IR 05000277/2020004: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
Line 67: Line 67:
==REACTOR SAFETY==
==REACTOR SAFETY==


==71111.04 - Equipment Alignment Partial Walkdown Sample (IP Section 03.01) ==
==71111.04 - Equipment Alignment==
{{IP sample|IP=IP 71111.04|count=3}}


===Partial Walkdown Sample (IP Section 03.01) (3 Samples)===
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
: (1) Unit 2 reactor core isolation cooling (RCIC) system during planned high-pressure coolant injection (HPCI) system testing on October 5, 2020
: (1) Unit 2 reactor core isolation cooling (RCIC) system during planned high-pressure coolant injection (HPCI) system testing on October 5, 2020
Line 78: Line 78:
: (1) The inspectors evaluated system configurations during a complete walkdown of the Unit 2 RCIC system. The inspectors inspected the normally inaccessible portions of the Unit 2 RCIC system on October 10, 2020, during the refueling outage, and inspected the normally accessible portions of the system during the week of November 16, 2020.
: (1) The inspectors evaluated system configurations during a complete walkdown of the Unit 2 RCIC system. The inspectors inspected the normally inaccessible portions of the Unit 2 RCIC system on October 10, 2020, during the refueling outage, and inspected the normally accessible portions of the system during the week of November 16, 2020.


==71111.05 - Fire Protection Fire Area Walkdown and Inspection Sample (IP Section 03.01) ==
==71111.05 - Fire Protection==
{{IP sample|IP=IP 71111.05|count=4}}


===Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)===
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
: (1) PF-78W, Unit 2 turbine building moisture separator area on October 21, 2020
: (1) PF-78W, Unit 2 turbine building moisture separator area on October 21, 2020
Line 87: Line 87:
: (4) PF-19, South isolation valve room on October 24, 2020
: (4) PF-19, South isolation valve room on October 24, 2020


==71111.06 - Flood Protection Measures Inspection Activities - Internal Flooding (IP Section 03.01) ==
==71111.06 - Flood Protection Measures==
{{IP sample|IP=IP 71111.06|count=1}}


===Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)===
The inspectors evaluated internal flooding mitigation protections in the:
The inspectors evaluated internal flooding mitigation protections in the:
: (1) Unit 2 HPCI pump room
: (1) Unit 2 HPCI pump room
Line 114: Line 114:
: (1) The inspectors observed and evaluated licensed operator performance in the control room after a trip of the Unit 3 'C' reactor feed pump on October 13, 2020, and during the Unit 2 reactor pressure vessel leakage pressure test on November 14, 2020
: (1) The inspectors observed and evaluated licensed operator performance in the control room after a trip of the Unit 3 'C' reactor feed pump on October 13, 2020, and during the Unit 2 reactor pressure vessel leakage pressure test on November 14, 2020


==71111.12 - Maintenance Effectiveness Maintenance Effectiveness (IP Section 03.01) ==
==71111.12 - Maintenance Effectiveness==
{{IP sample|IP=IP 71111.12|count=1}}


===Maintenance Effectiveness (IP Section 03.01) (1 Sample)===
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:
: (1) Unit 2 main steam isolation valves (MSIVs) from December 17, 2020 to December 21, 2020
: (1) Unit 2 main steam isolation valves (MSIVs) from December 17, 2020 to December 21, 2020
Line 146: Line 146:
: (1) Unit 2 instrument line nozzle 'N16A' replacement with a weld pad and half nozzle on November 14, 2020
: (1) Unit 2 instrument line nozzle 'N16A' replacement with a weld pad and half nozzle on November 14, 2020


==71111.19 - Post-Maintenance Testing Post-Maintenance Test Sample (IP Section 03.01) ==
==71111.19 - Post-Maintenance Testing==
{{IP sample|IP=IP 71111.19|count=6}}


===Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)===
The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:
The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:
: (1) Unit 2 'E224-R-B' motor control unit maintenance on October 27, 2020
: (1) Unit 2 'E224-R-B' motor control unit maintenance on October 27, 2020
Line 157: Line 157:
: (6) Unit 2 instrument line nozzle 'N16A' weld repair and replacement activities on November 14, 2020
: (6) Unit 2 instrument line nozzle 'N16A' weld repair and replacement activities on November 14, 2020


==71111.20 - Refueling and Other Outage Activities Refueling/Other Outage Sample (IP Section 03.01) ==
==71111.20 - Refueling and Other Outage Activities==
{{IP sample|IP=IP 71111.20|count=1}}
: (1) The inspectors evaluated Unit 2 Refueling Outage activities from October 19, 2020 to November 15, 2020


==71111.22 - Surveillance Testing The inspectors evaluated the following surveillance tests:==
===Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)===
: (1) The inspectors evaluated Unit 2 Refueling Outage activities from October 19, 2020 to          November 15, 2020
==71111.22 - Surveillance Testing==


