MONTHYEARGNRO-2011/00064, License Amendment Request to Revise Technical Specification 2.1.1.22011-10-28028 October 2011 License Amendment Request to Revise Technical Specification 2.1.1.2 Project stage: Request ML11350A0532012-01-0404 January 2012 Plan for the Scoping and Screening Regulatory Audit Regarding the Grand Gulf Nuclear Station, Unit 1 License Renewal Application Review Project stage: Other ML12009A1052012-01-18018 January 2012 Plan for the Aging Management Program Regulatory Audit Regarding the Grand Gulf Nuclear Station, Unit 1, License Renewal Application Review Project stage: Other ML12067A2352012-04-0303 April 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12068A2332012-04-0404 April 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12080A1912012-04-11011 April 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Grand Gulf LRA RAI Set 3 Project stage: RAI ML12074A0082012-04-12012 April 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12076A0142012-04-16016 April 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493) Grand Gulf LRA Draft RAI Set 5 Project stage: Draft RAI ML12076A0092012-04-17017 April 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal (TAC ME7493) Grand Gulf LRA Draft RAI Set 6 Project stage: Draft RAI GNRO-2012/00024, Supplemental Information Extended Power Uprate2012-04-18018 April 2012 Supplemental Information Extended Power Uprate Project stage: Request ML12087A0012012-04-18018 April 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC ME7493)Grand Gulf LRA RAI Set 07 Project stage: RAI ML12094A0092012-04-25025 April 2012 Requests for Additional Information for the Review of the Grand Gulf Nulcear Station Licesne Renewal Application Project stage: RAI ML12101A3602012-04-26026 April 2012 Request for Additional Information for the Review of Th Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493) Grand Gulf LRA RAI Set 09 Project stage: RAI ML12104A2192012-04-30030 April 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493)LRA RAI Set 10 Project stage: RAI GNRO-2012/00029, Response to Request for Additional Information (RAI) Regarding the License Renewal Application2012-05-0101 May 2012 Response to Request for Additional Information (RAI) Regarding the License Renewal Application Project stage: Response to RAI ML12109A2132012-05-0303 May 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493) Grand Gulf LRA RAI Set 11 Project stage: RAI ML12115A0902012-05-0909 May 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12115A2762012-05-0909 May 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493)Grand Gulf LRA RAI Set 13 Project stage: RAI GNRO-2012/00036, Response to Request for Additional Information (RAI) Dated April 12, 20122012-05-0909 May 2012 Response to Request for Additional Information (RAI) Dated April 12, 2012 Project stage: Response to RAI ML12117A3832012-05-14014 May 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12118A5392012-05-15015 May 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12125A3732012-05-24024 May 2012 Requests for Additional Information for the Review of the Grant Gulf Nuclear Station License Renewal Application (TAC No. ME7493)Grand Gulf LRA RAI Set 17 Project stage: RAI GNRO-2012/00033, Response to Request for Additional Information (RAI) Dated April 25, 20122012-05-25025 May 2012 Response to Request for Additional Information (RAI) Dated April 25, 2012 Project stage: Response to RAI ML12139A0552012-05-29029 May 2012 LRA RAI Set 19 Project stage: RAI ML12137A2962012-06-0505 June 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493) Grand Gulf LRA RAI Set 18 Project stage: RAI GNRO-2012/00056, Response to Request for Additional Information (RAI) Set 13 Dated May 9, 20122012-06-0505 June 2012 Response to Request for Additional Information (RAI) Set 13 Dated May 9, 2012 Project stage: Response to RAI ML12137A2902012-06-0808 June 2012 Aging Management Programs Audit