IR 05000275/2016003

From kanterella
Revision as of 04:56, 16 September 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Diablo Canyon Power Plant - NRC Integrated Inspection Report 05000275/2016003 and 05000323/2016003
ML16301A393
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 10/27/2016
From: Groom J R
NRC/RGN-IV/DRP
To: Halpin E D
Pacific Gas & Electric Co
Jeremy Groom
References
EA-16-104 IR 2016003
Download: ML16301A393 (46)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD.

ARLINGTON, TX 76011-4511 October 2 7, 2016 EA-16-104 Mr. Edward Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424

SUBJECT: DIABLO CANYON POWER PLANT - NRC INTEGRATED INSPECTION REPORT 05000275/2016003 AND 05000323/2016003

Dear Mr. Halpin:

On September 30, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Diablo Canyon Power Plant, Units 1 and 2. On October 5, 2016, the NRC inspectors discussed the results of this inspection with Mr. J. Nimick, Senior Director of Nuclear Services, and other members of your staff. Inspectors documented the results of this inspection in the enclosed inspection report.

No NRC-identified or self

-revealing findings of more than minor significance were identified during this inspection. However, as discussed in Section 4OA5 of this report, the inspectors identified an additional example of the previous Severity Level IV non-cited violation documented in NRC Inspection Report 05000275/2015002 and 05000323/2015002. This violation involved the licensee's failure to maintain fire protection records complete and accurate in all material respects as required by Title 10 of the Code of Federal Regulations (10 CFR) 50.9, "Completeness and accuracy of information." Because the additional example occurred during the same time period as the original violation, was caused by the same licensee employee, the significance is similar to the previous violation, and because your corrective actions address the cause of the violation, including this additional example, no new enforcement action is issued in this report.

If you contest the violation or significance of the non

-cited violation, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555

-0001; and the NRC resident inspector at the Diablo Canyon Power Plant. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Sincerely,/RA/ Jeremy R. Groom, Chief Project Branch A Division of Reactor Projects Docket Nos. 50-275 and 50

-323 License Nos. DPR-80 and DPR

-82

Enclosure:

Inspection Report 05000275/2016003 and 05000323/2016003 w/ Attachmen ts: 1.Supplemental Information 2.Request for Information for OccupationalRadiation Safety Inspection cc w/ enclosure: Electronic Distribution

SUNSI Review By: RDA ADAMS Yes No Non-Sensitive Sensitive Publicly Available Non-Publicly Available Keyword: NRC-002 OFFICE SRI:DRP/A SRI:DRP/A RI:DRP/A RI:DRP/A C:DRS/EB1 C:DRS/EB2 C:DRS/OB NAME CNewport JReynoso JChoate EUribe TFarnholtz GWerner VGaddy SIGNATURE /RA/ /RA/-E /RA/ /RA/-E /RA/ /RA/ /RA/ DATE 10/18/16 10/23/16 10/18/16 10/24/16 10/18/16 10/18/16 10/18/16 OFFICE C:DRS/PSB2 C:DRS/IPAT SPE:DRP/A ORA/ACES BC:DRP/A NAME HGepford THipschman RAlexander JKramer JGroom SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/ DATE 10-18-16 10/19/16 10/19/16 10/21/16 10/26/16 Letter to Edward from Jeremy R. Groom dated October 2 7, 2016

SUBJECT: DIABLO CANYON POWER PLANT

- NRC INSPECTION REPORT 05000275/2016003 and 05000323/2016003 DISTRIBUTION

Regional Administrator (Kriss.Kennedy@nrc.gov)

Deputy Regional Administrator (Scott.Morris@nrc.gov) DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Christopher.Newport@nrc.gov)

Acting Senior Resident Inspector (John.Reynoso@nrc.gov)

Acting Resident Inspector (Eduardo.Uribe@nrc.gov

) Acting Resident Inspector (Jackson.Choate@nrc.gov)

Administrative Assistant (Madeleine.Arel

-Davis@nrc.gov)

Branch Chief, DRP/A (Jeremy.Groom@nrc.gov)

Senior Project Engineer, DRP/A (Ryan.Alexander@nrc.gov)

Project Engineer, DRP/A (Matthew.Kirk@nrc.gov) Project Engineer, DRP/A (Thomas.Sullivan@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov

) Project Manager (Balwant.Singal@nrc.gov) Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)

RIV RSLO (Bill.Maier@nrc.gov)

ROPreports.Resource@nrc.gov ROPassessment.Resource@nrc.gov

Enclosure U.S. NUCLEAR REGULATORY COMMISSION REGION IV Docket: 05000275; 05000323 License: DPR-80; DPR-82 Report: 05000275/2016003; 05000323/201600 3 Licensee: Pacific Gas and Electric Company Facility: Diablo Canyon Power Plant, Units 1 and 2 Location: 7 1/2 miles NW of Avila Beach Avila Beach, CA Dates: July 1 through September 30, 2016 Inspectors:

C. Newport, Senior Resident Inspector J. Reynoso, Acting Senior Resident Inspector R. Alexander, Sr. Project Engineer J. Choate, Acting Resident Inspector C. Peabody, Senior Resident Inspector E. Uribe, Acting Resident Inspector L. Carson II, Sr. Health Physicist C. Osterholtz, Senior Operations Engineer G. George, Senior Reactor Inspector S. Money, Health Physicist J. O'Donnell, CHP, Health Physicist M. Phalen, Sr. Health Physicist Approved By: Jeremy R. Groom Chief, Project Branch A Division of Reactor Projects

SUMMARY

I R 05000275/201600 3, 05000323/201600 3; 07/01/2016 - 09/30/2016; Diablo Canyon Power Plant; Integrated Inspection Report. The inspection activities described in this report were performed between July 1 and September 30, 2016 , by the resident inspectors at Diablo Canyon Power Plant and inspectors from the NRC's Region IV office. The significance of inspection findings is indicated by their color (Green, White, Yellow, or Red), which is determined using Inspection Manual Chapter 0609, "Significance Determination Process." Their cross-cutting aspects are determined using Inspection Manual Chapter 0310, "Aspects within the Cross-Cutting Areas." Violations of NRC requirements are dispositioned in accordance with the NRC Enforcement Policy. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG

-1649, "Reactor Oversight Process."

No findings were identified.

PLANT STATUS

Unit 1 operated at or near full power for the duration of the inspection period.

Unit 2 began the inspection period at full power.

On August 4, 2016, Unit 2 reduced power to 70 percent reactor power due to a misaligned control rod. Following realignment of the control rod, Unit 2 was returned to full power on August 5, 2016 , and operated at or near full power for the remainder of this inspection period.

REPORT DETAILS

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and Emergency Preparedness

1R01 Adverse Weather Protection

.1 Summer Readiness for Offsite and Alternate

AC Power Systems

a. Inspection Scope

On July 21, 2016, the inspectors completed an inspection of the station's off

-site and alternate-ac power systems.

The inspectors inspected the material condition of these systems, including transformers and other switchyard equipment to verify that plant features and procedures were appropriate for operation and continued availability of off-site and alternate

-ac power systems. The inspectors reviewed outstanding work orders and open condition reports for these systems

. The inspectors walked down the switchyard to observe the material condition of equipment providing off-site power sources. The inspectors assessed corrective actions for identified degraded conditions and verified that the licensee had considered the degraded conditions in its risk evaluations and had established appropriate compensatory measures.

The inspectors verified that the licensee's procedures included appropriate measures to monitor and maintain availability and reliability of the off

-site and alternate

-ac power systems. These activities constitute d one sample of summer readiness of off-site and alternate

-ac power systems , as defined in Inspection Procedure 71111.01.

b. Findings

No findings were identified.

.2 Readiness for Seasonal Extreme Weather Conditions

a. Inspection Scope

On September 30, 2016, the inspectors completed an inspection of the station's readiness for seasonal extreme weather conditions. The inspectors reviewed the licensee's adverse weather procedures for ocean high swells and circulating water intake management during the storm season and evaluated the licensee's implementation of these procedures. The inspectors verified that prior to onset of the storm season , the licensee had corrected weather-related equipment deficiencies identified during the previous storm season related to auxiliary saltwater, component cooling water, and intake systems

. The inspectors reviewed the licensee's procedures and design information to ensure the circulating water systems would remain functional when challenge d by debris loading due to high ocean swells.

The inspectors verified that operator actions described in the licensee's procedures were adequate to maintain readiness of these systems. The inspectors walked down portions of these systems to verify the physical condition of the circulating water system.

These activities constitute d one sample of readiness for seasonal adverse weather , a s defined in Inspection Procedure 71111.01.

b. Findings

No findings were identified.

