MONTHYEARML17310B2322017-11-0707 November 2017 Presentation Slides - NextEra Energy/Fpl - GSI-191 Issue Resolution, Pre-submittal Meeting, September 20, 2017 Project stage: Meeting ML17310B2062017-11-20020 November 2017 Summary of September 20, 2017, Meeting with Florida Power & Light Company and NextEra Energy Regarding Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 Project stage: Meeting ML18136A9052018-05-31031 May 2018 Summary of April 25, 2017, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of Exemption Requests to Support Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 Project stage: Meeting L-20-162, Supplemental Response to NRC Generic Letter 2004-022020-11-30030 November 2020 Supplemental Response to NRC Generic Letter 2004-02 Project stage: Request 0CAN122001, Final Response to NRC Generic Letter 2004-022020-12-10010 December 2020 Final Response to NRC Generic Letter 2004-02 Project stage: Request ML21062A0642021-03-0202 March 2021 NRR E-mail Capture - Request for Additional Information for Diablo Canyon Generic Letter 2004-02 Submittal (L-2017-LRC-0000) Project stage: RAI NL-21-0020, Final Supplemental Response to NRC Generic Letter 2004-022021-03-23023 March 2021 Final Supplemental Response to NRC Generic Letter 2004-02 Project stage: Request DCL-21-034, Response to Request for Additional Information on Final Supplemental Response to Generic Letter 20042021-04-15015 April 2021 Response to Request for Additional Information on Final Supplemental Response to Generic Letter 2004 Project stage: Supplement ML21118A0072021-04-28028 April 2021 Final Response and Close-out to Generic Letter 2004-02 Project stage: Request PMNS20210610, Public Meeting Regarding Path Forward for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 22021-05-17017 May 2021 Public Meeting Regarding Path Forward for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 2 Project stage: Request ML21134A0232021-05-18018 May 2021 GL 2004-02 Resolution Update - NextEra Energy Point Beach, LLC (NextEra) Project stage: Request L-04-002, Response to Request for Additional Information Regarding Generic Letter 2004-022021-05-27027 May 2021 Response to Request for Additional Information Regarding Generic Letter 2004-02 Project stage: Response to RAI ML21161A2992021-06-17017 June 2021 Summary of May 18, 2021 Public Webinar with Nextera Energy Point Beach, LLC Regarding Path Forward for Generic Letter 2004-02 Closure Project stage: Other ML21168A2612021-06-17017 June 2021 (Vcsns), Unit 1 - NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-water Reactors - Final Supplemental Response Project stage: Request ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 Project stage: RAI ML21203A3142021-07-29029 July 2021 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML21232A0402021-08-20020 August 2021 Notice of Teleconference with Entergy Operations, Inc. Concerning Final Response to Generic Letter 2004-02 at Arkansas Nuclear One, Units 1 and 2 Project stage: Meeting ML21252A3212021-08-20020 August 2021, 30 August 2021, 14 September 2021 ANO Meeting Summary for September 1, 2020 Public Meeting/Teleconference Project stage: Request ML21242A2792021-08-30030 August 2021 ANO Slides Presentation for 9-1-21 Public Meeting Project stage: Meeting ML21252A2662021-09-14014 September 2021 Summary of September 1, 2021, Teleconference Meeting with Entergy Operations, Inc. Concerning the Final Response to Generic Letter 2004-02 for Arkansas Nuclear One, Units 1 and 2 Project stage: Meeting ML21211A0822021-09-24024 September 2021 Closeout of Generic Letter 2004 02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML21260A1612021-09-24024 September 2021 Closeout of Generic Letter 2004 02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other RA-21-0230, Duke Energy - Final Supplemental Response to NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors2021-09-30030 September 2021 Duke Energy - Final Supplemental Response to NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Request 0CAN102101, Final Request for Additional Information Concerning Generic Letter 2004-022021-10-0404 October 2021 Final Request for Additional Information Concerning Generic Letter 2004-02 Project stage: Request ML21214A1782021-10-0808 October 2021 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors Project stage: Other PMNS20211455, Pre-Submittal Public Meeting Regarding License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 22021-12-0303 December 2021 Pre-Submittal Public Meeting Regarding License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 2 Project stage: Meeting ML21336A7972021-12-0909 December 2021 GL 