Report Regarding the Grand Gulf Nuclear Station, Unit 1 (TAC No. ME7493) Grand Gulf AMP Audit Report Cover Letter Project stage: Other ML12151A2652012-06-15015 June 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493) Grand Gulf LRA RAI Set 20 Project stage: RAI ML12165A3872012-06-20020 June 2012 Scoping and Screening Methodology Audit Report Regarding the Grand Gulf Nuclear Station, Unit 1, License Renewal Application Project stage: Other ML12151A3682012-06-20020 June 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12152A3452012-06-22022 June 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (Tac No. ME7493) Project stage: RAI ML12152A3932012-06-22022 June 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI 05000416/LER-2012-004, Regarding Weld Defect Indication Found in Residual Heat Removal System to Reactor Pressure Vessel Boundary Nozzle2012-06-27027 June 2012 Regarding Weld Defect Indication Found in Residual Heat Removal System to Reactor Pressure Vessel Boundary Nozzle Project stage: Request ML12164A1742012-06-27027 June 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493) Grand Gulf LRA RAI Set 26 Project stage: RAI ML12157A0562012-06-27027 June 2012 Request for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application (TAC No. ME7493)Grand Gulf LRA RAI Set 24 Project stage: RAI ML12164A7262012-06-27027 June 2012 RAI for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12179A1372012-07-17017 July 2012 Summary of Telephone Conference Call Between NRC and Entergy Operations, Inc., Concerning Requests for Additional Information Pertaining to Grand Gulf License Renewal Application Project stage: RAI ML12180A5412012-07-17017 July 2012 Summary of Telephone Conference Call Held on March 14, 2012, Between NRC and Entergy Operations, Inc., Concerning RAI Pertaining to the Grand Gulf Nuclear Station, LRA Project stage: RAI ML12188A7062012-07-17017 July 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12188A5162012-07-23023 July 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI GNRO-2012/00080, Response to Request for Additional Information (RAI) Set 24 Dated June 27, 20122012-07-25025 July 2012 Response to Request for Additional Information (RAI) Set 24 Dated June 27, 2012 Project stage: Response to RAI ML12200A1382012-07-27027 July 2012 Requests for Additional Information for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12201B4762012-07-27027 July 2012 LRA RAI Set 30 Project stage: RAI ML12180A4672012-07-31031 July 2012 LRA RAI Telecon 2012-04-03 Project stage: RAI ML12191A1872012-07-31031 July 2012 LRA RAI Telecon 2012-04-13 Project stage: RAI ML12208A2672012-08-0707 August 2012 RAI for the Review of the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12193A0712012-08-15015 August 2012 Summary of Telephone Conference Call Held on 5/15/12 Between the U.S. Nuclear Regulatory Commission and Entergy Operations, Inc., Concerning Requests for Additional Information Pertaining to the Grand Gulf Nuclear Station, LRA Project stage: RAI GNRO-2012/00092, Response to Requests for Additional Information (RAI) Set 28 Dated July 23, 20122012-08-15015 August 2012 Response to Requests for Additional Information (RAI) Set 28 Dated July 23, 2012 Project stage: Response to RAI ML12201B5042012-08-15015 August 2012 Summary of Telephone Conference Call Held on 5/23/12 Between the U.S. Nuclear Regulatory Commission and Entergy Operations, Inc., Concerning the RAIs Pertaining to the Grand Gulf Nuclear Station License Renewal Application Project stage: RAI ML12202A2142012-08-15015 August 2012 5/30/12 Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Entergy Operations, Inc., Concerning Requests for Additional Information Pertaining to the Grand Gulf Nuclear Station, LRA Project stage: RAI 2012-05-24
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON. D.C. 20555-0001 September 7.2012 Mr. Michael Perito Vice President. Site Entergy Operations. Inc.
