Mid-Cycle Performance Review and Inspection Plan 2010 - R.E. Ginna Nuclear Power Plant
ML102440199
Person / Time
Site: Ginna Constellation icon.png
Issue date: 09/01/2010
From: Dapas M
NRC Region 1
To: John Carlin
Ginna
Dentel, G RGN-I/DRP/BR1/610-337-5233
References
Download: ML102440199 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406.1415 September 1, 2010 Mr. John T. Carlln Vice President R E. Ginna Nuclear Power Plant R E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519 SUB~'ECT: MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - R E.

GINNA NUCLEAR POWER PLANT

Dear Mr. Carlin:

On August 10, 2010, the Nuclear Regulatory Commission (NRC) staff completed its performance review of the R E. Ginna Nuclear Power Plant (Ginna). Our technical staff reviewed performance indicators (Pis) for the most recent quarter and inspection results for the period from July 1, 2009, through June 30. 2010. The purpose of this letter is to inform you of the results of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only~-Security Information" will include the security cornerstone review and resultant inspection plan.

Safety performance at Ginna for the most recent quarter was within the Degraded Cornerstone column of the NRC's Action matrix, based on two findings having low to moderate safety significance (White) and one White Performance (PI) in the Mitigating Systems Cornerstone.

The first White finding, originating in the first quarter 2009, was related to inadequate implementation of a preventive maintenance program for the turbine-driven auxiliary feedwater (TDAFW) pump governor. The second White finding, originating in the fourth quarter 2009, was related to inadequate corrective actions which led to binding of the governor control valve and failure of the same TDAFW pump. The White PI was related to exceeding the White Significance threshold for the Mitigating Systems Performance Index (MSPI). Heat Removal Systems PI, in the third quarter 2009, due to the reliability issues associated with auxiliary feedwater system and specifically, the TDAFW pump.

On July 23, 2010, we completed a supplemental inspection pursuant to Inspection Procedure 95002, "Inspection for One Degraded Cornerstone or Any Three White Inputs In a Strategic Performance Area." This inspection was conducted to provide assurance that the root and contributing causes for the risk significant performance issues (White findings and White PI) are understood, to independently assess the extent of condition, to independently determine if safety culture components contributed to the performance issues, and to provide assurance that the corrective actions are sufficient to prevent recurrEmce. The public exit meeting and the regulatory performance meeting for the supplemental inspection were conducted on August 4, 2010, and the report was issued on August 31,2010. Based on the results of the 95002 inspection, the NRC did not identify any findings of significance and determined that all of the 95002 objectives were satisfied. Therefore, based on these results, Ginna returned to the Regulatory Response Column of the NRC's Action Matrix in the third quarter of 201 O.

J. Carlin 2 The enclosed inspection plan details the inspections. less those related to physical protection, scheduled through December 31, 2011. In addition to the baseline inspections, we plan on conducting independent spent fuel storage installatiem inspections. The inspection plan is provided to allow for the resolution of any schedulint~ conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRC's "Ru!l3s of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Glenn Dentel of my staff at 610-337-5233 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

!!:::.?~

Acting Regional Administrator Region I Docket No. 50-244 License No. DPR-18 Enclosure Ginna Inspection I Activity Plan ccw/encl: Distribution via ListServ

J. Carlin 2 The enclosed inspection plan details the inspections, less those related to physical protection.

scheduled through December 31, 2011. In addition to the baseline inspections, we plan on conducting independent spent fuel storage installation inspections. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.

The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice,* a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room*

or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room). .

If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Glenn Dentel of my staff at 610-337-5233 with any questions you may have regarding this Jetter or the inspection plan.

Sincerely, IRA!

Marc L. Dapas Acting Regional Administrator Region I Docket No. 50-244 License No. DPR-18 Enclosure Ginna Inspection I Activity Plan Distribution w/encl:(via E-mail)

M. Dapas, Acting RA J. Hawkins, DRP DRS Branch Chiefs (6)

D. Lew, Acting ORA G. Hunegs, DRP, SRI D. Serenci, PAO, J. Clifford, DRP L. Casey, DRP. RI N. Sheehan, PAO D. Collins, DRP M. Rose, DRP, OA R Barkley, ORA D. Roberts, DRS D. 8earde, DRS N. McNamara, SLO P. Wilson, DRS RidsNrrPMREGinna Resource D. Tifft, SLO

l. Trocine, RI OEDO RidsNrrDorlLpl1-1 Resource A. Klett, NRR G. Dentel, DRP RidsNrrDirslpabResoul'ce@nrc.gov N. Perry, ORP ROPreportsResource@nrc.gov SUNSI Review Complete: JRH (Reviewer'S Initials) ML102440199 DOCUMENT NAME: S:\ROP-11 Mid-Cycle Review\Branch 1\Ginna MC LTR.doc After declaring this document "An Official Agency Record" it will be released to the Public.

