Letter Sequence RAI |
---|
EPID:L-2018-LRO-0022, Summary of 7/17/2018 Public Meeting in Forked River, Nj, to Receive Public Comments on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate (Approved, Closed) |
|
MONTHYEARML18149A0942018-06-0505 June 2018 FRN, Notice of Receipt, Public Meeting, Request for Comment, Post-Shutdown Decommissioning Activities Report Project stage: Meeting ML18149A0722018-06-0505 June 2018 Letter, Notice of Receipt, Public Meeting, and Request for Comment on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate Project stage: Meeting ML18201A2602018-06-13013 June 2018, 17 July 2018, 31 August 2018 Summary of 7/17/2018 Public Meeting in Forked River, Nj, to Receive Public Comments on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate Project stage: Request NRC-2018-0111, Comment (1) of Patrick Mulligan on Exelon Generation Company, LLC; Oyster Creek Nuclear Generating Station; Post-Shutdown Decommissioning Activities Report2018-06-29029 June 2018 Comment (1) of Patrick Mulligan on Exelon Generation Company, LLC; Oyster Creek Nuclear Generating Station; Post-Shutdown Decommissioning Activities Report Project stage: Request ML18201A2372018-07-17017 July 2018 Slides 7/17/2018 PSDAR Meeting Project stage: Meeting ML18201A3772018-07-17017 July 2018 Meeting Transcript for 7/17/2018 Public Meeting in Forked River, Nj, to Receive Public Comments on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate Project stage: Meeting ML18201A3072018-07-17017 July 2018 Post Shutdown Decommissioning Activities Report (PSDAR) Public Meeting Presentation Project stage: Meeting ML18201A2842018-07-17017 July 2018 PSDAR Public Meeting the NRC Review Process Project stage: Meeting ML18205A5502018-08-0606 August 2018 Memorandum to File - Public Feedback to 7/17/18 Public Meeting in Forked River, Nj, to Receive Public Comments on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate Project stage: Meeting ML18201A2632018-08-31031 August 2018 Summary of Public Meeting in Forked River, Nj, to Discuss Oyster Creek Nuclear Generating Station Post-Shutdown Decommissioning Activities Report Project stage: Meeting ML18256A0022018-09-12012 September 2018 NRR E-mail Capture - for Your Action: RAIs for Oyster Creek Post Shutdown Decommissioning Activities Report (PSDAR) Project stage: RAI RA-18-093, Request to Reinitiate Consultation Regarding the OCNGS Sea Turtle Incidental Take Statement2018-10-16016 October 2018 Request to Reinitiate Consultation Regarding the OCNGS Sea Turtle Incidental Take Statement Project stage: Request ML18241A0682018-12-17017 December 2018 Creek - Review of Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost Estimate Project stage: Approval 2018-06-05
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML22235A7862022-08-23023 August 2022 Acceptance Review: Exemption Request from 10 CFR 20, Appendix G, LLW Shipping Investigation Requirements ML21181A1882021-06-30030 June 2021 E-mail from S. Johnston, Holtec, to A. Snyder and F. Bower, NRC - Oyster Creek Nuclear Generating Station - Readiness Status for ISFSI Only Inspection ML21175A2092021-06-24024 June 2021 E-mail from A. Sterdis to P. Longmire - Oyster Creek Nuclear Generating Station: ISFSI-only Physical Security Plan (Stating Implementation Intent) ML21162A3602021-06-11011 June 2021 E-mail Response from the State of New Jersey Regarding the Pending Revision to the Emergency Plan to Reflect Independent Spent Fuel Storage Installation Only Status ML21162A1172021-06-11011 June 2021 E-mail to HDI: Acceptance Review - FOF Exemption ML21168A0172021-06-10010 June 2021 E-mail from HDI: RAI Response ML21161A2572021-06-0707 June 2021 State Consultation: ISFSI-only Physical Security Plan (Email Response) ML21175A0712021-06-0202 June 2021 Issuance of Request for Additional Information: Oyster Creek Nuclear Generating Station. Request for Amendment to Technical Specifications ML21148A0562021-05-27027 May 2021 E-mail to State of New Jersey Informing of the