UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 March 2, 2006 Ms. Mary G. Korsnick Vice President R. E. Ginna Nuclear Power Plant R. E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519
SUBJECT:
ANNUAL ASSESSMENT LETTER - R. E. GINNA NUCLEAR POWER PLANT (REPORT 05000244/2006001)
Dear Ms. Korsnick:
On February 8, 2006, the NRC staff completed its performance review of R. E. Ginna Nuclear Power Plant. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2005. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Official Use Only - Security-Related Information will include the physical protection review and resultant inspection plan.
Overall, Ginna operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through September 30, 2007. Planned inspections include power uprate. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
M. Korsnick 2
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact Brian McDermott at 610-337-5233 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
James M. Trapp, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket No. 50-244 License Nos. DPR-18
Enclosure:
R. E. Ginna Inspection/ Activity Plan cc w/encl:
M. J. Wallace, President, Constellation Generation J. M. Heffley, Senior Vice President and Chief Nuclear Officer P. Eddy, Electric Division, NYS Department of Public Service C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law C. W. Fleming, Esquire, Senior Counsel, Constellation Energy Group, Inc.
P. R. Smith, New York State Energy Research and Development Authority J. Spath, SLO Designee New York State Energy Research and Development Authority T. Wideman, Director, Wayne County Emergency Management Office M. Meisenzahl, Administrator, Monroe County, Office of Emergency Preparedness T. Judson, Central New York Citizens Awareness Network
M. Korsnick 3
Distribution w/encl:
(via E-mail)
S. Collins, RA M. Dapas, DRA B. Holian, DRP A. Blough, DRS D. Lew, DRP M. Gamberoni, DRS B. Sosa, RI OEDO R. Laufer, NRR P. Milano, PM, NRR J. Boska, (Backup PM), NRR J. Trapp, DRP B. McDermott, DRP C. Khan, DRP K. Kolaczyk, DRP, Senior Resident Inspector M. Marshfield, DRP, Resident Inspector S. DiMora, DRP, Resident OA D. Screnci, ORA N. Sheehan, ORA DRS Branch Chiefs Institute of Nuclear Power Operations (INPO)
RidsNrrDirsIpab@nrc.gov ROPreports@nrc.gov (All IRs)
Region I Docket Room (with concurrences)
DOCUMENT NAME: S:\\ROP-6 EOC Review\\ROP-6 Annual Assessment Letters\\GIN EOC.wpd SISP Review Complete: JMT (Reviewers Initials)
After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP RI/DRP NAME KKolaczyk/JMT for CKhan/JMT for JTrapp/JMT DATE 02/28/06 02/28/06 02/28/06 OFFICIAL RECORD COPY
Ginna Inspection / Activity Plan 03/01/2006 - 09/30/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 3 03/02/2006 16:17:15 Report 22 1
71121
- OCC RADIATION SAFETY Baseline Inspections 03/20/2006 03/24/2006 1
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 03/20/2006 03/24/2006 1
7112102 IP ALARA Planning and Controls Baseline Inspections 03/20/2006 03/24/2006 1
7112103 IP Radiation Monitoring Instrumentation and Protective Equipment Baseline Inspections 03/20/2006 03/24/2006 1
71151 IP Performance Indicator Verification 1
71114
- EP PRGM INSP & PI VERIFICATION Baseline Inspections 04/03/2006 04/07/2006 1
7111402 IP Alert and Notification System Testing Baseline Inspections 04/03/2006 04/07/2006 1
7111403 IP Emergency Response Organization Augmentation Testing Baseline Inspections 04/03/2006 04/07/2006 1
7111404 IP Emergency Action Level and Emergency Plan Changes Baseline Inspections 04/03/2006 04/07/2006 1
7111405 IP Correction of Emergency Preparedness Weaknesses and Deficiencies Baseline Inspections 04/03/2006 04/07/2006 1
71151 IP Performance Indicator Verification 1
7112203
- PUB RAD SAFETY - REMP Baseline Inspections 05/08/2006 05/12/2006 1
7112203 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P Baseline Inspections 05/08/2006 05/12/2006 1
71151 IP Performance Indicator Verification 4
TRI FIRE
- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 06/05/2006 06/09/2006 1
7111105T IP Fire Protection [Triennial]
Baseline Inspections 06/19/2006 06/23/2006 1
7111105T IP Fire Protection [Triennial]
3 7/17 EXM
- OPERATOR LICENSING INITIAL EXAMS Not Applicable 06/26/2006 06/30/2006 1
U01658 FY06 - GINNA INITIAL OPERATOR EXAM Not Applicable 07/17/2006 07/21/2006 1
