ML20332A147
| ML20332A147 | |
| Person / Time | |
|---|---|
| Site: | Oyster Creek |
| Issue date: | 11/24/2020 |
| From: | Cruz Z Office of Nuclear Material Safety and Safeguards |
| To: | Sterdis A Holtec |
| Cruz Z, NMSS/DUWP | |
| References | |
| Download: ML20332A147 (1) | |
Text
From:
Cruz Perez, Zahira To:
Andrea Sterdis Cc:
James Frank; Watson, Bruce Bcc:
Williams, Vince
Subject:
Acceptance Review: November 20, 2020 Exemption Request from 10 CFR Part 73 Appendix B requirements for Oyster Creek Date:
Tuesday, November 24, 2020 3:13:00 PM
- Andrea,
The staff reviewed the Oyster Creek request for exemption from 10 CFR Part 73, Appendix B, during COVID-19 pandemic dated November 20, 2020 and have determined that the licensee has provided the necessary information for a review of their submittal. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
The NRC staff will endeavor to complete this review before December 31, 2020. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date, it will be communicated during the routine interactions.
If you have any questions, please contact me.
Zahira Cruz
Zahira Cruz Project Manager U.S. Nuclear Regulatory Commission Office of Nuclear Material Safety and Safeguards Reactor Decommissioning Branch Mail Stop: T-5A10 Rockville, MD 20852 Zahira.Cruz@nrc.gov 301-415-3808 Office: T-5B47