===Surveillance Tests (other) (IP Section 03.01) (2 Samples)===
The inspectors evaluated the following surveillance tests:
 
===Surveillance Tests (other) (IP Section 03.01)===
{{IP sample|IP=IP 71111.22|count=2}}
: (1) Unit 3 'A' RHR pump, valve, and flow surveillance test on November 30, 2020
: (1) Unit 3 'A' RHR pump, valve, and flow surveillance test on November 30, 2020
: (2) Functional test of the Unit 2 torus to reactor building vacuum breakers on
: (2) Functional test of the Unit 2 torus to reactor building vacuum breakers on


===December 3, 2020 Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)===
===December 3, 2020 Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)===
: (1) Local leak rate testing results of containment isolation valve, feedwater long path           recirculation isolation valve on December 11,
: (1) Local leak rate testing results of containment isolation valve, feedwater long path recirculation isolation valve on December 11,


==RADIATION SAFETY==
==RADIATION SAFETY==
Line 224: Line 227:
: (1) Radiological Effluent TS/ODCM Radiological Effluent Occurrences for the period of October 1, 2019 to September 30, 2020
: (1) Radiological Effluent TS/ODCM Radiological Effluent Occurrences for the period of October 1, 2019 to September 30, 2020


==71152 - Problem Identification and Resolution Semiannual Trend Review (IP Section 02.02) ==
==71152 - Problem Identification and Resolution==
{{IP sample|IP=IP 71152|count=1}}
 
===Semiannual Trend Review (IP Section 02.02) (1 Sample)===
: (1) The inspectors reviewed the licensees corrective action program (CAP) for potential adverse trends in third and fourth quarters of 2020 that might be indicative of a more significant safety issue
: (1) The inspectors reviewed the licensees corrective action program (CAP) for potential adverse trends in third and fourth quarters of 2020 that might be indicative of a more significant safety issue



Revision as of 00:18, 16 April 2021

Integrated Inspection Report 05000277/2020004 and 05000278/2020004 and Independent Spent Fuel Storage Installation Inspection Report 07200029/2020401
ML21036A021
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 02/05/2021
From: Christopher Lally
Reactor Projects Region 1 Branch 4
To: Rhoades D
Exelon Generation Co, Exelon Nuclear
Lally C
References
IR 2020004, IR 2020401
Download: ML21036A021 (22)


Text

February 5, 2021

SUBJECT:

PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 -

INTEGRATED INSPECTION REPORT 05000277/2020004 AND 05000278/2020004 AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION INSPECTION REPORT 07200029/2020401

Dear Mr. Rhoades:

On December 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Peach Bottom Atomic Power Station, Units 2 and 3. On January 15, 2021, the NRC inspectors discussed the results of this inspection with Mr. Matthew Herr, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Peach Bottom Atomic Power Station, Unit 2 and 3.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; and the NRC Resident Inspector at Peach Bottom Atomic Power Station, Unit 2 and 3. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, X /RA/

Signed by: Christopher Lally Chris M. Lally, Acting Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos. 05000277, 05000278, and 07200029 License Nos. DPR-44 and DPR-56

Enclosure:

As stated

Inspection Report

Docket Numbers: 05000277, 05000278, and 07200029 License Numbers: DPR-44 and DPR-56 Report Numbers: 05000277/2020004, 05000278/2020004, and 07200029/2020401 Enterprise Identifier: I-2020-004-0022 I-2020-401-0009 Licensee: Exelon Generation Company, LLC Facility: Peach Bottom Atomic Power Station, Units 2 and 3 Location: Delta, PA 17314 Inspection Dates: October 1, 2020 to December 31, 2020 Inspectors: S. Rutenkroger, Senior Resident Inspector P. Boguszewski, Resident Inspector E. Andrews, Health Physicist J. Bream, Reactor Operations Engineer L. Casey, Senior Project Engineer P. Cataldo, Senior Reactor Inspector E. Dipaolo, Senior Reactor Inspector A. Turilin, Reactor Inspector Approved By: Chris M. Lally, Acting Chief Reactor Projects Branch 4 Division of Reactor Projects Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Peach Bottom Atomic Power Station,

Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Low-Pressure Coolant Injection Swing Bus and 480V Breaker Hoist Design Control Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green [P.3] - 71152 Systems NCV 05000277,05000278/2020004-01 Resolution Open/Closed The inspectors identified a Green non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion III, Design Control, because Exelon did not maintain safety-related equipment in a seismically analyzed condition. Specifically, on two occasions, Exelon personnel stored seismically unrestrained equipment in close proximity to safety-related components, challenging the seismic qualifications of the equipment.

Additional Tracking Items

None.