To recelye a copy of this document, Indicate in the box: 'C' =Copy without attachmentlenclosura "E':: Copy with attachmenVenclosure "N' No copy OFFIC RIIDRP RIIDRP NAME GDentelfGTD JCliffordfJWC DATE 08/24 110 081 30 110 OFFICIAL RECORD COpy

Page 1 of2 Ginna 08/3012010 10:14:40 Inspection 1Activity Plan Report 22 08/0112010 - 12/31/2011 Planned Dates m~~:&~iMg~':'~~:~"il411 MiimtfMflg=CiIWifl'~lnb~~"'fU'Bninl'nWI~&l.iWiiW"!!~'jt'~iil.lili!liiia~iI'ii~'IIJ~i~:

Start End ISFSI -ISFSI DRY RUN AND INITIAL LOADING 8 1 0810212010 08127/2010 IP 60854 Preoperational Testing Of An ISFSI 0810212010 08127/2010 IP 60855 Operation Of An ISFSI 711111B

  • REQUAL INSP WI P/F RESULTS 3 1 11/0812010 11/12/2010 IP 7111111B Licensed Operator Requalification Program TI179
  • 25151T1179 NSTS VERIFICATION 1 1 09120/2010 1010812010 IP 25151179 Verification of Licensee Responses to NRC Requirement fOr Inventories of Materials Tracked in NSTS 71124 - RAD SAFETY - RAD HAZZARD ASSESS/ALARA 1 0912712010 10/0112010 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 09/27/2010 10/0112010 IP 71124.02 Occupational ALARA Planning and Controls 09/2712010 10/01/2010 IP 71151 Performance Indicator Verification CDBI - COMPONENT DESIGN BASES INSPECTION 7 10/18/2010 10/2212010 IP 7111121 Component Design Bases Inspection 11/01/2010 1111212010 IP 7111121 Component Design Bases Inspection 71124.05 - RAD INSTRUMENTATION 1 01/10/2011 01114/2011 IP 71124.05 Radiation Monitoring Instrumentation 71124.01 - RAD HAZZARD ASSESS, ALARA, AIR, DOSE 1 03/2812011 04/01/2011 IP 71124.01 Radiological Hazard Assessment and Exposure COntrols 1 0312812011 04/0112011 IP 71124.02 Occupational ALARA Planning and Controls 1 03128/2011 04/0112011 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 0312812011 04101/2011 IP 71124.04 Occupational Dose Assessment 1 03128/2011 04/0112011 IP 71124.05 Radiation Monitoring Instrumentatlon TI-177 - MANAGING GAS ACCUMULATION IN ECCS 2 1 04/0412011 04/08/2011 IP 25151177 Managing Gas Accumulation In Emergency Core Cooling. Decay Heat Removal & Containment Spray System 7111108P - INSERVICE INSPECTION 1 05/09/2011 05/20/2011 IP 7111108P Inservice Inspection ActiVities PWR 71124.01 - RAD HAZARD ASSESS, ALARA, AIR, DOSE 05/09/2011 05/27/2011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 05/09/2011 05/27/2011 IP 71124.02 Occupational ALARA Planning and Controls 05/09/2011 05/27/2011 IP 71124.03 In-Plant Airbome Radioactivity ContrOl and Mitigation 05/09/2011 05/27/2011 IP 71124.04 Occupational Dose Assessment 05/09/2011 05/27/2011 IP 71124.05 Radiation MonitOring Instrumentation 71124.06 -RETS 09/1212011 09/1612011 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 0911212011 09116/2011 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment

Page 2of2 Ginna 08130/2010 10:14:40 Inspection I Activity Plan Report 22 08/01/2010 - 12131/2011 Planned Dates Start End Title 71124.06 - RETS 09/12/2011 09116/2011 IP 71151-0R01 Occupational Exposure Control Effectiveness 09/12/2011 09/16/2011 IP 71151*PR01 RETS/ODCM Radiological Effluent 7111107T - TRIENNIAL HEAT SINK 1 09/19/2011 0912312011 IP 7111107T Heat Sink Performance 7111117 - PERMANENT PLANT MODIFICATIONS 3 10/03/2011 10/07/2011 IP 7111117T Evaluations of Changes, Tests. or Experiments and Permanent Plant Modifications 10/1712011 10/2112011 IP 7111117T Evaluations of Changes. Tests. or Experiments and Permanent Plant Modifications EPEX - EP EXERCISE EVALUATION 4 10/2412011 10/2812011 IP 7111401 Exercise Evaluation 10/2412011 1012812011 lP 7111404 Emergency Action Level and Emergency Plan Changes 1 10/24/2011 10/2812011 IP 71151-EP01 DrililExercise Performance 1 10/24/2011 10/2812011 IP 71151-EP02 ERO Drill Participation 10/24/2011 10/28/2011 IP 71151-EP03 Alert & Notification System his report does not include INPO and OUTAGEactivllies.

This report shows only on,.gite and announced inspection procedures.

mr.arrm:ItU,R.i>il(~,h5.!d.HIHGtf?,(.t.""(;ar~,, ..i!'iti.,ntl. *..ttiiiIT',i'f0FIimt~:<<;,.... ;;:;! ""*IIPipphi(!'tf\3IH!bilh}f,l?lh,,,i,,.,+l;',,,i)I,;:1.,,hH>t,:'<i4>4i!-:-<k...)::u*.I."U

.---'-----~.-'--." ..-. --