Similar Documents at Ginna |
---|
Category:Inspection Plan
MONTHYEARIR 05000244/20240052024-08-29029 August 2024 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2024005) ML24134A0042024-05-13013 May 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000244/2024010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) IR 05000244/20220052022-08-31031 August 2022 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2022005) IR 05000244/20210062022-03-0202 March 2022 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2021006) IR 05000244/20210052021-09-0101 September 2021 Updated Inspection Plan for the R.E. Ginna Nuclear Power Plant, Llc (Report 05000244/2021005 ML21119A1082021-04-27027 April 2021 Ti 2515/194 Inspection Documentation Request IR 05000244/20200062021-03-0303 March 2021 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2020006) ML21011A0872021-01-11011 January 2021 LLC: Notification of Conduct of a Fire Protection Team Inspection IR 05000244/20200052020-08-31031 August 2020 Updated Inspection Plan for the R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2020005) IR 05000244/20190062020-03-0303 March 2020 Annual Assessment Letter for the R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2019006) IR 05000244/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 0500244/2019005) IR 05000244/20180062019-03-0404 March 2019 Annual Assessment Letter for the R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2018006) IR 05000244/20180052018-08-28028 August 2018 R. E. Ginna Nuclear Power Plant LLC Updated Inspection Plan: Inspection Report 05000244/2018005 IR 05000244/20170062018-02-28028 February 2018 Annual Assessment Letter for R. E. Ginna Nuclear Power Plant, LLC (Reports 05000244/2017006, 05000244/2017402, and 05000244/2017501) IR 05000244/20170052017-08-28028 August 2017 Updated Inspection Plan for R. E. Ginna Nuclear Power Plant - Inspection Report 05000244/2017005 IR 05000244/20160062017-03-0101 March 2017 Annual Assessment Letter for the R.E. Ginna Nuclear Power Plant (Report 05000244/2016006) IR 05000244/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for R.E. Ginna Nuclear Power Plant, (Report 0500244/2016005) IR 05000244/20150062016-03-0202 March 2016 2015 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant (Report 05000244/2015006) IR 05000244/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for R.E. Ginna Nuclear Power Plant (Report 05000244/2015005) ML15170A3942015-06-17017 June 2015 Document Request for Appendix R Licensing Basis (Updated and Modified Request List of Documents from the Inspection Plan) ML15147A0042015-05-26026 May 2015 LLC - Notification of Conduct of a Triennial Fire Protection Baseline Inspection and Request for Information (9-2015) IR 05000244/20140012015-03-0404 March 2015 2014 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant (Report 05000244/2014001)(w/Inspection Plan) IR 05000244/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter and Inspection Plan 2014 (ROP-15) - R.E. Ginna Nuclear Power Plant (Report 05000244-14-006) IR 05000244/20130012014-03-0404 March 2014 2013 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant (Report 05000244/2013001)(w/Inspection Plan) IR 05000244/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan 2013 (ROP-14) - R.E. Ginna Nuclear Power Plant (Report 05000244-13-006) IR 05000244/20120012013-03-0404 March 2013 Annual Assessment Letter for the R.E. Ginna Nuclear Power Plant (Report 05000244/2012001) ML12244A3322012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - 2013 Ginna Nuclear Power Plant IR 05000244/20110012012-03-0505 March 2012 Annual Assessment Letter (Report 05000244-11-001) ML1124207882011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - R. E. Ginna Nuclear Power Plant IR 05000244/20100012011-03-0404 March 2011 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant (Report 05000244/2010001) ML1024401992010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - R.E. Ginna Nuclear Power Plant ML1016600092010-06-15015 June 2010 Pre-Inspection Cover Sheet and Inspection Plan (6/21-6/25/10) ML1006208332010-03-0303 March 2010 Annual Assessment Letter (Report 05000244-10-001) ML0924402302009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - R.E. Ginna Nuclear Power Plant, Dated 09/01/09 IR 05000244/20090012009-03-0404 March 2009 IR 05000244-09-001, Ginna Nuclear Power Plant Annual Assessment Letter, Dated 03/04/09 IR 