PLANT STATUS

Unit 2 began the inspection period at 83 percent of rated thermal power (RTP) in end of cycle coastdown. The unit was down powered on October 18, 2020, and taken offline for a scheduled refueling outage on October 19, 2020. The unit was returned to operation on November 15, 2020, reaching RTP on November 18, 2020. On December 19, 2020, the unit was down powered to 31 percent in single loop operation when the 'B' reactor recirculation pump tripped due to an issue with the adjustable speed drive power supply system. After replacing the controller components, the pump was placed back in service, restoring two loop operation, and the unit was returned to RTP on December 21, 2020. The unit remained at or near RTP for the remainder of the inspection period.

Unit 3 began the inspection period at RTP. On October 13, 2020, the '3C' reactor feedwater pump tripped, and the unit was down powered to 55 percent. The pump was returned to service, and the unit was returned to RTP the same day. On December 18, 2020, the unit was down powered to 73 percent for a control rod pattern adjustment and turbine valve testing and was returned to RTP on December 21, 2020, after resolving a failure of control valve number 1 to indicate closed when tested. The unit remained at or near RTP for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week, increasing the amount of time on site as local COVID-19 conditions permitted. As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D, observed risk significant activities, and completed on site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2 reactor core isolation cooling (RCIC) system during planned high-pressure coolant injection (HPCI) system testing on October 5, 2020
(2) Unit 2 shutdown cooling shortly after it was placed in service for the refueling outage on October 19, 2020
(3) E-1 emergency diesel generator (EDG) while Unit 2 'A' residual heat removal (RHR)was in service for shutdown cooling on November 10, 2020

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 2 RCIC system. The inspectors inspected the normally inaccessible portions of the Unit 2 RCIC system on October 10, 2020, during the refueling outage, and inspected the normally accessible portions of the system during the week of November 16, 2020.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) PF-78W, Unit 2 turbine building moisture separator area on October 21, 2020
(2) PF-3, Unit 2 'B' and 'D' RHR walkdown during heat exchanger bottom head welding on October 15, 2020
(3) PF-23, North isolation valve room on October 24, 2020
(4) PF-19, South isolation valve room on October 24, 2020

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Unit 2 HPCI pump room

Cable Degradation (IP Section 03.02) (1 Sample)

The inspectors evaluated cable submergence protection in:

(1) Manholes (MHs) MH-062, MH-091A, and MH-016A

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

(1) The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation, and that repairs and replacements were appropriately fabricated, examined, and accepted by reviewing the following activities from October 19 to December 14, 2020:

03.01.a - Nondestructive Examination and Welding Activities.

1. Ultrasonic Examination of CH-MB, Reactor Pressure Vessel (RPV) Closure Head Meridian Weld at 60 degrees Az. (PEA-2-008900)2. Ultrasonic Examination of 3-I-19R, Nozzle N9 to Cap (ISI-UT-010)3. Ultrasonic Examination of CH-C-1, RPV Closure Head Dollar Plate Weld 0 -

360 degrees (PEA-2-008600)4. Ultrasonic Examination of CH-C-2, RPV Closure Head to Flange Weld (PEA-2-008700)5. Magnetic Particle Examination of CH-C-2, RPV Closure Head to Flange Weld (ISI-MT-001)6. Visual Examination (GV) of 4.1.3.7, Drywell Interior Moisture Barrier (4.2.1.4.AF and 4.2.1.4.AF2)7. Visual Examination (GV) of 4.5.2.1 thru 4.5.2.16, Accessible Torus Shell Inside Surface Above the Water Line (4.5.2)8. Visual Examination (GV) of the Drywell Airgap Drains (4.8.5)9. Visual Examination (GV) of 4.1.3.1, Drywell walls below 135' (4.2.1.3)10. Visual Examination (GV) of 4.1.3.1 and 4.1.3.4, N1 Equipment Hatch Penetration at Elevation 140' at 315 deg Az. and associated bolting (4.2.2.4)11. Visual Examination (GV) of 4.1.3.1, Accessible Containment Surfaces of the Drywell Walls between 157' and 186' elevation (4.2.3.3)12. Visual Examination (GV) of 4.1.3.1, Accessible Containment Surfaces of the Drywell Walls between 186' and 210'-4" elevation (4.2.4.3)13. Repair/Replacement Activity a. Repair activity associated with the repair of RPV N-16A nozzle due to a leak discovered during a VT-2 exam (CR 4380514, Relief Request I5R-14)

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room after a trip of the Unit 3 'C' reactor feed pump on October 13, 2020, and during the Unit 2 reactor pressure vessel leakage pressure test on November 14, 2020

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 2 main steam isolation valves (MSIVs) from December 17, 2020 to December 21, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 2 'B' RHR inoperability due to a failed surveillance test on October 6, 2020
(2) Unit 2 planned loss-of-coolant accident/loss of offsite power testing on October 28, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 3 'K' erratic safety/relief valve steam line temperature readings on October 1, 2020
(2) Unit 2 control rod '30-19' was slow to settle on October 18, 2020
(3) Unit 2 reactor feedwater pump '2B' discharge check valve had seat cracking on October 21, 2020
(4) Unit 2 station battery '2A' rail insulators were degraded on October 23, 2020
(5) Unit 2 operability of RPS and primary containment isolation system (PCIS) with

