

31.21

71111.19

Procedures

NMP-MA-014

Post Maintenance Testing/Post Modification Testing

2.1

71111.19

Procedures

NMP-MA-014-001

Post Maintenance Testing Guidance

5.2

71111.19

Work Orders

SNC1093049

2/17/2021

71111.19

Work Orders

SNC1130203

01/29/2021

71111.19

Work Orders

SNC1137368

2/05/2021

71111.19

Work Orders

SNC1137428

2/26/2021

71111.19

Work Orders

SNC1139786

01/29/2021

71111.19

Work Orders

SNC1139991

01/29/2021

71111.20

Corrective Action

Documents

Resulting from

Inspection

10773870

2/12/2021

71111.20

Corrective Action

Documents

Resulting from

Inspection

10773870

2/12/2021

71111.20

Miscellaneous

OCC - All OPS Activities Next 7 Days By Team, Outage

Schedule

01/21/2021

71111.20

Miscellaneous

H2R26 Final Outage Safety Assessment Report

0.0

71111.20

Miscellaneous

H2R26 Final Outage Safety Assessment Report

1.0

71111.20

Procedures

34GO-OPS 001-2

Plant Startup

51.9

71111.20

Procedures

34GO-OPS-013-2

Normal Plant Shutdown

33.5

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.20

Procedures

34GO-OPS-015-2

Maintaining Cold Shutdown or Refueling Condition

16.2

71111.20

Procedures

34GO-OPS-025-0

RPV Water Inventory Control

3.3

71111.20

Procedures

34GO-OPS-028-2

Drywell Closeout

7.21

71111.20

Procedures

34GO-OPS-029-0

Torus & Torus Area Closeout

3.2

71111.20

Procedures

2GM-MME-004-2

Reactor Vessel Reassembly

21.0

71111.20

Procedures

2GM-MME-015-2

Reactor Vessel Disassembly

18.9

71111.20

Procedures

NMP-RE-007,

Attachments 1, 2 And

H2C27 Core Loading Verification

2/26/2021

71111.20

Procedures

NMP-RE-008-F01

Detailed Reactivity Management Plan

03/08/2021

71111.20

Work Orders

SNC946845

2/01/2021

71111.22

Calibration

Records

10773100, 10773182,

10773184 and

10773217

2/10/2021

71111.22

Corrective Action

Documents

10766461

01/11/2021

71111.22

Corrective Action

Documents

10766491

01/13/2021

71111.22

Corrective Action

Documents

10769440

01/26/2021

71111.22

Corrective Action

Documents

10780410

03/05/2021

71111.22

Corrective Action

Documents

10780501

03/05/2021

71111.22

Drawings

H-16329-16330

RHR System P&ID Sheets 1 & 2

84.0 and

75.0

71111.22

Procedures

34SV-E11-004-1

RHR Service Water Pump Operability

2.1

71111.22

Procedures

34SV-E21-001-1

Core Spray Pump Operability

24.2

71111.22

Procedures

34SV-E41-002-2

High Pressure Coolant Injection Pump Operability CPT

39.1

71111.22

Procedures

34SV-E41-010-2

HPCI Logic System Functional Test

1.2

71111.22

Procedures

34SV-E51-010-2

RCIC Logic System Functional Test

1.5

71111.22

Procedures

34SV-R43-003-1

Diesel Generator 1C Monthly Test

20.2

71111.22

Procedures

34SV-R43-020-2

Diesel Generator 2A LOCA/LOSP LSFT

4.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.22

Procedures

34SV-T48-002-2

Suppression Chamber to Drywell Vacuum Breaker

Operability And Containment Purge/Vent Valve Position

Check

5.8

71111.22

Work Orders

SNC1060565

Mode 5 Core Cooling Pump Functional Test

January 11,

21

71124.01

Corrective Action

Documents

CR 10752676

71124.01

Radiation

Surveys

2603

U2 CPS A Pump Room

08/25/20

71124.02

Procedures

NMP-AD-035

ALARA Program

Version 1.9

71124.02

Procedures

NMP-HP-204

ALARA Planning and Job Review

Ver. 7.2

71124.02

Procedures

NMP-HP-204-001

ALARA Planning

Version 2.2

71124.02

Procedures

NMP-HP-206

Issuance, Use, and Control of Radiation Work Permits

Version 6.1

71124.03

Corrective Action

Documents

CR 10771551

71124.03

Corrective Action

Documents

Resulting from

Inspection

CR 10778343

71124.03

Self-

Assessments

TE 1058722

RP Pre-NRC check-in self-assessment

2/06/2020

71124.04

Corrective Action

Documents

Resulting from

Inspection

10778784

71124.04

Miscellaneous

Technical Position

Evaluation of Tritium Monitoring Plant Hatch Nuclear

Station

