Similar Documents at Ginna |
---|
Category:Inspection Plan
MONTHYEARIR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) IR 05000244/20220052022-08-31031 August 2022 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2022005) IR 05000244/20210062022-03-0202 March 2022 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2021006) IR 05000244/20210052021-09-0101 September 2021 Updated Inspection Plan for the R.E. Ginna Nuclear Power Plant, Llc (Report 05000244/2021005 ML21119A1082021-04-27027 April 2021 Ti 2515/194 Inspection Documentation Request IR 05000244/20200062021-03-0303 March 2021 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2020006) ML21011A0872021-01-11011 January 2021 LLC: Notification of Conduct of a Fire Protection Team Inspection IR 05000244/20200052020-08-31031 August 2020 Updated Inspection Plan for the R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2020005) IR 05000244/20190062020-03-0303 March 2020 Annual Assessment Letter for the R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2019006) IR 05000244/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 0500244/2019005) IR 05000244/20180062019-03-0404 March 2019 Annual Assessment Letter for the R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2018006) IR 05000244/20180052018-08-28028 August 2018 R. E. Ginna Nuclear Power Plant LLC Updated Inspection Plan: Inspection Report 05000244/2018005 IR 05000244/20170062018-02-28028 February 2018 Annual Assessment Letter for R. E. Ginna Nuclear Power Plant, LLC (Reports 05000244/2017006, 05000244/2017402, and 05000244/2017501) IR 05000244/20170052017-08-28028 August 2017 Updated Inspection Plan for R. E. Ginna Nuclear Power Plant - Inspection Report 05000244/2017005 IR 05000244/20160062017-03-0101 March 2017 Annual Assessment Letter for the R.E. Ginna Nuclear Power Plant (Report 05000244/2016006) IR 05000244/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for R.E. Ginna Nuclear Power Plant, (Report 0500244/2016005) IR 05000244/20150062016-03-0202 March 2016 2015 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant (Report 05000244/2015006) IR 05000244/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for R.E. Ginna Nuclear Power Plant (Report 05000244/2015005) ML15170A3942015-06-17017 June 2015 Document Request for Appendix R Licensing Basis (Updated and Modified Request List of Documents from the Inspection Plan) ML15147A0042015-05-26026 May 2015 LLC - Notification of Conduct of a Triennial Fire Protection Baseline Inspection and Request for Information (9-2015) IR 05000244/20140012015-03-0404 March 2015 2014 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant (Report 05000244/2014001)(w/Inspection Plan) IR 05000244/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter and Inspection Plan 2014 (ROP-15) - R.E. Ginna Nuclear Power Plant (Report 05000244-14-006) IR 05000244/20130012014-03-0404 March 2014 2013 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant (Report 05000244/2013001)(w/Inspection Plan) IR 05000244/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan 2013 (ROP-14) - R.E. Ginna Nuclear Power Plant (Report 05000244-13-006) IR 05000244/20120012013-03-0404 March 2013 Annual Assessment Letter for the R.E. Ginna Nuclear Power Plant (Report 05000244/2012001) ML12244A3322012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - 2013 Ginna Nuclear Power Plant IR 05000244/20110012012-03-0505 March 2012 Annual Assessment Letter (Report 05000244-11-001) ML1124207882011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - R. E. Ginna Nuclear Power Plant IR 05000244/20100012011-03-0404 March 2011 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant (Report 05000244/2010001) ML1024401992010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - R.E. Ginna Nuclear Power Plant ML1016600092010-06-15015 June 2010 Pre-Inspection Cover Sheet and Inspection Plan (6/21-6/25/10) ML1006208332010-03-0303 March 2010 Annual Assessment Letter (Report 05000244-10-001) ML0924402302009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - R.E. Ginna Nuclear Power Plant, Dated 09/01/09 IR 05000244/20090012009-03-0404 March 2009 IR 05000244-09-001, Ginna Nuclear Power Plant Annual Assessment Letter, Dated 03/04/09 IR 05000244/20080012008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan, R.E. Ginna, (IR 05000244-08-001) ML0806100142008-03-0303 March 2008 Annual Assessment Letter EOC 2007 ROP8 - Ginna Station (05000244/2008001) ML0734709602007-12-13013 December 2007 ROP8 - Ginna - Change to Inspection Plan, 12/13/07 ML0724309382007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - R.E. Ginna ML0706106172007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Ginna Station (05-244/2007001) ML0624304962006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan - R. E. Ginna Nuclear Power Plant ML0606203182006-03-0202 March 2006 2006-001 - Annual Assessment Letter - R. E. Ginna Nuclear Power Plant (Report 05-244/2006001) ML0524206822005-08-30030 August 2005 Mid-Cycle Performance Review and Inspection Plan - R. E. Ginna Nuclear Power Plant IR 05000244/20050012005-03-0202 March 2005 Annual Assessment Letter - R.E. Ginna Nuclear Power Plant (Report 05000244/2005001) ML0424408312004-08-30030 August 2004 2004 Ginna Mid-Cycle Performance Review and Inspection Plan ML0406301752004-03-0202 March 2004 2003-04 Annual Assessment Letter - Ginna ML0306200212003-03-0303 March 2003 2003 Annual Assessment Letter - R.E. Ginna Nuclear Power Plant ML0223802522002-08-26026 August 2002 2002 Ginna Mid-Cycle Performance Review and Inspection Plan IR 05000244/20020012002-03-0101 March 2002 2002 Annual Assessment Letter - R. E. Ginna (Report 50-244/02-01) 2023-08-31
