Ro:On 860311,fire Pump Taken Out of Svc to Perform Maint on Fire Main Supplied by Pump.Pump Out of Svc Beyond 7-day Limit Permitted by Tech Specs.Pump Will Be Returned to Svc in Approx 45 Days,Upon Completion of Repair Work
ML20203P541
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 04/07/1986
From: Selman M
CONSOLIDATED EDISON CO. OF NEW YORK, INC.
To: Murley T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
NUDOCS 8605070419
Download: ML20203P541 (1)


Text

.__

CVuo PieiiderG Consolidated Edison Company of New York, Inc.

. Indian Point Station Broadway & B!eakley Ave, Buchanan, NY 10511 Telephone (914) 737-8116 April 7, 1986 Re: Indian Point Unit No. 2 Docket No. 50-247 Dr. Thomas E. Murley Regional Administrator U.S. Nuclear Regulatory Commission Region I 631 Park Avenue King of Prussia, PA 19406

SUBJECT:

Inoperable High Pressure Water Protection System 30-day Report

Dear Dr. Murley:

Technical Specification 3.13.A.2 requires that a 30-day report be submitted if a motor driven fire pump - is inoperable for greater than 7 days. This report is being submitted in accordance with this requirement.

On March 11, 1986, No. 11 fire pump was taken out of service to perform necessary maintenance on a section of the fire main supplied by this pump.

The fire pump remained out of service beyond the 7 day period permitted by.

the Technical Specifications. The scope of the maintenance planned requires approximately 45 days. The pump will be returned to service upon completion of repair work.

Very truly yours, fp '

17.250.4.3.1 cc: Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 38 Buchanan, NY 10511 8605070419 860407 i PDR ADOCK0500g7 4