IR 05000321/2021011

From kanterella
Jump to navigation Jump to search
Design Bases Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000321/2021011 and 05000366/2021011
ML21176A042
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 06/25/2021
From: James Baptist
Division of Reactor Safety II
To: Gayheart C
Southern Nuclear Operating Co
References
IR 2021011
Download: ML21176A042 (15)


Text

June 25, 2021

SUBJECT:

EDWIN I. HATCH NUCLEAR PLANT UNITS 1 & 2 - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000321/2021011 AND 05000366/2021011

Dear Ms. Gayheart:

On May 14, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Edwin I. Hatch Nuclear Plant Units 1 & 2 and discussed the results of this inspection with Johnny Weissinger - Plant Manager and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety

Docket Nos. 05000321 and 05000366 License Nos. DPR-57 and NPF-5

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000321 and 05000366

License Numbers:

DPR-57 and NPF-5

Report Numbers:

05000321/2021011 and 05000366/2021011

Enterprise Identifier: I-2021-011-0010

Licensee:

Southern Nuclear Operating Company, Inc.

Facility:

Edwin I. Hatch Nuclear Plant Units 1 & 2

Location:

Baxley, GA

Inspection Dates:

April 26, 2021 to May 14, 2021

Inspectors:

P. Braxton, Reactor Inspector

P. Carman, Senior Reactor Inspector

K. Mangan, Senior Reactor Inspector

M. Schwieg, Reactor Inspector

R. Smith, Senior Resident Inspector

T. Su, Reactor Inspector

Approved By:

James B. Baptist, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Edwin I.

Hatch Nuclear Plant Units 1 & 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Teams)

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (5 Samples)

(1) Time Critical Operator Actions to Reduce Containment Pressure During a Small Break Loss of Coolant Accident (LOCA) and Drywell Pressure is 35 PSIG, within 10 Minutes via one of following methods; Time Critical Operator Action to Start Standby Liquid Control (SBLC) after a LOCA to Buffer Suppression Pool, within Two Hours by one of the following methods:
  • Initiating SBLC Using the Control Switch from the Main Control Room (MCR)
  • Initiating SBLC Using Links and Jumpers from the MCR
  • Initiating SBLC Using Links and Jumpers and Switch Manipulation Locally
(2) Main Steam Isolation Valve, 1B21-FO22A
  • Component Degradation
  • Component Inputs/Outputs
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance effectiveness and records, and corrective action history
  • Modifications
  • Equipment/Environmental Qualification
  • Design calculations
  • Instrumentation (range, accuracy, and setpoint)
  • Surveillance testing and recent test results
  • Energy Source (air)
(3) U1 LPCI MCC 1R24-S018B
  • Compliance with UFSAR, Technical Specifications (TS), and TS Bases
  • Conformance with manufacturer instructions for installation, maintenance, and operation
  • Material condition and configuration (i.e. photos provided by licensee)
  • System health reports
  • Design requirements
(4) Diesel Generating Building ventilation system
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • Maintenance effectiveness and records, and corrective action history
  • Design calculations
  • Surveillance testing and recent test results
  • Electrical and logic diagrams
(5) Unit 1 Emergency Diesel Generator 1C
  • Design bases documents, system descriptions, and training documents
  • Primary design calculations
  • System/component health report
  • Condition reports associated with component
  • Completed surveillance and test procedures

Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===

(1) Unit 1 Reactor Building-to-Suppression Chamber Vacuum Breakers, 1T48-F328A/B
  • UFSAR and other applicable design and licensing basis documents
  • Design calculations
  • Surveillance and in-service testing results
  • Consistency between station documentation and vendor specifications
  • Corrective maintenance records and corrective action history
  • Maintenance effectiveness
  • System/component health report

Modification Review - Permanent Mods (IP Section 02.03) (4 Samples)

(1) EDG Fuel Oil Storage Tank Vent Line Missile Protection, SNC799744
(2) Degraded Grid - U2 Degraded Voltage Replacement, SNC489866
(3) SNC338333, Dissolved Gas Monitors - U1 & U2 Kelman Gas Analyzers for Large Power Transformers
(4) SNC950252, Masterpact Part 21

Review of Operating Experience Issues (IP Section 02.06) (2 Samples)

(1) NRC Information Notice 2019-03: Inadequate Implementation of Clearance Processes Resulting in Configuration Control Issues.
(2) IER L3 18-3 - Inadequate Use of Operating Experience and Declining Personnel Experience Lead to Damage to Rod Control Cluster Assembly Extension Shaft While Setting the Reactor Vessel Head.

