ML17335A563: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:c>TZaoaz REGULATORY INFORMATION DISTRIBUTIO SYSTEM (RIDS)TARIZED: NO DOCKET FACIL:50-315 Donald C.Cook Nuclear Power Plant, Unit 1, Indiana M 05000315 AUTH.NAME AUTHOR AFFILIATION MINOR,J.W.
{{#Wiki_filter:c>TZaoaz REGULATORY INFORMATION DISTRIBUTIO           SYSTEM (RIDS)
Indiana Michigan Power Co.RICHARDSON,S.A.
TARIZED:   NO           DOCKET FACIL:50-315 Donald C. Cook Nuclear Power Plant, Unit 1, Indiana                     M   05000315 AUTH. NAME             AUTHOR AFFILIATION MINOR,J.W.             Indiana Michigan Power Co.
Indiana Michigan Power Co.RECIP.NAME RECIPIENT AFFILIATION I  
RICHARDSON,S.A.       Indiana Michigan Power Co.
RECIP.NAME             RECIPIENT AFFILIATION ltr. t I


==SUBJECT:==
==SUBJECT:==
Monthly operatin t 1999 for DC Cook Nuclear Plant, Unit.With 991012 ltr.DISTRIBUTION CODE: IE24D COP1ES RECEIVED:LTR ENCL SIZE: TITLE: Monthly Operating Report (per Tech Specs)NOTES: E RECIPIENT XD CODE/NAME STANG, J COPIES LTTR ENCL 1 1 RECIPIENT ID CODE/NAME COPIES LTTR ENCL EXTERNAL: LMITCO MARSHALL NRC PDR 1 1 1 1 INTERNAL: FILE CENTER 01 1 1~RES'/DRAA'/OERAE~
Monthly operatin                         1999 for DC Cook Nuclear Plant, Unit .With 991012 DISTRIBUTION CODE: IE24D         COP1ES   RECEIVED:LTR       ENCL       SIZE:
1 1 OC/DBA/PAD RGN3 NOAC 1 1 1 1 1 1 D M'E NOTE TO ALL"RZDS" RECIPZENTS:
TITLE: Monthly Operating Report (per Tech Specs)
PLEASE HELP US TO REDUCE WASTE.TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRZBUTZON LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL'ESK tDCD)ON EXTENSION 415-2083*TOTAL NUMBER OF.COPIES REQUIRED: LTTR 8 ENCL 8 One Cook Pbce BridgnarLMI 49106 61646991 g lMlkl8A NECNEGQN PQWM October 12, 1999 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Document Control Manager: Pursuant to the requirements of Donald C.Cook Nuclear Plant Unit 1 Technical Specification 6.9.1.8, the attached Monthly Operating Report for September 1999 is submitted.
NOTES:                                                                                                         E RECIPIENT           COPIES              RECIPIENT            COPIES XD CODE/NAME         LTTR ENCL         ID CODE/NAME         LTTR ENCL STANG, J                  1     1 INTERNAL: FILE CENTER         01       1    1      OC/DBA/PAD                1     1
Sincerely, R.C.Godley Regulatory Affairs Director RCG/mbd Attachment c: NRC Region III NRC Project Manager-NRR NRC Resident Inspector ANI Nuclear Engineering Department INPO Records Center A.C.Bakken, III G.T.Gaffney-Canton D.R.Hahn-Department of Health S.Hamming-Department of Labor G.John B.Lewis-McGraw-Hill Companies D.H.Malin T.P.Noonan-D.W.Paul-Lancaster J.E.Pollock R.P.Powers Regulatory Licensing Manager M.W.Rencheck W.H.Schalk D.G.Turner'Ir9'i02i0i6i 990930....
        ~RES'/DRAA'/OERAE~ 1                 1       RGN3                     1     1 EXTERNAL: LMITCO MARSHALL              1     1       NOAC                      1     1 NRC PDR                  1    1 D
