Special Rept:During Cycle 6/7 Refueling Outage Scheduled from Feb-May 1989,openings Will Be Made in Plant Penetration Fire Barriers in Order to Install Various Mods. Fire Watches Posted & Fire Detection Tests Completed
ML20235V593
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 03/02/1989
From: Josiger W
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
IP3-89-JJA-041H, IP3-89-JJA-41H, IP3-89-WAJ-012, IP3-89-WAJ-12, NUDOCS 8903100246
Download: ML20235V593 (1)


Text

, - . _ _ _ . - . . _ . - - - - - _ . . - _ . _ _ _ - . - - - _ _ - . _ _ _ _ _ _ _ _ - - _ _ _ . - _ _ _ _ _

Nuclear Power Plant

.e *

  • PO. Box 215 .

Buchanan, NewYork 10511 914 739.8200

  1. > NewYorkPbwer tv Authority March 2, 1989 IP3-89-WAJ-012 IP3-89-JJA-041H Docket No.'50-286 ,

License No. DPR-64 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Station PI-137 Washington, D.C. 20555

Dear Sir:

The following is a Special Report on Penetration Fire Barriers at Indian Point Unit 3, prepared in accordance with the requirements of Technical Specification 6.9.2.f. The event described is covered by Technical Specification 3.14.C.2.b.

During the cycle' 6/7 refueling outage scheduled from February 1989 through ' May 1989, openings will be made in several plant penetration fire barriers in order to install various plant modifications. 'The appropriate fire watches were be posted and fire detection tests completed as required by Technical Specification 3.14.C.2.a. The affected penetration fire barriers are those cor red under Technical Specification 3.14.C.1.

The plant is presently scheduled to be brought above the cold shutdown condition in late May, 1989. All required penetration fire barriers will be returned to their functional status. Appropriate surveillance testing will be performed to ensure functionality of the penetration fire barriers.

Very truly yours, ,

1

/ JK 4 fam A. Jo iger Resident a ger Indian P 3 Nuclear Power Plant

\ WJ:J .sd:6:47 cc: Mr. William Russell, Regional Administrator Region 1 '

U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, Pennsylvania 19406 k7 l D

^

'8903100246 890302 PDR ADOCK 05000286

, S PDC .