Rev to ONS Selected Licensee Commitments (SLC) Manual, Revising SLC 16.6.1, Containment Leakage Tests to Reflect Current Plant Configuration & Update Testing Info
ML20095H129
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 12/05/1995
From: Nix D
DUKE POWER CO.
To:
Shared Package
ML16141A984 List:
References
PROC-951205, NUDOCS 9512220141
Download: ML20095H129 (13)


Text

. 1 1

december 5, 1995 l To: Manual Holders

Subject:

Oconee SLC Revision Please revise your SLC Manual according to instructions. This SLC 16.6.1 Containment Leakage Tests is being revised to reflect current plant configuration and to update testing information.

Please update your copy of this manual as follows:

Remove These Pages Insert These Pages:

LOEP 1 LOEP 1 LOEP 2 LOEP 2 16.6-1 16.6-1 <

16.6-2 16.6-2 16.6-3 16.6-3 16.6-4 16.6-4 16.6-5 16.6-5 16.6-6 16.6-6 16.6-7 16.6-7 16.6-8 16.6-8 16.6-9 16.6-9 16.6-10 1

l Any questions concerning this revision may be directed to David Nix at 803- I 885-3634.

l i

David Nix.

Regulatory Compliance By: Conice Breazeale Regulatory Compliance t-I I

1 I

~ 9512220141 951205 l ADOCK 05000269 PDR p,,,._ PDR j

Oconee Nuclear Station Selected Licensee Commitments List of Effective Pages Page Revision Date Cover Letter LOEP 1 11/29/95 LOEP 2 11/29/95 LOEP 3 10/5/95 LOEP 4 10/5/95 LOEP 5 10/5/95 LOEP 6 10/5/95 LOEP 7 10/5/95 Tab 16.0 16.0-1 1/9/95 16.0-2 10/5/95 16.0-3 10/5/95 Tab 16.1 16.1-1 Tab 16.2 16.2-1 16.2-2 l

16.2-3 l Tab 16.3 ,

16.3-1 2/91 Tab 16.5 16.5-1 3/91 16.5-2 2/17/94 16.5-3 2/17/94 16.5-4 2/17/94 16.5-5 2/17/94 11/29/9f:

l Page 1

.- .~ . _ _ . - . . . . . - -~- . _ _ . _ _ . . . - . - . - - - . - .

4 Nace No. Revision Date 16.5-7 2/91 16.5-8 2/91 16.5-9 7/92 16.5-10 7/92 16.5-11 7/92 16.5-12 7/92 16.5-13 7/92 16.5-14 7/92 16.5-15 7/97 16.5-16 7/92 16.5-17 7/92 16.5-18 7/92 16.5-19 7/92 Tab 16.6 l

16.6-1 11/29/95 16.6-2 11/29/95 16.6-3 11/29/95  ;

i 16 6-4 11/29/95 )

l 16.6-5 11/29/95 16.6-6 11/29/95 l 16.6-7 11/29/95 16.6-0 11/29/95 16.6-9 11/29/95 16.6-10 11/29/95 Tab 16.7 I 16.7-1 16.7-2 11/29/95 Page 2

_ _ _ . _ . . . _ . _ _ . _ . . _ _ _ . - . _ _ _ . ~ . . . _ . _ . _ . _ . . _ _ _ . . _

's 4

16.6 ENGINFFRFn SAFETY FEATURES 16.6.1 CONTAINMENT LEAKAGE TESTS COMMITMENT The loca) l sk rate shall be measured for the containment penetrations listed in Table 16.6-1 in accordance with Technical Specification 4.4.1.2.

APPLICABILITY: ,

Applies to containment leakage 1

1 ACTION:

Not applicable SURVEILLANCE:

See Technical Specification 4.4.1.2 -

BASES:

This commitment establishes t. ilist of penetrations that require local leak rate testing in accordance with Technical Specification 4.4.1.2. This list was removed from the Technical Specifications in accordance with the guidance in NRC Generic Letter 91-08.