1R04 Equipment Alignment

Partial Walk

-Down

a. Inspection Scope

The inspectors performed partial system walk

-downs of the following risk

-significant systems: July 7, 2016, Unit 2, turbine driven auxiliary feedwater pump 2-1 August 9, 2016, Unit 2, motor driven auxiliary feedwater pump 2-2 August 16, 2016, Unit 1, emergency diesel generator 1-2 September 1, 2016, Unit 2, turbine driven auxiliary feedwater pump 2

-1 The inspectors reviewed the licensee's procedures and system design information to determine the correct lineup for the systems. They visually verified that critical portions of the systems were correctly aligned for the existing plant configuration

. These activities constitute d four partial system walk

-down sample s as defined i n Inspection Procedure 71111.04.

b. Findings

No findings were identified.

1R05 Fire Protection

Quarterly Inspection

a. Inspection Scope

The inspectors evaluated the licensee's fire protection program for operational status and material condition. The inspectors focused their inspection o n five plant areas important to safety

July 6, 2016, Unit s 1 and 2, fire area RA

-3; in the auxiliary building 73 foot elevation July 26, 2016, Unit 1, fire area RA

-7; auxiliary building fire areas located on the 100 foot elevation August 11, 2016, Unit s 1 and 2, fire areas TB-7, 3-BB, and 3-H-1; turbine building, and auxiliary building areas from 64 foot elevation to 115 foot elevations August 18, 2016, Unit 2, fire areas 5A

-1, 5A-2, and 5A-3; 480Vac switchgear rooms, auxiliary building 100 foot elevati on August 18, 2016, Unit 2, fire areas 6A

-1, 6A-2, and 6A-3; 120Vdc switchgear and battery rooms, auxiliary building 115 foot elevation For each area, the inspectors evaluated the fire plan against defined hazards and defense-in-depth features in the licensee's fire protection program. The inspectors evaluated control of transient combustibles and ignition sources, fire detection and suppression systems, manual firefighting equipment and capability, passive fire protection features, and compensatory measures for degraded conditions.

These activities constitute d five quarterly inspection sample s , as defined in Inspection Procedure 71111.05.

b. Findings

No findings were identified.

1R07 Heat Sink Performance

a. Inspection Scope

The inspectors reviewed licensee programs to verify heat exchanger performance and operability for the following heat exchangers and safety

-related structure:

emergency diesel generator 1

-2 cooling system safety injection lube oil cooler 1-1 intake structure The inspectors verified whether testing, inspection, maintenance, and chemistry control programs are adequate to ensure proper heat transfer. The inspectors verified that the periodic testing and monitoring methods, as outlined in commitments to NRC Generic Letter 89-13, "Service Water System Problems Affecting Safety

-Related Equipment," utilized proper industry heat exchanger guidance. Additionally, the inspectors verified that the licensee's chemistry program ensured that biological fouling was properly controlled between tests. The inspectors reviewed previous maintenance records of the heat exchangers to verify that the licensee's heat exchanger inspections adequately addressed structural integrity and cleanliness of their tubes. Specific documents reviewed during this inspection are listed in the attachment.

These activities constituted completion of three triennial heat sink inspection samples as defined in Inspection Procedure

71111.07 - 05.

b. Findings

No findings were identified.

1R11 Licensed Operator Requalification Program and Licensed Operator Performance

.1 Review of Licensed Operator Requalification

a. Inspection Scope

On August 24, 2016, the inspectors observed simulator training for an operating crew. The inspectors assessed the performance of the operators and the evaluators' critique of their performance. The inspectors also assessed the modeling and performance of the simulator during the simulator training scenario

. These activities constitute d completion of one quarterly licensed operator requalification program sample , as defined in Inspection Procedure 71111.11.

b. Findings

No findings were identified.

.2 Review of Licensed Operator Performance

a. Inspection Scope

The inspectors observed the performance of on

-shift licensed operators in the plant's main control room. At the time of the observations, the plant was in a period of heightened activity.

The inspectors observed the operators' performance of the following activities:

September 11, 2016, Units 1 and 2, 230 kV switchyard outage September 30, 2016, Unit 2, 500 kV line hot wash In addition, the inspectors assessed the operators' adherence to plant procedures, including conduct of operations procedure and other operations department policies. These activities constitute d completion of one quarterly licensed operator performance sample , a s defined in Inspection Procedure 71111.11.

b. Findings

No findings were identified.

.3 Annual Review of Requalification Examination Results

a. Inspection Scope

The licensed operator requalification program involves two training cycles that are conducted over a two

-year period. In the first cycle, the annual cycle, the operators are administered an operating test consisting of job performance measures and simulator scenarios. In the second part of the training cycle, the biennial cycle, operators are administered an operating test and a comprehensive written examination. For this annual inspection requirement the licensee was in the first part of the training cycle.

The inspector reviewed the results of the operating tests for both units to satisfy the annual requirements.

On August 8, 2016, the licensee informed the inspector of the following results combining both units:

13 of 13 crews passed the simulator portion of the operating test 73 of 73 licensed operators passed the simulator portion of the operating test 72 of 73 licensed operators passed the job performance measure portion of the operating test One individual senior reactor operator failed the job performance measure portion of the operating test, was remediated, retested, and passed the retake examination.

These activities constituted completion of one annual licensed operator requalification program sample, as defined in Inspection Procedure 71111.11.

b. Findings

No findings of significance were identified.

1R12 Maintenance Effectiveness

a. Inspection Scope

The inspectors reviewed two instances of degraded performance or condition of safety-related structures, systems, and components (SSCs): August 15-18, 2016, inadequate disconnect connection on 230 kV switchyard circuit switcher 211-1, Notification 50864563 September 16, 2016, Units 1 and 2, auxiliary saltwater vault room s ventilation snorkel corrosion technical evaluation, Notification 50866092 The inspectors reviewed the extent of condition of possible common cause SSC failures and evaluated the adequacy of the licensee's corrective actions. The inspectors reviewed the licensee's work practices to evaluate whether these may have played a role in the degradation of the SSCs. The inspectors assessed the licensee's characterization of the degradation in accordance with 10 CFR 50.65 (the Maintenance Rule), and verified that the licensee was appropriately tracking degraded performance and conditions in accordance with the Maintenance Rule.

These activities constitute d completion of two maintenance effectiveness sample s , a s defined in Inspection Procedure 71111.12.

b. Findings

No findings were identified.

1R13 Maintenance Risk Assessments and Emergent Work Control

a. Inspection Scope

The inspectors reviewed four risk assessments performed by the licensee prior to changes in plant configuration and the risk management actions taken by the licensee in response to elevated risk:

July 25, 2016, 4 kV Vital Bus F, elevated risk during undervoltage relay calibration September 11, 2016, Units 1 and 2, elevated risk during 230 kV switchyard outage September 21, 2016, Units 1 and 2, elevated risk during 500 kV tower hot wash September 26, 2016, Unit 1, elevated risk during startup transformer 1-1 load tap changer control relay change

-out The inspectors verified that these risk assessment were performed timely and in accordance with the requirements of 10 CFR 50.65 (the Maintenance Rule) and plant procedures. The inspectors reviewed the accuracy and completeness of the licensee's risk assessment s and verified that the licensee implemented appropriate risk management actions based on the result of the assessment s. The inspectors verified that the licensee appropriately developed and followed a work plan for these activities. The inspectors verified that the licensee took precautions to minimize the impact of the work activities on unaffected SSCs. These activities constitute d completion of four maintenance risk assessments and emergent work control inspection sample s , as defined in Inspection Procedure 71111.13.

b. Findings

No findings were identified.

1R15 Operability Determinations

and Functionality Assessments (71111.15)

a. Inspection Scope

The inspectors reviewed seven operability determinations that the licensee performed for degraded or nonconforming SSCs:

July 12, 2016, operability determination of emergency diesel generator 1-1 jacket cooling water leak discovered during maintenance, Notification 50862106 July 13, 2016, operability determination of emergency diesel generator s 2-2 and 2-3 potential cap screw failures discovered during maintenance , Notification 50652094 August 16-17, 2016, operability determination of Unit 1, train B, engineered safeguards feature slave relay K634 failure , Notification 50866135 August 20, 2016, operability determination of Unit 2 main steam isolation bypass valve FCV-23 failure to stroke, Notification 50861913 August 22, 2016, operability determination of emergency diesel generator 1-2, lube oil leak from cylinder 1L during routine surveillance test, Notification 50867914 August 25-26, 2016, operability determination of Unit 1, control room air conditioner inadequate thermal overload/4 kV coordination, Notification 50868945 September 9, 2016, Units 1 and 2, operability determination of operator work around conditions to compensate for degraded or non-conforming conditions The inspectors reviewed the timeliness and technical adequacy of the licensee's evaluations. Where the licensee determined the degraded SSC to be operable, t he inspectors verified that the licensee's compensatory measures were appropriate to provide reasonable assurance of operability. The inspectors verified that the licensee had considered the effect of other degraded conditions on the operability of the degraded SSC

. The inspectors reviewed operator actions taken or planned to compensate for degraded or nonconforming conditions.

The inspectors verified that the licensee effectively managed these operator workarounds to prevent adverse effects on the function of mitigating systems and to minimize their impact on the operators' ability to implement abnormal and emergency operating procedures.

