ML21336A797: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:}}
{{#Wiki_filter:Point Beach GL 2004-02 Resolution Update NextEra Energy Point Beach, LLC (NextEra)
December 9, 2021
 
Meeting Agenda
* Overview of Plant Layout and Strainer Configuration
* Overview of Risk-Informed Resolution Approach
* Risk and Uncertainty Quantification
* Content of Submittal
* Current Status and Submittal Schedule Meeting Objectives
* Communicate current status of PBN response to GL 2004-02
* Obtain staff feedback on the overall risk-informed resolution path 2
 
PBN Plant Layout
* Westinghouse 2-loop pressurized water reactor (PWR) with large dry containment
* Two redundant emergency core cooling system (ECCS) and containment spray (CS) trains
    - Each train has a high-head safety injection (SI) pump, residual heat removal (RHR) pump, and CS pump
    - During recirculation, the CS and SI pumps take suction from the RHR pump discharge 3
 
Sump Strainer Arrangement Unit 1              Unit 2
* PCI Sure-Flow strainers
* Vertical disk modules around a core tube
* Surface area of 1904.6 ft2 per train 4
 
===Background===
* Previous GL Response submitted to the NRC in 2017 (ML17363A253)
* NRC performed an audit of the submittal in January 2019 and issued an audit report in December 2019 with several questions
* PBN was able to address all questions from the audit report except for Mineral Wool cassettes having a lower destruction pressure than assumed
* NextEra conducted an alternative analysis for PBN to determine the best path for closeout of GL 2004-02
* The selected option was the use of a risk-informed resolution approach 5
 
Overview of Risk-Informed Approach
* PBNs risk-informed approach is similar to Vogtle
* Overall evaluation based on models that have been used in the past and accepted by the NRC for GSl-191 resolution
* Screening of break scenarios and high likelihood equipment configurations
* Multiple breaks postulated at each Class 1 weld within first isolation valve on primary loop
* NARWHAL software evaluated each primary side break to determine if it would result in strainer failures due to effects of debris
* In-vessel downstream effects analyzed in a bounding evaluation outside of NARWHAL 6
 
Overview of Risk-Informed Approach
* Conditional failure probabilities (CFPs) calculated for each equipment lineup and PRA break size category
* Change in core damage frequency (CDF) calculated outside PRA model using LOCA frequencies and equipment failure probabilities
* Change in large early release frequency (LERF) calculated from conditional large early release probability for a large LOCA given core damage
* Risk contribution of secondary side breaks evaluated conservatively assuming all breaks fail the strainers due to effects of debris
* The total CDF and LERF values are obtained from the PBN PRA model
* Risk quantification results compared with RG 1.174 acceptance guidelines 7
 
PBN Risk-Informed Approach 8
 
Revision to Debris Generation Calculations
* ZOI size for mineral wool increased to 5.4D
* Mineral wool insulation is similar to K-Wool, which is classified as unjacketed mineral wool with wire mesh reinforcement in NEI 04-07
* K-Wool went through air jet impact testing and was assigned a ZOI size of 5.4D per NEI 04-07 SE
    - Tested K-Wool had wire mesh lining and fabric cover
* Mineral wool insulation at PBN is encapsulated in stainless steel cassettes
* All mineral wool within the 5.4D ZOI is assumed to be fines
    - Shown to be more conservative than using 17D ZOI and LDFG size distribution
* This assumption is similar to that used by Surry and North Anna 9
 
Acceptance Criteria for Risk Quantification
* NARWHAL software used to evaluate strainer performance
    - Strainer head loss vs. pump NPSH margin and strainer structural margin NPSHr adjusted for degasification using RG 1.82 methodology
    - Gas voids from degasification or flashing compared with acceptance limits
    - Debris loads of a break compared with debris limits
    - Head loss compared with acceptance criterion for partially submerged strainer
* Bounding analyses were performed for the following acceptance criteria
    - Upstream blockage does not prevent water from reaching sump
    - Pump performance not affected by air intrusion from vortexing
    - Penetrated debris within ex-vessel wear and blockage limits
    - In-vessel fiber load within WCAP-17788 limit for Westinghouse two-loop plant 10
 
Evaluation of In-Vessel Downstream Effects
* In-vessel downstream effects was analyzed outside of NARWHAL following latest NRC review guidance
* Determined total in-vessel fiber load for the bounding hot leg break using WCAP-17788 methodology
* Maximum total in-vessel fiber load is ~85 g/FA, which is less than the limit in WCAP-17788 for Westinghouse 2-loop plants
* Boric acid precipitation is mitigated by starting an SI pump ~3-5 hours after the accident to supply flow to the cold legs and reactor core inlet
* PBN meets the requirements in the NRC review guide on in-vessel effects
    - In-vessel effects have no contribution to the risk quantification 11
 
