IR 05000277/2021010

From kanterella
Jump to navigation Jump to search
Triennial Fire Protection Inspection Report 05000277/2021010 and 05000278/2021010
ML21200A176
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 07/20/2021
From: Glenn Dentel
Division of Operating Reactors
To: Rhoades D
Exelon Generation Co LLC, Exelon Nuclear
Dentel G
References
IR 2021010
Download: ML21200A176 (8)


Text

July 20, 2021

SUBJECT:

PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000277/2021010 AND 05000278/2021010

Dear Mr. Rhoades:

On June 24, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Peach Bottom Atomic Power Station, Units 2 and 3 and discussed the results of this inspection with Mr. David Henry, Plant Manager and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Glenn T. Dentel, Chief Engineering Branch 2 Division of Operating Reactor Safety

Docket Nos. 05000277 and 05000278 License Nos. DPR-44 and DPR-56

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000277 and 05000278

License Numbers:

DPR-44 and DPR-56

Report Numbers:

05000277/2021010 and 05000278/2021010

Enterprise Identifier: I-2021-010-0015

Licensee:

Exelon Generation Company, LLC

Facility:

Peach Bottom Atomic Power Station, Units 2 and 3

Location:

Delta, PA 17314

Inspection Dates:

June 7, 2021 to June 24, 2021

Inspectors:

C. Bickett, Senior Reactor Inspector

D. Kern, Senior Reactor Inspector

J. Lilliendahl, Senior Emergency Response Coord

Approved By:

Glenn T. Dentel, Chief

Engineering Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Peach Bottom Atomic Power Station, Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site.

However, all the inspection activities were performed onsite. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

===71111.21N.05 - Fire Protection Team Inspection (FPTI)

Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)===

The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).

(1) Fire Protection Water Supply System
(2) Automatic Suppression Systems
(3) Residual Heat Removal (RHR) system
(4) High Pressure Coolant Injection (HPCI) system

Fire Protection Program Administrative Controls (IP Section 03.02) (2 Samples)

The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees FPP contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.

(1) Control of Transient Combustible Material
(2) Fire Protection System Impairment Control

Fire Protection Program Changes/Modifications (IP Section 03.03) (2 Samples)

The inspectors verified the following:

a. Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown.

b. The adequacy of the design modification, if applicable.

c. Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications.

d. The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, FHA, and SSA were updated consistent with the FPP or design change.

e. Post-fire SSD operating procedures, such as abnormal operating procedures, affected by the modification were updated.

(1) EC 627869 - Implement Fire Hose Removal Strategy
(2) EC 623631 - Fire Safety Shutdown Improvements following 2017 Functional Areas Self-Assessment

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On June 24, 2021, the inspectors presented the triennial fire protection inspection results to Mr. David Henry, Plant Manager and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.05 Corrective Action

Documents

2673479

04115309

04125405

04127608

04153095

230804

Corrective Action

Documents

Resulting from

Inspection

04418605

04428400

04428402

04428589

04428649

04428822

04430609

Drawings

M-1-S-65, Sht. 17 Unit 2 Residual Heat Removal System Electrical

Schematic

101

M-1-S-65, Sht. 20 Unit 2 Residual Heat Removal System Electrical

Schematic

101

Engineering

Changes

EC 623631

FSSD Program Improvements following FASA 2017

07/13/2018

EC 626469

86-10 Evaluation Supporting Removal of Fire Hose at

Interior Hose Stations at Peach Bottom Atomic Power

Station

EC 627495

Replacement of MO-2-10-089A/B/C/D for HPSW Pressure

Reduction

EC 627869

Implement Fire Hose Removal Strategy Need to Create

WO to Drive Planning

EC 630114

HPCI/RCIC Pump Low Suction Pressure Trip Elimination

Miscellaneous

Fire Protection Program

NE-00296

Specification for Post-Fire Safe Shutdown Program

Requirements at Peach Bottom Atomic Power Station

PEA-05738

Failure Analysis of Fire Protection Piping IR 04133867

and 04190107

11/01/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PEA-57860

Evaluation of Fire Valve for Selective Leaching /Corrosion

- Fire Water System East Main Header South Division

Shutoff PIV-D-2

2/30/2014

PEA-71643

Selective Leaching Evaluation of One Fire Valve and One

Piping Tee

05/26/2017

Procedures

OP-AA-201-007

Fire Protection System Impairment Control

OP-AA-201-009

Control of Transient Combustible Material

OP-PB-102-106

Operator Response Time Program at Peach Bottom

SE-10

Alternative Shut Down

23