These activities constitute d completion of seven operability and functionality review sample s, which included one operator work

-around sample, as defined in Inspection Procedure 71111.15.

b. Findings

No findings were identified.

1R18 Plant Modifications

a. Inspection Scope

On September 29, 2016, the inspectors reviewed a permanent modification to the Units 1 and 2 safety injection check valve test header s.

The inspectors reviewed the design and implementation of the modification. The inspectors verified that work activities involved in implementing the modification did not adversely impact operator actions that may be required in response to an emergency or other unplanned event. The inspectors verified that post

-modification testing was adequate to establish the operability of the SSC as modified.

These activities constitute d completion of one sample of permanent modifications , a s defined in Inspection Procedure 71111.18.

b. Findings

No findings were identified.

1R19 Post-Maintenance

Testing (71111.19)

a. Inspection Scope

The inspectors reviewed six post-maintenance testing activities that affected risk-significant SSCs:

July 12, 2016 , Unit 1, emergency diesel generator 1

-1, post maintenance test , Work Order 64164765 July 22, 2016, Unit 1, emergency diesel generator 1

-2, post maintenance test , Work Order 64165082 August 31, 2016, Unit 2, travelling screen 2

-7 drive and chain assembly replacement, Work Order 60083123 September 16, 2016, Unit 2, emergency diesel generator 2

-1 starting air valve 2-21P-41 replacement, Work Order 60088870 September 19, 2016, Unit 2, auxiliary salt water pump 2-1 stuffing box packing stud hole installation, Work Order 60093902 September 28, 2016, Unit 1, auxiliary feedwater supply level control valve, LCV-115, positioner control replacement, Work Order 60093787 The inspectors reviewed licensing- and design

-basis documents for the SSCs and the maintenance and post-maintenance test procedures.

The inspectors observed the performance of the post

-maintenance tests to verify that the licensee performed the tests in accordance with approved procedures, satisfied the established acceptance criteria, and restored the operability of the affected SSCs.

These activities constitute d completion of six post-maintenance testing inspection sample s , as defined in Inspection Procedure 71111.19.

b. Findings

No findings were identified.

1R22 Surveillance Testing

a. Inspection Scope

The inspectors observed four risk-significant surveillance tests and reviewed test results to verify that these tests adequately demonstrated that the SSCs were capable of performing their safety functions:

Reactor coolant system leak detection tests: September 23, 2016, Unit 1, reactor coolant system leak detection system test during period of an elevated leak rate, per procedure STP R-10C Other surveillance tests:

July 21, 2016, Unit 2, solid state protection system testing, per procedure STP I-38-B September 13, 2016, Unit 1, protection set IV, rack 16 channel operational test, per procedure STP I-36-S4R16 September 20, 2016, Unit 1, solid state protection system slave relay testing, per procedure STP M-16N The inspectors verified that these test s me t technical specification requirements, that the licensee performed the tests in accordance with their procedures, and that the results of the test satisfied appropriate acceptance criteria. The inspectors verified that the licensee restored the operability of the affected SSCs following testing.

These activities constitute d completion of four surveillance testing inspection sample s , as defined in Inspection Procedure 71111.22.

b. Findings

No findings were identified.

Cornerstone:

Emergency Preparedness

1EP6 Drill Evaluation

Emergency Preparedness Drill Observation

a. Inspection Scope

During the inspection period, the inspectors observed two separate emergency preparedness drills to verify the adequacy and capability of the licensee's assessment of drill performance:

On August 24, 2016, the inspectors reviewed the drill scenario, observed the drill from the technical support center, and attended the post

-drill critique.

On September 21, 2016, the inspectors reviewed the drill scenario, observed the drill from the technical support center, the emergency operations facility, and the simulator, and attended the post

-drill critiques.

The inspectors verified that the licensee's emergency classifications, off

-site notifications, and protective action recommendations were appropriate and timely. The inspectors verified that any emergency preparedness weaknesses were appropriately identified by the licensee in the post

-drill critique and entered into the corrective action program for resolution.

These activities constitute d completion of two emergency preparedness drill observation sample s, as defined in Inspection Procedure 71114.06.

b. Findings

No findings were identified.

RADIATION SAFETY

Cornerstones: Public Radiation Safety and Occupational Radiation Safety

2RS5 Radiation Monitoring Instrumentation

a. Inspection Scope

The inspectors evaluated the accuracy and operability of the radiation monitoring equipment used by the licensee to monitor areas, materials, and workers to ensure a radiologically safe work environment. This evaluation included equipment used to monitor radiological conditions related to normal plant operations, anticipated operational occurrences, and conditions resulting from postulated accidents. The inspectors interviewed licensee personnel, walked down various portions of the plant, and reviewed licensee performance associated with radiation monitoring instrumentation, as described below: The inspectors performed walk downs and observations of selected plant radiation monitoring equipment and instrumentation, including portable survey instruments, area radiation monitors, continuous air monitors, personnel contamination monitors, portal monitors, and small article monitors. The inspectors assessed material condition and operability, evaluated positioning of instruments relative to the radiation sources or areas they were intended to monitor, and verified performance of source checks and calibrations.

The inspectors evaluated the calibration and testing program, including laboratory instrumentation, whole body counters, post

-accident monitoring instrumentation, portal monitors, personnel contamination monitors, small article monitors, portable survey instruments, area radiation monitors, electronic dosimetry, air samplers, and continuous air monitors.

The inspectors assessed problem identification and resolution for radiation monitoring instrumentation. The inspectors reviewed audits, self

-assessments, and corrective action program documents to verify problems were being identified and properly addressed for resolution.

These activities constitute completion of the three required samples of radiation monitoring instrumentation, as defined in Inspection Procedure 71124.05.

b. Findings

No findings were identified.

2RS6 Radioactive Gaseous and Liquid Effluent Treatment

a. Inspection Scope

The inspectors evaluated whether the licensee maintained gaseous and liquid effluent processing systems and properly mitigated, monitored, and evaluated radiological discharges with respect to public exposure. The inspectors verified that abnormal radioactive gaseous or liquid discharges and conditions, when effluent radiation monitors are out-of-service, were controlled in accordance with the applicable regulatory requirements and licensee procedures. The inspectors verified that the licensee's quality control program ensured radioactive effluent sampling and analysis adequately quantified and evaluated discharges of radioactive materials. The inspectors verified the adequacy of public dose projections resulting from radioactive effluent discharges. The inspectors interviewed licensee personnel and reviewed licensee performance in the following areas:

During walk downs and observations of selected portions of the radioactive gaseous and liquid effluent equipment, the inspectors evaluated routine processing and discharge of effluents, including sample collection and analysis. The inspectors observed equipment configuration and flow paths of selected gaseous and liquid discharge system components, effluent monitoring systems, filtered ventilation system material condition, and significant changes to effluent release points.

Calibration and testing program for process and effluent monitors, including National Institute of Standards and Technology (NIST) traceability of sources, primary and secondary calibration data, channel calibrations, set

-point determination bases, and surveillance test results.

Sampling and analysis controls used to ensure representative sampling and appropriate compensatory sampling. Reviews included results of the inter

-laboratory comparison program, Instrumentation and equipment, including effluent flow measuring instruments, air cleaning systems, and post

-accident effluent monitoring instruments.

Dose calculations for effluent releases. The inspectors reviewed a selection of radioactive liquid and gaseous waste discharge permits and abnormal gaseous or liquid tank discharges, and verified the projected doses were accurate. The inspectors also reviewed 10 CFR Part 61 analyses and methods used to determine which isotopes were included in the source term. The inspectors reviewed land use census results, offsite dose calculation manual changes, and significant changes in reported dose values from previous years.

Problem identification and resolution for radioactive gaseous and liquid effluent treatment. The inspectors reviewed audits, self

-assessments, and corrective action program documents to verify problems were being identified and properly addressed for resolution.

These activities constitute completion of the six required samples of radioactive gaseous and liquid effluent treatment program, as defined in Inspection Procedure 71124.06.

b. Findings

No findings were identified.

2RS7 Radiological

Environmental Monitoring Program (71124.07)

a. Inspection Scope

The inspectors evaluated whether the licensee's radiological environmental monitoring program quantified the impact of radioactive effluent releases to the environment and sufficiently validated the integrity of the radioactive gaseous and liquid effluent release program. The inspectors also verified that the licensee continued to implement the voluntary Nuclear Energy Institute (NEI)/Industry Ground Water Protection Initiative. The inspectors reviewed or observed the following items:

The inspectors observed selected air sampling and dosimeter monitoring stations, sampler station modifications, and the collection and preparation of environmental samples. The inspectors reviewed calibration and maintenance records for selected air samplers, composite water samplers, and environmental sample radiation measurement instrumentation, and inter

-laboratory comparison program results. The inspectors reviewed selected events documented in the annual environmental monitoring report and significant changes made by the licensee to the offsite dose calculation manual as the result of changes to the land census. The inspectors evaluated the operability, calibration, and maintenance of meteorological instruments and assessed the meteorological dispersion and deposition factors. The inspectors verified the licensee had implemented a sampling and monitoring program sufficient to detect leakage from SSCs with credible mechanism for licensed material to reach ground water and reviewed changes to the licensee's written program for identifying and controlling contaminated spills/leaks to groundwater.