Pending Revision to the Emergency Plan to Reflect Independent Spent Fuel Storage Installation Only Status ML21132A3182021-05-12012 May 2021 E-Mail from V. Gubbi, DEP to Z. Cruz, NRC - Oyster Creek Nuclear Generating Station - State of New Jersey Response to the Pending Revision to the Defueled Technical Specifications to Reflect Independent Spent Fuel Storage Installation Only ML21132A0312021-05-11011 May 2021 E-mail to State of New Jersey Informing of the Pending Revision to the Physical Security Plan to Reflect Independent Spent Fuel Storage Installation Only Status ML21119A1422021-04-28028 April 2021 E-mail to State of New Jersey Informing of the Pending Revision to the Emergency Plan to Reflect Independent Spent Fuel Storage Installation Only Status ML21113A0742021-04-23023 April 2021 Acceptance Review Email - April 20, 2021 Oyster Creek Request for Exemption from 10 CFR Part 73 Requirements Due to Covid ML21099A0382021-04-0808 April 2021 Email from Z. Cruz to A. Sterdis - Request for Additional Information - HDI Request for Approval of Oyster Creek Nuclear Generating Station Independent Spent Fuel Storage Installation Facility Only Emergency Plan ML21085A4872021-03-26026 March 2021 E-mail from Z. Cruz to A. Sterdis - Acceptance Review: Oyster Creek Nuclear Generating Station - Request for Approval of Independent Spent Fuel Storage Installation Only Permanently Defueled Technical Specifications ML21064A2432021-03-0505 March 2021 Email from Z. Cruz to A. Sterdis Acceptance Review_ Oyster Creek Nuclear Generating Station - Request for Approval of Independent Spent Fuel Storage Installation Facility Only Emergency Plan and Emergency Action Level Scheme ML21064A2392021-03-0202 March 2021 E-mail from Z. Cruz to A. Sterdis Acceptance Review - Oyster Creek Nuclear Generating Station - Request for Approval of Independent Spent Fuel Storage Installation Only Physical Security Plan ML20345A1462020-12-0909 December 2020 E-mail - Response to Request for Additional Information: HDI Request for One-Time Exemption from Part 73, Appendix B FOF Requirements ML20335A3112020-11-30030 November 2020 Request for Additional Information Regarding Request for a one-time Exemption from Part 73, Appendix B Requirements for Oyster Creek Nuclear Generating Station ML20332A1472020-11-24024 November 2020 Acceptance Review: November 20 2020 Exemption Request from 10 CFR Part 73 Appendix B Requirements for Oyster Creek ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20279A5082020-10-0505 October 2020 Email to Holtec - Response to Notification of Oyster Creek Onsite Property Insurance Coverage ML20266G4032020-09-22022 September 2020 Acceptance Review Email - Request for Approval of HDI Fleet Decommissioning Quality Assurance Program, Revision 0 ML20134H8742020-05-12012 May 2020 Request for Additional Information Regarding Request for Temporary Exemption from Part 73, Appendix B Requirements ML20133J9182020-05-11011 May 2020 Acceptance Review Email - Oyster Creek Request for Exemption from Part 73 Qualification Requirements ML20120A0252020-04-22022 April 2020 NRR E-mail Capture - (External_Sender) Oyster Creek Sea Turtle Handling and Conservation Recommendation Obligations NRC-2019-0073, Response from NEIMA Local Community Advisory Board Questionnaire 10-30-2019 R Discenza2019-10-30030 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-30-2019 R Discenza ML19344C8022019-10-20020 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-20-2019 a Dressler ML19344C8002019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 W Mcmullin ML19344C7982019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 M Noto ML19344C7992019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 s Feldman ML19344C7932019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 C Bischoff ML19344C7962019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 G Adams ML19344C7912019-10-0808 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-08-2019 J Branciforte ML19344C7902019-10-0808 