SUBJECT:

ANNUAL ASSESSMENT LETTER FOR EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 (REPORT 05000321/2022006 AND 05000366/2022006)

Dear Cheryl Gayheart:

The NRC has completed its end-ofcycle performance assessment of Edwin I. Hatch Nuclear Plant (Hatch), Units 1 and 2, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2022, through December 31, 2022. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.

The NRC determined the performance at Edwin I. Hatch Nuclear Plant, Units 1 and 2, during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2024. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In response to the COVID19 public health emergency (PHE), the NRC adjusted inspection plans and schedules to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. While the PHE continues, overall conditions throughout the country support performance of our inspection and oversight activities returning to normal onsite presence by our resident and region-based inspectors and completion of nominal baseline inspection samples. We continue to monitor site-specific conditions and, as discussed in our November 2, 2021, memo, Implementation of Inspection Programs Following Re-Entry from the Public Health Emergency for the Reactor Safety Program (ML21295A302), it may be necessary to alter how and when we perform our inspection and oversight activities as we balance the importance of protecting the health and safety of our staff with the need to conduct effective oversight that supports the NRCs critical safety mission.

March 1, 2023 For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-onforce inspections cannot be completed as scheduled due to an emergency, such as the COVID19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.

Beginning on January 1, 2023, the engineering inspection frequency will transition from a triennial (3-year) to a quadrennial (4-year) cycle. The new engineering inspection program will consist of a Comprehensive Engineering Team Inspection (CETI)1 and three Focused Engineering Inspections (FEIs), that will be performed in each quadrennial cycle. For the cycle beginning in 2023, the FEIs will be: Fire Protection Team Inspection, Commercial Grade Dedication, and Age-Related Degradation.2 In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (404) 9974892 with any questions you may have regarding this letter.

Sincerely, Donna Jackson, Acting Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos. 05000321 and 05000366 License Nos. DPR57 and NPF5 Enclosure: Hatch Inspection/Activity Plan (03/01/2023-12/31/2024)

cc: Distribution via ListServ 1 Aspects of the Design Basis Assurance Inspection (DBAI), Evaluations of Changes, Tests, & Experiments, and Heat Sink inspections will be included in the new CETI inspection. Previously scheduled Evaluation of Changes, Tests, & Experiments and Heat Sink inspections have been cancelled and removed from attached Report 22.

2 The Age-Related Degradation procedure is publicly available, and the NRC plans to implement the first inspection of this type beginning in July 2023.

Signed by Jackson, Donna on 03/01/23

ML23054A164 X

SUNSI Review X

Non-Sensitive

Sensitive X

Publicly Available

Non-Publicly Available OFFICE RII/DRP RII/DRP RII/DRP NAME A. Alen R. Smith D. Jackson DATE 2/23/2023 2/23/2023 3/1/2023

Site Inspection Activity Plan 07200036 - Hatch (ISFSI)

03/01/2023 - 12/31/2024 Unit Start End Activity CAC Title Staff Count SECURITY BASELINE INSPECTION (ISFSI)

11/13/2023 11/17/2023 IP 81311 001006 Physical Security Requirements for Independent Spent Fuel Storage Installations AGING MANAGEMENT OF AN ISFSI

8/5/2024 8/9/2024 IP 60859 INDEPENDENT SPENT FUEL STORAGE INSTALLATION (ISFSI) LICENSE RENEWAL INSPECTION Enclosure

Site Inspection Activity Plan Hatch 03/01/2023 - 12/31/2024 FOCUSED ENGINEERING INSPECTION (CGD)

1,2 4/24/2023 4/28/2023 IP 71111.21N.03 001808 Commercial Grade Dedication 1,2 5/8/2023 5/12/2023 IP 71111.21N.03 001808 Commercial Grade Dedication OPERATION ON AN ISFSI

1,2 5/15/2023 5/19/2023 IP 60855 001001 Operation Of An ISFSI POST-APPROVAL LICENSE RENEWAL PHASE 4

1,2 5/22/2023 5/26/2023 IP 71003 000687 Post-Approval Site Inspection for License Renewal RP PUBLIC RADIATION SAFETY BASELINE INSPECTION

1,2 7/10/2023 7/14/2023 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1,2 7/10/2023 7/14/2023 IP 71124.07 000731 Radiological Environmental Monitoring Program 1,2 7/10/2023 7/14/2023 IP 71151 000746 Performance Indicator Verification SNC CORPORATE SECURITY INSPECTION AA/FFD