Groundwater protection initiative implementation, including assessment of groundwater monitoring results, identified leakage or spill events and entries made into 10 CFR 50.75(g) records, licensee evaluations of the extent of the contamination and the radiological source term, and reports of events associated with spills, leaks, and groundwater monitoring results.

Problem identification and resolution for the radiological environmental monitoring program. The inspectors reviewed audits, self

-assessments, and corrective action program documents to verify problems were being identified and properly addressed for resolution. These activities constitute completion of the three required samples of radiological environmental monitoring program, as defined in Inspection Procedure 71124.07.

b. Findings

No findings were identified.

2RS8 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation

a. Inspection Scope

The inspectors evaluated the effectiveness of the licensee

's programs for processing, handling, storage, and transportation of radioactive material.

The inspectors interviewed licensee personnel and reviewed the following items:

Radioactive material storage, including waste storage areas including container labeling/marking and monitoring containers for deformation or signs of waste decomposition

. Radioactive waste system

, including walk

-downs of the accessible portions of the radioactive waste processing systems and handling equipment. The inspectors also review ed or observed changes made to the radioactive waste processing systems, methods for dewatering and waste stabilization, waste stream mixing methodology, and waste processing equipment that was not operational or abandoned in place.

Waste characterization and classification

, including radio-chemical sample analysis results for radioactive waste streams and use of scaling factors and calculations to account for difficult

-to-measure radionuclides, and processes for waste classification including use of scaling factors and 10 CFR Part 61 analyses. Shipment preparation, including packaging, surveying, labeling, marking, placarding, vehicle checking, driver instructing, and preparation of the disposal manifest s. Shipping records for Low Specific Activity (LSA) I, II, III; Surface Contaminated Objects (SCO)

I, II; Type A; or Type B radioactive material or radioactive waste shipments.

Problem identification and resolution for radioactive solid waste processing and radioactive material handling, storage, and transportation. The inspectors reviewed audits, self

-assessments, and corrective action program documents to verify problems were being identified and properly addressed for resolution.

These activities constitute completion of the six required samples of radioactive solid waste processing, and radioactive material handling, storage, and transportation program, as defined in Inspection Procedure 71124.08.

b. Findings

No findings were identified.

OTHER ACTIVITIES

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Security

4OA1 Performance Indicator Verification

.1 Mitigating Systems Performance Index

Heat Removal System s (MS08)

a. Inspection Scope

The inspectors reviewed the licensee's mitigating system performance index data for the period of July 2015 through June 2016 to verify the accuracy and completeness of the reported data. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 7, to determine the accuracy of the reported data.

These activities constituted verification of the mitigating system performance index for heat removal systems

, Units 1 and 2, as defined in Inspection Procedure 71151.

b. Findings

No findings were identified.

.2 Mitigating Systems

Performance Index

Residual Heat Removal System s (MS09)

a. Inspection Scope

The inspectors reviewed the licensee's mitigating system performance index data for the period of July 2015 through June 2016 to verify the accuracy and completeness of the reported data. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 7, to determine the accuracy of the reported data.

These activities constituted verification of the mitigating system performance index for residual heat removal systems

, Units 1 and 2, as defined in Inspection Procedure 71151.

b. Findings

No findings were identified.

.3 Mitigating Systems Performance Index

Cooling Water Support Systems (MS10)

a. Inspection Scope

The inspectors reviewed the licensee's mitigating system performance index data for the period of July 2015 through June 2016 to verify the accuracy and completeness of t he reported data. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 7, to determine the accuracy of the reported data.

These activities constituted verification of the mitigating system performance index for cooling water support systems

, Units 1 and 2, as defined in Inspection Procedure 71151.

b. Findings

No findings were identified.

4OA2 Problem Identification and Resolution

(71152) Routine Review

a. Inspection Scope

Throughout the inspection period, the inspectors performed daily reviews of items entered into the licensee's corrective action program and periodically attended the licensee's condition report screening meetings. The inspectors verified that licensee personnel were identifying problems at an appropriate threshold and entering these problems into the corrective action program for resolution. The inspectors verified that the licensee developed and implemented corrective actions commensurate with the significance of the problems identified.

The inspectors also reviewed the licensee's problem identification and resolution activities during the performance of the other inspection activities documented in this report.

b. Findings

No findings were identified.

4OA5 Other Activities

a. Inspection Scope

The inspectors performed a follow

-up review of a licensee identified non

-cited violation of 10 CFR 50.9, "Completeness and accuracy of information," documented in NRC Inspection Report 05000275/2015002 and 05000323/2015002 (ADAMS Accession Number ML15219A599). This non

-cited violation, identified by the licensee, involved the deliberate falsification of fire protection transient combustible walkdown records, required to be performed by the Diablo Canyon Unit 1 and 2 Operating License, Conditions 2.C.(5) and 2.C.(4), respectively.

The inspectors reviewed fire protection records and licensee corrective action documents to ensure an adequate extent of condition evaluation was performed. Th e inspectors also reviewed transcripts of interview s conducted by the NRC's Office of Investigations.

b. Findings

The inspectors identified an additional example of the previous Severity Level IV non-cited violation of 10 CFR Part 50.9, documented in NRC Inspection Report 05000275/2015002 and 05000323/2015002. Title 10 CFR 50.9 requires, in part, that information required by statute or by the Commission's regulations, orders, or license conditions to be maintained by the applicant or the licensee shall be complete and accurate in all material respects. Contrary to the above, between May 20 and June 10, 2014, fire protection records, required by License Condition 2.C.(5) for Unit 1 and 2.C.(4)for Unit 2, "Fire Protection," were not complete and accurate in all material respects. Specifically, the records of inspection of fire barrier and high energy line break (HELB) penetration seals completed using Procedure STP M-70A, "Inspection of Fire Barrier and HELB Penetration Seals,"

Revision 8, were incomplete and inaccurate. These records were incomplete and inaccurate because a licensee employee falsified completion of fire penetration seal inspections in the cable spreading room on the 128 foot elevation of the Auxiliary Building.

The NRC determined this violation to be an additional example of the previously documented licensee identified, Severity Level IV , non-cited violation in NRC Inspection Report 05000275/2015002 and 05000323/2015002 since the violation occurred during the same time period as the original violation and the same licensee employee was responsible for deliberately falsifying the fire protection records.

The additional example of the violation was entered into the licensee's correction action program as Notification 50865296. As immediate corrective actions, the licensee re-performed fire barrier and HELB penetration seals inspection in accordance with Procedure STP M-70A for seal inspections in the cable spreading room on the 128 foot elevation of the auxiliary building. No deficiencies were noted.

(EA-16-104)

4OA6 Meetings, Including Exit

Exit Meeting Summary

On August 4, 2016, the inspectors conducted a technical debrief of the triennial inspection Procedure 71111.07, "Heat Sink Performance" inspection to T. Baldwin, Director of Site Services, and other members of the licensee staff.

On August 4, 2016 , the inspector s discussed the final licensed operator requalification program annual cycle results via telephone with Mr. R. Fortier, Operations Examination Developer, and on August 8, 2016 , formally exited with Mr. Fortier via e

-mail. On August 11, 2016, the inspectors presented the radiation safety inspection results (Sections 2RS5, 2RS6, and 2RS7) to Mr. K. Johnston, Acting Station Director, and other members of the licensee staff.

On September 29, 2016, the inspector presented the radiation safety inspection results (Section 2RS8) to Mr. J. Welsch, Site Vice President, and other members of the licensee staff.

On October 5, 2016, the resident inspectors presented the inspection results to Mr. J. Nimick , Senior Director

, Nuclear Services, and other members of the licensee staff.