'N16A' nozzle instrumentation out of service on November 3, 2020

(6) Unit 3 scram discharge volume level transmitter flange damage on December 22, 2020

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

(1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit 2 instrument line nozzle 'N16A' replacement with a weld pad and half nozzle on November 14, 2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Unit 2 'E224-R-B' motor control unit maintenance on October 27, 2020
(2) Unit 2 'B' low pressure coolant injection (LPCI) swing bus testing following outage preventative maintenance on October 28, 2020
(3) Unit 2 'B' outboard MSIV post-maintenance testing following the installation of a poppet stabilization modification on November 2, 2020
(4) Unit 2 'D' outboard MSIV post-maintenance leakage testing following maintenance on November 2, 2020
(5) Unit 2 HPCI maintenance on November 15, 2020
(6) Unit 2 instrument line nozzle 'N16A' weld repair and replacement activities on November 14, 2020

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated Unit 2 Refueling Outage activities from October 19, 2020 to November 15, 2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Unit 3 'A' RHR pump, valve, and flow surveillance test on November 30, 2020
(2) Functional test of the Unit 2 torus to reactor building vacuum breakers on

December 3, 2020 Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) Local leak rate testing results of containment isolation valve, feedwater long path recirculation isolation valve on December 11,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated radiological protection-related instructions to plant workers

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) Observed licensee surveys of potentially contaminated material leaving the radiologically controlled area
(2) Observed workers exiting the radiologically controlled area during the Unit 2 Refueling Outage

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.

(1) Observed Unit 2 reactor cavity decontamination
(2) Observed hydraulic control unit maintenance
(3) Observed worker briefings for entry into high radiation areas and contaminated areas
(4) Reviewed radiological surveys and documentation associated with control rod drive exchange High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:

(1) Unit 2 drywell entrance
(2) Unit 3 3A steam jet air ejector room
(3) Unit 2 traversing incore probe room Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements

SAFEGUARDS

71130.09 - Security Plan Changes

The inspectors evaluated the security plan changes through completion of the following

procedure elements: Review Security Plan Changes (IP Section 02.01)

The inspectors evaluated the security plan changes through completion of the following procedure elements:

(1) Since the last NRC inspection of this program area, Security Plan Revisions 20 and 21 were implemented based on your determination, in accordance with 10 CFR 50.54(p)(2), that the changes resulted in no decrease in safeguards effectiveness of the security plan, and that the revised security plan continues to meet the requirements of 10 CFR 73.55(b). The inspectors conducted a review of the security plan changes to evaluate for potential decrease in safeguards effectiveness of the security plan. However, this review does not constitute formal NRC approval of the changes. Therefore, these changes remain subject to future NRC inspection in their entirety.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04) ===

(1) Unit 2 October 1, 2019 to September 30, 2020
(2) Unit 3 October 1, 2019 to September 30, 2020

MS06: Emergency AC Power Systems (IP Section 02.05) (2 Samples)

(1) Unit 2 October 1, 2019 to September 30, 2020
(2) Unit 3 October 1, 2019 to September 30, 2020

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) Occupational Exposure Control Effectiveness for the period of October 1, 2019 to September 30, 2020 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) Radiological Effluent TS/ODCM Radiological Effluent Occurrences for the period of October 1, 2019 to September 30, 2020

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program (CAP) for potential adverse trends in third and fourth quarters of 2020 that might be indicative of a more significant safety issue

Annual Follow-up of Selected Issues (IP Section 02.03) (3 Samples)

The inspectors reviewed the licensees implementation of its CAP related to the following issues:

(1) E-1 EDG cable failure due to water treeing and cable monitoring program testing delays to determine if the corrective actions to implement the cable monitoring program were timely, comprehensive, and adequate
(2) Review of Selected Non-Compliances with the Peach Bottom Atomic Power Station Cyber Security Plan
(3) High-pressure service water (HPSW) system raw water piping corrosion, wall-thinning, and through-wall leak conditions

71153 - Followup of Events and Notices of Enforcement Discretion Event Followup (IP Section 03.01)

(1) The inspectors followed up on a reactor coolant system leak from the Unit 2 instrument line nozzle 'N16' identified during the reactor pressure vessel pressure test on October 29, 2020

Personnel Performance (IP Section 03.03) (2 Samples)

(1) The inspectors followed up on the trip of the Unit 3 'C' reactor feedwater pump and subsequent recirculation pump runback and unit downpower on October 13, 2020
(2) The inspectors followed up on a Unit 2 'B' reactor recirculation pump trip on December 20,

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

===81311 - Physical Security Requirements for Independent Spent Fuel Storage Installations The inspectors assessed the adequacy of Exelon's Independent Spent Fuel Storage Installation (ISFSI) co-located at Peach Bottom Atomic Power Station.