Risk Quantification Results
* Risk quantification results for base case:
    - CDF on the order of 1E-08 /yr
    - LERF less than 1E-10 /yr
* Total CDF and LERF were based on PBN PRA model of record for internal and external events
    - Total CDF less than 1E-04 /yr
    - Total LERF on the order of 1E-6 /yr
* Risk increase due to strainer and reactor failures caused by LOCA-generated debris is within Region III of RG 1.174 guideline 12
 
Uncertainty Evaluation
* Following the guidance in NUREG-1855, uncertainty evaluation addresses parametric uncertainty, model uncertainty and completeness uncertainty
* Parametric uncertainty analyzed by rerunning base case model and shifting all input parameters that are not bounding to the more conservative direction
    - Parametric uncertainty cases showed increase in CDF but the result is well within Region III of RG 1.174 guideline
* Model uncertainty quantified by replacing each non-consensus model with an alternative model
    - Four model uncertainty scenarios were analyzed
    - All model uncertainty cases showed results within RG 1.174 Region III
* Completeness uncertainty qualitatively determined to be low, given over four decades of industry and NRC research and analysis in this area 13
 
PBN PRA Model Status
* Internal events and fire PRA models developed and maintained in accordance with RG 1.200, Revision 2
* Recent NRC approved applications
    - TS Initiative 5.b - Surveillance Frequency Control Program
    - 10 CFR 50.69
    - NFPA-805
* The open peer review facts and observations (F&Os) were determined to have no significant impact on the risk-informed resolution of GL 2004-02
* The relevant PRA model assumptions were reviewed and none of the assumptions are key sources of uncertainty for the risk-informed resolution of GL 2004-02 14
 
Submittal Content and Schedule
* Submittal will address the five principles from RG 1.174
* Submittal will include the following enclosures
    - Enclosure 1: Request for exemption from the requirement of using deterministic methodology in 10 CFR 50.46(a)(1)
    - Enclosure 2: License amendment request (LAR) for implementation of risk-informed approach to address debris effects
    - Enclosure 3: Updated GL 2004-02 responses following the NRC content guide (revision bars will be shown for technical changes from the 2017 GL submittal)
    - Enclosure 4: Risk quantification and uncertainty analyses
    - Enclosure 5: Defense in depth measures and safety margin
* NextEra is currently working on the submittal
* Projected date for submittal to the NRC: Spring 2022 15
 
Questions?}}

Latest revision as of 11:12, 18 January 2022

GL 2004-02 Resolution Update - NextEra Energy Point Beach, LLC - December 9, 2021 (Slides)
ML21336A797
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 12/09/2021
From:
Point Beach
To: Booma Venkataraman
NRC/NRR/DORL/LPL3
Venkataraman B
References
Download: ML21336A797 (16)


Text

Point Beach GL 2004-02 Resolution Update NextEra Energy Point Beach, LLC (NextEra)

December 9, 2021

Meeting Agenda

  • Overview of Plant Layout and Strainer Configuration
  • Overview of Risk-Informed Resolution Approach
  • Risk and Uncertainty Quantification
  • Content of Submittal
  • Current Status and Submittal Schedule Meeting Objectives
  • Communicate current status of PBN response to GL 2004-02
  • Obtain staff feedback on the overall risk-informed resolution path 2

PBN Plant Layout

  • Westinghouse 2-loop pressurized water reactor (PWR) with large dry containment

- Each train has a high-head safety injection (SI) pump, residual heat removal (RHR) pump, and CS pump

- During recirculation, the CS and SI pumps take suction from the RHR pump discharge 3

Sump Strainer Arrangement Unit 1 Unit 2

  • PCI Sure-Flow strainers
  • Vertical disk modules around a core tube
  • Surface area of 1904.6 ft2 per train 4

Background

  • Previous GL Response submitted to the NRC in 2017 (ML17363A253)
  • NRC performed an audit of the submittal in January 2019 and issued an audit report in December 2019 with several questions
  • PBN was able to address all questions from the audit report except for Mineral Wool cassettes having a lower destruction pressure than assumed
  • NextEra conducted an alternative analysis for PBN to determine the best path for closeout of GL 2004-02
  • The selected option was the use of a risk-informed resolution approach 5

Overview of Risk-Informed Approach

  • PBNs risk-informed approach is similar to Vogtle
  • Overall evaluation based on models that have been used in the past and accepted by the NRC for GSl-191 resolution
  • Screening of break scenarios and high likelihood equipment configurations
  • Multiple breaks postulated at each Class 1 weld within first isolation valve on primary loop
  • NARWHAL software evaluated each primary side break to determine if it would result in strainer failures due to effects of debris
  • In-vessel downstream effects analyzed in a bounding evaluation outside of NARWHAL 6