2004-02 Resolution Update - NextEra Energy Point Beach, LLC - December 9, 2021 (Slides) Project stage: Request ML22019A2792022-01-20020 January 2022 Summary of Public Webinar with NextEra Energy Point Beach, LLC Regarding Future License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Project stage: Other ML22013A3722022-01-27027 January 2022, 31 January 2022 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Request ML22019A2652022-01-27027 January 2022 Us NRC Staff Review of Documentation Provided by Firstenergy Nuclear Operating Co. for Beaver Valley, Units 1&2 Concerning Resolution of Generic Letter 2004-02 - Potential Impact of Debris Blockage on Emergency Recirculation During Design B Project stage: Approval ML22013A3392022-01-31031 January 2022 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML22061A0562022-03-29029 March 2022 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML22112A1482022-04-22022 April 2022 Correction_H. B. Robinson Steam Electric Plant, Unit 2 - Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-02 Project stage: RAI ML22109A1752022-04-27027 April 2022 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other RA-22-0144, Response to NRC Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-022022-05-19019 May 2022 Response to NRC Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-02 Project stage: Supplement ML22164A8612022-06-24024 June 2022 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML22167A1702022-07-14014 July 2022 Closeout of Generic Letter 2004 02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) Project stage: Draft RAI ML22251A1292022-09-0909 September 2022 Request for Additional Information Related to Response to Generic Letter 2004-04 Project stage: RAI ML22335A4142022-12-21021 December 2022 Request for Withholding Information from Public Disclosure for Dominion Fleet Response to Request for Additional Information Regarding NRC Generic Letter 2004-02 Project stage: RAI L-2023-075, Response to Request for Additional Information (RAI) Regarding Exemption Request, License Amendment Request and Revised Response in Support of a Risk-Informed Resolution of Generic Letter 2004-022023-06-0909 June 2023 Response to Request for Additional Information (RAI) Regarding Exemption Request, License Amendment Request and Revised Response in Support of a Risk-Informed Resolution of Generic Letter 2004-02 Project stage: Response to RAI ML23193A9382023-07-18018 July 2023 – Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML23188A0202023-07-26026 July 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML23200A1832023-08-0303 August 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML23243A9102023-09-0606 September 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML24012A0492024-01-11011 January 2024 Request for Additional Information Regarding Final Response to Generic Letter 2004-02 Project stage: RAI ML24040A1492024-02-0909 February 2024 Response to NRC Request for Additional Information Regarding Final Response to Generic Letter 2004-02 Project stage: Response to RAI ML24040A0962024-02-0909 February 2024 Notification of Readiness for NRC 95001 Inspection Project stage: Request ML24101A1942024-04-22022 April 2024 Closeout Letter for GL 2004-02 Project stage: Other ML24067A1032024-04-25025 April 2024 Closeout of Generic Letter 2004 02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other 2021-09-24
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24296A0652024-10-22022 October 2024 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - Verbal Authorization of Relief Request for the Proposed Alternative ANO2-RR-24-001 ML24227A0072024-08-13013 August 2024 NRR E-mail Capture - LIC-109 Acceptance - ANO 2 - Proposed Alternative for Implementation of Extended Reactor Vessel In-Service Inspection Interval (ANO2-ISI-24-02) - EPID L-2024-LLR-0048 ML24218A0652024-08-0202 August 2024 NRR E-mail Capture - LIC-109 Acceptance Review - Arkansas Nuclear One, Unit 1 - License Amendment Request - Request for Review and Approval Changes to SAR and to a Confirmatory Order - Pzr Htr Emergency Power Supply - EPID L-2024-LLA-0092 ML24180A0022024-06-26026 June 2024 NRR E-mail Capture - LIC-109 Acceptance - ANO 1 and 2 - Proposed Alternatives for Examinations of SG Pressure Retaining Welds and Full Penetrations Nozzles - EPID L-2024-LLR-0038 ML24149A3672024-05-28028 May 2024 August 2024 Emergency Preparedness Exercise Inspection - Request for Information ML24117A0262024-04-26026 April 2024 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action License Amendment Request to Revise Typographical Errors in Technical Specifications