05000244/20080012008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan, R.E. Ginna, (IR 05000244-08-001) ML0806100142008-03-0303 March 2008 Annual Assessment Letter EOC 2007 ROP8 - Ginna Station (05000244/2008001) ML0734709602007-12-13013 December 2007 ROP8 - Ginna - Change to Inspection Plan, 12/13/07 ML0724309382007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - R.E. Ginna ML0706106172007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Ginna Station (05-244/2007001) ML0624304962006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan - R. E. Ginna Nuclear Power Plant ML0606203182006-03-0202 March 2006 2006-001 - Annual Assessment Letter - R. E. Ginna Nuclear Power Plant (Report 05-244/2006001) ML0524206822005-08-30030 August 2005 Mid-Cycle Performance Review and Inspection Plan - R. E. Ginna Nuclear Power Plant IR 05000244/20050012005-03-0202 March 2005 Annual Assessment Letter - R.E. Ginna Nuclear Power Plant (Report 05000244/2005001) ML0424408312004-08-30030 August 2004 2004 Ginna Mid-Cycle Performance Review and Inspection Plan ML0406301752004-03-0202 March 2004 2003-04 Annual Assessment Letter - Ginna ML0306200212003-03-0303 March 2003 2003 Annual Assessment Letter - R.E. Ginna Nuclear Power Plant ML0223802522002-08-26026 August 2002 2002 Ginna Mid-Cycle Performance Review and Inspection Plan 2024-08-29
[Table view] Category:Inspection Report
MONTHYEARIR 05000244/20243012024-10-22022 October 2024 Initial Operator Licensing Examination Report 05000244/2024301 IR 05000244/20245012024-09-24024 September 2024 LLC - Emergency Preparedness Biennial Exercise Inspection Report 05000244/2024501 IR 05000244/20240052024-08-29029 August 2024 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2024005) IR 05000244/20240102024-08-19019 August 2024 Biennial Problem Identification and Resolution Inspection Report 05000244/2024010 IR 05000244/20240022024-08-0505 August 2024 LLC - Integrated Inspection Report 05000244/2024002 and Independent Spent Fuel Storage Installation Report 07200067/2024001 IR 05000244/20244022024-06-20020 June 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000244/2024402 IR 05000244/20240012024-04-24024 April 2024 LLC - Integrated Inspection Report 05000244/2024001 IR 05000244/20240112024-04-10010 April 2024 LLC - Fire Protection Team Inspection Report 05000244/2024011 IR 05000244/20230062024-02-28028 February 2024 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC, (Report 05000244/2023006) IR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) IR 05000244/20234012023-08-15015 August 2023 LLC - Material Control and Accounting Program Inspection Report 05000244/2023401 (Cover Letter Only) IR 05000244/20230022023-08-0303 August 2023 LLC - Integrated Inspection Report 05000244/2023002 IR 05000244/20234022023-07-19019 July 2023 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2023402 (Cover Letter Only) IR 05000244/20230012023-04-26026 April 2023 LLC - Integrated Inspection Report 05000244/2023001 IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) IR 05000244/20220042023-01-31031 January 2023 LLC - Integrated Inspection Report 05000244/2022004 IR 05000244/20223012023-01-20020 January 2023 Initial Operator Licensing Examination Report 05000244/2022301 IR 05000244/20220122023-01-12012 January 2023 LLC - Design Basis Assurance Inspection (Teams) Inspection Report 05000244/2022012 IR 05000244/20224202022-11-22022 November 2022 Security Baseline Inspection Report 05000244-2022420 Cover Letter IR 05000244/20220032022-11-0303 November 2022 LLC - Integrated Inspection Report 05000244/2022003 IR 05000244/20225012022-09-21021 September 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000244/2022501 IR 05000244/20220102022-09-13013 September 2022 Biennial Problem Identification and Resolution Inspection Report 05000244/2022010 IR 05000244/20220052022-08-31031 August 2022 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2022005) IR 05000244/20224022022-08-0303 August 2022 Security Baseline Inspection Report 05000244/2022402 IR 05000244/20220022022-08-0303 August 2022 LLC - Integrated Inspection Report 05000244/2022002 ML22160A3962022-06-0909 June 2022 R. E. Ginna Nuclear Power Plant, LLC - Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000244/2022010 IR 05000244/20224032022-05-24024 May 2022 R. E. Ginna Nuclear Power Plant, LLC - Cyber Security Inspection Report 05000244/2022403 (Cover Letter Only) IR 05000244/20220012022-05-0303 