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-08-2019 Anonymous ML19344C7892019-10-0505 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-05-2019 P Dressler ML19263D1222019-09-20020 September 2019 for Your Action Request for Additional Information Hdi Oyster Creek PSDAR ML19214A0452019-08-0202 August 2019 NRC to NMFS, Revised Proposed Action for Oyster Creek Endangered Species Act Section 7 Consultation ML19182A3422019-07-0101 July 2019 Transaction ML19178A0702019-06-26026 June 2019 Email to State of New Jersey - Oyster Creek - Request Comments on Proposed Amendment to Remove Reference to the Oyster Creek Cyber Security Plan and Update License Condition 2.C.(4) in the Renewed Facility License ML19196A3422019-06-20020 June 2019 Email: Courtesy Notice on the Issuance of the Oyster Creek License Transfer and Exemption (Sierra Club) ML19196A3342019-06-20020 June 2019 Email: Courtesy Notice on the Issuance of the Oyster Creek License Transfer and Exemption ML19162A2242019-06-11011 June 2019 NRC to NMFS, NRC Responses to NMFS Requests for Additional Information for Oyster Creek ESA Section 7 Consultation NRC-2018-0237, Comment from Paul Dressler of the Concerned Citizens for Lacey Coalition, Regarding the Oyster Creek Nuclear Plant License Transfer Application2019-06-0707 June 2019 Comment from Paul Dressler of the Concerned Citizens for Lacey Coalition, Regarding the Oyster Creek Nuclear Plant License Transfer Application ML19155A1182019-06-0404 June 2019 Incoming E-mail from State of New Jersey on the Oyster Creek Exemption for Reduced Insurances and Use of Decommissioning Trust Fund for Spent Fuel Management and Site Restoration ML19155A1192019-06-0404 June 2019 State of New Jersey Comments - Oyster Creek Conforming Amendment Associated with the Oyster Creek Generating Station License Transfer Application ML19154A0582019-05-31031 May 2019 E-mail Response from State of New Jersey Dated May 31, 2019, Notification-and-Request-Oyster Creek License Transfer Application L-2018-LLM-0002 ML19158A2912019-05-30030 May 2019 NRR E-mail Capture - Oyster Creek ESA Consultation: Information Requests from NMFS ML19158A2772019-05-28028 May 2019 NRR E-mail Capture - Oyster Creek ESA Consultation: Information Requests from NMFS ML19148A4392019-05-24024 May 2019 NMFS to NRC, Requests for Additional Information to Support Oyster Creek Reinitiated Section 7 Consultation 2022-08-23
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML21099A0442021-04-0808 April 2021 Enclosure - Request for Additional Information Related to Request for Approval of Oyster Creek Nuclear Generating Station Independent Spent Fuel Storage Installation Only Emergency Plan Holtec Decommissioning International, LLC ML20335A3102020-11-30030 November 2020 RAI November 2020 Part 73 FOF Exemption Request ML20297A2382020-10-22022 October 2020 Fleet DQAP RAIs - Enclosure ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20134H8732020-05-12012 May 2020 E-mail - Request for Additional Information: Oyster Creek Request for Temporary Exemption from Part 73, Appendix B Requirements ML19263D2142019-09-20020 September 2019 Hdi PSDAR Environmental RAI Enclosure (002) ML19158A2772019-05-28028 May 2019 NRR E-mail Capture - Oyster Creek ESA Consultation: Information Requests from NMFS ML19025A1172019-01-24024 January 2019 NRR E-mail Capture - for Your Action - RAI for Oyster Creek EP Exemption (Change to Adiabatic Heat-Up Calculation) ML18256A0022018-09-12012 September 2018 NRR E-mail Capture - for Your Action: RAIs for Oyster Creek Post Shutdown Decommissioning Activities Report (PSDAR) ML18135A0732018-05-15015 May 2018 NRR E-mail Capture - RAIs - Oyster Creek - Request Approval of the Decommissioning Quality Assurance Program ML18068A6582018-03-0909 March 2018 NRR E-mail Capture - RAIs - Oyster Creek Defueled TS LAR ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML18024B0642018-01-24024 January 2018 NRR E-mail Capture - for Your Action - RAI for Oyster Creek Permanently Defueled