PDR ADOCK 050003i5" R PDR AEfr~lrrrerfca's Errergr f'arlrrer I~~~)r,>o,~~~'p (+t E I)
M
I\1 J~~~N.R.C.OPERATING DATA REPOR DOCKET NO.DATE COMPLETED BY TELEPHONE 50-315 October 4, 1999 J.W.Minor 616-465-5901 D.C.Cook Unit1 Sept-99 3250 1152 1020 MWe)1056 1000 OPERATING STATUS 1.Unit Name 2.Reporting Period 3.Licensed Thermal Power (MWt)4.Name Plate Rating (Gross MWe)5.Design Electrical Rating (Net MWe)6.Maximum Dependable Capacity (GROSS 7.Maximum Dependable Capacity (Net MWe)Notes: 8.If Changes Occur in Capacity Ratings (Items no.3 through 7)Since Last Report Give Reasons: 9.Power Level to Which Restricted, If Any (Net MWe): 10.Reasons For Restrictions, If Any: 11.Hours in Reporting Period 12.No.of Hrs.Reactor Was Critical 13.Reactor Reserve Shutdown Hours 14.Hours Generator on Line 15.Unit Reserve Shutdown Hours 16.Gross Thermal Energy Gen.(MWH)17.Gross Electrical Energy Gen.(MWH)18.Net Electrical Energy Gen.(MWH)19.Unit Service Factor 20.Unit Availability Factor 21.Unit Capacity Factor (MDC Net)22.Unit Capacity Factor (DER Net)23.Unit Forced Outage Rate This Month 720.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 100.0 Year-to-Date 6552.0 0.0 0.0 0.0 , 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 100.0 Cumulative 216936.0 151285.3 463.0 148821.1 321.0 440194814.0 143013940.0 137597640.0 69.2 69.2 63.1 61.5 15.6 24.Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):
                                                                                                              'E NOTE TO ALL "RZDS" RECIPZENTS:
None 25.If Shut Down At End of Report Period, Estimated Date of Startup: September 2000 26.Units in Test Status (Prior to Commercial Operation):
PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, FROM DISTRZBUTZON          LISTS CONTACT THE DOCUMENT tDCD) ON EXTENSION 415-2083
INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION Forecast Achieved DOCKET NO.UNIT NAME DATE COMPLETED BY TELEPHONE 50-315 D.C.Cook Unit1 October 4, 1999 J.W.Minor 616-465-5901 AVERAGE DAILY POWER LEVEL (MWe-Net)September 1999 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL 9/1/99 9/2/S9 9/3/99 9/4/99 9/5/99 9/6/99 9/7/99 9/8/99 9/9/99 9/10/99 9/11/99 9/12/S9 9/13/99 9/14/99 9/15/99 9/16/99 9/1 7/99 9/18/99 9/19/99 9/20/99 9/21/99 9/22/S9 9/23199 9/24/99 9/25/99 9/26/99 9/27/99 9/28/99 9/29/99 9/30/99 4f lf I I DOCKET NO.UNIT NAME.DATE COMPLETED BY TELEPHONE PAGE 50-315 D.C.Cook Unit 1.October 1, 1999 S.A.Richardson 616-465-5901 1 of1 UNIT SHUTDOWNS AND POWER REDUCTIONS
* CONTROL'ESK TOTAL NUMBER     OF. COPIES REQUIRED: LTTR         8   ENCL     8
-September 1999 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT NO.DATE TYPE'OURS REASON REACTOR REPORT NO.CODE CODEs CAUSE AND CORRECTIVE ACTION TO PREVENT RECURRENCE 333 090897 F 720.0 F 97-010 97-011 97-012 97-013 97-014 97-016 NIA N/A N/A N/A N/A N/A NIA NIA NIA NIA N/A N/A The unit remained shutdown to resolve design basis questions discovered during the NRC Architect and Engineering (AE)Inspection.
 