1,2 8/28/2023 9/1/2023 IP 71130.01 000733 Access Authorization 1,2 8/28/2023 9/1/2023 IP 71130.06 000738 Protection of Safeguards Information 1,2 8/28/2023 9/1/2023 IP 71130.08 000740 Fitness For Duty Program PROBLEM IDENTIFICATION & RESOLUTION

1,2 9/11/2023 9/15/2023 IP 71152B 000747 Problem Identification and Resolution 1,2 9/25/2023 9/29/2023 IP 71152B 000747 Problem Identification and Resolution SECURITY BASELINE INSPECTION

1,2 9/18/2023 9/22/2023 IP 71130.01 000733 Access Authorization 1,2 9/18/2023 9/22/2023 IP 71130.06 000738 Protection of Safeguards Information 1,2 9/18/2023 9/22/2023 IP 71130.08 000740 Fitness For Duty Program CYBER SECURITY INSPECTION

1,2 10/2/2023 10/6/2023 IP 71130.10 000741 Cybersecurity HATCH INITIAL LICENSE EXAM

1,2 10/23/2023 10/27/2023 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1,2 11/27/2023 12/9/2023 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)

EMERGENCY PREPAREDNESS EXERCISE INSPECTION

1,2 10/30/2023 11/3/2023 IP 71114.01 000716 Exercise Evaluation 1,2 10/30/2023 11/3/2023 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 10/30/2023 11/3/2023 IP 71114.08 000723 Exercise Evaluation - Scenario Review 1,2 10/30/2023 11/3/2023 IP 71151 001397 Performance Indicator Verification SECURITY BASELINE INSPECTION

2 Unit Start End Activity CAC Title Staff Count

Site Inspection Activity Plan 1,2 11/13/2023 11/17/2023 IP 71130.02 000734 Access Control 1,2 11/13/2023 11/17/2023 IP 71130.09 001656 Security Plan Changes 1,2 11/13/2023 11/17/2023 IP 71151 001338 Performance Indicator Verification 1,2 11/13/2023 11/17/2023 IP 81311 000831 Physical Security Requirements for Independent Spent Fuel Storage Installations RP RAD SAFETY OCCUPATIONAL AND TRANSPORTATION BASELINE INSPECTION

1,2 2/5/2024 2/9/2024 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 2/5/2024 2/9/2024 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation 1,2 2/5/2024 2/9/2024 IP 71151 000746 Performance Indicator Verification UNIT 1 IN-SERVICE INSPECTION

SECURITY BASELINE INSPECTION

1,2 3/18/2024 3/22/2024 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1,2 3/18/2024 3/22/2024 IP 71130.07 000739 Security Training SECURITY BASELINE INSPECTION

1,2 9/16/2024 9/20/2024 IP 71130.02 000734 Access Control 1,2 9/16/2024 9/20/2024 IP 71130.05 000737 Protective Strategy Evaluation 1,2 9/16/2024 9/20/2024 IP 71130.09 001656 Security Plan Changes 1,2 9/16/2024 9/20/2024 IP 71151 001338 Performance Indicator Verification HATCH REQUAL INSPECTION

1,2 10/21/2024 10/25/2024 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance COMPREHENSIVE ENGINEERING TEAM INSPECTION (CETI)

1,2 11/4/2024 11/8/2024 IP 71111.21M 000713 Design Bases Assurance (DBA) Inspection 1,2 11/18/2024 11/22/2024 IP 71111.21M 000713 Design Bases Assurance (DBA) Inspection EMERGENCY PREPAREDNESS PROGRAM INSPECTION

1,2 12/2/2024 12/6/2024 IP 71114.02 000717 Alert and Notification System Testing 1,2 12/2/2024 12/6/2024 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 12/2/2024 12/6/2024 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 12/2/2024 12/6/2024 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 12/2/2024 12/6/2024 IP 71151 001397 Performance Indicator Verification SECURITY BASELINE INSPECTION

1,2 12/2/2024 12/6/2024 IP 71130.02 000734 Access Control 1,2 12/2/2024 12/6/2024 IP 71130.09 001656 Security Plan Changes 1,2 12/2/2024 12/6/2024 IP 71151 001338 Performance Indicator Verification

1 2/12/2024 2/16/2024 IP 71111.08G 000701 Inservice Inspection Activities (BWR)