EP and EAL Scheme LAR (CAC No. MG0160; EPID: L-2017-LLA-0307) ML18012A0782018-01-12012 January 2018 NRR E-mail Capture - for Your Review - Draft RAI for Oyster Creek Permanently Defueled EP and EAL Scheme LAR (CAC No. MG0160; EPID: L-2017-LLA-0307) ML18003A4122018-01-0303 January 2018 NRR E-mail Capture - for Your Action - RAI - Oyster Creek BWRVIP LAR (CAC No. MG0180; EPID No. L-LLA-2017-0304) ML17320A6372017-11-16016 November 2017 NRR E-mail Capture - Oyster Creek Nuclear Generating Station - Request for Additional Information Regarding License Amendment Request for Emergency Plan Exemption (CAC No. MG0153; EPID L-2017-LLE-0020) ML17319A9422017-11-15015 November 2017 NRR E-mail Capture - Oyster Creek Nuclear Generating Station - Request for Additional Information Regarding License Amendment Request for Emergency Plan Exemption (CAC No. MG0153; EPID L-2017-LLE-0020) ML17208A7472017-09-14014 September 2017 Request for Additional Information, License Amendment Request to Revise the Site Emergency Plan for On-Shift and Emergency Response Organization Staffing for Permanently Defueled Condition ML17136A3852017-05-12012 May 2017 NRR E-mail Capture - (External_Sender) Oyster Creek Response to NRC Flood MSA Audit Review Questions ML17038A5152017-02-0303 February 2017 NRR E-mail Capture - (External_Sender) Oyster Creek Nuclear Generating Station Response to Environmental Questions Regarding the Mitigating Strategies Final Integrated Plan and SPF Instrumentation Compliance Letter ML16244A3112016-10-0707 October 2016 Request for Additional Information Regarding License Amendment Request for Technical Specifications Section 6.0, Administrative Controls for Permanently Defueled Condition ML16125A2452016-05-16016 May 2016 Request for Additional Information Regarding Request for Approval of a Certified Fuel Handler Training and Retraining Program ML16060A1722016-03-0707 March 2016 Request for Additional Information Regarding Preliminary Decommissioning Cost Estimate and Spent Fuel Management Program ML16056A0012016-02-24024 February 2016 NRR E-mail Capture - Request for Additional Information - Oyster Creek Security Plan - Revision 14 ML17144A3702015-05-0606 May 2015 NRC Email J. Hughey( NRC) to Dave Distel (Exelon)- Request for Additional Information Regarding Request for Extension to Comply with NRC Order EA-13-109, Dated May 6, 2015 ML15005A0692015-01-0606 January 2015 Request for Additional Information Regarding the Fourth 10-Year Interval Inservice Inspection Program Plan Requests for Relief ML14246A5182014-09-17017 September 2014 Request for Additional Information Regarding the Fourth 10-Year Interval Inservice Inspection Program Plan Requests for Relief ML14252A7032014-09-17017 September 2014 Request for Additional Information Regarding Preliminary Decommissioning Cost Estimate and Annual Decommissioning Funding Status Reports ML14247A5862014-09-16016 September 2014 Request for Additional Information Regarding License Amendment Request to Revise Snubber Surveillance Requirements (Tac No. MF4124) ML14114A5632014-09-10010 September 2014 Request for Additional Information Regarding License Amendment Request Related to Reactor Building Vital Area Access Control ML14220A0272014-08-27027 August 2014 Request for Additional Information Regarding Request for Extension to Comply with NRC Order EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions ML14083A1602014-03-31031 March 2014 Request for Additional Information Regarding Bulletin 2012-01, Design Vulnerability in Electric Power System ML13351A3142013-12-20020 December 2013 Request for Additional Information Regarding Response to Bulletin 2012-01, Design Vulnerability in Electric Power System. ML13268A0312013-11-0808 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13227A3042013-08-28028 August 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML13196A3382013-07-15015 July 2013 2013 Decommissioning Fund Report RAI ML12229A4332012-09-0606 September 2012 Request for Additional Information