Physical Security Requirements for Independent Spent Fuel Storage Installations ===

(1) The inspectors completed one sample in accordance with Section 02.01 for a general license ISFSI licensed under 10 CFR 72.210 of Subpart K

INSPECTION RESULTS

Low-Pressure Coolant Injection Swing Bus and 480V Breaker Hoist Design Control Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green [P.3] - 71152 Systems NCV 05000277,05000278/2020004-01 Resolution Open/Closed The inspectors identified a Green non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion III, Design Control, because Exelon did not maintain safety-related equipment in a seismically analyzed condition. Specifically, on two occasions, Exelon personnel stored seismically unrestrained equipment in close proximity to safety-related components, challenging the seismic qualifications of the equipment.

Description:

The NRC inspectors identified two examples of design control violations. The first example affects the RHR system and a primary containment isolation valve (PCIV). The second example affects the safety-related 480V power distribution system.

The LPCI mode of RHR provides water to the reactor vessel via the recirculation system discharge piping to cool the fuel in the event of a loss of coolant accident. There are two LPCI subsystems per unit, each consisting of two motor driven pumps, piping, and valves to transfer water from the suppression pool to the reactor vessel via the corresponding recirculation loop. The two LPCI pumps and associated motor operated valves in each LPCI subsystem are powered from separate 4 kV emergency buses. Both pumps in a LPCI subsystem inject water into the reactor vessel through a common inboard injection valve and depend on the closure of the recirculation pump discharge valve following a LPCI signal.

Therefore, each LPCI subsystems' common inboard injection valve and recirculation pump discharge valve is powered from one of the two 4 kV emergency buses associated with that subsystem (normal source) and has the capability for automatic transfer to the second 4 kV emergency bus associated with that LPCI subsystem via the corresponding LPCI subsystem LPCI swing bus. The ability to provide power to the inboard injection valve and the recirculation pump discharge valve from either 4 kV emergency bus associated with the LPCI subsystem ensures that the single failure of a diesel generator (DG) will not result in the failure of both LPCI pumps in one subsystem. Although the LPCI swing bus is not required to meet single failure criteria for the other modes of RHR, some additional RHR modes, such as shutdown cooling, require repositioning the RHR inboard injection valve or recirculation pump discharge valve.

The function of the PCIVs is to limit fission product release during and following postulated Design Basis Accidents (DBAs) to within limits. PCIVs ensure that the release of radioactive material to the environment will be consistent with the assumptions used in the analyses for a DBA.

On September 23, 2020, the inspectors discovered a large standing radiation shield stored next the Unit 3 B LPCI swing bus and a nearby PCIV. Upon discovery, the licensee stated that the placement had been analyzed but was unable to locate the analysis. After further review, Exelon determined that the shield was not permitted to be stored in its current location, as in a seismic event, the shield would likely tip, possibly impacting the Unit 3 B LPCI swing bus and a nearby nitrogen header supply PCIV.

The second example affects the AC electrical power distribution system. This system ensures the availability of AC electrical power for systems required to shutdown the reactor and maintain it in a safe condition after an operational transient or design basis event. On October 25, 2020, the NRC inspectors identified that a non-seismically supported breaker hoist was stored in an unapproved location next to a safety-related 480V load center. This exact issue was previously identified by the NRC Design Basis Assurance (DBA) inspection team in July 2020 and resulted in an NCV, 2020011-003. After the DBA inspection documented the issue and Exelon performed corrective actions, the NRC resident inspectors discovered the breaker hoist had been moved back to the unapproved storage location. After the DBA inspection teams inspection finding, Exelon determined that when subject to design basis seismic forces, the breaker hoists would experience forces large enough to cause them to overturn. The station determined that based on this analysis, a new restraint design would need to be developed and implemented to prevent tipping during expected seismic forces.

Corrective Actions: Exelon immediately relocated the rolling shield and breaker hoist to locations away from safety-related equipment and documented the issue in their CAP.

Corrective Action References: IRs 04371568 and 04379330

Performance Assessment:

Performance Deficiency: The inspectors identified a Green NCV of 10 CFR Part 50, Appendix B, Criterion III, Design Control, because Exelon did not maintain safety-related equipment in a seismically analyzed condition. Specifically, on two occasions, Exelon personnel stored seismically unrestrained equipment in close proximity to safety-related components, challenging the seismic qualifications of the equipment.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the inspectors identified two instances where the site seismic analyses associated with safety-related equipment was not consistent with installed plant configuration, and these variations adversely affected the availability, reliability, and capability of safety-related systems.

In the first example, Exelons engineering evaluation of the rolling shield found that the shield would have fallen over if it had been subjected to design basis seismic forces adversely affecting the availability, reliability, and capability of a low-pressure injection swing bus and a PCIV. Specifically, taking into account the weight of the shield and the force it would have produced upon impact, the impacted equipment would have been rendered inoperable if impacted. This issue is also similar to example 4.a in IMC 0612, Appendix E, Examples of Minor Issues, in that, the engineering evaluation confirmed that the affected safety-related equipment would be subject to seismic induced forces that had not been considered in the original analysis and increased the probability of failure during accident mitigation.