INSPECTION RESULTS

Very Low Safety Significance Issue Resolution Process: Capability of Diesel Building Ventilation System to Withstand the Effects of a Tornado 71111.21 M

This issue is a current licensing basis question and inspection effort is being discontinued in accordance with the Very Low Safety Significance Issue Resolution (VLSSIR) process. No further evaluation is required.

Description:

The DBAI inspectors identified an issue of concern in that the diesel building ventilation system was not specifically shown to be designed to withstand the effects of a tornado re-pressurization. It is postulated that the differential pressure developed by a specific magnitude tornado could potentially damage the diesel building room ventilation system and challenge the emergency diesel generators (EDGs) to maintain their safety functions due to rapidly increasing room temperatures.

Each EDG and Switchgear room ventilation system consists of two large 100 percent capacity exhaust ventilation fans, associated automatic dampers, and motorized room louver that are arranged to maintain minimum ventilation requirements during diesel operation. The maximum temperature is not expected to exceed 122°F.

When the room ventilation fans are not running, the room louver and auto dampers would be closed. During a tornado re-pressurization event, there would be no venting path to equalize the pressure differential which could damage the room louver and auto dampers

As a result of inspector concerns, the licensee hired a contractor (MPR) to conduct a computer analysis of the louvers and dampers during a tornado event. The evaluation results indicate that the differential pressure caused by the room re-pressurization after the design basis tornado passing will cause the LV-6 louver blades to fail. The LV-6 blades are expected to survive the less severe tornado recommended in Regulatory Guide 1.76. Additionally, the fan dampers are expected to survive the design basis tornado.

Licensing Basis: The NRC staff reviewed the licensing basis documents, regulatory requirements, and regulatory correspondence related to the diesel building tornado protection criterion. The main documents reviewed are detailed below.

  • FSAR 3.3.2 TORNADO LOADINGS o All above-ground Seismic Category 1 structures are designed to withstand tornado loadings and horizontal tornado-generated missiles. Components which directly affect the ultimate safe shutdown of the plant are located either under the protection of reinforced concrete or underground. These components include the following o Standby diesel generator system
  • FSAR 3.3.2.1 Applicable Design Parameters o For Seismic Category 1 structures designed to withstand tornadoes and horizontal tornado-generated missiles, the following parameters are applied in combinations producing the most critical conditions o Pressure Differential

The structure interior bursting pressure is taken as rising 1 psi/s for 3 s, followed by a 3-s calm, then decreasing at 1 psi/s for 3 s. This cycle accounts for reduced pressure in the eye of a passing tornado. All fully enclosed Category 1 structures are designed to withstand the full 3-psi pressure differential.

  • 10 CFR 50, Appendix A, I. Overall Requirements, Criterion 2Design bases for protection against natural phenomena: Structures, systems, and components important to safety shall be designed to withstand the effects of natural phenomena such as earthquakes, tornadoes, hurricanes, floods, tsunami, and seiches without loss of capability to perform their safety functions. The design bases for these structures, systems, and components shall reflect:
(1) Appropriate consideration of the most severe of the natural phenomena that have been historically reported for the site and surrounding area, with sufficient margin for the limited accuracy, quantity, and period of time in which the historical data have been accumulated,
(2) appropriate combinations of the effects of normal and accident conditions with the effects of the natural phenomena and
(3) the importance of the safety functions to be performed.
  • 10 CFR 50, Appendix B, Criterion III, Design Control: Measures shall be established to assure that applicable regulatory requirements and the design basis, as defined in 10 CFR 50.2 and as specified in the license application, for those structures, systems, and components to which this appendix applies are correctly translated into specifications, drawings, procedures, and instructions.
  • Regulatory Issue Summary (RIS) 2006-23: Notifies licensees of its regulatory position regarding loading effects caused by natural phenomena to safety related systems and components housed inside a structure partially exposed to the outside environment, specifically ventilating and air-conditioning (VAC) systems housed in the EDG room.
  • Regulatory Guide 1.76 (issued in March 2007): Provides licensees and applicants with new guidance that the NRC staff considers acceptable for use in selecting the design-basis tornado and design-basis tornado-generated missiles that a nuclear power plant should be designed to withstand to prevent undue risk to the health and safety of the public.