Regarding Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 12 (TAC No. D91660) ML12056A0502012-03-12012 March 2012 Enclosure 4 - Recommendation 2.3: Flooding ML12056A0482012-03-12012 March 2012 Enclosure 2 - Recommendation 2.1: Flooding ML12056A0472012-03-12012 March 2012 Enclosure 1 - Recommendation 2.1: Seismic ML12056A0492012-03-12012 March 2012 Enclosure 3 - Recommendation 2.3: Seismic ML12056A0512012-03-12012 March 2012 Enclosure 5 - Recommendation 9.3: Emergency Preparedness ML12032A1872012-02-21021 February 2012 Request for Additional Information Related to the Response to License Renewal Commitment No. 10 Regarding Thermal Aging Irradiation Embrittlement of Cast Austenitic Stainless Steel ML12025A2542012-01-23023 January 2012 Request for Additional Information - License Renewal Commitment Regarding Thermal Aging and Neutron Irradiation Embrittlement of CASS Materials ML1200603242012-01-19019 January 2012 Fleet, RAI, Proposed Alternative to Use American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Case N-789 (N-789) ML1131200572011-11-22022 November 2011 Fleet - Bulletin 2011 01, Mitigating Strategies Request for Additional Information Regarding 60-Day Response ML1123604472011-08-24024 August 2011 E-mail, Miller to Loomis, Oyster Creek Flaw Evaluation Draft RAI Questions ML1120910012011-07-22022 July 2011 Generation Station - Licensed Operator Request for Additional Information ML1116805642011-07-0707 July 2011 Fleet, Request for Additional Information, 2011 Report on Status of Decommissioning Funding for Reactors 2021-04-08
[Table view] |
Text
NRR-DMPSPEm Resource From: Lamb, John Sent: Wednesday, September 12, 2018 11:13 AM To: 'david.helker@exeloncorp.com'; Richard.Gropp@exeloncorp.com; Bonnett, Frederick Paul:(GenCo-Nuc); Dostal, Jeffrey Paul:(GenCo-Nuc)
Subject:
For Your Action: RAIs for Oyster Creek PSDAR (EPID: L-2018-LRO-0022)
Importance: High
Dear Mr. Helker:
By letter dated January 7, 2011 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML110070507), Exelon Generation Company, LLC (Exelon or the licensee), submitted its Notification of Permanent Cessation of Power Operations for Oyster Creek Nuclear Generating Station (Oyster Creek). In this letter, Exelon provided notification to the U.S. Nuclear Regulatory Commission (NRC) of its intent to permanently cease power operation no later than December 31, 2019.
By letter dated February 14, 2018 (ADAMS Accession No. ML18045A084), Exelon submitted its updated Notification of Permanent Cessation of Power Operations for Oyster Creek. In this letter, Exelon provided notification to the NRC of its intent to permanently cease power operation no later than October 31, 2018.
By letter dated May 21, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18141A775), Exelon Generation Company, LLC (Exelon or the licensee) submitted a Post Shutdown Decommissioning Activities Report (PSDAR) in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Section 82(a)(4)(i). In this letter, Exelon stated that it planned to permanently cease operations at Oyster Creek on September 17, 2018.
The NRC staff has reviewed Exelon's submittal and determined that additional information is required to enable the U.S. Nuclear Regulatory Commission (NRC) staff to make an independent assessment regarding its technical review.
The enclosure to this email provides the request for additional information (RAI). On July 11, and August 30, 2018, the draft RAI questions were sent to Mr. Richard Gropp, and Mr. Paul Bonnet of your staff to ensure that they were understandable, the regulatory bases for the questions were clear, and to determine if the information was previously docketed. Teleconference were held on July 12, and September 12, 2018, with Mr.
Bonnet and Mr. Gropp of your staff to clarify the RAI questions. Exelon stated they would respond to the RAI within 30 days of the date of this email.
If you have any questions, please contact me at 301-415-3100 or via e-mail at John.Lamb@nrc.gov.