[Table view] Category:Letter
MONTHYEARIR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of B Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23258A1382023-09-18018 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000244/2023010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23235A1722023-08-23023 August 2023 Re. Ginna Nuclear Power Plant, Transmittal of 2023 Owner'S Activity Report IR 05000244/20234012023-08-15015 August 2023 LLC - Material Control and Accounting Program Inspection Report 05000244/2023401 (Cover Letter Only) IR 05000244/20230022023-08-0303 August 2023 LLC - Integrated Inspection Report 05000244/2023002 ML23191A0592023-07-21021 July 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 155 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 IR 05000244/20234022023-07-19019 July 2023 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2023402 (Cover Letter Only) RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-050, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube.2023-05-22022 May 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube. ML23135A0412023-05-15015 May 2023 2022 Annual Radioactive Effluent Release Report and 2022 Annual Radiological Environmental Operating Report ML23121A0482023-05-0101 May 2023 R. E. Ginna Nuclear Power Plant Core Operating Limits Report Cycle 44, Revision 0 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI IR 05000244/20230012023-04-26026 April 2023 LLC - Integrated Inspection Report 05000244/2023001 ML23100A0302023-04-10010 April 2023 2023 10 CFR 50.46 Annual Report ML23114A1152023-03-29029 March 2023 Electronic Reporting of Exposure Data for 2022 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23075A0872023-03-15015 March 2023 R. E. Ginna Nuclear Power Plant - Project Manager Assignment ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) ML22364A0242023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant Issuance of Amendments Nos. 231, 231, 232, 232, and 154 Regarding Adoption of TSTF-246 ML23060A1622023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 ML23005A1762023-02-23023 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 153 Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes ML23005A1222023-02-22022 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No 152 Adopt TSTF-315-Revise Technical Specification 3.1.8, Physics Tests Exceptions - Mode 2 RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators ML22287A0692023-02-0808 February 2023 R. E. Ginna Station - Forward Fit Analysis (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and 0094) ML23031A2992023-02-0707 February 2023 R. E. Ginna Nuclear Power Plant - Withdrawal of an Amendment Request ML23010A0112023-02-0101 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Inservice Testing of Refueling Water Storage Tank Outlet Value RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000244/20223012023-01-20020 January 2023 Initial Operator Licensing Examination Report 05000244/2022301 IR 05000244/20220122023-01-12012 January 2023 LLC - Design Basis Assurance Inspection (Teams) Inspection Report 05000244/2022012 ML22362A0382022-12-28028 December 2022 R. E. Ginna Nuclear Power Plant - Letter to Withdraw Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML22348A2062022-12-14014 December 2022 Re. Ginna Nuclear Power Plant - Annual Commitment Change Notification RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator 2024-02-05
[Table view] |
Inspection Report - Ginna - 2018006 |
---|
|
|
Text
rch 4, 2019
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR THE R.E. GINNA NUCLEAR POWER PLANT, LLC (REPORT 05000244/2018006)
Dear Mr. Hanson,
The NRC has completed its end-of-cycle performance assessment of your R.E. Ginna Nuclear Power Plant, LLC (Ginna), reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2018, through December 31, 2018. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.
The NRC determined the performance at Ginna during the most recent quarter was within the Licensee Response Column (Column 1) of the NRCs Reactor Oversight Process (ROP) Action Matrix in Inspection Manual Chapter 0305, Operating Reactor Assessment Program, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at Ginna.
The enclosed inspection plan lists the inspections scheduled through December 31, 2020. This updated inspection plan now includes planned security inspections which were formerly transmitted under separate correspondence. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections). Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020. Furthermore, all the inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In addition to normal baseline inspections, the NRC will be performing Inspection Procedure (IP)
71003, Post-Approval Site Inspection for License Renewal, and IP 60855.1, Operation of an Independent Spent Fuel Storage Installation at Operating Plants, at your facility. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRCs Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 610-337-5120 with any questions you have regarding this letter.