2/06/2019

71124.04

Procedures

NMP-HP-108

Issuance, Use and Collection of Personnel Dosimetry

Version 2.9

71124.05

Calibration

Records

109114

Hatch Main Stack Radiation Monitor calibration source

ID # 0080.00.00 (Cd-109 simulated gas in a Marinelli

beaker) - Eckert & Ziegler Certification of Calibration

04/30/2018

71124.05

Calibration

Records

29

Victoreen Model 878-10 Calibrator Certification of

Calibration (Hatch source ID # Cs-137-243)

10/01/1997

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.05

Calibration

Records

29

Victoreen Model 878-10 Calibrator Certification of

Calibration (Hatch source ID # Cs-137-243)

05/07/1991

71124.05

Calibration

Records

1D11-K604

Unit 1 Liquid Radwaste Monitor radiation monitor initial

source calibration with liquid Cs-137 source using 62CI-

CAL-009-0, v1.0

06/20/1985

71124.05

Calibration

Records

1D11-K604

Initial solid source response calibration performed per

2CI-OCB-009-0, Rev 1 after NBS-traceable liquid Cs-

137 source for efficiency factor determination. Cs-137

source, Serial number Cs-137-179, used for traceable

source count rate determination.

06/21/1985

71124.05

Calibration

Records

1D11-K604

Calibration source transfer performed (Cs-137-179, Cs-

137-183) per 64CI-OCB-009-0.

11/14/1995

71124.05

Calibration

Records

1D11-K619B

Unit 1 Reactor Building Ventilation Radiation Monitor

(RBV) 1D1-K619B source calibration [performed after

detector replacement and HV and discriminator set]

04/20/2020

71124.05

Calibration

Records

73713-06

Hatch Main Stack Radiation Monitor calibration source

ID # Cs-137-284 (simulated gas in a Marinelli beaker) -

Analytics Certification of Calibration

09/18/2006

71124.05

Calibration

Records

73715-06

Hatch Main Stack Radiation Monitor calibration source

ID # Co-60-146 (simulated gas in a Marinelli beaker) -

Analytics Certification of Calibration

09/18/2006

71124.05

Calibration

Records

243-121

Hatch calibration source ID # Tc-99-77 - Eckert &

Ziegler Certification of Calibration

2/12/2011

71124.05

Calibration

Records

93549F

Hatch Main Stack Radiation Monitor calibration source

ID # Cd-109-147 (simulated gas in a Marinelli beaker) -

Eckert & Ziegler Certification of Calibration

06/28/2013

71124.05

Calibration

Records

W/O 1036883

Unit 2 Liquid Radwaste Radiation Monitor (MPL: 2D11-

K604) source calibration (per Procedure 64CI-OCB-009-

0)

08/12/2019

71124.05

Calibration

Records

W/O SNC754124

Unit 2 Drywell High Range Radiation Monitor 2D11-

21A & B Loop Calibration [24 month calibration -

electronics only]

01/26/2017

71124.05

Calibration

Records

W/O SNC761756

Unit 2 Reactor Building Ventilation Post Accident Noble

Gas Radiation Monitor 2D11-K636A & B FT&C (channel

03/01/2017

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

functional test) [24 month calibration - electronics only]

71124.05

Calibration

Records

W/O SNC909309

Unit 2 Reactor Building Ventilation Post Accident Noble

Gas Radiation Monitor 2D11-K636A & B FT&C (channel

functional test) [24 month calibration - electronics only]

04/25/2019

71124.05

Calibration

Records

W/O SNC961179

Reactor Building Ventilation Radiation Monitor 1D1-

K619A FT&C (channel functional test) [24 month

calibration - electronics only]

08/22/2019

71124.05

Calibration

Records

Work Order (W/O)

SNC 878503

Unit 2 Drywell High Range Radiation Monitor 2D11-

21A & B Loop Calibration [24 month calibration -

electronics only]

05/11/2019

71124.05

Corrective Action

Documents

CR Numbers: 10448588, 10572155, 10586543,

10629838, 10629675, and 10640037

Various

71124.05

Corrective Action

Documents

Resulting from

Inspection

CR 10772650

Current certified source calibration data not being used

for Drywell radiation monitor (Victoreen 878-10 field

calibrator S/N 129, Hatch source ID # Cs-137-243).