REFERENCES:

1.- 10 CFR 50, Appendix J

2. NRC Generic Letter 91-08
3. FSAR Topic Nos. 3.8.1.7.4, 6.2.3, and 6.2.4.

STATION MANAGER APPROVAL DATE l1-R-15 16.6-1 11/29/95

TABLE 16.6-1 LIST OF PENETRATIONS WITH 10CFR50, ~

, APPENDIX J TEST REQUIREMENTS ,

PENETRATION TYPE A TEST LOCAL LEAK NUMBER. SYSTEM SYSTEM CONDITION TEST REMARKS-i 1 Pressurizerliquid sample line Note 1 Type C Note 2,7b ,

(Unit 1 only)  !

2 OTSG A Sampleline Note 1 Type C Note 7b ]

3 Component Cooling inlet line Note 1 Type C . Note 3, 7d 4 OTSG B drain line Note 1 None required Note 7b 5a RB normal sump drain line Note 10 Type C Note 7a,7b,9 Sb Post Accident Liquid Sample Line Note 1 None Required Note 2,7c j 6 Letdown line Note 1 Type C Note 2, 7b .

7 RC Pump seal return line Note 1 Type C Note 7b,9(Units 2 & 3)

Note 3,7b,9 (Unit 1) -

l t

8a Pressurizer Aux. Spray Line Not Vented None Required Note 5,7d i

i 8b Loop A nozzle warming line Not Vented None required Note 5,7d i 9 RCS normal makeup line and HP Not Vented None required Note 5 l l injection 'A' loop j l I 10a RC Pump B1 sealinjection Not Vented Type C Note 5, 7d, 9,12 i

f 16.6-2 11/29/95  ;

, r I

s

_m____...___ . . _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ . _ _ . _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ -

i TABLE 16.6-1 l LIST OF PENETRATIONS WITH 10CFR50, . ;

f APPENDIX J TEST REQUIREMENTS ,

PENETRATION TYPE A TEST LOCAL LEAK ]

NUMBER SYSTEM SYSTEM CONDITION TEST REMARKS  !

10b RC Pump B2 sealinjection Not Vented Type C Note 5,7d,9,12 I 11a Fuel transfer tube cover Not Vented Type B Note 6a,11 11b RC Makeup Pump suction Note 1 Type C Note 2 l t

llc Fuel transfer tube drain Not Vented Type C Note 5 12a Fuel transfer tube cover Not Vented Type B Note 6a,11 12b RC Makeup Pump discharge Note 1 Type C Note 2 13 RB Sprayinlet line Not Vented None required Note 5,7d [

14 RB Spray inlet line Not Vented None required Note 5,7d  !

i 15 LPI and DHR inlet line Not Vented None required Note 4,5 16 LPI and DHR inlet line Not Vented None required Note 4,5 I l

17 OTSG B Emergency FDW line Not Vented None required Note 5,7d l t

i 18 Quench tank vent line Note 1 Type C Note 3, 7b,9 19 RB purge inlet line Vented Type C Note 7a,7b,9 [

I f

16.6-3 11/29 S 5 l 3

f

TABLE 16.6-1 l LIST OF PENETRATIONS WITH 10CFR50, ,-

APPENDIX J TEST REQUIREMEN FS ,

PENETRATION TYPE A TEST LOCAL LEAK -

NUMBER SYSTEM SYSTEM CONDITION TEST REMARKS 20 RB purge outlet line Vented Type C Note 7a,7b,9 21 LPSW to RC Pump motors and lube Not Vented None required Note 7b, 9 oil coolers inlet 22 LPSW from RC Pump motors and Not Vented Type C Note 7b lube oil coolers outlet 23a RC Pump Al sealinjection Not Vented Type C Note 5,7d,9 23b RC Pump A2 sealinjection Not Vented Type C Note 5,7d,9 24a RB H2Analyzer Train A Vented Type C Note 7c 24b RC H2 Analyzer Train A Vented Type C Note 7c 25 OTSG B Feedwater line Not Vented None required Note 5 26 OTSG A Main steam line Not Vented None required Note 5 27 OTSG A Feedwaterline Not Vented None required Note 5 28 OTSG B Main steam line Not Vented None required Note 5 16.6-4 11/29/95