The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

J. Bailey, Supervisor, Systems Engineering
T. Baldwin, Director, Nuclear Site Services
D. Evans, Director, Security & Emergency Services
R. Fortier, Operations Examination Developer
P. Gerfen, Senior Director Plant Manager
M. Ginn, Manager, Emergency Planning
D. Gonzales, Supervisor, Inservice Inspection
E. Halpin, Sr. Vice President, Chief Nuclear Officer Generation
H. Hamzehee, Manager, Regulatory Services
M. Hayes, Supervisor, Radiation Protection
A. Heffner, NRC Interface, Regulatory Services
J. Hinds, Director, Quality Verification
L. Hopson, Director Maintenance Services
T. Irving, Manager, Radiation Protection
K. Johnston, Director of Operations

/ Acting Station Director

J. Loya, Manager, Quality Verification
M. McCoy, NRC Interface, Regulatory Services
C. Miller, Systems Engineering
J. Morris, Senior Advising Engineer
C. Murry, Director Nuclear Work Management
J. Nimick, Senior Director

, Nuclear Services

D. Overland, Assistant Director, Maintenanc

e

A. Peck, Director, Nuclear Engineering
R. Rogers, Supervisor, Radiation Protection
A. Warwick, Supervisor, Emergency Planning
J. Welsch, Site Vice President

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

None

LIST OF DOCUMENTS REVIEWED

Section 1R01: Adverse Weather Protection

Procedures

Number Title Revision CP M-16 Severe Weather
OM1.ID4 Interface Requirements for Transmission & Distribution Facilities at DCPP
CP M-12 Stranded Plant
TS5.ID1 System Engineering Program
OP O-28 Intake Management
CP M-16 Severe Weather
MA1.ID23 Review of Intake Preparedness for High Debris Loading Event 3
ENV.EM2 Ocean Jellyfish Influx Monitoring

Notifications

50695480
50696009
50872715
50872716
50872806
50699196
50825645
50833485
50514748
Preventive Maintenance
64164305
Drawing Number Title Revision
502110, Sh. 1
Single Line Diagram 500/230/25/12/4.16

kV Systems Section 1R04

Equipment Alignment

Procedures

Number Title Revision DCM S-3B Auxiliary Feedwater System
OP-D-1:11 Auxiliary Feedwater System

- Alignment Verification For Plant Startup

OP-J-6B:II-A Diesel Generator 1

-2 - Alignment Checklist

OP D-1:IV Turbine Driven AFW Restart or make Available After an Overspeed Trip

Notifications

50569346
50833614
Work Order
64155735
Drawing s Number Description Revision
107703 Auxiliary Feedwater System
106703 OVID Unit 2 Auxiliary Feedwater System
108003 Unit 2: Feedwater System
106721 OVID Diesel Engine Generator Section 1R05
Fire Protection Miscellaneou

s Number Description Revision Fire Pre-Plans Diablo Canyon Fire Pre

-plans 6 Fire Hazards Analysis UFSAR:

Fire Hazards Analysis

Notifications

50863479
50863477
50572486
Drawing s Number Title Revision / Date 0-AB-73 Fire Plan, Radiological Control Area Elev. 73' Unit 1 & 2
106718-10 OVID, Units 1 & 2 Inside Auxiliary Building
181
111906-16 Fire Protection, Auxiliary Building Elev. 73'
DC-693299-2 AUX. BLDG EL 73

-0 (Isometric)

1-AB-85 Radiological Control Area (RCA) & H Block Elev. 85'
1-AB-100 Radiological Control Area (RCA) & H Block Elev. 100'
FHARE Eval
2013-011 Sprinkler Protected Doors Evaluation; FHARE 159
May 20, 2013
FHARE Eval
2012-008 Fire Rated Assemblies Evaluation; ECG 18.7
April 6, 2012
Section 1R07
Heat Sink Performance Calculation

s Number Title Revision

PME-0-21-TI-504 DG Jacket WTR RAD inlet and eng lube oil pmp disch temperature
0322-0024-01 EDG Jacket Water Temperature Vs. Load Design Basis Analysis 1 52.18.10 Evaluate ASW Pump Vaults
4-01
Drawing s Number Title Revision 468434-1 Ventilation Shaft Modification Intake Structure
663032-1 Doors W.T.Q.A.

-Sliding Dog Type 26"x66" Medium Steel

- 10 Dog 15 PSI Arrangement

B
Letter s and Memoranda Number Title Date ATS 420.DC

-16.14 Atmospheric Corrosion Rate of Low Carbon Steel at DCPP August 9, 2016

DCL-90-027 Service Water System Problems Affecting Safety

-Related Equipment January 26, 1990

DCL-91-286 Supplemental Response to Generic Letter
89-13 Service Water System Problems Affecting Safety

-Related Equipment November 25, 1991

DCL-91-307 Tests and Analysis of Structural Concrete at the Intake Structure December 19, 1991
PGE-94-691 Component Cooling Water Temperature and Flow Limits for Auxiliary Pumps December 7, 1994
PGE-96-605 Evaluation of Auxiliary Pumps for Elevated Component Cooling Water Temperatures September 3, 1996
Miscellaneou

s Title

System Health Report for Unit 1 System 14

- Component Cooling Water System Health Report for Unit 2 System 17B

- Auxiliary Saltwater System Health Report for Unit 1 System 17B

- Auxiliary Saltwater System Health Report for Unit 2 System 14

- Component Cooling Water

Vendor Document

Number Title Revision
DC 663216 Pacific Pumps Division

-Dresser Industries Inc. Safety Injection Pumps

Procedures

Number Title Revision
AD7.ID2 Daily Notification Review Team (DRT) & Standard Plant Priority Assignment Scheme
AP PK02-03 Unit 1 Annunciator Response "SI PPS TEMP/OC Trip"
AWP E-016 Inspection Guide

- Maintenance Rule & License Renewal Structural Monitoring Programs

- Civil 6 CAP A-9 Auxiliary Systems Sampling Schedule

MA.ID22 Heat Exchanger Program
2A MIP C-7.0 Grouting and Repair of Concrete Defects
MP M-21-HX.2 Diesel Generator Lube Oil Heat Exchanger
OM7.ID1 Problem Identification and Resolution
OM7.ID12 Operability Determination
OM7.ID13 Technical Evaluation
OP
AP-10 Loss of Auxiliary Salt Water
OP F-5:III Chemistry Control Limits and Action Guidelines for the Plant Support Systems
PEP C-17.13 Coatings Surveillance Program for the Saltwater Systems
PEP C-17.14 Concrete Surveillance Program for the Saltwater Systems
STP M-21-ENG.1 Diesel Engine Generator Inspection (Every Refueling Outage) 22 STP M-21-ENG.6 Diesel Engine Generator Inspection (Every Sixth Refueling Outage) 5
STP M-235C ASW Piping Inspection at Intake Structure
STP M-9A2 Diesel Engine Generator 1

-2 Routine Surveillance Test

STP P-SIP-11 Routine Surveillance Test of Safety Injection Pump
1-1 14

Notifications

A0184820
50317661
50514572
50514855
50526434
50568724
50575830
50658976
50804871
50865486
50865601
50866092
50866093
50866094
50866095
50866110
50866113
50866114
50866115
50584072
50658975

Work Orders

64106682
64094121
64104709
64113309
64121524
54121523
60082830
60082831
60082832 60082833

Section 1R11: Licensed Operator Requalification Program and Licensed Operator Performance

Procedures

Number Title Revision / Date
OP1.DC10 Conduct of Operations
46A
AD7.ID14, Att 4
Risk Management Plan

- Energized Hot Wash

500 kV Towers September 21, 2016
R162S1 Deg Problems and Recovery
0A OP
AP-1 Excessive Reactor Coolant System Leakage
EOP F-0 Critical Safety Function Status Trees
ECA-0.3 Restore 4 kV Buses 19
Work Order

s

64157260
64156902
Section 1R12
Maintenance Effectiveness

Notifications

50864563
50864695
50867042
50867140
50866092
50866485
50866484
50514855
Other Number Description Revision
PC-69-01 Scoping Evaluation System 69: 230 kV
Section 1R13
Maintenance Risk Assessments and Emergent Work Control

Procedures

Number Title Revision STP M-75F 4 kV Vital Bus F Undervoltage Relay Calibration
MP E-50.33A Westinghouse Type SSV

-T One Unit Voltage Relay 14 MP E-50.61 Basler Type BE1

-27 Medium Inverse Undervoltage Relay Maintenance

AD7.ID14 Assessment of Integrated Risk
OP J-2:VII Offsite Power Sources

- Deenergizing SUT 1

-1 & 2-1 for 230 kV Maintenance

OP J-2:VIII Guidelines for Reliable Transmission Service for DCPP
Notification
50301167
Drawing s Number Description Revision
437533 Electrical Single Line Diagram Single Line Meter & Relay Diagram 4160 Volt System
437614 Electrical Schematic Diagram Bus Potential & Synchronizing 4160V System
437625 Electrical Wiring Diagram 4160V Bus Section "F" Automatic Transfer 32
448575 Electrical Wiring Diagram 4160 Volt Switchgear Bus "F" Cell
11
441286 Electrical Logic Diagram 4160 Volt Bus Section "F" Automatic Transfer 11
Work Order
60024242
Section 1R15
Operability Determinations and Functionality Assessments

Procedures

Number Title Revision / Date DCM S-21 Diesel Engine System Page
IE-21.3b, Volume 9 Data Diablo Canyon Power Plant Operations Data July 6, 1994
Page
IE-21.3a, Volume 9 Data Diablo Canyon Power Plant Operations Data July 6, 2001
Calcu lation No.
22-0034-01 Analyses to Support Past Operability Evaluation of DEGs 2

-2 and 2-3 Due to Fuel Header

-to-Fuel Inlet Special Cap Screw Failure and Cracking April 2015

- DCPP Vendor Technical Manual No. 6011476

-322, "Maintenance Manual"