Sincerely, John G. Lamb, Senior Project Manager Special Projects and Process Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-219
Enclosure:
Request for Additional Information 1
ENCLOSURE REQUEST FOR ADDITIONAL INFORMATION RELATED TO POST SHUTDOWN DECOMMISSIONG ACTIVITIES REPORT FOR OYSTER CREEK NUCLEAR GENERATING STATION EXELON GENERATION COMPANY, LLC OYSTER CREEK NUCLEAR GENERATING STATION DOCKET NOS. 50-219 AND 72-15 By letter dated May 21, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18141A775), Exelon Generation Company, LLC (Exelon or the licensee) submitted a Post Shutdown Decommissioning Activities Report (PSDAR) in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Section 82(a)(4)(i).
The NRC staff has reviewed Exelon's submittal and determined that additional information is required to enable the U.S. Nuclear Regulatory Commission (NRC) staff to make an independent assessment regarding its technical review.
Regulatory Basis The regulation 10 CFR 50.82(a)(4)(i) states that the licensee shall submit a PSDAR to the NRC that includes a discussion that provides the reasons for concluding that the environmental impacts associated with site-specific decommissioning activities will be bounded by appropriate previously issued environmental impact statements. The regulation 10 CFR 50.82(a)(6) states, in part, that [l]icensees shall not perform any decommissioning activities that [r]esult in significant environmental impacts not previously reviewed .
In NUREG-0586, Generic Environmental Impact Statement on Decommissioning of Nuclear Facilities:
Supplement 1, Regarding the Decommissioning of Nuclear Power Reactors (decommissioning GEIS), the NRC evaluated the environmental impacts during the decommissioning of nuclear power reactors. The decommissioning GEIS concludes that:
For those issues that have been determined to be generic, licensees may proceed with the decommissioning activity without further analysis provided that the impacts resulting from those activities fall within the range of impacts as described in Chapter 4. However, if the impacts of an activity fall outside the range predicted in Chapter 4, or if the activity results in impacts to environmental issues not considered in this Supplement, or if the impact involves an environmental issue determined to be conditionally site-specific as defined above, then the activity cannot be performed until a further site-specific analysis is completed along with a license-amendment request and NRC has approved the license amendment (the license amendment request will provide an opportunity for a public hearing).
Consistent with the decommissioning GEIS, 10 CFR 50.82(a)(4)(i) could be satisfied by stating in the PSDAR that, prior to performing decommissioning activities that result in significant environmental impacts, the licensee will complete a further site-specific analysis along with a license amendment request or, alternatively, along with an exemption request.
Aquatic and Terrestrial Resources 2
In Section 5.1.5, Aquatic Ecology, and Section 5.1.6, Terrestrial Ecology, of Exelons PSDAR (ADAMS Accession No. ML18141A775), Exelon states that offsite impacts to aquatic and terrestrial resources may result from dredging and from ground disturbing activities associated with moving large plant components from the Oyster Creek Nuclear Generating Station (OCNGS) powerblock area to the barge landing, which is outside of the operational area. Exelon concludes that that the offsite impacts from dredging are bounded by the impacts in the NRCs GEIS for License Renewal of Nuclear Plants (NUREG-1437, Revision 1). Exelon concludes that the impacts from erosion and sedimentation on aquatic resources and that the impacts from decommissioning activities on terrestrial resources outside of the operational area would be small and bounded by the analysis in the decommissioning GEIS.
The decommissioning GEIS, however, states that the issues of aquatic and terrestrial ecology for activities beyond the operational area are conditionally site-specific and that any planned decommissioning activity would require a site-specific analysis along with a license amendment request prior to undertaking the proposed activity.
A/T-1 Consistent with 10 CFR 50.82(a)(4)(i), please provide the reasons for concluding that the environmental impacts to aquatic and terrestrial ecology associated with ground disturbing activities beyond the operational area will be bounded by appropriate previously issued environmental impact statements.
Please explain why the decommissioning GEIS bounds these impacts despite its statement that the issues of aquatic and terrestrial ecology for activities beyond the operational area are conditionally site-specific and/or explain how any significant environmental impacts not previously reviewed will be addressed before the activities are performed (e.g., through the prior approval of a license amendment request or an exemption request).