1 TYPE: F: Forced S: Scheduled 2 REASON: A: Equipment Failure (Explain)B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error (Explain)H: Other (Explain)3 METHOD: 1: Manual 2: Manual Scram 3: Automatic Scram 4: Other (Explain)4 SYSTEM: Exhibit G-Instructions for preparation of data entry sheets for Licensee Event Report (LER)File (NUREG 0161)5 COMPONENT:
One Cook Pbce BridgnarLMI 49106 61646991 g
Exhibit I: Same Source r~4>~}}
lMlkl8A NECNEGQN PQWM October 12, 1999 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Document Control Manager:
Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 1 Technical Specification 6.9.1.8, the attached Monthly Operating Report for September 1999 is submitted.
Sincerely, R. C. Godley Regulatory Affairs Director RCG/mbd Attachment c:       NRC Region III NRC Project Manager- NRR NRC Resident Inspector ANI Nuclear Engineering Department INPO Records Center A. C.       Bakken, III G. T.       Gaffney Canton D. R.       Hahn Department of Health S.         Hamming Department of Labor G.         John B.         Lewis McGraw-Hill Companies D. H.       Malin T. P. Noonan-D. W. Paul Lancaster J. E. Pollock R. P. Powers Regulatory Licensing Manager M. W. Rencheck W. H. Schalk D. G. Turner
'Ir9'i02i0i6i 990930....
050003i5" PDR   ADOCK R                           PDR AEfr~lrrrerfca's Errergr f'arlrrer
 
I
        ~ ~ ~ ) r,>o, ~~
                          ~ '
p
(+
t E
I )
 
I     \
J 1                               N.R.C. OPERATING DATA REPOR
                                      ~ ~  ~
DOCKET NO.             50- 315 DATE                  October 4, 1999 COMPLETED BY          J. W. Minor TELEPHONE              616-465-5901 OPERATING STATUS                                                      Notes:
: 1. Unit Name                                D. C. Cook Unit1
: 2. Reporting Period                                     Sept-99
: 3. Licensed Thermal Power (MWt)                         3250
: 4. Name Plate Rating (Gross MWe)                       1152
: 5. Design Electrical Rating (Net MWe)                   1020
: 6. Maximum Dependable Capacity (GROSS MWe)              1056
: 7. Maximum Dependable Capacity (Net MWe)               1000
: 8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons:
: 9. Power Level to Which Restricted, If Any (Net MWe):
: 10. Reasons For Restrictions, If Any:
This Month              Year-to-Date              Cumulative
: 11. Hours in Reporting Period                     720.0                  6552.0                      216936.0
: 12. No. of Hrs. Reactor Was Critical               0.0                      0.0                      151285.3
: 13. Reactor Reserve Shutdown Hours                 0.0                      0.0                        463.0
: 14. Hours Generator on Line                       0.0                      0.0                      148821.1
: 15. Unit Reserve Shutdown Hours                   0.0                    , 0.0                        321.0
: 16. Gross Thermal Energy Gen. (MWH)               0.0                      0.0                  440194814.0
: 17. Gross Electrical Energy Gen. (MWH)             0.0                      0.0                  143013940.0
: 18. Net Electrical Energy Gen. (MWH)               0.0                       0.0                   137597640.0
: 19. Unit Service Factor                            0.0                       0.0                           69.2
: 20. Unit Availability Factor                      0.0                       0.0                           69.2
: 21. Unit Capacity Factor (MDC Net)                  0.0                       0.0                           63.1
: 22. Unit Capacity Factor (DER Net)                  0.0                       0.0                           61.5
: 23. Unit Forced Outage Rate                        100.0                   100.0                           15.6
: 24. Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):
None
: 25. If Shut Down At End of Report Period, Estimated Date of Startup:
September 2000
: 26. Units in Test Status (Prior to Commercial Operation):
Forecast               Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION
 
DOCKET NO. 50- 315 UNIT NAME      D.C. Cook Unit1 DATE          October 4, 1999 COMPLETED BY  J. W. Minor TELEPHONE      616-465-5901 AVERAGE DAILYPOWER LEVEL (MWe-Net)
September 1999 DAY   AVERAGE DAILY                       DAY   AVERAGE DAILY POWER LEVEL                                POWER LEVEL 9/1/99                                   9/1 7/99 9/2/S9                                    9/18/99 9/3/99                                   9/19/99 9/4/99                                   9/20/99 9/5/99                                   9/21/99 9/6/99                                   9/22/S9 9/7/99                                   9/23199 9/8/99                                   9/24/99 9/9/99                                   9/25/99 9/10/99                                   9/26/99 9/11/99                                   9/27/99 9/12/S9                                   9/28/99 9/13/99                                   9/29/99 9/14/99                                   9/30/99 9/15/99 9/16/99
 
4f lf I I
 
DOCKET NO.           50- 315 UNIT NAME            D.C. Cook Unit 1.
                                                                                                        . DATE                  October 1, 1999 COMPLETED BY          S. A. Richardson TELEPHONE            616-465-5901 PAGE                  1 of1 UNIT SHUTDOWNS AND POWER REDUCTIONS - September 1999 METHOD OF SHUTTING     LICENSEE DURATION                   DOWN         EVENT         SYSTEM     COMPONENT             CAUSE AND CORRECTIVE ACTION NO. DATE TYPE'OURS             REASON     REACTOR     REPORT NO. CODE       CODEs                       TO PREVENT RECURRENCE 333   090897 F     720.0             F                     97-010       NIA        NIA          The unit remained shutdown to resolve design 97-011       N/A        NIA          basis questions discovered during the NRC 97-012       N/A        NIA          Architect and Engineering (AE) Inspection.
97-013       N/A        NIA 97-014       N/A       N/A 97-016        N/A       N/A 1 TYPE:         2 REASON:                              3 METHOD:                4 SYSTEM:                                  5 COMPONENT:
F: Forced       A: Equipment Failure (Explain)         1: Manual                Exhibit G - Instructions                  Exhibit I: Same Source S: Scheduled    B: Maintenance or Test                 2: Manual Scram          for preparation of data C: Refueling                           3: Automatic Scram        entry sheets for Licensee D: Regulatory Restriction             4: Other (Explain)        Event Report (LER) File E: Operator Training and                                         (NUREG 0161)
License Examination F: Administrative G: Operational Error (Explain)
H: Other (Explain)
 
4 r ~ >~}}

Latest revision as of 11:52, 22 October 2019

Monthly Operating Rept for Sept 1999 for DC Cook Nuclear Plant,Unit 1.With 991012 Ltr
ML17335A563
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 09/30/1999
From: Minor J, Richardson S
INDIANA MICHIGAN POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9910210161
Download: ML17335A563 (8)


Text

c>TZaoaz REGULATORY INFORMATION DISTRIBUTIO SYSTEM (RIDS)

TARIZED: NO DOCKET FACIL:50-315 Donald C. Cook Nuclear Power Plant, Unit 1, Indiana M 05000315 AUTH. NAME AUTHOR AFFILIATION MINOR,J.W. Indiana Michigan Power Co.

RICHARDSON,S.A. Indiana Michigan Power Co.

RECIP.NAME RECIPIENT AFFILIATION ltr. t I

SUBJECT:

Monthly operatin 1999 for DC Cook Nuclear Plant, Unit .With 991012 DISTRIBUTION CODE: IE24D COP1ES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs)

NOTES: E RECIPIENT COPIES RECIPIENT COPIES XD CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL STANG, J 1 1 INTERNAL: FILE CENTER 01 1 1 OC/DBA/PAD 1 1

~RES'/DRAA'/OERAE~ 1 1 RGN3 1 1 EXTERNAL: LMITCO MARSHALL 1 1 NOAC 1 1 NRC PDR 1 1 D

M

'E NOTE TO ALL "RZDS" RECIPZENTS:

PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, FROM DISTRZBUTZON LISTS CONTACT THE DOCUMENT tDCD) ON EXTENSION 415-2083

  • CONTROL'ESK TOTAL NUMBER OF. COPIES REQUIRED: LTTR 8 ENCL 8

One Cook Pbce BridgnarLMI 49106 61646991 g

lMlkl8A NECNEGQN PQWM October 12, 1999 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Document Control Manager:

Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 1 Technical Specification 6.9.1.8, the attached Monthly Operating Report for September 1999 is submitted.

Sincerely, R. C. Godley Regulatory Affairs Director RCG/mbd Attachment c: NRC Region III NRC Project Manager- NRR NRC Resident Inspector ANI Nuclear Engineering Department INPO Records Center A. C. Bakken, III G. T. Gaffney Canton D. R. Hahn Department of Health S. Hamming Department of Labor G. John B. Lewis McGraw-Hill Companies D. H. Malin T. P. Noonan-D. W. Paul Lancaster J. E. Pollock R. P. Powers Regulatory Licensing Manager M. W. Rencheck W. H. Schalk D. G. Turner

'Ir9'i02i0i6i 990930....

050003i5" PDR ADOCK R PDR AEfr~lrrrerfca's Errergr f'arlrrer

I

~ ~ ~ ) r,>o, ~~

~ '

p

(+

t E

I )

I \

J 1 N.R.C. OPERATING DATA REPOR

~ ~ ~

DOCKET NO. 50- 315 DATE October 4, 1999 COMPLETED BY J. W. Minor TELEPHONE 616-465-5901 OPERATING STATUS Notes:

1. Unit Name D. C. Cook Unit1
2. Reporting Period Sept-99
3. Licensed Thermal Power (MWt) 3250
4. Name Plate Rating (Gross MWe) 1152
5. Design Electrical Rating (Net MWe) 1020
6. Maximum Dependable Capacity (GROSS MWe) 1056
7. Maximum Dependable Capacity (Net MWe) 1000
8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons:
9. Power Level to Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Year-to-Date Cumulative

11. Hours in Reporting Period 720.0 6552.0 216936.0
12. No. of Hrs. Reactor Was Critical 0.0 0.0 151285.3
13. Reactor Reserve Shutdown Hours 0.0 0.0 463.0
14. Hours Generator on Line 0.0 0.0 148821.1
15. Unit Reserve Shutdown Hours 0.0 , 0.0 321.0
16. Gross Thermal Energy Gen. (MWH) 0.0 0.0 440194814.0
17. Gross Electrical Energy Gen. (MWH) 0.0 0.0 143013940.0
18. Net Electrical Energy Gen. (MWH) 0.0 0.0 137597640.0
19. Unit Service Factor 0.0 0.0 69.2
20. Unit Availability Factor 0.0 0.0 69.2
21. Unit Capacity Factor (MDC Net) 0.0 0.0 63.1
22. Unit Capacity Factor (DER Net) 0.0 0.0 61.5
23. Unit Forced Outage Rate 100.0 100.0 15.6
24. Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):

None

25. If Shut Down At End of Report Period, Estimated Date of Startup:

September 2000

26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION

DOCKET NO. 50- 315 UNIT NAME D.C. Cook Unit1 DATE October 4, 1999 COMPLETED BY J. W. Minor TELEPHONE 616-465-5901 AVERAGE DAILYPOWER LEVEL (MWe-Net)

September 1999 DAY AVERAGE DAILY DAY AVERAGE DAILY POWER LEVEL POWER LEVEL 9/1/99 9/1 7/99 9/2/S9 9/18/99 9/3/99 9/19/99 9/4/99 9/20/99 9/5/99 9/21/99 9/6/99 9/22/S9 9/7/99 9/23199 9/8/99 9/24/99 9/9/99 9/25/99 9/10/99 9/26/99 9/11/99 9/27/99 9/12/S9 9/28/99 9/13/99 9/29/99 9/14/99 9/30/99 9/15/99 9/16/99

4f lf I I

DOCKET NO. 50- 315 UNIT NAME D.C. Cook Unit 1.

. DATE October 1, 1999 COMPLETED BY S. A. Richardson TELEPHONE 616-465-5901 PAGE 1 of1 UNIT SHUTDOWNS AND POWER REDUCTIONS - September 1999 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE'OURS REASON REACTOR REPORT NO. CODE CODEs TO PREVENT RECURRENCE 333 090897 F 720.0 F 97-010 NIA NIA The unit remained shutdown to resolve design 97-011 N/A NIA basis questions discovered during the NRC 97-012 N/A NIA Architect and Engineering (AE) Inspection.97-013 N/A NIA 97-014 N/A N/A 97-016 N/A N/A 1 TYPE: 2 REASON: 3 METHOD: 4 SYSTEM: 5 COMPONENT:

F: Forced A: Equipment Failure (Explain) 1: Manual Exhibit G - Instructions Exhibit I: Same Source S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Licensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161)

License Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain)

4 r ~ >~