OM7.ID12 Operability Determination
STP V-3R4 Exercising Main Steam Isolation Bypass Valves
STP M-9A2 Diesel Engine Generator 1

-2 Routine Surveillance Test Diablo Canyon Equipment Control Guidelines Diablo Canyon Technical Specifications

OP1.DC40 Operations Equipment Deficiency Tracking

Notifications

50862106
50838199
50042135
50652094
50866134
50866135
50861913
50862262
50867914
50682094
50868945
50394106
50402610
50669034
50701876
50703561
50803453
50821008
50821119
50825559
50847472
50852016
50855158
50871253
Section 1R18
Plant Modifications Other Number Title Revision / Date LBIE 2010-008 License Basis Impact Evaluation, SI Test Header Project
14078101-MR-101 Technical Report, GL 96

-06 Thermal Overpressure Assessment April 2015

Notifications

50864770
50586903
50586902
Section 1R19
Post-Maintenance Testing

Procedures

Number Title Revision STP M-9A1 Diesel Engine Generator 1

-1 Routine Surveillance Test

DCM S-21 Diesel Engine System
STP M-9A2 Diesel Engine Generator 1

-2 Routine Surveillance Test

STP M-91 Diesel Generator Start and Load Tracking
26A MP I-3-L115 Steam Generator 1

-3 Aux FW Supply Level Control Channel

LCV-115 Calibration
STP V-2U3D Exercising SG 1

-3 AFW Supply Valves LCV

-108 and

LCV-115 11 STP V-3P6B Exercising Valves LCV

-115 and 113 Auxiliary Feedwater Pump Discharge Work Order

s

64164765
60083123
60088870
60093787
60093902

Notifications

50807526
50869581
50869683
50843432
50870033
50872938
50871986
50871987
50871988
50871994
Drawing s Number Description Revision
437579 Schematic Diagram 4

kV Diesel Generator Control No. 11 & 12

437580 Schematic Diagram 4

kV Diesel Generator Control No. 11 & 12

Section 1R22
Surveillance Testing

Procedures

Number Title Revision STP I-38-B.1 SSPS Train B Actuation Logic Testing in Modes 1, 2, 3, or 4
STP I-38-B.2 SSPS Train B SI Reset Timer and Slave Relay K602 Test in Modes 1, 2, 3, or 4
STP I-36-S4R16 Protection Set IV, Rack 16 Channel Operational Test
AD4.ID2 Plant Leakage Evaluation
STP R-10C Reactor Coolant System Water Inventory Balance
STP M-16N Operation of trains A and B Slave Relays K632

and K634 16

Notification
50868682

Work Orders

64140530
64140585
Section 1EP6
Drill Evaluation

Procedures

Number Title Revision / Date OM10.ID6 Equipment Important to Emergency Response
OM10.ID1 Maintaining Emergency Preparedness Diablo Canyon Power Plant Emergency Planning Scenario Synopsis/Event Description

- Ingestion Pathway Drill September 21, 2016

Notifications

50599999
50599765
50599009
Other Number Title Date ECTL1601 ERO Drill 8/24/16, DEP Opportunity #1 Scenario August 24, 201
ECTL1602 ERO Drill 8/24/16, Training Scenario August 24, 2016

Section 2RS5: Radiation Monitoring Instrumentation

Procedures

Number Title Revision MP I-RX01 Initial On

-Site Calibration of Portable Radiation Detection Instruments

RCP D-900 Performance Tests for Radiation Protection Instruments
RCP D-970 Radiation Protection Instrument Calibration Schedule
RCP D-981 Annual Verification of the J.L Shepherd Model 89 Shielded Calibrator
STP I-104B Calibration of CCW Discharge Headers Radiation Monitors
RM-17A and RM

-17B 5 STP I-107B Calibration of Miscellaneous Area Radiation Monitors RM

-1, 2, 4, 6, 7, and 10

STP I-119B Calibration of Fuel Handling Building Area Radiation Monitors RM

-58 &

RM-59 6 STP I-18AA2D Radiation Source Calibration of RM

-48 Area Monitor

STP I-39-R30.B Containment High Range Area Radiation Monitor
RM-30/RM-31 Calibration
STP I-39-R71.B Calibration of Main Steam Line Radiation Monitors
RM-71, 72, 73, 74
Audits and Self

-Assessments Number Title Date

50857263 Quick Hit Self

-Assessment:

NRC Pre-Inspection 71124.05 Radiation Monitoring Instrumentation July 26, 2016
2930028 2016 Radiation Protection Programs Audit Report February 16, 2016

Notifications

50638952
50639291
50697677
50812696
50817720
50855525
50855527
Radiation Monitoring System Calibration Records Number Title Date
64095074 I39R30.B Cal Hi Range Rad Mon 2

-RM-31 April 15, 2016

64140283 I107B Cal Control Room Area Mon 0

-RM-1 August 10, 2016

64083662 I107B Cal NSSS Sampling Room Mon 1

-RM-6 February 19, 2015

64094552 I119B Cal Spent Fuel Pool Area 2

-RM-58 June 6, 2015

64105678 I119B New Fuel Area Mon 1

-RM-59 December 28 2015

64061360 I39R71.B Cal Main Steam Rad Mon
1-RM-72 September 14, 2014
64063485 I39R71.B Cal Main Steam Rad Mon
1-RM-73 December 16, 2014
Source Calibration Records Number Title Date
RS-001 Annual Verification of Calibration for the J.L.
Shepherd Model 89 Irradiator (260 Ci Cs

-137) March 22, 2016

RS-002 Annual Verification of Calibration for the J.L.
Shepherd Model 89 Irradiator (400 Ci Cs

-137) March 21, 2016

1789 Eckert & Ziegler

- 1.0 Liter Solid in 130G in GA

-MA Beaker (SN 85609

-34) October 1, 2011

Portable Radiation Instrument Calibration Records Number Title Date RP 01.14.029
Ludlum Model 177
March 9, 2016
RP 03.07.039
Thermo 6112B (Teletector)
May 15, 2016
RP 03.12.017
Eberline R

-02A March 22, 2016

RP 03.14.008
Eberline ASP

-1 March 29, 2016

RP 03.22.002
MGP
AMP-100 October 5, 2015
RP 04.38.001 Thermo AMS

-4 May 15, 2016

RP 06.13.001
Ludlum Model 3030
August 21, 2015
Stationary Radiation Instrument Calibration Records Number Title Date 66554 Tennelec Series 5XLB Alpha/Beta Counter September 1, 2015
97-2391 FastScan Whole Body Counter Calibration:
85' Elevation June 17, 2015
97-5119 FastScan Whole Body Counter Calibration:
Dosimetry June 16, 2015
RP 05.12.05
ARGOS-5AB Personnel Contamination Monitor March 31, 2016
RP 05.13.07
GEM-5 Portal Monitor March 31, 2016 RP 06.25.03
SAM12 Small Article Monitor June 28, 2016

Miscellaneous Documents

Number Title Date 2016 System Health Report:
Unit 1

- 1 st Quarter April 26, 2016

2016 System Health Report:
Unit 2

- 1 st Quarter April 26, 2016

50381 Radiation Survey - Instrument Calibration Facility August 8, 2016

Section 2RS6: Radioactive Gaseous and Liquid Effluent Treatment

Procedures

Number Title Revision CAP A-6A Gaseous Radwaste Release Permit Generation Using REMS 2 CAP A-6B Gaseous Radwaste Postrelease Summary Update Using REMS 0 CAP A-8 Off-Site Dose Calculations
CAP E-2:VI Sampling Primary Chemistry Lab Fume Hood Exhaust
CAP E-5:1 Liquid Radwaste and Miscellaneous Discharge Sampling
CAP E-6:III Secondary Sampling at 85' Auxiliary Building 1 / 2 CAP Q-6 Radiochemical Cross

-Check Program

CY2.ID1 Radioactive Effluent Controls Program
CY2 Radiological Monitoring and Controls Program
7A
CY2.DC1 Radiological Monitoring System High Alarm Set

-Point Control Program

RP1.ID11 Environmental Radiological Monitoring Procedure

Notifications

50816085
50639308
50834457
50659099
50637665
50636984
50640298
50652642
50688029
50652357
50624472
50641774
50636956
50654567
50655919
Radiation Monitor Calibrations Instrument Number Description Date 0-RM-18 Liquid Radioactive Waste Discharge March 2015
1-RM-14 Unit 1 Plant Vent Noble Gas Monitor March 2016
1-RM-14R Unit 1 Plant Vent Noble Gas Monitor

- Redundant March 2016

2-RM-14 Unit 2 Plant Vent Noble Gas Monitor March 2016
2-RM-14R Unit 2 Plant Vent Noble Gas Monitor