U01658 FY06 - GINNA INITIAL OPERATOR EXAM 2
7111107B
- HEAT SINK Baseline Inspections 07/24/2006 07/28/2006 1
7111107B IP Heat Sink Performance 4
- PI&R Baseline Inspections 08/14/2006 08/18/2006 1
71152B IP Identification and Resolution of Problems Baseline Inspections 08/28/2006 09/01/2006 1
71152B IP Identification and Resolution of Problems 2
MODS
- MODS AND 50.59 Baseline Inspections 08/07/2006 08/11/2006 1
7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 08/07/2006 08/11/2006 1
7111117B IP Permanent Plant Modifications 3
71004
- POWER UPRATE Other Routine 09/01/2006 09/30/2006 1
71004 IP Power Uprate 3
71004
- POWER UPRATE Other Routine 10/01/2006 12/31/2006 1
71004 IP Power Uprate 1
7111108P
- INSERVICE INSPECTION Baseline Inspections 10/10/2006 10/13/2006 1
7111108P IP Inservice Inspection Activities - PWR Baseline Inspections 10/16/2006 10/20/2006 1
7111108P IP Inservice Inspection Activities - PWR This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Ginna Inspection / Activity Plan 03/01/2006 - 09/30/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 3 03/02/2006 16:17:15 Report 22 1
71121
- OCC RAD SAFETY Baseline Inspections 10/16/2006 10/20/2006 1
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 10/16/2006 10/20/2006 1
7112102 IP ALARA Planning and Controls Baseline Inspections 10/16/2006 10/20/2006 1
7112103 IP Radiation Monitoring Instrumentation and Protective Equipment Baseline Inspections 10/16/2006 10/20/2006 1
71151 IP Performance Indicator Verification 1
7112202
- PUB RAD SAFETY - RADWASTE Baseline Inspections 10/30/2006 11/03/2006 1
7112202 IP Radioactive Material Processing and Transportation Baseline Inspections 10/30/2006 11/03/2006 1
71151 IP Performance Indicator Verification 1
71121
- OCC RAD SAFETY Baseline Inspections 11/27/2006 12/01/2006 1
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 11/27/2006 12/01/2006 1
7112102 IP ALARA Planning and Controls Baseline Inspections 11/27/2006 12/01/2006 1
7112103 IP Radiation Monitoring Instrumentation and Protective Equipment Baseline Inspections 11/27/2006 12/01/2006 1
71151 IP Performance Indicator Verification 4
7111111B
- LO REQUAL. PROG. + P/F REVIEW Baseline Inspections 01/22/2007 01/26/2007 1
7111111B IP Licensed Operator Requalification Program Baseline Inspections 01/29/2007 02/02/2007 1
7111111B IP Licensed Operator Requalification Program 1
71121
- OCC RAD PROT Baseline Inspections 03/19/2007 03/23/2007 1
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 03/19/2007 03/23/2007 1
7112102 IP ALARA Planning and Controls Baseline Inspections 03/19/2007 03/23/2007 1
7112103 IP Radiation Monitoring Instrumentation and Protective Equipment Baseline Inspections 03/19/2007 03/23/2007 1
71151 IP Performance Indicator Verification 1
7112201
- PUB RAD SAFETY - RETS Baseline Inspections 05/07/2007 05/11/2007 1
7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems Baseline Inspections 05/07/2007 05/11/2007 1
71151 IP Performance Indicator Verification 4
7111401
- EP EXERCISE & PI VERIFICATION Baseline Inspections 05/21/2007 05/25/2007 1
7111401 IP Exercise Evaluation Baseline Inspections 05/21/2007 05/25/2007 1
71151-EP01 IP Drill/Exercise Performance Baseline Inspections 05/21/2007 05/25/2007 1
71151-EP02 IP ERO Drill Participation Baseline Inspections 05/21/2007 05/25/2007 1
71151-EP03 IP Alert & Notification System 1
71121
- OCC RAD SAFETY Baseline Inspections 07/09/2007 07/13/2007 1
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 07/09/2007 07/13/2007 1
7112102 IP ALARA Planning and Controls Baseline Inspections 07/09/2007 07/13/2007 1
7112103 IP Radiation Monitoring Instrumentation and Protective Equipment Baseline Inspections 07/09/2007 07/13/2007 1
71151 IP Performance Indicator Verification This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Ginna Inspection / Activity Plan 03/01/2006 - 09/30/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 3 of 3 03/02/2006 16:17:15 Report 22 7
7111121
- CDBI Baseline Inspections 08/13/2007 08/17/2007 1
7111121 IP Component Design Bases Inspection Baseline Inspections 08/27/2007 08/31/2007 1
7111121 IP Component Design Bases Inspection Baseline Inspections 09/10/2007 09/14/2007 1
7111121 IP Component Design Bases Inspection Baseline Inspections 09/17/2007 09/21/2007 1
7111121 IP Component Design Bases Inspection This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.