May 2022 R. E. Ginna Nuclear Power Plant, LLC - Integrated Inspection Report 05000244/2022001 IR 05000244/20224012022-03-0404 March 2022 LLC - Security Baseline Inspection Report 05000244/2022401 IR 05000244/20210062022-03-0202 March 2022 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2021006) IR 05000244/20210042022-01-20020 January 2022 R. E. Ginna Nuclear Power Plant, LLC - Integrated Inspection Report 05000244/2021004 IR 05000244/20220112021-12-16016 December 2021 R. E. Ginna Nuclear Power Plant, LLC - Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000244/2022011 IR 05000244/20210032021-11-0404 November 2021 Integrated Inspection Report 05000244/2021003 IR 05000244/20215012021-09-29029 September 2021 LLC - Emergency Preparedness Biennial Exercise Inspection Report 05000244/2021501 IR 05000244/20210052021-09-0101 September 2021 Updated Inspection Plan for the R.E. Ginna Nuclear Power Plant, Llc (Report 05000244/2021005 IR 05000244/20210022021-08-0303 August 2021 LLC: Integrated Inspection Report 05000244/2021002 IR 05000244/20214012021-07-0202 July 2021 R. E. Ginna Nuclear Power Plant: Security Baseline Inspection Report 05000244/2021401 IR 05000244/20210102021-06-0707 June 2021 LLC: NRC Inspection Report 05000244/2021010 IR 05000244/20210012021-05-0505 May 2021 LLC: Integrated Inspection Report 05000244/2021001 IR 05000244/20210112021-04-27027 April 2021 LLC: Temporary Instruction 2515/194 Inspection Report 05000244/2021011 IR 05000244/20200032021-04-15015 April 2021 R. E. Ginna Nuclear Power Plant, LLC: Reissued Integrated Inspection Report 05000244/2020003 IR 05000244/20200062021-03-0303 March 2021 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2020006) IR 05000244/20200132021-02-17017 February 2021 R. E. Ginna Nuclear Power Plant, LLC: Design Basis Assurance Inspection (Programs) Inspection Report 05000244/2020013 IR 05000244/20200042021-02-0808 February 2021 R. E. Ginna Nuclear Power Plant, LLC: Integrated Inspection Report 05000244/2020004 IR 07200067/20200022021-01-21021 January 2021 Independent Spent Fuel Storage Installation (ISFSI) NRC Inspection Report No. 07200067/2020002 IR 05000244/20203012020-12-0101 December 2020 R. E. Ginna Nuclear Power Plant, Initial Operator Licensing Examination Report 05000244/2020301 ML20315A3682020-11-10010 November 2020 R. E. Ginna Nuclear Power Plant, LLC - Integrated Inspection Report 05000244/2020003 2024-09-24
[Table view] Category:Letter
MONTHYEARIR 05000244/20243012024-10-22022 October 2024 Initial Operator Licensing Examination Report 05000244/2024301 ML24286A0022024-10-11011 October 2024 Core Operating Limits Report Cycle 45, Revision 0 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing RS-24-092, Revised Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-09-25025 September 2024 Revised Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000244/20245012024-09-24024 September 2024 LLC - Emergency Preparedness Biennial Exercise Inspection Report 05000244/2024501 IR 05000244/20240052024-08-29029 August 2024 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2024005) ML24234A0922024-08-21021 August 2024 Requalification Program Inspection IR 05000244/20240102024-08-19019 August 2024 Biennial Problem Identification and Resolution Inspection Report 05000244/2024010 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000244/20240022024-08-0505 August 2024 LLC - Integrated Inspection Report 05000244/2024002 and Independent Spent Fuel Storage Installation Report 07200067/2024001 ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24170A3852024-07-16016 July 2024 R. E. Ginna Nuclear Power Plant - Alternative Associated with Inservice Testing of B Auxiliary Feedwater Pump - PR-03 ML24197A0302024-07-15015 July 2024 LLC - Operator Licensing Examination Approval RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions IR 05000244/20244022024-06-20020 June 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000244/2024402 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24143A0752024-05-22022 May 2024 Re. Ginna Nuclear Power Plant and Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License ISFSI Casks ML24136A1692024-05-14014 May 2024 And Independent Spent Fuel Storage Installation (ISFSI) - 2023 Annual Radioactive Effluent Release Report and 2023 Annual Radiological Environmental Operating Report ML24134A0042024-05-13013 May 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000244/2024010 