- Redundant March 2016

1-RM-24 Unit 1 Plant Vent Iodine Monitor April 2015
1-RM-28 Unit 1 Plant Vent Particulate Monitor April 2015
2-RM-87 Unit 2 Plant Vent High Range Noble Gas Monitor July 2016
Release Permits Number Title Date 2016-1-26 Containment July 11, 2016
2016-1-27 Containment July 11, 2016
2016-0-68 Liquid Radwaste July 21, 2016
Ventilation System Filter Testing Records Number Title Date U1-STP M-3A Unit 1, Auxiliary Building Ventilation System October 2015
U1-STP M-41 Unit 1, Fuel Handling Building January 2015
U1-STP M-53 Unit 1, Control Room Ventilation System April 2015
U2-STP M-3A Unit 2, Auxiliary Building Ventilation System April 2016
U2-STP M-41 Unit 2, Fuel Handling Building Ventilation July 2015 U2-STP M-53 Unit 2, Control Room Ventilation System April 2015
PEP M-96 Technical Support Center (TSC) Ventilation System

- DOP and Halide penetration Tests October 2015

Miscellaneous

Number Title Date 2014 Annual Radioactive Effluent Release Report April 29, 2015
2015 Annual Radioactive Effluent Release Report April 27, 2016
50857264 Pre-Inspection QHSA of DCPP Chemistry Functions in NRC Procedure 71124, Attachments 05, 06, and 07
Focus Areas July 20, 2016
50839230 Pre-Inspection QHSA of NRC Performance Indicator PR01 - RETS/ODCM Occurrences April 8, 2016
N/A Effluent Radiation Monitors Inoperable for >7 Days August 2016
N/A Maintenance Rule System 39 Radiation Monitors August 2016

Section 2RS7: Radiological Environmental Monitoring Program

Procedures

Number Title Revision CY2 Radiological Monitoring and Controls Program
7A
CY2.ID1 Radioactive Effluent Controls Program
RP1.ID11 Environmental Radiological Monitoring Procedure
CAP A-8 Offsite Dose Calculations
RCP
EM-1 Radiological Environmental Biological Sampling
2A RCP
EM-2 Radiological Environmental Air Sampling
RCP
EM-3 Use of Panasonic Environmental Thermoluminescent Dosimeters
RCP
EM-4 Area TLD Monitoring
RCP
EM-5 DCPP Groundwater Sampling
RCP
EM-21 GPI Well Maintenance Plan
RP1.ID13 DCPP Ground Water Protection Initiative Program
TS5.ID3 Buried Pipe and Tanks Program
RCP D-540 Humboldt Bay ISFSI

- Radiation Protection Surveys

GL-QS-B-001 Gel Laboratories Quality Assurance Plan Audits and Self

-Assessments Number Title Date

152930028 2016 Radiation Protection Programs Audit February 8, 2016
100555-0 National Institute of Standards and Technology November 2, 2015
JQA-14-097 NUPIC Audit/Survey of GEL Laboratories, LLC
May 29, 2014
255 NUPIC Audit/Survey of MIRION Technologies INC.
April 22, 2016

Notifications

50852035
50849290
50837902
50828842
50828646
50600291
50598509
50584618
50582121
50581368
50826745
50826744
50804416
50798548
50711226
50710898
50710007
50707798
50706355
50705207
50704588
50702149
50702148
50702016
50702013
50694988
50691605
50691328
50686075
50654567
50638090
50814106
50695725
50694538
50488860
Annual Reports Title Date XOQDOQ Analysis for Calendar Year 2015 Based on the 2011

-2015 Joint Frequency Distribution of Wind and Stability March 30, 2016

2014 Annual Radiological Environmental Operating Report Diablo Canyon Power Plant April 16, 2015
2015 Annual Radiological Environmental Operating Report Diablo Canyo

n Power Plant April 4, 2016

2015 DCPP Land Use Census Groundwater Protection Documents Number Title Date
Effectiveness Review of Groundwater Protection Initiative formal self

-assessment November 17, 2014

29627 Diablo Canyon Power Plant Site Conceptual Model Report July 30, 2014
Meteorological Tower Calibrations Ord er Title Date
64126761 Backup Met Facility Equipment Calibration May 28, 2015
64131311 Backup Met Facility Equipment Calibration January 14, 2016
64140949 Cal Primary Met Instrumentation Channel (PME)
February 9, 2016
64131071 Cal Primary Met Instrumentation Channel (PME)
August 21, 2015

Section 2RS8: Radioactive Solid Waste Processing, and Radioactive Material Handling, Storage, and

Transportation

Procedures

Number Title Revision RCP D-631 Radioactive Material Shipments
RCP
RW-3 Radioactive Waste Nuclide Fractions and Correlation Factors Determination
9 RCP
RW-4 Solid Radioactive Waste Shipments
RCP
RW-5 Receiving, Loading, and Releasing of Transport Vehicle for Radioactive Waste Shipment
CY2.ID1 Radioactive Effluent Controls Program
RP2.DC1 Radioactive Waste Classification Program
RP2.DC3 Radioactive Waste Process Control Program
RCP.RW-1 Collection & Packaging of LLRW
Audits and Self-Assessments Number Title Date
50857266
Quick Hit Self

-Assessment:

NRC Pre-Inspection 71124.08 Radiation Monitoring Instrumentation July 26, 2016
2930028 2016 Radiation Protection Programs Audit Report February 16, 2016

Notifications

50484885
50639291 5
0803788 508 73232
Radioactive Material Shipments Number Title Date
RMS-14-112A Dry Active Waste Solid Material Filter Media October 9, 201 4
RMS-14-112B Dry Active Waste Solid Material Filter Media November 19, 201 4
RMS-14-101 Dry Active Waste Solid for Processing & Disposal October 9, 201 4
RWS-15-003 Solidified Spent Metal Oxide-Resin for Disposal April 01, 201 5
RWS-15-002 Solidified Spent Metal Oxide-Resin for Disposal March 25, 201 5
RWS-15-001 Dewatered Spent Resin February 24, 201 5
RWS-14-003 Solidified Spent Filters in Cement for Disposal December 3, 201 4
RWS-14-002 Solidified Spent Filters in Cement for Disposal July 24, 201 4
RWS-14-001 Solidified Spent Filters in Cement for Disposal
July 16, 201 4
RMS-15-106 Dry Active Waste Solid for Processing & Disposal November 5, 2015
RMS-15-068 Dewatered Spent Resin for Processing & Disposal July 16, 201 5
RMS-15-029 Relief Valves 8010 for Rework May 29, 2015

Miscellaneous Documents

Number Title Revision / Date
2014 Annual Radioactive Effluent Release Report April 29, 2015
2015 Annual Radioactive Effluent Release Report April 27, 2016
Updated Safety Analysis Report

- Chapter 11: Radioactive Waste Management Updated Safety Analysis Report

- Chapter 12: Radiation Protection

Section 4OA1
Performance Indicator Verification

Procedure

Number Title Revision
MA1.ID17 Maintenance Rule Monitoring Program

Notifications

50043028
50664473
50397381
50658301
Other Document Number Title Date Diablo Canyon Consolidated Data Entry 4.0 MSPI Deviation Report Unit 1 and 2
July 2016
The following items are requested for the Occupational/Public Radiation Safety Inspection at Diablo Canyon
DATES: I/P 71124.05

- August 8-12, 2016 I/P 71124.06

- August 8-12, 2016 I/P 71124.07

- August 8-12, 2016 I/P 71124.08

- September 12

-16, 2016 Integrated Report

2016003 Inspection areas are listed in the attachments below.
Please provide the requested information on or before July 19, 2016.
Please submit this information using the same lettering system as below.
For example, all contacts and phone numbers for Inspection Procedure 71124.0

should be in a file/folder titled

"1- A," applicable organization charts in file/folde

r "1- B," etc. If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at least 30 days later than the onsite inspection dates, so the inspectors will have access to the information while writing the report.

In addition to the corrective action document lists provided for each inspection procedure listed below, please provide updated lists of corrective action documents at the entrance meeting.
The dates for these lists should range from the end dates of the original lists to the day of the entrance meeting.
If more than one inspection procedure is to be conducted and the information requests appear to be redundant, there is no need to provide duplicate copies.
Enter a note explaining in which file the information can be found.
If you have any questions or comments, please contact Martin J. Phalen at (817) 817-200-1158 or martin.phal en@nrc.gov.
PAPERWORK REDUCTION ACT STATEMENT
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).
Existing information collection requirements were approved by the Office of Management and Budget, control number 3150

-0011.

