Summary of Telephone Conference Call Held on October 9, 2012, Between the U.S. Nuclear Regulatory Commission and Entergy Operations, Inc., Concerning Requests for Additional Information Pertaining to the Grand Gulf Nuclear Station
ML12334A586
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 01/03/2013
From: Ferrer N B
License Renewal Projects Branch 1
To:
Office of Nuclear Reactor Regulation
Ferrer N B, 415-1045
References
TAC ME7493
Download: ML12334A586 (7)


Text

...",Po REGUl UNITED STATES

"/"'0'1' NUCLEAR REGULATORY COMMISSION

! WASHINGTON, D.C. 20555*0001 0 t; : r; January 3, 2013 If/. ****-t<

Entergy Operations, Inc.

Grand Gulf Nuclear Station

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 9,2012, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC., CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION (TAC. NO. ME7493) The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Operations, Inc., held a telephone conference call on October 9, 2012, to discuss and clarify the staff's requests for additional information (RAls) concerning the Grand Gulf Nuclear Station license renewal application.

The telephone conference call was useful in clarifying the intent of the staff's RAls. Enclosure 1 provides a listing of the participants and Enclosure 2 contains a listing of the RAls discussed with the applicant, including a brief description on the status of the items. The applicant had an opportunity to comment on this summary.

Nathaniel Ferrer, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-416 As cc w/encls: Listserv TELEPHONE CONFERENCE CALL GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION LIST OF OCTOBER 9, PARTICIPANTS Nate Ferrer Pat Purtscher Dan Widrevitz Ted Ivy Andy Taylor Alan Cox Stan Batch Kirk Ehren Robert Fuller Jacque Lingenfelter Ed Schrull Paul Guinn Bob Carter AFFILIATIONS U.S. Nuclear Regulatory Commission (NRC) NRC NRC Entergy Operations, Inc. (Entergy)

Entergy Entergy Entergy Entergy Entergy Entergy General Electric-Hitachi (GEH) GEH Electric Power Research Institute ENCLOSURE REQUESTS FOR ADDITIONAL INFORMATION (SET LICENSE RENEWAL OCTOBER 9, The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Operations, Inc., held a telephone conference call on October 9, 2012, to discuss and clarify the following requests for additional information (RAls) concerning the license renewal application (LRA). Draft RAI 4.2.4-1 The staff has identified an issue about the applicant's disposition of this TLAA for the circumferential weld inspection relief. SRP-LR Section 4.2.3.1.4 states that if the applicant indicates that relief from circumferential weld examination will be made under 10 CFR 50.55a(a)(3), the applicant will manage this TLAA in accordance with 10 CFR 54.21 (c)(1)(iii).

In contrast, the applicant dispositioned this TLAA in accordance with 10 CFR 54.21 (c)(1 )(ii), inconsistent with the SRP-LR. Justify why the TLAA for the circumferenlial weld inspection relief is dispositioned in accordance with 10 CFR 54.21 (c)(1 )(ii). Discussion:

The applicant stated that request did not allow for the possibility of a revision of the TLAA disposition.

The staff did not intend to preclude a revision to the TLAA disposition and will reword the request as follows: The U.S. Nuclear Regulatory Commission (NRC or the staff) has identified an issue about Entergy Operations, Inc. (the applicant), disposition of this limited aging analysis (TLAA) for the circumferential weld inspection relief. The Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants (SRP-LR) Section 4.2.3.1.4 states that if the applicant indicates that relief from circumferential weld examination will be made under 10 CFR 50.55a(a)(3), the applicant will manage this TLAA in accordance with 10 CFR 54.21 (c)(1 )(iii). In contrast, the applicant dispositioned this TLAA in accordance with 10 CFR 54.21 (c)(1)(ii), inconsistent with the SRP-LR. Explain why the TLAA for the circumferential weld inspection relief is dispositioned in accordance with 10 CFR (c)(1)(ii).

Alternatively, revise the TLAA disposition to be in accordance with 10 CFR 54.21 (c)(1 )(iii). The staff will issue the revised question as a formal RAI. Draft RAI 8.1.11-2a The "detection of aging effects" program element of the GALL Report AMPXI.M9 states that portions of the susceptible components determined to be limiting will be inspected as part of the 10 year in-service inspection (lSI) program during the period of extended operation.

Furthermore, the sample size should be 100 percent of the accessible component population, excluding components that may be in compression during normal operations.

However, during its audit, the staff found that the description of the enhancement to the applicant's BWR Vessels Internals AMP could be taken to be a sampling-based, condition monitoring program where 100 percent of the accessible and susceptible components would not be inspected.

ENCLOSURE 2

-By letter dated June 27, 2012, the staff issued RAI B.1.11-2 requesting that the applicant provide more details so that the nature of the enhancement can be verified by a future license renewal audit. In the applicant's July 25, 2012 response to RAI B.1.11-2, the applicant states: The enhancement stated in LRA Section B.1.11, BWR Vessel Internals, for the management of loss of fracture toughness due to neutron irradiation and thermal aging embrittlement is consistent with the guidance provided in NUREG-1801, Rev. 2,Section XI.M9, BWR Vessel Internals.