Special Status Species & Habitats SS-1 The OCNGS license states that Exelon shall comply with the terms and conditions of the Incidental Take Statement associated with certain sea turtles in the Biological Opinion in effect or as subsequently issued by the National Marine Fisheries Service (NMFS) regarding operation of the facility.
The Biological Opinion in effect regarding operation of the OCNGS contains an Incidental Take Statement with 12 terms and conditions. The Biological Opinion, however, did not consider effects to listed species from any decommissioning plans or other activities associated with the future termination of operations at OCNGS because [a]s there is no information on future activities currently available, any effects of decommissioning or activities associated with the termination of operation are not knowable at this time. (ADAMS Accession No. ML12006A217, p. 8).
Please explain how Exelon will continue to comply with each of the 12 terms and conditions during decommissioning. For instance, Term and Condition 2 states that inspection of the cooling water system and dilution water system intake trash bars and immediate area upstream must be conducted at least once every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> from June 1 through October 31. How would decommissioning affect Exelons continued conduct of such inspections? Alternatively, should the NRC reinitiate consultation with the NMFS in order to amend these terms and conditions for the decommissioning period?
SS-2 In its PSDAR, Exelon describes several State and Federally listed species with the potential to occur within the vicinity of OCNGS (see Table 5.1). In addition, Exelon provides a site-specific assessment of environmental impacts associated with decommissioning activities at OCNGS. Exelon concludes that OCNGS decommissioning activities are unlikely to adversely affect any threatened or endangered species and will have no effect on any designated critical habitat.
The regulation 10 CFR 50.82(a)(4)(i), however, requires that the PSDAR provide the reasons for concluding that the environmental impacts associated with site-specific decommissioning activities will be bounded by appropriate previously issued environmental impact statements.
3
Consistent with 10 CFR 50.82(a)(4)(i), please explain whether the impacts to the State and Federally listed species with the potential to occur within the vicinity of OCNGS are bounded by appropriate previously issued environmental impact statements. If these impacts are not bounded by appropriate previously issued environmental impact statements, how will Exelon ensure that they will be bounded?
For instance, will Exelon complete a site-specific analysis of the issue along with a license amendment request, as discussed in the decommissioning GEIS, before performing any decommissioning activities that result in significant impacts to threatened and endangered species?
Historic and Cultural Resources Section 5.1.14 of the PSDAR provides an analysis of potential impacts to cultural, historic, and archeological resources, and indicates that Exelons review of available information identified no historic properties present within the OCGNS operational area.
The decommissioning GEIS states:
In a few situations, the nuclear facility itself could be potentially eligible for inclusion in the National Register of Historic Places, especially if it is older than 50 years and represents a significant historic or engineering achievement. In this case, appropriate mitigation would be developed in consultation with the SHPO [State Historic Preservation Officer]. Even for buildings that are less than 50 years old, the processes and engineering that were employed may be of interest and may be eligible for the Historic American Engineering Record.
HC-1 Does Exelon plan to address with the New Jersey SHPO the potential eligibility of all or portions of the OCNGS facility itself for inclusion in the to the National Register of Historic Places or Historic American Engineering Record, and identify appropriate mitigation measures potentially resulting from this consultation in the PSDAR?
4
Hearing Identifier: NRR_DMPS Email Number: 560 Mail Envelope Properties (John.Lamb@nrc.gov20180912111300)
Subject:
For Your Action: RAIs for Oyster Creek PSDAR (EPID: L-2018-LRO-0022)
Sent Date: 9/12/2018 11:13:12 AM Received Date: 9/12/2018 11:13:00 AM From: Lamb, John Created By: John.Lamb@nrc.gov Recipients:
"'david.helker@exeloncorp.com'" <david.helker@exeloncorp.com>
Tracking Status: None "Richard.Gropp@exeloncorp.com" <Richard.Gropp@exeloncorp.com>
Tracking Status: None "Bonnett, Frederick Paul:(GenCo-Nuc)" <Frederick.Bonnett@exeloncorp.com>
Tracking Status: None "Dostal, Jeffrey Paul:(GenCo-Nuc)" <Jeffrey.Dostal@exeloncorp.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 11562 9/12/2018 11:13:00 AM Options Priority: High Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: