September 18, 2023
David P. Rhoades
Senior Vice President
Constellation Energy Generation, LLC
President and Chief Nuclear Officer (CNO)
Constellation Nuclear
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: R.E. GINNA NUCLEAR POWER PLANT - REQUEST FOR INFORMATION
AND NOTIFICATION OF CONDUCT OF IP 71111.21.N.04, AGE -RELATED
DEGRADATION, REFERENCE INSPECTION REPORT 05000244/2023010
Dear David Rhoades:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
staff will conduct IP 71111.21N.04, Age-Related Degradation baseline inspection at the R.E.
Ginna Nuclear Power Station in November 2023. Paul Cataldo, a Senior Reactor Inspector from
the NRCs Region I office, will lead the inspection team. The team will be composed of
personnel from the NRC Region I Office. The inspection will be conducted in accordance with IP 71111.21N.04 (ADAMS Accession No. ML22210A107). The inspection will evaluate the
implementation of the programs and activities to determine on a sampling basis that age- related
degradation of structures and components (SCs) is identified and addressed.
The schedule for the inspection is as follows:
- Information gathering visit: Week of October 9, 2023
- Onsite inspection: Weeks of November 13 and November 27, 2023
The purpose of the information gathering visit is to become familiar with the station
maintenance, surveillance, testing, inspection, and condition monitoring programs, become
familiar with plant layout, support identification of SCs that will be reviewed during the
inspection, and, as necessary, obtain plant specific site access training and badging for
unescorted site access. An initial list of documents that the team will review during the
information gathering visit are listed in the attached Enclosures .
During the information gathering visit, the team leader will also discuss the following inspection
support administrative details: office space size and location; specific documents requested to
be made available to the team in their office spaces; arrangements for reactor site access and
the availability of knowledgeable plant staff and licensing organization personnel to serve as
points of contact during the inspection.
D. Rhoades 2
For SCs that the inspection will review, an initial list of the documents the team will review
during the conduct of the inspection are also listed in the Enclosure. The team leader will
contact you with identified S Cs by October 30, 2023. Also, personnel should be available at the
site during the inspection who are knowledgeable regarding maintenance, surveillance, testing,
inspection, and condition monitoring programs.
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, under Control Number
3150- 0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a
request for information or an information collection requirement unless the requesting document
displays a currently valid Office of Management and Budget control number.
In accordance with 10 Code of Federal Regulations (CFR) 2.390 of the NRC rules and
practices, a copy of this letter and its enclosures will be available electronically for public
inspection in the NRC public document room or from the publicly available records component
of NRCs document system (ADAMS). ADAMS is accessible from the NRC website
(http://www.nrc.gov/reading- rm/adams.html).
This baseline inspection and the supporting inspection procedure and documentation template
are new to the Reactor Oversight Process this year. As such, please communicate with the
team lead readily if there are questions as to document scope or suggestions to better
accomplish this process.
Sincerely,
Mel Gray, Chief
Engineering Branch 1
Division of Operating Reactor Safety
Docket No. 05000244
License No. DPR-18
Enclosure:
1. Documents requested for Information
Gathering Visit
2. Documents requested for Inspection
cc w/ encl: Distribution via LISTSERV
D. Rhoades 3
SUBJECT: R.E. GINNA NUCLEAR POWER PLANT - REQUEST FOR INFORMATION
AND NOTIFICATION OF CONDUCT OF IP 71111.21.N.04, AGE -RELATED
DEGRADATION, REFERENCE INSPECTION REPORT 05000244/2023010
DATED SEPTEMBER 18, 2023
DISTRIBUTION:
PCataldo, DORS
MGray, DORS
ECarfang, DORS
MHardgrove, DORS
TWinkel, DORS
JSchussler, DORS, SRI
CSwisher, DORS, RI
ACass, DORS, AA
JJosey, RI OEDO
RidsNrrPMREGinna Resource
RidsNrrDorlLpl1 Resource
DOCUMENT NAME: https://usnrc.sharepoint.com/teams/Region-I-
EB1/Documents/Inspections/Current/Ginna ARD/Ginna 2023 ARD Information Request
Letter.docx
ADAMS ACCESSION NUMBER: ML23258A138
x Non-Sensitive x Publvlle
SUNSI Review
x Sensitive n -Publiclyvlable
OFFICE / /
NA PC ray
D E 14/2023 14/2023
OFFIAL RERD COP
Enclosure 1: Documents Requested for Information Gathering Visit
The following information is requested by October 10, 2023, which is during the information
gathering trip. Electronic format is the preferred media. If electronic media is made available via
an internet based remote document management system, then the remote document access
must allow inspectors to download, save, and print the documents in the NRC's regional office.