In the second example, the initial engineering evaluation associated with the breaker hoist determined that the breaker hoists were susceptible to tipping during expected seismic forces, adversely affecting the availability, reliability, and capability of the safety-related 480V load center. The station determined that based on this analysis, a new restraint design would need to be developed and implemented to prevent tipping during expected seismic forces.

This issue is similar to example 3.a in IMC 0612, Appendix E, Examples of Minor Issues, in that, there was a reasonable doubt with respect to the seismic qualifications of the breaker hoists, which affected the assurance of availability and reliability of safety-related equipment.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. For both examples, the inspectors assessed the significance of the finding using IMC 0609 Appendix A, Exhibit 2, Mitigating Systems Screening Questions. The inspectors determined that this finding was a deficiency affecting the design or qualification of mitigating SSCs, where the SSCs maintained their operability or functionality. Therefore, the inspectors determined the finding to be of very low safety significance (Green).

Cross-Cutting Aspect: P.3 - Resolution: The organization takes effective corrective actions to address issues in a timely manner commensurate with their safety significance. On July 2020, the NRC DBA inspection team documented a violation for the storage of breaker hoists located near 480V safety-related switchgear cabinets, which were not seismically analyzed or maintained in accordance with established engineering seismic analyses. Exelon did not implement effective corrective actions and, as a result, the inspectors identified two additional instances of unrestrained equipment, which challenged the seismic qualifications of safety-related equipment.

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires, in part, that design changes, including field changes, shall be subject to design control measures commensurate with the original design and be approved by the responsible organization.

Contrary to the above, a non-seismically restrained portable shield was stored near the Unit 3 B LPCI swing bus and nitrogen A supply header to drywell PCIV. Additionally, a breaker hoist stored near the E-424 480V load center was not restrained to prevent tipping. In both instances, the affected safety-related equipment would be subject to seismic induced forces that had not been considered in the original analysis and would have increased the probability of failure during accident mitigation.

Enforcement Action: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.

Observation: Semi-Annual Trend 71152 The inspectors conducted a semi-annual trend review by evaluating sample issues that occurred in the third and fourth quarter of 2020. During the evaluation, the inspectors verified the issues identified were addressed within the scope of the CAP. The inspectors reviewed health reports and related databases for trends and considered prior issues while performing routine walkdowns and attending the plan of the day meetings. No notable adverse performance trends or substantive repetitive equipment failures were identified during this time. However, during the fourth quarter, the inspectors identified an issue where Exelon placed a non-seismically supported breaker hoist next to a safety-related piece of equipment, which was previously identified by the NRC Design Basis Assurance Inspection team earlier in the year (Inspection Report 05000277/2020011 and 05000278/2020011, ML20252A081).

The inspectors also identified a non-seismically supported portable lead shielding placed next to safety-related equipment. These issues were determined to be two examples of one Finding documented in this inspection report (Green NCV 2020011-003). However, following the identification of these issues, the inspectors did not identify further examples to indicate development of an adverse trend.

In addition, other than the non-isolable leakage identified from the weld of the 'N16A' instrument line nozzle during the reactor pressure vessel pressure testing (Licensee Event Report 2-20-002, ML20357B113) no significant safety-related equipment failures were identified during this time. The inspectors reviewed scram solenoid pilot valve buzzing, hydraulic control unit pressure alarms, and pump vibration trending issues. For the selected samples, the inspectors determined that the issues were appropriately evaluated by Exelon staff for potential trends at a low threshold, and resolved within the scope of the CAP. Based on the overall results of the semi-annual trend review, the inspectors determined that Exelon had identified adverse trends at Peach Bottom before they could become more significant safety problems. The inspectors continue to monitor the CAP and maintenance effectiveness during routine inspection activities.

Observation: E-1 EDG Cable Failure Due to Water Treeing and Cable 71152 Monitoring Program Testing Delays The inspectors reviewed the corrective actions taken for the delays in the implementation of the cable monitoring program as described in AR 04252679 that contributed to the E-1 EDG cable failure on May 29, 2019. The inspectors evaluated the current implementation of the cable monitoring program by reviewing the medium and low voltage cable program action plan items described in AR 0428277 and AR 04282788. The inspectors also reviewed CAP documentation of subsequent cable failures in AR 04241082 and AR 04376239. The inspectors reviewed ER-AA-300-150, Revision 7, Cable Condition Monitoring Program, to assess the licensees categorization and ranking of the cables in the cable monitoring program and assessed the prioritization and timeliness of the licensees corrective actions.

As a result of the review, inspectors concluded that the licensee has planned and completed adequate corrective actions to restore compliance with the cable monitoring program.

Observation: High-Pressure Service Water System Degradation 71152 The inspectors reviewed corrective action documents, dating back to 2015, which described HPSW piping degradation and licensee actions to address these conditions. In particular, the inspectors noted that for conditions such as through-wall leaks and wall thinning, Peach Bottom personnel completed non-destructive examinations and appropriately evaluated the conditions for operability (i.e., capability to perform specified safety functions in accordance with technical specifications) and applicable regulatory (i.e., 10 CFR 50.55a and License Renewal Commitments under Appendix R of the PBAPS UFSAR) or piping code compliance (i.e., original USAS/ANS B31.1 construction code, ASME Section XI repair/replacement requirements, or ASME code cases, such as N-513-3 and N-513-4.)

The inspectors verified that the overall management of piping degradation associated with the HPSW and emergency service water (ESW) systems was consistent with the licensees raw water integrity program under procedure ER-AA-5400-1001, Raw Water Piping Integrity Management Guide, Revision 11. The inspectors determined the licensee identified the causes of the degradation to involve microbiologically-induced corrosion (MIC) and turbulent flow-induced corrosion on the raw water systems at PBAPS. The inspectors observed the licensee had replaced pipe sections, and planned further corrective actions to increase pipe design margin by decreasing the required system design pressure via pump and valve modifications as described in NRC approval of PBAPS Unit 2 and Unit 3 License Amendments No. 327 and 330 (ML19182A006, dated August 28, 2019, respectively.

The inspectors observed that systematic replacement of components that were contributing to turbulent flow-induced corrosion, will most likely reduce, but not eliminate, the detrimental effects on the HPSW and ESW systems.

The NRC inspectors determined that, based on a sampling of corrective action documents, the licensees management of raw water piping associated with the high-pressure and ESW systems, as it pertains to degradation mechanisms of corrosion, wall-thinning, and through-wall leaks were appropriately identified, assessed and resolved within the CAP.

Observation: Review of Selected Non-Compliances with the Peach Bottom 71152 Atomic Power Station Cyber Security Plan During the Peach Bottom Atomic Power Station, Units 2 and 3, cyber security inspection completed in May 2019, four non-compliances with the stations Cyber Security Plan were identified as documented in NRC Inspection Report 05000277/2019403 and 05000278/2019403 (ML19154A110). Two NRC-identified and two licensee-identified NCVs were documented. One NRC-identified NCV was applicable to an Exelon corporate-wide practice. The actions to address this NCV were sufficiently reviewed during cyber security inspections at other Exelon sites.

The scope of this inspection evaluated Exelons initial, interim, and long-term corrective actions and extent of condition related to the three NCVs that were attributed to Peach Bottom specific implementation of the Cyber Security Plan. These issues were documented in the Exelon CAP as IRs 04259069, 04327691, and 04327692. The inspectors reviewed the cause analyses, technical evaluations performed, and the corrective actions taken and planned. The inspectors assessed Exelons problem identification threshold, prioritization of the issues, apparent cause analyses, use of operating experience, and timeliness of corrective actions.

As a result of the review, the inspectors concluded that Exelon appropriately evaluated the issues, performed thorough extent of condition reviews, performed thorough reviews of operating experience, and completed timely and appropriate corrective actions. The inspectors concluded that Exelon appropriately addressed the issues to restore compliance with the Peach Bottom Cyber Security Plan.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 15, 2021, the inspectors presented the integrated inspection results to Mr. Matthew Herr, Site Vice President, and other members of the licensee staff.
  • On December 17, 2020, the inspectors presented the High Pressure Service Water System inspection results to Mr. Matthew Rector and other members of the licensee staff.
  • On December 14, 2020, the inspectors presented the inspection results of the Problem Identification and Resolution Annual Follow-up of Selected Issues Associated with Non-compliances with the Peach Bottom Atomic Power Station Cyber Security Plan to Mr. Matthew Herr, Site Vice President, and other members of the licensee staff.
  • On November 4, 2020, the inspectors presented the In-Service Inspection results to Mr. Matthew Herr, Site Vice President, and other members of the licensee staff.
  • On October 30, 2020, the inspectors presented the Radiological Hazard Assessment and Exposure Controls inspection results to Mr. Matthew Herr, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.06 Corrective Action IR 4359805

Documents IR 4359805

IR 4372429

Procedures AO 20A.1 Temporary Removal and Installation of Flood Barriers in the Revision 18

Reactor Building Drainage System

RT-W-020-930-2 Survey for Flood Barriers in Reactor Building Drainage Revision 6

System

Work Orders WR 1471851

WR 1475634

WR 1480787

WR 4881847

71111.08G Corrective Action 04379124 P2R23 ISI CNF-002 - Moisture Barrier Damage 10/24/2020

Documents 04379541 P2R23SU: ISI CNF-004 - Additional Moisture Barrier 10/26/2020

Damage

04380514 Unit-2 Instrument Nozzle During Leak Test N-16A 10/29/2020

Engineering 0000632907 Half Nozzle Repair of RPV Nozzle N-16A Revision 0

Changes

Miscellaneous20-113 ASME Section XI Repair/Replacement Plan 11/04/2020

NDE Reports 4.8.5 Drywell Airgap Drains 10/28/29020

4.2.1.3 Drywall walls below 135' 10/28/2020

4.2.1.4.AF Drywell Interior Moisture Barrier 10/29/2020

4.2.1.4.AF2 Drywell Interior Moisture Barrier 10/29/2020

4.2.2.4 N1 Equipment Hatch Penetration at Elevation 140' at 315 10/28/2020

deg Az. and associated bolting

4.2.3.3 Accessible Containment Surfaces of the Drywell Walls 10/27/2020

between 157' and 186' elevation

4.2.4.3 Accessible Containment Surfaces of the Drywell Walls 10/27/2020

between 186' and 210'-4" elevation

4.5.2 Accessible Torus Shell Inside Surface Above the Water Line 10/30/2020

ISI-MT-001 RPV Closure Head to Flange Weld 10/24/2020

ISI-UT-010 Nozzle N9 to Cap 10/27/2020

Inspection Type Designation Description or Title Revision or

Procedure Date

PEA-2-008600 CH-C-1 RPV Closure Head Dollar Plate Weld 0 - 360 11/03/2020

degrees

PEA-2-008700 RPV Closure Head to Flange Weld 11/03/2020

PEA-2-008900 CH-MB, Top Head Meridian Weld at 60 degrees Az. 11/03/2020

Work Orders 04997289 ISI-07 DW119 Drywell Moisture Barrier Inspection 10/26/2020

05003055 ISI-04 Fuel Floor RPV Top Head Auto UT CH-MB 10/23/2020

05003055 ISI-04 Fuel Floor RPV Top Head NDE CH-C-2 MT and UT 10/23/2020

05003055 ISI-04 Fuel Floor RPV Top Head NDE CH-C-1 10/23/2020

05004057 ISI-04 DW135 Noz N9 and IRS and Weld 3-I-19R 10/23/2020

05005444 ISI-07 CISI Drywell/Reactor BDG Containment Exam, Torus 10/26/2020

NDE VT Exterior 91' 6" and Catwalk

71111.15 Corrective Action IR 4377851

Documents IR 4378845

IR 4379202

71111.19 Procedures ST-O-023-200-2 HPCI Flow Rate at Less Than or Equal to 175 PSIG Revision 21

71124.01 ALARA Plans PB-2-20-00513 DW: Control Rod Drive Exchange 1

Corrective Action IR 4300191

Documents

71130.09 Miscellaneous Peach Bottom Atomic Power Station Security Plan, Training Revision 20

and Qualification Plan, Safeguards Contingency Plan, and

Independent Spent Fuel Storage Installation Security Plan

Peach Bottom Atomic Power Station Security Plan, Training Revision 21

and Qualification Plan, Safeguards Contingency Plan, and

Independent Spent Fuel Storage Installation Security Plan

Procedures SY-PB-101-501 Site Protective Strategy Revision 8

SY-PB-101-503 Physical Protection Measures for the Independent Spent Revision 3

Fuel Storage Installation

71151 Corrective Action 4256366

Documents 4349262

71152 Calibration 4249279

Records

Corrective Action 1541900-2 Technical Evaluation for PBAPS Raw Water Corrosion Rate

Documents & Remaining Life Basis

Inspection Type Designation Description or Title Revision or

Procedure Date

2494904

23505

2568856

2734068

3969672

4176155

25404

28807

232165

234974

236637

240265

240877

249279

259069

27691

27692

4346624

4359573

IR 04379330

Miscellaneous NOSA-PEA-20- Cyber Security Program Audit Report 11/25/2020

(AR 4379505)

PBAPS UFSAR Appendix R - Second License Renewal UFSAR Supplement Revision 28

Procedures ER-AA-330-009 ASME Section XI Repair/Replacement Program Revision 17

PI-AA-120 Issue Identification and Screen Process Revision 11

PI-AA-125 Corrective Action Program (CAP) Procedure Revision 7

SO.10.1.B-3 Residual Heat Removal System Shutdown Cooling Mode Revision 54

Manual Start

ST-O-010-405-3 LPCI System Valves Swing Bus B Functional Test Revision 6

81311 Procedures SY-AA-101-106 Control and Classification of Safeguards Information Revision 21

SY-AA-101-112- Protected Area Search Processes Revision 4

1004

SY-PB-101-116- Security Patrols Revision 15

Inspection Type Designation Description or Title Revision or

Procedure Date

1001

SY-PB-101-116- Owner Controlled Area and ISFSI Patrol Revision 121

1001-F-07

SY-PB-101-122- Performance of Security System Tests Revision

1001 6a54

19