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests IR 05000244/20240012024-04-24024 April 2024 LLC - Integrated Inspection Report 05000244/2024001 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24101A0432024-04-10010 April 2024 2024 10 CFR 50.46 Annual Report IR 05000244/20240112024-04-10010 April 2024 LLC - Fire Protection Team Inspection Report 05000244/2024011 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24088A2042024-03-28028 March 2024 R. E. Ginna Nuclear Power Plant - Response to NRC Request for Additional Information Regarding Relief Request Associated with Inservice Testing of ‘B’ Auxiliary Feedwater Pump ML24110A0122024-03-28028 March 2024 2023 Report of Individual Monitoring for R.E. Ginna Nuclear Power Plant LLC, License DPR-18 05000244/LER-2023-003-01, Re. Ginna Nuclear Power Plant, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam2024-03-0707 March 2024 Re. Ginna Nuclear Power Plant, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam IR 05000244/20230062024-02-28028 February 2024 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC, (Report 05000244/2023006) IR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of ‘B’ Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations 05000244/LER-2023-003, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam Generator Level2023-12-11011 December 2023 Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam Generator Level ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums 05000244/LER-2023-002, Overtemperature Delta Temperature Reactor Protection System and Auxiliary Feedwater System Actuations on Due to 100% Load Rejection Caused by Turbine Overspeed Circuit Card Failure2023-11-0808 November 2023 Overtemperature Delta Temperature Reactor Protection System and Auxiliary Feedwater System Actuations on Due to 100% Load Rejection Caused by Turbine Overspeed Circuit Card Failure. IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23258A1382023-09-18018 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000244/2023010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) 2024-09-25
[Table view] |
Inspection Report - Ginna - 2014006 |
---|
|
|
Text
UNITED STATES ber 2, 2014
SUBJECT:
MID CYCLE ASSESSMENT LETTER FOR R.E. GINNA NUCLEAR POWER PLANT (REPORT 05000244/2014006)
Dear Mr. Pacher:
On August 13, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of your R.E. Ginna Nuclear Power Plant (Ginna). The NRC reviewed the most recent quarterly performance indicators in addition to inspection results and enforcement actions from July 1, 2013, through June 30, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Ginna operated in a manner that preserved public health and safety and met all cornerstone objectives with minimal degradation in safety performance.
Ginna was in the Regulatory Response Column of the NRCs Reactor Oversight Process Action Matrix for the most recent quarter, due to a White Notice of Violation and Assessment Follow-Up Letter (ML14107A080) issued on April 17, 2014. The finding involved the failure to assure prompt identification and correction of conditions adverse to quality concerning two cable penetrations between manhole 1 and battery room B at Ginna which were not hydrostatically sealed as required. As stated in the letter, this finding and the plants transition to the Regulatory Response Column of the Action Matrix were retroactive to the fourth quarter of 2013.
On July 16, 2014, you notified the NRC of your readiness for it to conduct a supplemental inspection to review the actions taken to address the performance issues. Therefore, in addition to Reactor Oversight Process baseline inspections, the NRC is conducting a supplemental inspection in accordance with Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area, beginning on August 25, 2014. The objectives of the supplemental inspection are to provide assurance that the root causes and contributing causes of risk-significant performance issues are understood; to provide assurance that the extent of condition and extent of cause of risk-significant performance issues are identified; and to provide assurance that corrective actions for risk-significant performance issues are sufficient to address the root and contributing causes and prevent recurrence.
As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year 2014 reflect this revision to Inspection Manual Chapter (IMC) 0310.