2/08/2021

71124.05

Corrective Action

Documents

Resulting from

Inspection

CR 10772654

Chemistry radiation monitor source calibration

procedures should all be revised to require recording of

the applicable work order number on the quality record

for all source calibrations.

2/08/2021

71124.05

Corrective Action

Documents

Resulting from

Inspection

CR 10773027

Chemistry procedures for source calibrations on various

radiation monitors generally specify that the technician

should ensure the source has 'sufficient strength' but

how to determine what is 'sufficient' is not defined. The

procedures should be revised to include this information.

2/09/2021

71124.05

Corrective Action

Documents

Resulting from

Inspection

CR 10773254

Revise Procedure NMP-HP-400 to include a counting

geometry for NI-63 smear sample analysis (used for

source leak testing).

2/10/2021

71124.05

Corrective Action

Documents

Resulting from

Inspection

CR 10773533

NRC observation - evaluate inclusion of Accident Range

Ventilation Effluent Monitoring System (ARVEMS) in the

Chemistry Continuing Training Program to ensure

sampling proficiency is maintained.

2/11/2021

71124.05

Corrective Action

CR 10775274

NRC inspector identified that the 2020 vendor

2/16/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Resulting from

Inspection

calibration package for the dosimetry office whole body

counter had incorrect dates (2019 vs. 2020).

71124.05

Corrective Action

Documents

Resulting from

Inspection

CR 10777540

Procedure 57SV-D11-021-1 and -2 needs to be revised

such that the special requirements state that a

Functional Test is required every time an electronic

calibration is performed. It also needs to also require a

source calibration per the Chemistry procedure when

the 2-year cal is performed as well.

2/23/2021

71124.05

Corrective Action

Documents

Resulting from

Inspection

CR 10778227

Liquid Radwaste radiation monitor calibration source #

Cs-137-183 NIST traceability documentation cannot be

located.

2/25/2021

71124.07

Corrective Action

Documents

CAR 276603

71124.07

Corrective Action

Documents

CR 10600292

71124.07

Corrective Action

Documents

CR 10635234

71124.07

Corrective Action

Documents

TE 1071055

71124.07

Miscellaneous

EPRI Groundwater Protection Program Assessment

08/20/2020

71124.07

Miscellaneous

Groundwater Monitoring Data for Sample Well NW-10

01/01/2019 -

2/10/2021

71124.07

Procedures

NMP-EN-002

Radiological Groundwater Protection Program

Version 9.2

71124.07

Procedures

NMP-EN-002-GL02

Hatch Nuclear Plant Groundwater Monitoring Plan for

Radionuclides

Version 1.1

71124.07

Procedures

NMP-EN-002-GL04

Radiological GWPP Technical Bases

Version 1.0

71124.07

Procedures

NMP-ES-036-001

Underground Pipe and Tanks Monitoring Program

Implementation

Version 11

71124.07

Procedures

ODCM

Offsite Dose Calculation Manual for Edwin I. Hatch

Nuclear Plant

Version 26

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.07

Radiation

Surveys

Plant Hatch

Radiological

Information Survey #

185685

Routine Survey Unit 2 CST

01/23/2021

71124.07

Radiation

Surveys

Plant Hatch

Radiological

Information Survey #

186959

U2 CST Routine Survey

2/20/2020

71151

Miscellaneous

LER 2020-001-000

March 2,

20

71151

Miscellaneous

LER 2020-001-000

December

10, 2020

71151

Miscellaneous

LER 2020-002-000

June 18,

20

71151

Miscellaneous

NEI 99-02

Regulatory Assessment Performance Indicator

Guideline

7.0

71152

Corrective Action

Documents

RCE278526

2/18/2020

71152

Corrective Action

Documents

RCE278526

2/18/2020

71153

Corrective Action

Documents

10695910

03/15/2020

71153

Corrective Action

Documents

10707660

05/07/2020

71153

Corrective Action

Documents

10707858

05/08/2020

71153

Corrective Action

Documents

CAR 277887

10/28/2020

71153

Corrective Action

Documents

Resulting from

Inspection

10728101

08/05/2020

71153

Corrective Action

Documents

10747434

10/20/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Resulting from

Inspection

71153

Corrective Action

Documents

Resulting from

Inspection

10764815

01/06/2021

71153

Corrective Action

Documents

Resulting from

Inspection

CAR 278739

01/06/2021

71153

Engineering

Evaluations

TE 1067120

1A EDG Past Operability

05/14/2020

71153

Miscellaneous

ML20345A083

LER 2020-001-00 for Edwin I. Hatch Nuclear Plant Unit

1, 1A EDG Inoperable Due to Water in the Day Tank

2/10/2020