TABLE 16.6-1 LIST OF PENETRATIONS WITH 10CFR50, ,-

' APPENDIX J TEST REQUIREMENTS ,

PENETRATION TYPE ATEST LOCAL LEAK NUMBER SYSTEM SYSTEM CONDITION TEST REMARKS 29 Quench tank drain line Note 1 Type C Note 3,7b,9 30, LPSW for RB Not Vented None required Note 5 31, Cooling units 32 inlet line 33, LPSW for RB Not Vented None required Note 5 34, cooling units 35 outlet line 36, RB emergency sump recirculation line Not Vented None required - Note 5 37 38 Quench tank coolerinlet line Note 1 Type C Note 2, 7d,12 39a (Unit 2,3 CFT Vent Line Note 1 None Required Note 3 only) 39b HP Nitrogen supply Note 1 Type C - Note 2,3, 13 40 RB emergency sump drain line Note 1 None required 41 Instrument air supply & ILRT Vented None required Note 3 verification line 16.6-5 11/29/95

1

. 1 TABLE 16.6-1 LIST OF PENETRATIONS WITH 10CFR50, ,-

APPENDIX J TEST REQUIREMENTS ,

PENETRATION TYPE A TEST LOCAI, LEAK NUMBER SYSTEM SYSTEM CONDITION TEST REMARKS '

42a RB H2Analyzer Train B Vented Type C Note 7c 42b RB H2Analyzer Train B Vented Type C Note 7c 43 OTSG A drain line Note 1 None required Note 7b 44 Component cooling to control rod Note 1 Type C Note 3,7d drive inlet line 45a ILRT instrument line Vented Type C Note 3, 7a 45b ILRT instrument line Vented Type C Note 3, 7a 45c (Units 2 & 3) ILRT instrument line Vented Type C Note 3, 7a 46 Reactor head-wash filtered water inlet Note 1 Type C Note 3,9 47 (Unit I only) Demineralized water supply to RC Note 1 Type C Note 3, 7d pump seal vents 48 Breathing air inlet Vented Nonc required Note 3 49 (Unit I only) LP Nitrogen supply Vented None required Note 3 16.6-6 11/29/95

TABLE 16.6-1 LIST OF PENETRATIONS WITH 10CFR50, ,-

APPENDIX J TEST REQUIREMENTS ,

PENETRATION TYPE A TEST LOCAL LEAK NUMBER SYSTEM SYSTEM CONDITION TEST REMARKS -

50 OTSG A Emergency FDW line Not Vented None required Note 5 51 ILRT Pressurization line Vented None required Note 6a,7a 52 HP Injection to 'B' loop Not Vented None required Note 5 53a (All) HP Nitrogen supply to 'A' core flood Note 1 Type C Note 2, 3, 7d,13 ,

tank 53b (Units 2,3) LP Nitrogen supply Vented None required Note 2,3, 7d 54 Component cooling outlet line Note 1 Type C Note 3, 7b, 9(8) '

55 Demineralized water supply Note 1 Type C (Unit 1) Note 3,12 (Unit 2,3) Note 3,9 56 Spent fuel canal fill and drain Note 1 None required Note 3 57 (Unit I only) DHR return line Not vented None required Note 4 58a (Unit 2,3) Note 2, 7b Pressurizer sample line Note 1 Type C I

58b (All) OTSG B sample line Note 1 Type C Note 7b i

r 16.6-7 11/29/95 l

1

- . - _ _ _ . _ _ _ - _ _ _ . _ _ _ . - _ - . _ . - - _ -_ . _ _ _ . - _ _ _ _ _ _ = _ _ . _ _ _ _ _ _ - - _ - . - _ - _ - - - - - - _ - . - _ _ _-- _ _ _ _ _ _ _ _ _ .

