MONTHYEARML24297A6392024-10-30030 October 2024 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML24128A2402024-05-0808 May 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24093A2502024-04-24024 April 2024 Management Directive 8.3 Evaluation for Waterford Steam Electric Station, Unit 3, Main Transformer Fire and Resulting Automatic Reactor Trip on March 21, 2024 ML24088A2672024-04-0808 April 2024 Management Directive 8.3 Evaluation for Waterford Steam Electric Station, Unit 3, Manual Trip on March 16, 2024 ML24088A2282024-04-0202 April 2024 License Renewal Application ML24019A0342024-01-30030 January 2024 Public Meeting Summary - 01-04-2024 - Comanche Peak LRA - Structures Monitoring Program ML23279A1052023-10-0606 October 2023 Memorandum from the Secretary to the Board and Parties ML23047A3822023-03-21021 March 2023 Summary of December 15, 2022 Periodic Advanced Reactor Stakeholder Public Meeting ML22349A5052023-02-0808 February 2023 Results of a Reactor Oversight Process Self Assessment Effectiveness Review of the Recommendations from IP 95003 at Arkansas Nuclear One ML22304A1912022-11-23023 November 2022 – Aging Management Audit Plan Regarding the License Renewal Application Review ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML21259A1492021-10-26026 October 2021 CPNPP, Unit Nos. 1 and 2 - Meeting Summary for Environmental Pre Submittal Meeting for Initial License Renewal Application on September 21, 2021 ML21295A0882021-10-21021 October 2021 Fiscal Year 2021 Research and Test Reactors Inspection Program Completion Status ML21288A0392021-10-18018 October 2021 September 14, 2021, Summary of Public Workshop on Scale/Melcor Source Term Demonstration Project - Pebble-Bed Molten-Salt-Cooled Reactor ML21259A1402021-10-0505 October 2021 Meeting Summary for Safety Pre Submittal Meeting for Initial License Renewal Application on September 21, 2021 ML21273A1772021-10-0101 October 2021 Fiscal Year 2021 Research and Test Reactors Inspection Program Completion Status ML21181A3352021-07-0101 July 2021 June 23, 2021, Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21176A1292021-06-25025 June 2021 CPNPP FFD Inspection Doc Request 2021 ML21174A0942021-06-23023 June 2021 Reactor Trip on June 7, 2021 - Management Directive 8.3 Screening ML21158A2232021-06-0808 June 2021 Meeting Summary for Ticap Workshop 3 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21132A2952021-05-14014 May 2021 Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21124A0052021-05-10010 May 2021 Memo for Environmental Pre-Submittal Meeting for Initial License Renewal Application ML21085A8652021-04-0808 April 2021 Summary of March 17, 2021, Category 1 Public Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06, Rev. 2, Licensing Processes (EPID L-2020-LLA-0164) Non ML20325A3212020-12-17017 December 2020 Summary of November 4, 2020, Nonproprietary - Category 1 Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06, Rev. 2, Licensing Processes (Redacted) ML20337A1572020-12-0808 December 2020 Summary of Teleconference Meeting with Entergy Operations, Inc. to Discuss the Forthcoming Supplemental Response Concerning Generic Letter 2004-02 for Arkansas Nuclear One, Units 1 and 2 ML20150A4212020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Entergy Nuclear Company, LLC Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Grand Gulf ISFSI ML20150A4372020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Entergy Operations, Inc., Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Waterford 3 ISFSI ML20149K5412020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Entergy Operations, Inc. Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Arkansas Nuclear One I ML20218A7512020-08-0707 August 2020 Summary of June 25, 2020 Teleconference with Grand Gulf Nuclear Station ML20057G5182020-02-27027 February 2020 Notice of Enforcement Conference with Waterford 3 Steam Generating Station to Discuss Apparent Violations of NRC Requirements Related to Waterford 3 Steam Electric Station'S Radiation Safety and Security Program ML19204A2972019-07-31031 July 2019 Memo to Management Review Board Arkansas Follow-up FY2019 Proposed Final Report ML19182A3562019-07-23023 July 2019 Quarterly Report on the Status of Public Petitions Under Title 10 of the Code of Federal Regulations, Section 2.206 - April 1 to June 30, 2019 ML19204A1492019-07-16016 July 2019 FEMA Region IV Memo 07-16-19: Hurricane Barry Preliminary Capabilities Assessment ML19204A1482019-07-15015 July 2019 FEMA Region VI Memo 07-15-19: Hurricane Barry Preliminary Capabilities Assessment ML19120A3382019-04-26026 April 2019 Memo to File Environmental Assessment and Finding of No Significant Impact for Luminant Generation Company, Llc'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and 10 CFR 72.30(c) for Comanche Peak ISFSI ML19102A0162019-04-16016 April 2019 4/10/2019 Summary of Public Teleconference Regarding Potential Submission of a Relief Request to Allow Use of Carbon Fiber Reinforced Polymer for Selected Piping Repairs at South Texas, Units 1 and 2 ML19018A2692019-03-12012 March 2019 Safety Evaluation Input for Grand Gulf Nuclear Station Unit 1, License Amendment Request to Implement Technical Specification Task Force-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control ML18346A1832019-01-0606 January 2019 FO Closure Audit Summary ML18257A0382018-11-23023 November 2018 Communications Plan Regarding the Renewal of the Waterford Steam Electric Station, Unit 3, Renewed Operating License ML18304A2902018-11-19019 November 2018 STP ISFSI PSP Rev 23 Review ML18303A2692018-10-30030 October 2018 License Renewal Application ML18289A5652018-10-16016 October 2018 Memorandum to D. White Technical Assistance Request - Review of Physical Security Plan for the South Texas Project Generating Station Independent Spent Fuel Storage Installation (CAC No.001027) ML18221A6322018-08-15015 August 2018 Eicb Safety Evaluation - Comanche Peak Nuclear Power Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.3.2 Engineered Safety Feature Actuation System Instrumentation Docket/Epid 000976/05000446/L-2018-LLA-0 ML18173A0082018-06-20020 June 2018 Cancelling Numerous Inspection Report Numbers IR 05000382/20170112017-12-20020 December 2017 NRC Special Inspection Report 05000382/2017011 ML17233A0082017-08-21021 August 2017 Notification of Administrative Correction to Renewed Facility Operating License ML17187A1782017-07-0606 July 2017 License Renewal Application ML17153A0012017-06-0606 June 2017 Staff Observations of Testing for Generic Safety Issue 191 During a May 10 to May 11, 2017, Trip to the Alden Test Facility for Control Components Inc. Strainer Tests 2024-05-08
[Table view] |
Text
February 23, 2004 MEMORANDUM TO: Robert A. Gramm, Chief, Section 1 Project Directorate IV Division of Licensing Project Management FROM: Dana M. Baxley, Secretary, Section 1/RA/
Project Directorate IV Division of Licensing Project Management
SUBJECT:
DRAFT INFORMATION FOR OCTOBER 3, 2003, TO NOVEMBER 24, 2003 The U. S. Nuclear Regulatory Commission (NRC) staff has received and/or transmitted the attached draft information and draft request for additional information. This information was received and/or transmitted for the purpose of facilitating ongoing, unrelated, reviews and was not used by the NRC staff for any regulatory decisions. The purpose of this memorandum is to place the information in the Public Document Room.