Overview of Risk-Informed Approach

  • Conditional failure probabilities (CFPs) calculated for each equipment lineup and PRA break size category
  • Change in core damage frequency (CDF) calculated outside PRA model using LOCA frequencies and equipment failure probabilities
  • Risk contribution of secondary side breaks evaluated conservatively assuming all breaks fail the strainers due to effects of debris
  • The total CDF and LERF values are obtained from the PBN PRA model
  • Risk quantification results compared with RG 1.174 acceptance guidelines 7

PBN Risk-Informed Approach 8

Revision to Debris Generation Calculations

  • ZOI size for mineral wool increased to 5.4D
  • Mineral wool insulation is similar to K-Wool, which is classified as unjacketed mineral wool with wire mesh reinforcement in NEI 04-07
  • K-Wool went through air jet impact testing and was assigned a ZOI size of 5.4D per NEI 04-07 SE

- Tested K-Wool had wire mesh lining and fabric cover

  • Mineral wool insulation at PBN is encapsulated in stainless steel cassettes
  • All mineral wool within the 5.4D ZOI is assumed to be fines

- Shown to be more conservative than using 17D ZOI and LDFG size distribution

  • This assumption is similar to that used by Surry and North Anna 9

Acceptance Criteria for Risk Quantification

  • NARWHAL software used to evaluate strainer performance

- Strainer head loss vs. pump NPSH margin and strainer structural margin NPSHr adjusted for degasification using RG 1.82 methodology

- Gas voids from degasification or flashing compared with acceptance limits

- Debris loads of a break compared with debris limits

- Head loss compared with acceptance criterion for partially submerged strainer

  • Bounding analyses were performed for the following acceptance criteria

- Upstream blockage does not prevent water from reaching sump

- Pump performance not affected by air intrusion from vortexing

- Penetrated debris within ex-vessel wear and blockage limits

- In-vessel fiber load within WCAP-17788 limit for Westinghouse two-loop plant 10

Evaluation of In-Vessel Downstream Effects

  • In-vessel downstream effects was analyzed outside of NARWHAL following latest NRC review guidance
  • Determined total in-vessel fiber load for the bounding hot leg break using WCAP-17788 methodology
  • Maximum total in-vessel fiber load is ~85 g/FA, which is less than the limit in WCAP-17788 for Westinghouse 2-loop plants
  • Boric acid precipitation is mitigated by starting an SI pump ~3-5 hours after the accident to supply flow to the cold legs and reactor core inlet
  • PBN meets the requirements in the NRC review guide on in-vessel effects

- In-vessel effects have no contribution to the risk quantification 11

Risk Quantification Results

  • Risk quantification results for base case:

- CDF on the order of 1E-08 /yr

- LERF less than 1E-10 /yr

  • Total CDF and LERF were based on PBN PRA model of record for internal and external events

- Total CDF less than 1E-04 /yr

- Total LERF on the order of 1E-6 /yr

  • Risk increase due to strainer and reactor failures caused by LOCA-generated debris is within Region III of RG 1.174 guideline 12

Uncertainty Evaluation

  • Following the guidance in NUREG-1855, uncertainty evaluation addresses parametric uncertainty, model uncertainty and completeness uncertainty
  • Parametric uncertainty analyzed by rerunning base case model and shifting all input parameters that are not bounding to the more conservative direction

- Parametric uncertainty cases showed increase in CDF but the result is well within Region III of RG 1.174 guideline

  • Model uncertainty quantified by replacing each non-consensus model with an alternative model

- Four model uncertainty scenarios were analyzed

- All model uncertainty cases showed results within RG 1.174 Region III

  • Completeness uncertainty qualitatively determined to be low, given over four decades of industry and NRC research and analysis in this area 13

PBN PRA Model Status

  • Internal events and fire PRA models developed and maintained in accordance with RG 1.200, Revision 2
  • Recent NRC approved applications

- TS Initiative 5.b - Surveillance Frequency Control Program

- 10 CFR 50.69

- NFPA-805

  • The open peer review facts and observations (F&Os) were determined to have no significant impact on the risk-informed resolution of GL 2004-02
  • The relevant PRA model assumptions were reviewed and none of the assumptions are key sources of uncertainty for the risk-informed resolution of GL 2004-02 14

Submittal Content and Schedule

  • Submittal will address the five principles from RG 1.174
  • Submittal will include the following enclosures

- Enclosure 1: Request for exemption from the requirement of using deterministic methodology in 10 CFR 50.46(a)(1)

- Enclosure 2: License amendment request (LAR) for implementation of risk-informed approach to address debris effects

- Enclosure 3: Updated GL 2004-02 responses following the NRC content guide (revision bars will be shown for technical changes from the 2017 GL submittal)

- Enclosure 4: Risk quantification and uncertainty analyses

- Enclosure 5: Defense in depth measures and safety margin

  • NextEra is currently working on the submittal
  • Projected date for submittal to the NRC: Spring 2022 15

Questions?