This guidance establishes the overall parameters of this aspect oUhe BWR Vessel Internals Program. Details of this aspect ofthe program remain to be determined, including: the specific scope of components susceptible to neutron irradiation and thermal aging embrittlement, the inspection techniques to be used, sequence of inspections to be conducted, and the methods for evaluating inspection results and extrapolating those results to inaccessible components.

These details will be developed as part of the implementation of the program enhancement described in LRA B.1.11. No revisions to UFSAR Supplement A.1.11 are warranted.

Based on its review of the applicant's response, the staff needed additional information to find the applicant's program acceptable.

The staff requests the applicant to address the following items: Provide a plant-specific description of the components made from the cast austenitic stainless steel (CASS), X-750 alloy, precipitation-hardened (PH) martensitic stainless steel, and martensitic stainless steel that are exposed to the reactor coolant and neutron flux environment, Describe if the sample size for the initial inspection of susceptible components will be 100 percent of the accessible components.

If only portions of susceptible components will be inspected, provide justification.

Revise part (b) of the enhancement, as necessary, consistent with the response. Clarify if the augmented inspections will be added to the GGNS 10 year lSI program. If they will not be included, provide justification.

Discussion:

The applicant stated that it was unclear about request (c) the relation to the lSI program. The staff's concern was related to clarifying if the inspections were to be one-time or periodic.

The staff will reword the request as follows: Provide a plant-specific description of the components made from the cast austenitic stainless steel (CASS), X-750 alloy, precipitation-hardened (PH) martensitic stainless steel, and martensitic stainless steel that are exposed to the reactor coolant and neutron flux environment. Describe if the sample size for the initial inspection of susceptible components will be 100 percent of the accessible components.

If only portions of susceptible components will be inspected, provide justification.

-3 Revise part (b) of the enhancement, as necessary, making it consistent with the response.

c. Clarify if the augmented inspections will be a one-time inspection or periodic.

The staff will issue the revised question as a formal RAI. Draft RAI B.1.38-3a Background.

In the GGNS response to RAI B.1.38-3 dated July 26, 2012, the applicant stated that one dosimetry capsule was pulled at the end of the first operating cycle and the results from that capsule have been used in the fluence evaluations performed through operating cycle 13. Since GGNS has been approved to use the ISP to meet the Appendix H requirements (November 4, 2003), no future withdrawals are planned. With input from the BWRVIP, the first cycle flux wire dosimetry results have been shown to be unreliable for reasonable end-of-license fluence projections.

BWRVIP-86, Revision 1, Section 5, includes provisions for ongoing vessel dosimetry for plants that do not have dosimetry capsules tested. The dosimetry activities for the GGNS Reactor Vessel Surveillance Program are adequate and therefore consistent with the . GALL Report. Issue. The staff is concerned that the July 26, 2012, response is not complete.

Request. Justify why the 1 st cycle flux wire dosimetry results are considered to be unreliable for reasonable end-of-license fluence projections.

Discussion:

The applicant stated that it was unclear what justification the request was seeking. The staff's concern was related to obtaining additional details on the omission of the 1 st cyle flux wire dosimetry.

The staff will reword the request as follows: Request. Explain why the 1 51 cycle flux wire dosimetry results are considered to be unreliable for reasonable end-of-license fluence projections.

The staff will issue the revised question as a formal RAI.

January 3, 2013 LICENSEE:

Entergy Operations, Inc. FACILITY:

Grand Gulf Nuclear Station

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 9,2012, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC., CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE GRAND GULF NUCLEAR STATION, LICENSE RENEWAL APPLICATION (TAC. NO. ME7493) The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Operations, Inc., held a telephone conference call on October 9,2012, to discuss and clarify the staff's requests for additional information (RAls) concerning the Grand Gulf Nuclear Station license renewal application.

The telephone conference call was useful in clarifying the intent of the staff's RAls. Enclosure 1 provides a listing of the participants and Enclosure 2 contains a listing of the RAls discussed with the applicant, including a brief description on the status of the items. The applicant had an opportunity to comment on this summary. IRA! Nathaniel Ferrer, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-416

Enclosures:

As stated cc w/encls: Listserv DISTRIBUTION:

See next page ADAMS Accession No'.. ML 12334A586

  • concurred via email OFFICE LA:DLR* PM:RPB1 :DLR BC:RPB1 :DLR PM:RPB1 :DLR NAME IKing NFerrer DMorey NFerrer DATE 12/3/12 12/4/12 12/28/12 113/13 OFFICIAL RECORD

SUMMARY

OF TELEPHOI'JE CONFERENCE CALL HELD OI'J OCTOBER 9,2012, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY OPERATIONS, INC., CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE GRAND GULF NUCLEAR STATION, LICENSE RENEWAL APPLICATION (TAC. NO. ME7493) DISTRIBUTIOI'J:

HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource Ridsl'JrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource NFerrer DDrucker DWrona DMorey AWang RSmith, RIV BRice, RIV DMclntyre, OPA