5. Radiation Monitoring Instrumentation (71124.05)
Date of Last Inspection:
July 7, 2014
A. List of contacts and telephone numbers for the following areas:
1. Effluent monitor calibration
2. Radiation protection instrument calibration
3. Installed instrument calibrations
4. Count room and Laboratory instrument calibrations
B. Applicable organization charts
C. Copies of audits, self

-assessments, vendor or NUPIC audits for contractor support and LERs, written since date of last inspection

, related to:

1. Area radiation monitors, continuous air monitors, criticality monitors, portable survey instruments, electronic dosimeters, teledosimetry, personnel contamination monitors, or whole body counters
2. Installed radiation monitors
D. Procedure index for:
1. Calibration, use and operation of continuous air monitors, criticality monitors, portable survey instruments, temporary area radiation monitors, electronic dosimeters, teledosimetry, personnel contamination monitors, and whole body counters. 2. Calibration of installed radiation monitors
E. Please provide specific procedures related to the following areas noted below.
Additional Specific Procedures will be requested by number after the inspector reviews the procedure indexes.
1. Calibration of portable radiation detection instruments (for portable ion chambers)
2. Whole body counter calibration
3. Laboratory instrumentation quality control F. A summary list of corrective action documents (including corporate and sub

-tiered systems) written since date of last inspection, related to the following programs:

1. Area radiation monitors, continuous air monitors, criticality monitors, portable survey instruments, electronic dosimeters, teledosimetry, personnel contamination monitors, whole body counters,
2. Installed radiation monitors,
3. Effluent radiation monitors
4. Count room radiation instruments
NOTE: The lists should indicate the significance level of each issue and the search criteria used.
Please provide in document formats which are "searchable" so that the inspector can perform word searches.
G. Offsite dose calculation manual, technical requirements manual, or licensee controlled specifications which lists the effluent monitors and calibration requirements.
H. Current calibration data for the whole body counter's.
I. Primary to secondary source calibration correlation for effluent monitors.
J. A list of the point of discharge effluent monitors with the two most recent calibration dates and the work order numbers associated with the calibrations.
K. Radiation Monitoring System health report for the previous 12 months

.

6. Radioactive Gaseous And Liquid Effluent Treatment (71124.06)
Date of Last Inspection:
July 7, 2014
A. List of contacts and telephone numbers for the following areas:
1. Radiological effluent control
2. Engineered safety feature air cleaning systems
B. Applicable organization charts

. C. Audits, self

-assessments, vendor or NUPIC audits of contractor support, and LERs written since date of last inspection, related to:

1.
Radioactive effluents
2.
Engineered Safety Feature Air cleaning systems
D. Procedure indexes for the following areas
1.
Radioactive effluents
2.
Engineered Safety Feature Air cleaning systems
E. Please provide specific procedures related to the following areas noted below.
Additional Specific Procedures will be requested by number after the inspector reviews the procedure indexes.
1. Sampling of radioactive effluents
2. Sample analysis
3. Generating radioactive effluent release permits
4. Laboratory instrumentation quality control
5. In-place testing of HEPA filters and charcoal adsorbers
6. New or applicable procedures for effluent programs (e.g., including ground water monitoring programs)
F. List of corrective action documents (including corporate and sub

-tiered systems) written since date of last inspection, associated with:

1.
Radioactive effluents
2.
Effluent radiation monitors
3.
Engineered Safety Feature Air cleaning systems
NOTE: The lists should indicate the significance level of each issue and the search criteria used.
Please provide in document formats which are "searchable" so that the inspector can perform word searches.
G. 2014 and 2015 Annual Radioactive Effluent Release Report, or the two most recent reports. H. Current Copy of the Offsite Dose Calculation Manual

. I. Copy of the

2014 and 2015 inter-laboratory comparison results for laboratory quality control performance of effluent sample analysis

, or the two most recent results.

J. Effluent sampling schedule for the week of the inspection

. K. New entries into 10

CFR 50.75(g) files since date of last inspection

. L. Operations department

(or other responsible dept.) log records for effluent monitors removed from service or out of service

. M. Listing or log of liquid and gaseous release permits since date of last inspection

N. A list of the technical specification

-required air cleaning systems with the two most recent surveillance test dates of in

-place filter testing (of HEPA filters and charcoal adsorbers) and laboratory testing (of charcoal efficiency) and the work order numbers associated with the surveillances

. O. System Health Report for radiation monitoring instrumentation.

Also, please provide a specific list of all effluent radiation monitors that were considered inoperable for 7 days or more since November 2011.
If applicable, please provide the relative Special Report and condition report(s).
P. A list of all radiation monitors that are considered §50.65/Maintenance Rule equipment.
Q. A list of all significant changes made to the Gaseous and Liquid Effluent Process Monitoring System since the last inspection.
If applicable, please provide the corresponding UFSAR section in which this change was documented.
R.
A list of any occurrences in which a non

-radioactive system was contaminated by a radioactive system.

Please include any relative condition report(s).
7. Radiological Environmental Monitoring Program (71124.07)
Date of Last Inspection:
July 7, 2014
A. List of contacts and telephone numbers for the following areas:
1. Radiological environmental monitoring
2. Meteorological monitoring
B. Applicable organization charts

. C. Audits, self

-assessments, vendor or NUPIC audits of contractor support, and LERs written since date of last inspection, related to:

1. Radiological environmental monitoring program (including contractor environmental laboratory audits, if used to perform environmental program functions)
2. Environmental TLD processing facility
3. Meteorological monitoring program
D. Procedure index for the following areas:
1. Radiological environmental monitoring program
2. Meteorological monitoring program
E. Please provide specific procedures related to the following areas noted below.
Additional Specific Procedures will be requested by number after the inspector reviews the procedure indexes.
1. Environmental Program Description
2. Sampling, collection and preparation of environmental samples
3. Sample analysis (if applicable)
4. Laboratory instrumentation quality control
5. Procedures associated with the Offsite Dose Calculation Manual
6. Appropriate QA Audit and program procedures, and/or sections of the station's QA manual (which pertain to the REMP)
F. A summary list of corrective action documents (including corporate and sub

-tiered systems) written since date of last inspection, related to the following programs:

1. Radiological environmental monitoring
2. Meteorological monitoring
NOTE: The lists should indicate the significance level of each issue and the search criteria used.
Please provide in document formats which are "searchable" so that the inspector can perform word searches.
G. Wind Rose data and evaluations used for establishing environmental sampling locations
H. Copies of the 2 most recent calibration packages for the meteorological tower instruments.
I. Copy of the
2014 and 2015 Annual Radiological Environmental Operating Report and Land Use Census, and current revision of the Offsite Dose Calculation Manual, or the two most recent reports.
J. Copy of the environmental laboratory

's inter-laboratory comparison program results for

2014 and 2015, or the two most recent results, if not included in the annual radiological environmental operating report

. K. Data from the environmental laboratory documenting the analytical detection sensitivities for the various environmental sample media (i

.e., air, water, soil, vegetation, and milk)

. L. Quality Assurance audits (e.g., NUPIC) for contracted services.

M. Current NEI Groundwater Initiative Plan and status

. N.

Technical requirements manual or licensee controlled specifications which lists the meteorological instruments calibration requirements

. O. A list of Regulatory Guides and/or NUREGs that you are currently committed to relative to the Radiological Environmental Monitoring Program.

Please include the revision and/or date for the committed item and where this can be located in your current licensing basis/UFSAR.
P. If applicable, per NEI 07

-07, provide any reports that document any spills/leaks to groundwater since the last inspection

. 8. Radioactive Solid Waste Processing, and Radioactive Material Handling, Storage, and Transportation (71124.08)

Date of Last Inspection:
July 7, 2014
A. List of contacts and telephone numbers for the following areas:
1. Solid Radioactive waste processing
2. Transportation of radioactive material/waste
B. Applicable organization charts (and list of personnel involved in solid radwaste processing, transferring, and transportation of radioactive waste/materials)
C. Copies of audits, department self

-assessments, and LERs written since date of last inspection related to:

1. Solid radioactive waste management
2. Radioactive material/waste transportation program
D. Procedure index for the following areas:
1. Solid radioactive waste management
2. Radioactive material/waste transportation
E. Please provide specific procedures related to the following areas noted below.
Additional Specific Procedures will be requested by number after the inspector reviews the procedure indexes.
1. Process control program
2. Solid and liquid radioactive waste processing
3. Radioactive material/waste shipping
4. Methodology used for waste concentration averaging, if applicable
5. Waste stream sampling and analysis
F. A summary list of corrective action documents (including corporate and sub

-tiered systems) written since date of last inspection related to:

1. Solid radioactive waste
2. Transportation of radioactive material/waste
NOTE: The lists should indicate the significance level of each issue and the search criteria used.
Please provide in document formats which are "searchable" so that the inspector can perform word searches.
G. Copies of training lesson plans for
49CFR172 subpart H, for radwaste processing, packaging, and shipping.
H. A summary of radioactive material and radioactive waste shipments made from date of last inspection to present

. I. Waste stream sample analyses results and resulting scaling factors for 2014 and 2015 , or the two most recent results.

J. Waste classification reports if performed by vendors (such as for irradiated hardware)

. K. A listing of all onsite radwaste storage facilities.

Please include a summary or listing of the items stored in each facility, including the total amount of radioactivity and the highest general area dose rate.
Although it is not necessary to compile the following information, the inspector will also review:
L. Training, and qualifications records of personnel responsible for the conduct of radioactive waste processing, package preparation, and shipping

.