Monthly Operating Rept for June 1999 for DC Cook Nuclear Plant,Unit 2.With 990709 Ltr
ML17326A051
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 06/30/1999
From: BAKKEN A C, PRATT M M
INDIANA MICHIGAN POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9907200216
Download: ML17326A051 (8)


Text

REGULAT dY INFORMATION DISTRIBUTIO SYSTEM (RIDS)-N FACIL:50-316 Donald C.Cook Nuclear Power Plant, Unit 2, Indiana M)AU~~H.NAME AUTHOR AFFILIATION PRATT,M.M.

Indiana Michigan Power Co.BAKKEN,A.C Indiana Michigan Power Co.RECIP.NAME RECIPIENT AFFILIATION DOCKET¹05000316

SUBJECT:

Monthly operatin'June 1999 for DC Cook Nuclear Plant, Unit.With 990709 ltr.DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE: TITLE: Monthly Operating Report (per Tech Specs)NOTES: RECIPIENT ID CODE/NAME STANG,J COPIES LTTR EiVCL 1 1 REC I 5'.I ENT ID CODE/NAME COPIES LTTR ENCL 0 INTERNA.FILE CENTE S/DRXA OE EXTERNAL: LMITCO MARSHALL NRC PDR 1 1 1 1 1 1 1 1 OC/DBA/PAD RGN3 NOAC 1 1 1 1 1.1 D 0 C M'E N NOTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE.*TO HAVE YOUR, NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATIONS CONTACT THE DOCUMENT CONTROL DESK (DCD)ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 8 ENCL 8 0

rrl 4806 616 465 5901 FI ENEMAS NICNlCQN PQWM July 9, 1999 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Document Control Manager: Pursuant to the requirements of Donald C;Cook Nuclear Piant Unit 2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for June 1999 is submitted.

Sincerely, A.Christopher Bakken, III Site Vice President ACB/bwo Attachment c: NRC Region III NRC Project Manager-NRR NRC Resident Inspector ANI Nuclear Engineering Department INPO Records Center G.P.Arer t G.T.Gaffney-Canton D.R.Hahn-Department of Health S.Hamming-Department of Labor G.John B.Lewis-McGraw-Hill Companies D.H.Malin T.P.Noonan D.W.Paul-Lancaster J.E.Pollock R.P.Powers Regulatory Licensing Manager M.W.Rencheck W.H.Schalk D.G.Turner V907'200aie 990630 F PDR ADQCK 050003i6.~t rf,SL f/'EP: Arrrerica's Erregl Parlrrer

~~.R.C.OPERATING DATA REPORT DOCKET NO.50-316 DATE July 1, 1999 COMPLETED BY M.M.Pratt TELEPHONE 616-465-5901 OPERATING STATUS 1.Unit Name 2.Reporting Period 3.Licensed Thermal Power (MWt)4.Name Plate Rating (Gross MWe)5.Design Electrical Rating (Net MWe)6.Maximum Dependable Capacity (GROSS M 7.Maximum Dependable Capacity (Net MWe)D.C.Cook Unit 2 Jun-99 3411 1133 1090 We)1100 1060 Notes: 8.If Changes Occur in Capacity Ratings (Items no.3 through 7)Since Last Report Give Reasons: 9.Power Level to Which Restricted, If Any (Net MWe): 10.Reasons For Restrictions, If Any: 11.Hours in Reporting Period 12.No.of Hrs.Reactor Was Critical 13.Reactor Reserve Shutdown Hours 14.Hours Generator on Line 15.Unit Reserve Shutdown Hours 16.Gross Thermal Energy Gen.(MWH)17.Gross Electrical Energy Gen.(MWH)18.Net Electrical Energy Gen.(MWH)19.Unit Service Factor 20.Unit Availability Factor 21.Unit Capacity Factor (MDC Net)22.Unit Capacity Factor (DER Net)23.Unit Forced Outage Rate This Month 720.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 100.0 Year-to-Date 4344.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 100.0 Cumulative 188424.0 121771.0 0.0 118153.4 0.0 366007650.4 118584640.0 114257779 0 63.5 63.5 57.8'6.3 21.7 24.Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):

None 25.If Shut Down At End of Report Period, Estimated Date of Startup: April 2000 26.Units in Test Status (Prior to Commercial Operation):

INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION Forecast Achieved DOCKET NO.UNIT NAME DATE COMPLETED BY TELEPHONE 50-316 D.C.Cook Unit 2 July 1, 1999 M.M.Pratt 616-465-5901 AVERAGE DAILY POWER LEVEL (MWe-Net)June 1999 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL 6/1/99 6/2/99 6/3/99 6/4/99 6/5/99 6/6/99 6/7/99 6/8/99 6/9/99 6/10/99 6/11/99 6/12/99 6/13/99 6/14/99 6/15/99 6/16/99 6/17/99 6/18/99 6/19/99 6/20/99 6/21/99 6/22/99 6/23/99 6/24/99 6/25/99 6/26/99 6/27/99 6/28/99 6/29/99 6/30/99 DOCKET NO.UNIT NAME DATE COMPLETED BY TELEPHONE PAGE 50-316 D.C.Cook Unit 2 July 6, 1999 S.A.Richardson 616-465-5901 1 of1 MONTHLY OPERATING ACTIVITIES

-June 1999 HIGHLIGHTS The unit entered this reporting period in Mode 5 at 0%RTP.The unit exited this reporting period in Mode 5 at 0%RTP.There were no challenges to the pressurizer safety valves or power operated relief valves.Gross electrical generation for the month of June was 0 MWh.DETAILS 06/01/99 The Reactor remains shutdown since 09/08/97 to resolve design basis questions identified during the NRC Architect and Engineering (AE)Inspection and subsequent Expanded System Readiness Reviews (ESRR).All time entries are Eastern Standard Time (EST).

DOCKET NO.UNIT NAME DATE COMPLETED BY TELEPHONE PAGE 50-316 D.C.Cook Unit 2 July 6, 1999 S.A.Richardson 616-465-5901 1 of1 UNIT SHUTDOWNS AND POWER REDUCTIONS

-June 1999, METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT NO.DATE TYPE1 HOURS REASON2 REACTOR3 REPORT NO.CODE4 CODE5 CAUSE AND CORRECTIVE ACTION TO PREVENT RECURRENCE 335 010798 F 720.0 NIA NIA NIA The unit remained shutdown to resolve design basis questions discovered during the NRC Architect and Engineering (AE)Inspection.

1 TYPE: F: Forced S: Scheduled 2 REASON: A: Equipment Failure (Explain)B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error (Explain)H: Other (Explain)3 METHOD: 1: Manual 2: Manual Scram 3: Automatic Scram 4: Other (Explain)4 SYSTEM: Exhibit G-Instructions for preparation of data entry sheets for Licensee Ev'ent Report (LER)File (NUREG 0161)5 COMPONENT:

Exhibit I: Same Source 0~~~~