Cross-cutting aspects identified in 2013 using the 2013 terminology were converted to the latest revision in accordance with the cross-reference in IMC 0310 during the mid-cycle assessment review and evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305.
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.
The enclosed inspection plan lists the inspections scheduled through December 31, 2015.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRC's Agencywide Document Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact Dan Schroeder at (610) 337-5262 with any questions you have regarding this letter.
Sincerely,
/RA/
Ho K. Nieh Director Division of Reactor Projects Docket No. 50-244 License No. DPR-18 Enclosure: Inspection Plan cc w/encl: Distribution via ListServ
ML14241A043 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME ARosebrook/AAR DSchroeder/DLS HNieh/HKN DATE 08/26/14 08/26/14 08/28/14
Page 1 of 2 Ginna 08/27/2014 15:24:04 Inspection / Activity Plan Report 22 07/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 7111107T - TRIENNIAL HEAT SINK 1 1 07/14/2014 07/18/2014 IP 7111107T Heat Sink Performance 71124 - RADIATION SAFETY INSPECTION - RETS 1 1 07/14/2014 07/18/2014 IP 71124.05 Radiation Monitoring Instrumentation 1 07/14/2014 07/18/2014 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 12/1EXAM - INITIAL OL EXAM 3 1 11/03/2014 11/07/2014 U01900 FY15-GINNA INITIAL OPERATOR LICENSING EXAM 1 12/01/2014 12/12/2014 U01900 FY15-GINNA INITIAL OPERATOR LICENSING EXAM MODS - PERMANENT PLANT MODIFICATIONS 6 1 08/04/2014 08/08/2014 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 1 08/18/2014 08/22/2014 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications EP PROG - EP PROGRAM INSPECTION 1 1 08/04/2014 08/08/2014 IP 7111402 Alert and Notification System Testing 1 08/04/2014 08/08/2014 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 08/04/2014 08/08/2014 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 95001 - 95001 SUPLEMENTAL INSPECTION 2 1 08/25/2014 08/29/2014 IP 95001 Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area 71124 - RADIATION SAFETY INSPECTION - INSTRUMENT 1 1 08/25/2014 08/29/2014 IP 71124.05 Radiation Monitoring Instrumentation 1 08/25/2014 08/29/2014 IP 71151-OR01 1 08/25/2014 08/29/2014 IP 71151-PR01 7111111B - REQUAL INSPECTION WITH P/F RESULTS 2 1 11/17/2014 11/21/2014 IP 7111111B Licensed Operator Requalification Program 71124 - RADIATION SAFETY INSPECTION - DOSE 1 1 04/13/2015 04/17/2015 IP 71124.04 Occupational Dose Assessment EP - EP EXERCISE 5 1 04/27/2015 05/01/2015 IP 7111401 Exercise Evaluation 1 04/27/2015 05/01/2015 IP 7111408 Exercise Evaluation - Scenario Review 71124 - RADIATION SAFETY INSPECTION - ALARA 1 1 07/13/2015 07/17/2015 IP 71124.02 Occupational ALARA Planning and Controls 71124 - RADIATION SAFETY INSPECTION - REMP 1 1 08/17/2015 08/21/2015 IP 71124.07 Radiological Environmental Monitoring Program This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures. Enclosure
Page 2 of 2 Ginna 08/27/2014 15:24:04 Inspection / Activity Plan Report 22 07/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site TRI FI - TRIENNIAL FIRE PROTECTION INSPECTION 4 1 09/14/2015 09/18/2015 IP 7111105T Fire Protection [Triennial]
1 09/28/2015 10/02/2015 IP 7111105T Fire Protection [Triennial]
71124 - RADIATION SAFETY INSPECTION 1 1 10/26/2015 10/30/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 7111108P - INSERVICE INSPECTION 1 1 10/26/2015 11/06/2015 IP 7111108P Inservice Inspection Activities - PWR 71124 - RADIATION SAFETY INSPECTION - DOSE 1 1 12/07/2015 12/11/2015 IP 71124.04 Occupational Dose Assessment 1 12/07/2015 12/11/2015 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures. Enclosure