1 TABLE 16.6-1 LIST OF PENETRATIONS WITH 10CFR50, ,-

APPENDIX J TEST REQUIREMENTS , 4 TYPE A TEST LOCAL LEAK PENETRATION SYSTEM SYSTEM CONDITION TEST REMARKS NUMBER 59 CF tank sample line Note 1 None required Note 2 ,

60 RB sample line (outlet) Note 1 Type C Note 2, 7b, 9 61 RB sample line (inlet) Note 1 Type C Note 2,7b,9 62 (Units 2,3 DHR return line Not Vented None required Note 4 l Only) 90 Personnel hatch Vented Type B Note 6b 91 Equipment hatch Vented Type B Note 6c 92 Emergency hatch Vented Type B Note 6b 101 through 105 Electrical Penetrations Vented Type B Note 6a,12 l

! 16.6-8 11/29/95

L a

1 TABLE 16.6-1 (NOTES) - ,

[

NOTE 1 All vented systems shall be drained of water or other fluids to the extent necessary to assure exposure of the system 7 l -

containment isolation valves to containment atmosphere and to assure they will be subjected to the test differential -  ;

pressure.

NOTE 2 Fluid system that is r :t of the reactor coolant pressure boundary or open directly to the containment atmosphere under post-accident conditons (vented to containment atmosphere during Type A test).  !

NOTE 3 Closed system inside containment that penetrates containment and postulated to rupture as a result of a loss of coolant ,

accident (vented to containment atmosphere during Type A test).  ;

i i NOTE 4 System required to maintain the plant in a safe condition during the test (need not be vented). j NOTE 5 System normally filled with water or under pressure and operating under post-accident condition (need not be vented). i

NOTE 6 a. Containment penetration whose design incorporates resilient seals, gaskets, or sealant compounds, piping penetration filled with expansion bellows, and electrical penetrations fitted with flexible metal seal assemblies.
b. Air lock door seals including door operating mechanisms which are part of the containment pressure boundary. ,

l c. Doors with resilient seals or gaskets except for seal welded doors.

d. Components other than those above which must meet the acceptance criteria of Type B tests.

NOTE 7 a. Isolation valves provide a direct connection between the inside and outside atmospheres of the primary reactor i containment under normal operation, such as purge and ventilation, vacuum relief, and instrument valves.

b. Isolation valves are required to close automatically upon receipt of a containment isolation signal in response to controls intended to affect containment isolation.

l i

16.6-9 11/29/95 1

o

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ___ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ . . _ ___ _ ____ _ _ ____ _ __. _ _ _ . . -__ ____ _ . . _ _ _ _ _ _ _ . ________t

TABLE 16.6-1 (NOTES) ,-

c. Isolation valves are required to operate intermittently under post accident conditions.
d. Check valve (s) used for containment isolation.

NOTE 8 DELETED NOTE 9 Reverse direction test ofinside containment isolation valve authorized. Leakage results are conservative.

NOTE 10 System is submerged during post-accident conditions and performance of Type A test. System will be drained to the extent possible. ,

NOTE 11 Type B test performed on the blind flanges inside the Reactor Building. Valves outside the containment are not tested.

NOTE 12 A one-time extension from the local leak test and corresponding exemption from Section III.D.2 and III.D.3 of Appendix J to 10 CFR Part 50 is granted such that it be performed during the 1983 Unit I refueling outage, provided that such outage begins nc later than July 16,1983.

NOTE 13 The requirements to perform a Type A test in accordance with Notes 1 and 3 of Table 4.4-1, will commence during the end ofcycle 12 refueling outage on Unit 1, and during the end of cycle 1I refueling outages on Units 2 and 3. For the Type C test, the initial test will be performed on Unit I during the end ofcycle 12 refueling outage, on Unit 2 no later than January 15,1990, and during the end ofcycle 11 refueling outage, on Unit 3. On Units 2 and 3, until Type C testing is performed, these penetrations may be utilized provided that compensatory measures described in W. H.

Owen's September 29,1989 letter and H. B. Tucker's October 4,1989 letter are implemented.

16.6-10 11/29/95