The licensee provided information on why they believed the issue of concern is not in their licensing basis. The licensees review concluded that tornado depressurization structural design criteria applies to the design of Category 1 structures only. There is no commitment or requirement in the UFSAR extending this structural design criteria to individual systems or components, or in this case to the DG building fans or related components.

The inspectors did not agree with the licensees design basis determination. The Diesel Generating room louvers and auto dampers are exposed to the outside pressure and will experience high differential pressure during a tornado. These components should be considered as part of the EDG building structural design and be designed to withstand the differential pressure caused by a design basis tornado.

Following the inspectors issue of concern, the licensee revised the site procedure 34AB-Y22-002-0 Naturally Occurring Phenomena to add an operator action during a tornado warning to start one Diesel and Switchgear room fan and to ensure room has its louver open. The licensee provided a hand calculation, with the room louver open, to show the maximum room pressure differential will be below the damper and louver design rating (0.28 psid). In other words, with the room fan running, the dampers and louvers would be protected by the design basis tornado.

Based on the low probability of an event of this magnitude and the licensees actions taken, the inspectors concluded that the issue could be closed without immediate enforcement action and treated under the very low safety significance issue resolution process.

Significance: A risk evaluation was performed by a regional senior reactor analyst using SAPHIRE Version 8.2.3 and NRC Hatch SPAR model Version 8.58. The conditional analysis assumed failure of the EDG ventilation louvers for tornado initiating events with wind speeds greater than 200 miles per hour with a one-year exposure time. The dominant sequences were a tornado initiator accompanied by a loss of offsite power with failures of the emergency diesel generators, the reactor core isolation cooling (RCIC) pump, and operator actions to recover offsite power. The analysis determined that if a performance deficiency was assumed to have existed, it would have resulted in an increase in core damage frequency of <1E-06/year and an estimated increase in large early release frequency of <1E-07/year, representing very low safety significance (Green).

Technical Assistance Request: A technical assistance request (TAR) was not initiated.

Corrective Action Reference: CR

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On May 14, 2021, the inspectors presented the design basis assurance inspection (teams) inspection results to Johnny Weissinger - Plant Manager and other members of the licensee staff.
  • On June 23, 2021, the inspectors presented the Phone Re-Exit for the Hatch DBAI Meeting inspection results to Brian Waltman and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculations

NEDE 10144

Vacuum Breaker Sizing for 67 Product Line, Torus/Lightbulb

Containments

2/1970

S18643

Discontinuity Calculations F/20X20 Vacuum Breaker

11/19/1971

S18646

Seismic Calculation for 20 X 20 Vacuum Breaker Vlv

Rev. A

SCNH-13-021

Evaluation Of Plant Hatch Local Intense Precipitation Severe

Accident Management (Sam) For Fukushima Near-Term

Task Force (NTTF) Recommendation 2.1 Flooding Re-

Evaluation

Rev. 1.0

SENH-89-009

Steady State Loading Emergency Buses 1E, 1F & 1G

During a LOCA/LOSP/SBO Event

Rev. 17

SENH-94-013

Coordination Study for Non-Appendix R Breakers and

Fuses in Response to REA HT-93753

Rev.7

SMNH-15-006

EDG Bay and Battery Rooms Exhaust Area Required to

Prevent Pressure Differential During Design Basis Tornado

Rev. 1

Corrective Action

Documents

10116247

209664,

212821,

213119,

232344,

10464440,

10527495

10467098

2/28/2018

10467100

2/28/2018

CAR265435

2/01/2016

CR10753014

11/11/2020

Corrective Action

Documents

Resulting from

Inspection

10793548

04/27/2021

10793550

04/27/2021

10793879

04/28/2021

10794181

04/29/2021

10794215

04/29/2021

10795264

U1 FSAR Code of Record

5/4/2021

10797616

21 Hatch DBAI - Vacuum Breaker Sizing Design

05/13/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Calculation

Drawings

B-44875

Diesel Generator Building North Access Door Modifications

Rev. 0

H-12615

Diesel Generating Building Roof and Floor Plan

Rev. 7

H-13395

Diesel Generator Heating and Ventilation

Rev. 20

H-16024

Primary Containment Purge & Inerting System P.&I.D.

Ver. 54.0

H-16062, SHT 1

Nuclear Boiler System P&ID

Rev. 57

H-17012

Reactor Building 600V MCC "1E-A" & " 1E-B' MPL R24-

S018A & R24-S018B

Rev. 30

S18136

B/M 20 X 20 VAC. BKR.

Rev. E

S71062

Bill of Material 20 Pallet Assembly

03/02/1990

SX-17731

Assembly Drawing 20 Vacuum Breakers 20 ST/20 Flange

Rev. J

Engineering

Changes

SNC338333

Kelman Gas Analyzers for Transformers

Rev. 3

Engineering

Evaluations

LR-REG-003-

0404

Response to OE 14370 (Testing Methodology For MSIVs

May Not Support USAR and Licensing Commitments)

04/13/2004

NMP-ES-050-F01 RER Response Form for SNC 510820 - Sequence 1

08/02/2013

NMP-ES-050-F01 RER Response Form for SNC510820 - Sequence 2

08/26/2014

NMP-GM-003-

F19

Focused Area Self-Assessment (FASA) Plan and Report

Rev. 3

SNC950252

Masterpack Part 21

Rev. 1

TE1047898

09/08/2019

TE1055365

09/18/2020

Miscellaneous

EDG Room Main Louvers and associated thermostat

Rev. 0

Hatch Position on Effects of Tornado Induced

depressurization on Emergency Diesel Generator Building

Ventilation System Components

05/13/2021

Ltr From Bechtel Power Corporation to

E.I Hatch, IEN 85-48

June 30,

1986

Volumetric Leak Rate Monitor Local Leak Rate Test Data

Sheet, MPL Number: 1T48-F310 & F328A

2/22/2018

Volumetric Leak Rate Monitor Local Leak Rate Test Data

Sheet, MPL Number: 1T48-F310 & F328A Retest

03/01/2020

Volumetric Leak Rate Monitor Local Leak Rate Test Data

2/11/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Sheet, MPL Number: 1T48-F311 & F328B

Volumetric Leak Rate Monitor Local Leak Rate Test Data

Sheet, MPL Number: 1T48-F311 & F328B

2/03/2020

Surveillance Frequency Control Program, Surveillance Test

Interval List

Rev. 22

Georgia Power Interoffice Correspondence from G.A. Goode

to

S.B Tipps, Plant E I Hatch IEN 85-84, MSIV Testing

January 13,

1987

1R24 System

Health Report

June 2019, June 2020, June 2021

H-LT-PP-X86-

FLEX-LOCT-

20303

Plant Hatch FLEX Strategies (X86)

Rev. 2.0

Information Notice No. 85-84

Inadequate Inservice Testing of Main Steam Isolation Valves

LDCR 2021-005

Vacuum Breaker Inspection

Ver. 1.0

NMP-OS-014-

2, Attachment

1, 2 and 3

HNP Time Critical Operator Action Program - Training for

TCOA

05/12/2021

S70572

Vendor Manual-Instruction Valueline Mark 1 MCC's

Installation, Operations, and Maintenance

SIL 482

MSIV Closure Testing Requirement

2/22/89

SNC338333

Design Input Record

Rev. 1

SS6914-19

Specification for Louvers for Diesel Generating Building U1

and U2

09/18/1972

SX-17731

Assembly Drawing 20 Vacuum Breakers 20 ST/20 Flange

Rev. J

Procedures

31-GO-OPS-006-

Condition, Required Actions, and Completion Times

Rev. 8.7

31EO-EOP-010-

1/2

RC RPV Control (Non-ATWS)

Rev.

2.0/12.0

31EO-EOP-012-

1/2

PC Primary Containment Control

Rev. 7.1/7.1

31EO-EOP-015-

1/2

CP-1 ALTERNATE LEVEL CONTROL, STEAM COOLING,

& EMERGENCY RPV DEPRESSURIZATION

Rev.

10.1/11.1

31EO-EOP-100-

Miscellaneous Emergency Overrides

Rev. 5.2/8.4

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1/2

31EO-EOP-107-

1/2

ALTERNATE RPV PRESSURE CONTROL

Rev. 5.6/5.5

31EO-SAG-002-

1/2

SEVERE ACCIDENT GUIDELINE 2

Rev. 7.0/7.0

34AB-B21-001-

1/2

MAIN STEAM LINE HIGH RADIATION OR SUSPECTED

FUEL ELEMENT FAILURE

Rev.

5.1/4.15

34AB-Y22-002-0

Naturally Occurring Phenomena

Rev. 20

34GO-OPS-056-0 Receipt of Diesel Generator, Security Diesel, Dry Storage

(ISFSI) Diesel, Diesel Fire Pumps, and Auxiliary Boiler Fuel

Oil

Rev. 12

34GO-SUV-001-0 Control And Surveillance Of Locked Valves,

Lock Wired Valves, And Locked Breakers

Rev. 28.6

34SO-C41-003-

1/2

STANDBY LIQUID CONTROL SYSTEM

Rev.

2.7/12.6

34SO-E11-010-

1/2

Residual Heat Removal System

Rev.

45.3/44.5

34SV-SUV-01901 Surveillance Procedure

Ver. 37.38

34SV-T48-001-1

Reactor Building to Suppression Chamber Vacuum Relief

System Operability

Ver. 8.1

2EN-INS-002-0

Containment Leakage Rate Testing Plan

Ver. 9.0

2GM-MME-004-

1/2

Reactor Vessel Reassembly

Rev. 26.7/21

2GM-MME-015-

1/2

Reactor Vessel Disassembly

Rev.

2.9/18.9

2PM-T48-002-0

Torus to Reactor Building Vacuum Breaker Major

Inspection/Overhaul

Rev. 5.3

2SV-T48-003-0

Torus to Reactor Building Vacuum Breaker Inspection

Rev. 2.0

HNP-AP-001-F08

Site Procedure Approval Form

09/28/2016

HNP-OS-014-002

HNP Time Critical Operator Action Program

Rev. 2.0

NMP-AD-003

Equipment Clearance and Tagging

Rev. 26.0

NMP-GM-005-

2

Human Performance Tools Instruction

Rev. 9.1

NMP-GM-005-

Communication Plan for Crew Learning - From NRC Design

04/29/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

005-F02

Basis Assessment Inspection

NMP-GM-008-

F02

Typical Operating Experience Evaluation Format

Rev. 6.2

NMP-OS-007

Conduct of Operations

Rev. 17.0

NMP-OS-007-001 Conduct of Operations Standards and Expectations

Rev. 17.1

NMP-OS-007-005 Site Specific Operations Expectations and Fleet Operations

Policies

Rev. 2.0

NMP-OS-014

Time Critical Operator Action Program

Rev. 3.0

NMP-OS-014-002 HNP Time Critical Operator Action Program

Rev. 4.0

NMP-OS-014-

2-F01

Exclusion of Actions from MCTCA/MLTSA

06/24/2014

NMP-OS-014-

2-F02

Operator Response Time Validation - for Placing MSIV ALT

Path in Service Within 90 Minutes

08/19/2021

NMP-OS-014-

2-F02

Operator Response Time Validation - Take Action Within 10

Minutes of Drywell Pressure Reaching 35 PSIG

08/19/2020

NMP-OS-014-

2-F02

Operator Response Time Validation - Start SBLC Within 2

Hours

08/17/2020

NMP-OS-017

Severe Weather

Rev. 3

Self-Assessments SNC 950252

CFR 50.59 Screening

Rev. 1

Work Orders

SNC 553933,

SNC 553942,

SNC 925687,

SNC 92856, SNC

25857, SNC

25858, SNC

1071304, SNC

359906, SNC

400164, SNC

400165, SNC

585222

SNC571213,

SNC571613,

SNC785958,

SNC786383,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SNC964804,

SNC965758,

SNC966852

SNC587388

Replace Fan Motor

SNC785593

SNC786889

SNC799744