September 3, 2013
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
R.E. GINNA NUCLEAR POWER PLANT (REPORT 05000244/2013006)
Dear Mr. Pacher:
On August 15, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of the R.E. Ginna Nuclear Power Plant (Ginna). The NRC reviewed the most recent quarterly performance indicators in addition to inspection results and enforcement actions from July 1, 2012, through June 30, 2013. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Ginna operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Ginna during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low safety significance (Green), and all performance indicators demonstrated that your performance was within the nominal, expected range (Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2014.
Routine inspections performed by resident inspectors are not included in the inspection plan.
In addition to baseline inspections, the NRC will perform Inspection Procedure 60855.1, Operation of an Independent Spent Fuel Storage Installation at Operating Plants, and Temporary Instruction 2515/182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks-Phase II. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In accordance with Title 10 of the Code of Federal Regulations Section 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (610) 337-5262 with any questions you have regarding this letter.
Sincerely,
/RA/
Daniel L. Schroeder, Chief Projects Branch 1 Division of Reactor Projects
Docket No:
50-244 License No:
Enclosure:
Ginna Inspection/Activity Plan
cc w/encl:
Distribution via ListServ
ML13240A154 SUNSI Review
Non-Sensitive Sensitive
Publicly Available
Non-Publicly Available OFFICE klm RI/DRP RI/DRP RI/DRP
NAME NPerry/NSP per telephone ARosebrook/AAR DSchroeder/DLS
DATE 8/27/13 8/26/13 9/3/13
Page 1 of 2 08/02/2013 13:18:06 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Ginna Inspection / Activity Plan 07/01/2013 - 12/31/2014 71124
- RADIATION SAFETY INSPECTION
1 IP Radiological Environmental Monitoring Program 71124.07 07/15/2013 07/19/2013 7111121
- CDBI
1 IP Component Design Bases Inspection 7111121 07/22/2013 07/26/2013
IP Component Design Bases Inspection 7111121 08/05/2013 08/09/2013
IP Component Design Bases Inspection 7111121 08/19/2013 08/23/2013 EP EX
- EP EXERCISE EVALUATION
1 IP Exercise Evaluation - Hostile Action (HA) Event 7111407 09/16/2013 09/20/2013
IP Exercise Evaluation - Scenario Review 7111408 09/16/2013 09/20/2013 71124
- RADIATION SAFETY INSPECTION
1 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 12/09/2013 12/13/2013
IP Radiological Environmental Monitoring Program 71124.07 12/09/2013 12/13/2013
IP Occupational Exposure Control Effectiveness 71151-OR01 12/09/2013 12/13/2013 71152B
- PI&R BIENNIAL
1 IP Problem Identification and Resolution 71152B 02/24/2014 03/01/2014
IP Problem Identification and Resolution 71152B 03/10/2014 03/15/2014 TI 182
- DEGRAD UNDERGROUND PIPING - PHASE 2
1 IP Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 2515/182 02/10/2014 02/14/2014 71124
- RADIATION SAFETY INSPECTION
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/03/2014 03/07/2014
IP Occupational ALARA Planning and Controls 71124.02 03/03/2014 03/07/2014 71124.08
- RADWASTE
1 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 03/31/2014 04/04/2014 ISFSI
- ISFSI ROUTINE INSPECTION
1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 04/07/2014 04/11/2014 7111108P
- INSERVICE INSPECTION
1 IP Inservice Inspection Activities - PWR 7111108P 05/05/2014 05/16/2014 HP
- HP OUTAGE INSPECTIONS
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 05/12/2014 05/16/2014
IP Occupational ALARA Planning and Controls 71124.02 05/12/2014 05/16/2014
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 05/12/2014 05/16/2014
IP Occupational Dose Assessment 71124.04 05/12/2014 05/16/2014 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Page 2 of 2 08/02/2013 13:18:06 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Ginna Inspection / Activity Plan 07/01/2013 - 12/31/2014 71124
- RADIATION SAFETY INSPECTION
1 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 06/02/2014 06/06/2014
IP Occupational Dose Assessment 71124.04 06/02/2014 06/06/2014 7111107T
- TRIENNIAL HEAT SINK
1 IP Heat Sink Performance 7111107T 06/23/2014 06/27/2014 12/1EXAM
- GINNA INITIAL EXAM
1 FY15-GINNA INITIAL OPERATOR LICENSING EXAM U01900 11/03/2014 11/07/2014
FY15-GINNA INITIAL OPERATOR LICENSING EXAM U01900 12/01/2014 12/12/2014 EP PROG
- EP PROGRAM INSPECTION
1 IP Alert and Notification System Testing 7111402 08/04/2014 08/08/2014
IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 08/04/2014 08/08/2014
IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 08/04/2014 08/08/2014 MODS
- PERMANENT PLANT MODIFICATIONS
1 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111117T 08/04/2014 08/08/2014
IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111117T 08/18/2014 08/22/2014 71124
- RADIATION SAFETY INSPECTION
1 IP Radiation Monitoring Instrumentation 71124.05 08/25/2014 08/29/2014 7111111B
- GINNA REQUAL INSPECTION WITH P/F RESULTS
1 IP Licensed Operator Requalification Program 7111111B 11/17/2014 11/21/2014 71124
- RADIATION SAFETY INSPECTION
1 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 11/03/2014 11/07/2014
IP Occupational Exposure Control Effectiveness 71151-OR01 11/03/2014 11/07/2014 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.