Revision of Schedule for the Conduct of Review of the Grand Gulf Nuclear Station, LRA
ML12242A545
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 09/07/2012
From: Galloway M
Division of License Renewal
To: Mike Perito
Entergy Operations
Ferrer N, 415-1045
References
TAC ME7493
Download: ML12242A545 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON. D.C. 20555-0001 September 7.2012 Mr. Michael Perito Vice President. Site Entergy Operations. Inc.

P.O. Box 756 Port Gibson, MS 39150

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE GRAND GULF NUCLEAR STATION, LICENSE RENEWAL APPLICATION (TAC NO. ME 7493)

Dear Mr. Perito:

Enclosed is a revised schedule for the review of the Grand Gulf Nuclear Station (GGNS),

license renewal application (LRA). The U.S. Nuclear Regulatory Commission (NRC or the staff)

LRA acceptance letter dated December 16, 2011, noted that the LRA did not provide sufficient plant-specific information in the program descriptions for aging management programs (AMPs) where you claim consistency with the Generic Aging Lesson Learned (GALL) Report recommendations and that the staff would need to verify the changes resulting from the pending extended power up rate (EPU) amendment, the outcome of which was indeterminate at that time. The letter also noted that the lack of sufficient plant-specific information and the pending EPU amendment would likely challenge staff resources. In the course of the GGNS safety review, the staff has required additional resources during audits and in preparation of requests for additional information (RAls) to verify AMP consistency and to verify changes resulting from your recently-approved EPU amendment. Therefore, the staff's safety review schedule has been revised to account for the need to process additional RAls beyond what is expected and the need to issue a greater number than expected of followup RAls based on the quality of initial responses.

Additionally. the staff noted in its letter to you dated August 28,2012, that additional followup RAls related to severe accident mitigation alternatives were needed. As discussed with Mr. Buckley of your staff. a mutually agreeable date for the response is within 45 days from the letter dated August 28, 2012. The staff has extended the environmental review schedule to accommodate review of your responses to these followup RAls. Furthermore, the final licensing decision has been revised to a to-be-determined status pending resolution of the Commission direction on waste confidence.

-2 If you have any questions on the revised schedule, please contact Mr. Nathaniel Ferrer, Project Manager, for the review of the GGNS LRA, by telephone at 301-415-1045 or bye-mail at nathaniel.ferrer@nrc.gov.

Sincerely.

~/J1J&wry(

Melanie A. Galloway, Acting ~ctor Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-416

Enclosure:

As stated cc w/encl: Listserv

GRAND GULF NUCLEAR STATIONLICENSE RENEWAL APPLICATION REVISION OF SCHEDULE Milestone Schedule Actual Receive license renewal application (LRA) 11/1/2011 11/1/2011 Publish Federal Register Notice (FRN) - LRA availability f11/2011 11/17/2011 Publish FRN - acceptancelrejection and opportunity for hearing 12/2011 12/27/2011 Publish FRN - environmental scoping meeting 12/2011 12/29/2011 Audit - Scoping & Screening Methodology 1/9/2012 1/9/2012 Audit - Aging Management Programs 1/23/2012 1/23/2012 Public Meeting - License Renewal Overview and Environmental Scoping 1/31/2012 1/31/2012 meeting Deadline for filing hearing requests and petitions for intervention 2/2012 2/27/2012 Environmental scoping period ends 2/2012 2/27/2012 Audit - Environmental 3/26/2012

~h~h~~~ I Inspection - Regional 8/2012 8/6/2012 Issue safety evaluation report (SER) with open items I 1/2013 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee 3/2013 meeting Issue draft supplemental environmental impact statement (SEIS) 2/2013 Publish FRN - draft SEIS available for comments 3/2013 Public Meeting - draft SEIS meeting 4/2013 End of draft SEIS comment period 5/2013 Issue final SER 7/2013 ACRS full committee meeting 9/2013 Issue final SEIS 8/2013 U.S. Environmental Protection Agency FRN Published - availability of final 9/2013 SEIS Decision - Director, NRR TBD Commission decision (if hearing is granted) TBD ENCLOSURE

- 2 If you have any questions on the revised schedule, please contact Mr. Nathaniel Ferrer, Project Manager, for the review of the GGNS LRA, by telephone at 301-415-1045 or bye-mail at nathaniel.ferrer@nrc.gov.

Sincerely, IRA!

Melanie A. Galloway, Acting Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-416

Enclosure:

As stated cc w/encl: Listserv DISTRIBUTION: See next page ADAMS Accession No.: ML12242A545 OFFICE LA:DLR PM: RPB1:DLR BC:RPB1 :DLR BC: RPB2: DLR D:DLR NAME IKing NFerrer DMorey DWrona MGalioway E 9/04/12 9/04/12 9/5112 9/7/12 OFFICIAL RECORD COpy

Letter to M. Perito From M. Galloway dated September 7,2012

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE GRAND GULF NUCLEAR STATION, LICENSE RENEWAL APPLICATION (TAC NO. ME7493)