Docket Nos. 50-368, 50-382, 50-416, 50-445, 50-446, 50-498, and 50-499 Attachments: 1. E-Mail on October 3, 2003 (50-368)
- 2. E-Mail on October 5, 2003 (50-368)
- 3. E-Mail on October 6, 2003 (50-368)
- 4. E-Mail on October 6, 2003 (50-298)
- 5. E-Mail on October 7, 2003 (50-368)
- 6. E-Mail on October 7, 2003 (50-368)
- 7. E-Mail on October 8, 2003 (50-416)
- 8. E-Mail on October 8, 2003 (50-368)
- 9. E-Mail on October 8, 2003 (50-368)
- 10. E-Mail on October 15, 2003 (50-416)
- 11. E-Mail on October 15, 2003 (50-368)
- 12. E-mail on October 16, 2003 (50-445 & 50-446)
- 13. E-Mail on October 20, 2003 (50-416)
- 14. E-Mail on October 22, 2003 (50-498 & 50-499)
- 15. E-Mail on October 22, 2003 (50-368)
- 16. E-Mail on October 28, 2003 (50-416)
- 17. E-Mail on October 29, 2003 (50-498 & 50-499)
- 18. E-Mail on November 4, 2003 (50-382)
- 19. E-Mail on November 5, 2003 (50-445 & 50-446)
- 20. E-Mail on November 24, 2003 (50-416)
February 23, 2004 MEMORANDUM TO: Robert A. Gramm, Chief, Section 1 Project Directorate IV Division of Licensing Project Management FROM: Dana M. Baxley, Secretary, Section 1/RA/
Project Directorate IV Division of Licensing Project Management
SUBJECT:
DRAFT INFORMATION FOR OCTOBER 3, 2003, TO NOVEMBER 24, 2003 The U. S. Nuclear Regulatory Commission (NRC) staff has received and/or transmitted the attached draft information and draft request for additional information. This information was received and/or transmitted for the purpose of facilitating ongoing, unrelated, reviews and was not used by the NRC staff for any regulatory decisions. The purpose of this memorandum is to place the information in the Public Document Room.
Docket Nos. 50-368, 50-382, 50-416, 50-445, 50-446, 50-498, and 50-499 Attachments: 1. E-Mail on October 3, 2003 (50-368)
- 2. E-Mail on October 5, 2003 (50-368)
- 3. E-Mail on October 6, 2003 (50-368)
- 4. E-Mail on October 6, 2003 (50-298)
- 5. E-Mail on October 7, 2003 (50-368)
- 6. E-Mail on October 7, 2003 (50-368)
- 7. E-Mail on October 8, 2003 (50-416)
- 8. E-Mail on October 8, 2003 (50-368)
- 9. E-Mail on October 8, 2003 (50-368)
- 10. E-Mail on October 15, 2003 (50-416)
- 11. E-Mail on October 15, 2003 (50-368)
- 12. E-mail on October 16, 2003 (50-445 & 50-446)
- 13. E-Mail on October 20, 2003 (50-416)
- 14. E-Mail on October 22, 2003 (50-498 & 50-499)
- 15. E-Mail on October 22, 2003 (50-368)
- 16. E-Mail on October 28, 2003 (50-416)
- 17. E-Mail on October 29, 2003 (50-498 & 50-499)
- 18. E-Mail on November 4, 2003 (50-382)
- 19. E-Mail on November 5, 2003 (50-445 & 50-446)
- 20. E-Mail on November 24, 2003 (50-416)
Distribution:
Public RidsNrrDlpmLpdiv1 (RGramm) RidsNrrPMBVaidya RidsNrrPMMHoncharik RidsNrrPMTAlexion RidsNrrPMMThadani Package: ML040220241 Attachment 1: ML033440273 Attachment 2: ML033440280 Memo: ML040220232 Attachment 3: ML033440281 Attachment 4: ML033440288 : ML033440292 Attachment 6: ML033440298 Attachment 7: ML033440301 : ML033440304 Attachment 9: ML033440308 Attachment 10: ML033440311 1: ML033440315 Attachment 12: ML033440319 Attachment 13: ML033440324 4: ML033440328 Attachment 15: ML033440333 Attachment 16: ML033440339 7: ML033440343 Attachment 18: ML033440349 Attachment 19: ML033440352 0: ML033440355 *SEE PREVIOUS CONCURRENCE OFFICE PDIV-1/SEC PDIV-1/PM* PDIV-1/PM* PDIV-1/PM PDIV-1/PM* PDIV-1/PM NAME DBaxley DJaffe TAlexion NKalyanam MThadani BVaidya DATE 1/30/04 1/22/04 1/22/04 2/5/04 1/23/04 1/30/04 C:\ORPCheckout\FileNET\ML040220232.wpd