Sincerely,
/RA/
Erin Carfang, Chief Projects Branch 1 Division of Reactor Projects Docket No. 50-244 License No. DPR-18 Enclosure:
R.E. Ginna Inspection Plan
ML19064B333 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME ARosebrook per email ECarfang DATE 2/22/19 2/26/19
IP 22 Inspection Activity Plan Report Ginna 01/01/2019 - 12/31/2020 Unit Start End Activity CAC Title Staff Count GINNA LICENSE RENEWAL PHASE 4 3 1 03/18/2019 03/22/2019 IP 71003 000687 Post-Approval Site Inspection for License Renewal RADIATION SAFETY - RAD HAZ 1 1 03/25/2019 03/29/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls RADIATION SAFETY - INSTRUMENTS 1 1 05/13/2019 05/17/2019 IP 71124.05 000729 Radiation Monitoring Instrumentation DBAI - Teams 6 1 06/10/2019 06/14/2019 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
1 06/24/2019 06/28/2019 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
RADIATION SAFETY - REMP 1 1 07/08/2019 07/12/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program FORCE-ON-FORCE PLANNING AND EXERCISES 8 1 08/05/2019 08/09/2019 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1 08/26/2019 08/30/2019 IP 71130.03 000735 Contingency Response - Force-On-Force Testing EP EXERCISE INSPECTION 5 1 08/19/2019 08/23/2019 IP 71114.01 000716 Exercise Evaluation 1 08/19/2019 08/23/2019 IP 71151 001397 Performance Indicator Verification ISFSI OPERATIONAL INSPECTION 1 1 09/30/2019 10/04/2019 IP 60855.1 000590 Operation of an Independent Spent Fuel Storage Installation at Operating Plants Radiation Safety - RETS & PIV 1 1 09/30/2019 10/04/2019 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1 09/30/2019 10/04/2019 IP 71151 000746 Performance Indicator Verification ACCESS AUTH & CONTROL, FITNESS FOR DUTY 3 1 10/21/2019 10/25/2019 IP 71130.01 000733 Access Authorization 1 10/21/2019 10/25/2019 IP 71130.02 000734 Access Control 1 10/21/2019 10/25/2019 IP 71130.06 000738 Protection of Safeguards Information 1 10/21/2019 10/25/2019 IP 71130.08 000740 Fitness For Duty Program 1 10/21/2019 10/25/2019 IP 71151 001338 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures.
1/14/2019 1:31:40 PM
IP 22 Inspection Activity Plan Report Ginna 01/01/2019 - 12/31/2020 Unit Start End Activity CAC Title Staff Count PI&R Biennial Team Inspection 4 1 02/10/2020 02/14/2020 IP 71152B 000747 Problem Identification and Resolution 1 02/24/2020 02/28/2020 IP 71152B 000747 Problem Identification and Resolution Radwaste 1 1 04/06/2020 04/10/2020 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation Radiation Safety - Rad Haz 1 1 04/13/2020 04/17/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1 04/13/2020 04/17/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 1 04/13/2020 04/17/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation ISI - UNIT 1 1 1 04/19/2020 05/02/2020 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
Radiation Safety - ALARA 1 1 06/01/2020 06/05/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls MATERIAL CONTROL AND ACCOUNTABILITY 1 1 07/13/2020 07/17/2020 IP 71130.11 000742 Material Control and Accounting (MC&A)
Access Control, Protective Strategy, TSR 4 1 07/20/2020 07/24/2020 IP 71130.02 000734 Access Control 1 07/20/2020 07/24/2020 IP 71130.05 000737 Protective Strategy Evaluation 1 07/20/2020 07/24/2020 IP 71130.14 000743 Review of Power Reactor Target Sets 1 07/20/2020 07/24/2020 IP 71151 001338 Performance Indicator Verification GINNA EP PROGRAM INSPECTION 1 1 07/27/2020 07/31/2020 IP 71114.02 000717 Alert and Notification System Testing 1 07/27/2020 07/31/2020 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1 07/27/2020 07/31/2020 IP 71114.05 000720 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 07/27/2020 07/31/2020 IP 71151 001397 Performance Indicator Verification TRIENNIAL HEAT SINK 1 1 08/03/2020 08/07/2020 IP 71111.07T 000700 Heat Sink Performance -Triennial This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.
1/14/2019 1:31:40 PM
IP 22 Inspection Activity Plan Report Ginna 01/01/2019 - 12/31/2020 Unit Start End Activity CAC Title Staff Count Radiation Safety - Airborne 1 1 08/17/2020 08/21/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 50.59 INSPECTION 3 1 09/14/2020 09/18/2020 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments FY2020 GINNA INITIAL OL EXAM 5 1 09/14/2020 09/18/2020 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1 10/12/2020 10/23/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
Radiation Safety - Dose & PIV 1 1 10/19/2020 10/23/2020 IP 71124.04 000729 Occupational Dose Assessment 1 10/19/2020 10/23/2020 IP 71151 000746 Performance Indicator Verification PROGRAM INSPECTION 3 1 11/02/2020 11/06/2020 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)
1 11/16/2020 11/20/2020 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)
Ginna Requal Inspection with P/F Results 2 1 12/14/2020 12/18/2020 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance (Annual)
1 12/14/2020 12/18/2020 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance (Biennial)
This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.
1/14/2019 1:31:40 PM