P.O. Box 756 Port Gibson, MS 39150
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE GRAND GULF NUCLEAR STATION, LICENSE RENEWAL APPLICATION (TAC NO. ME 7493)
Dear Mr. Perito:
Enclosed is a revised schedule for the review of the Grand Gulf Nuclear Station (GGNS),
license renewal application (LRA). The U.S. Nuclear Regulatory Commission (NRC or the staff)
LRA acceptance letter dated December 16, 2011, noted that the LRA did not provide sufficient plant-specific information in the program descriptions for aging management programs (AMPs) where you claim consistency with the Generic Aging Lesson Learned (GALL) Report recommendations and that the staff would need to verify the changes resulting from the pending extended power up rate (EPU) amendment, the outcome of which was indeterminate at that time. The letter also noted that the lack of sufficient plant-specific information and the pending EPU amendment would likely challenge staff resources. In the course of the GGNS safety review, the staff has required additional resources during audits and in preparation of requests for additional information (RAls) to verify AMP consistency and to verify changes resulting from your recently-approved EPU amendment. Therefore, the staff's safety review schedule has been revised to account for the need to process additional RAls beyond what is expected and the need to issue a greater number than expected of followup RAls based on the quality of initial responses.
Additionally. the staff noted in its letter to you dated August 28,2012, that additional followup RAls related to severe accident mitigation alternatives were needed. As discussed with Mr. Buckley of your staff. a mutually agreeable date for the response is within 45 days from the letter dated August 28, 2012. The staff has extended the environmental review schedule to accommodate review of your responses to these followup RAls. Furthermore, the final licensing decision has been revised to a to-be-determined status pending resolution of the Commission direction on waste confidence.
-2 If you have any questions on the revised schedule, please contact Mr. Nathaniel Ferrer, Project Manager, for the review of the GGNS LRA, by telephone at 301-415-1045 or bye-mail at nathaniel.ferrer@nrc.gov.
Sincerely.
~/J1J&wry(
Melanie A. Galloway, Acting ~ctor Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-416
Enclosure:
As stated cc w/encl: Listserv
GRAND GULF NUCLEAR STATIONLICENSE RENEWAL APPLICATION REVISION OF SCHEDULE Milestone Schedule Actual Receive license renewal application (LRA) 11/1/2011 11/1/2011 Publish Federal Register Notice (FRN) - LRA availability f11/2011 11/17/2011 Publish FRN - acceptancelrejection and opportunity for hearing 12/2011 12/27/2011 Publish FRN - environmental scoping meeting 12/2011 12/29/2011 Audit - Scoping & Screening Methodology 1/9/2012 1/9/2012 Audit - Aging Management Programs 1/23/2012 1/23/2012 Public Meeting - License Renewal Overview and Environmental Scoping meeting 1/31/2012 1/31/2012 Deadline for filing hearing requests and petitions for intervention 2/2012 2/27/2012 Environmental scoping period ends 2/2012 2/27/2012 Audit - Environmental 3/26/2012
~h~h~~~ I Inspection - Regional 8/2012 8/6/2012 Issue safety evaluation report (SER) with open items I
1/2013 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 3/2013 Issue draft supplemental environmental impact statement (SEIS) 2/2013 Publish FRN - draft SEIS available for comments 3/2013 Public Meeting - draft SEIS meeting 4/2013 End of draft SEIS comment period 5/2013 Issue final SER 7/2013 ACRS full committee meeting 9/2013 Issue final SEIS 8/2013 U.S. Environmental Protection Agency FRN Published - availability of final SEIS 9/2013 Decision - Director, NRR TBD Commission decision (if hearing is granted)
TBD ENCLOSURE
- 2 If you have any questions on the revised schedule, please contact Mr. Nathaniel Ferrer, Project Manager, for the review of the GGNS LRA, by telephone at 301-415-1045 or bye-mail at nathaniel.ferrer@nrc.gov.
Sincerely, IRA!
Melanie A. Galloway, Acting Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-416
Enclosure:
As stated cc w/encl: Listserv DISTRIBUTION: See next page ADAMS Accession No.: ML12242A545 OFFICE LA:DLR PM: RPB1:DLR BC:RPB1 :DLR BC: RPB2: DLR D:DLR NAME IKing NFerrer DMorey DWrona MGalioway E
9/04/12 9/04/12 9/5112 9/7/12 OFFICIAL RECORD COpy
Letter to M. Perito From M. Galloway dated September 7,2012
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE GRAND GULF NUCLEAR STATION, LICENSE RENEWAL APPLICATION (TAC NO. ME7493)