Electronic media on compact disc or paper records (hard copy) are acceptable. At the end of
the inspection, the documents in the team's possession will not be retained.
This document request is based on typical documents that a generic plant might have. As such,
this document request is not meant to imply that your plant is required to have all of the listed
documents. In addition, your plant specific document titles may vary from the document titles
listed below.
Contact Information:
Team Lead: Paul Cataldo
Email: paul.cataldo@nrc.gov
Telephone: (603) 395-5536
Documents Requested:
1) A list of 50.65 (a)(1) SSCs from the past 5 years.
2) A list of maintenance rule functional failures from the past 5 years.
3) A list of the most recent system health/maintenance rule status for High Safety
Significance (HSS) and Low Safety Significance (LSS) systems, as defined in the Ginna
maintenance rule procedures/process.
4) The most recent site component obsolescence list, and associated Plant Health
Committee (PHC) package that introduced the list for the semi-annual review, and any
applicable guidance documents regarding the control of, and additions to, this list.
5) The most recent evaluation of maintenance effectiveness required per 10 CFR
50.65(a)(3).
6) The maintenance rule scoping document SSCs and performance criteria.
7) List of corrective action documents associated with component failures, applicable
corrective action program trend codes , or keyword search of aging, age- related,
wear, accelerated wear, corrosion, abnormal wear, accelerated degradation, and
abnormal degradation from the past 5 years. Please include a short description of the
issue in the system generated listing.
8) A list of Part 21 Reports applicable to the site from the past 5 years.
9) A list of top 100 most risk-significant structures and components. If possible, designate
the component as active or passive in the risk ranking.
Enclosure 1
Enclosure 1: Documents Requested for Information Gathering Visit
10) The site- specific probabilistic risk assessment (PRA) identifying risk-significant functions
and SSCs, and if possible, the re-baselined PRA Summary Document from 2023.
11) Scoping and basis document for 10 CFR 50.49, Environmental Qualification.
12) Aging management programs and basis documents.
13) Technical requirements manual.
14) List of systems (system numbers / designators and corresponding names).
15) List of PM deferrals and PM change requests in the last 5 years.
Enclosure 2: Documents Requested for Inspection
The following information will be requested to be available by October 30, 2023. The team lead
will identify specific samples (i.e., SCs ) after the information gathering visit. This information
represents a partial list of needed information for the onsite team inspection. The information
should be separated for each selected SC .
Documents Requested:
1) List of corrective action documents associated with each selected SC for the last 5
years.
2) Maintenance, surveillance, testing, inspection, and condition monitoring testing
requirements, acceptance criteria, and periodicities for the selected SC samples.
3) The bases documents associated with maintenance, surveillance, testing, inspection,
condition monitoring testing requirements, acceptance criteria, and periodicities.
4) The last two years of maintenance, surveillance, testing, inspection, and condition
monitoring testing results for the selected SC samples. For periodicities greater than two
years, provide the last two test results.
5) Self-imposed and vendor recommendations.
6) A list of technical specification operability determinations associated with applicable SCs
from the past 5 years as defined in Ginna implementing procedures.
Enclosure 2