ML24088A0082024-03-27027 March 2024 NRR E-mail Capture - ANO-2 -- TSTF-505 Post-Audit Final RAI (L-2023-LLA-0052) ML23269A0232023-09-22022 September 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - TSTF-505 Audit Questions ML23240A3412023-08-28028 August 2023 NRR E-mail Capture - ANO-2, Grand Gulf, and River Bend - Acceptance Review of LAR Revising TSs to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23194A1752023-07-13013 July 2023 NRR E-mail Capture - ANO-1 - Acceptance Review of Alternative Request ANO1-ISI-037 ML23187A0432023-07-0303 July 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 1 - TSTF-505 Audit Agenda ML23166A0132023-06-14014 June 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 1 - TSTF-505 Audit Questions ML23130A2752023-05-10010 May 2023 NRR E-mail Capture - ANO Unit 2- Acceptance of Requested Licensing Action LAR to Adopt TSTF-505 Revision 2 ML23118A0692023-04-28028 April 2023 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to Modify ANO-1 TS 3.3.1, Reactor Protection System Instrumentation (L-2023-LLA-0048) ML23104A1052023-03-10010 March 2023 NRR E-mail Capture - ANO-2 Final RAI Alternative Request for Life-of-Repair of RVCH Pen. 46 ML23072A3672023-03-0909 March 2023 NRR E-mail Capture - Entergy Fleet - Acceptance Review of Quality Assurance Program Manual Reduction in Commitment ML23039A0872023-02-0808 February 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - Acceptance Review of Relief Request ANO2-RR-23-001, Half-Nozzle Repair of RVCH Penetration 46 (L-2023-LLR-0000) ML23026A1322023-01-26026 January 2023 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to Adopt TSTF-505 Revision 2 ML22354A0122022-12-19019 December 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Acceptance Review of Request for Alternative ANO-CISI-002 Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (L-2022-LLR-0080) ML22349A0112022-12-14014 December 2022 NRR E-mail Capture - Final RAI Relief Request ANO1-ISI-035 ML22341A1202022-12-0707 December 2022 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation (L-2022-LLA-0161) ML22273A0982022-09-30030 September 2022 NRR E-mail Capture - ANO Units 1 and 2 - Acceptance of Requested Licensing Action Emergency Plan Staffing Requirements ML22265A2012022-09-22022 September 2022 NRR E-mail Capture - ANO-1 - Acceptance Review of Relief Request ANO1-ISI-036 ML22188A1782022-07-0707 July 2022 NRR E-mail Capture - ANO-1 - Acceptance Review of Relief Request ANO1-ISI-035 ML22174A1362022-06-23023 June 2022 NRR E-mail Capture - ANO-2 Final RAI Relief Requests ANO2-ISI-023 Through -028 (EPIDs L-2022-LLR-0022 Through -0027) ML22151A3262022-05-31031 May 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22124A2452022-05-0404 May 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI 2 License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22108A1642022-04-18018 April 2022 NRR E-mail Capture - ANO-1: Final RAI License Amendment Request Concerning TS Changes Due to Revised Dose Calculations (L-2021-LLA-0181) ML22081A3902022-03-22022 March 2022 NRR E-mail Capture - ANO-2 - Acceptance Review of Relief Requests ANO2-ISI-023, -024, -025, -026, -027, and -028 (Epids: L-2022-LLR-022, -023, -024, -025, -026, and -027) ML22034A5482022-02-0303 February 2022 NRR E-mail Capture - Final RAI License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22020A0822022-01-19019 January 2022 NRR E-mail Capture - ANO-1 and 2 - Final RAI 2 License Amendment Requests to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML22020A0742022-01-13013 January 2022 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action Alternative ANO2-PT-003 ML21314A1212021-11-0909 November 2021 Verbal Authorization of Relief Request ANO2-RR-21-002 ML21312A0382021-11-0505 November 2021 NRR E-mail Capture - ANO-2 RAI Relief Request ANO2-RR-21-002 ML21312A4792021-11-0505 November 2021 Email: NRC Staff Preliminary Questions Regarding X Energy LLC Xe-100 Topical Report: Risk-Informed Performance-Based Licensing Basis Development ML21308A5602021-11-0404 November 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, Grand Gulf, River Bend, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML21292A0112021-10-18018 October 2021 NRR E-mail Capture - ANO, 1 and 2, Grand Gulf, River Bend, Waterford, 3 - Acceptance Review of LAR to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21287A1692021-10-13013 October 2021 Record of 10-13-21 Verbal Authorization of ANO2-R&R-012 (L-2021-LLR-0082) ML21298A1562021-10-11011 October 2021 NRR E-mail Capture - ANO-2 Final RAI Relief Request ANO2-R&R-012 Concerning Rv Closure Head Penetration 46 ML21273A0672021-09-29029 September 2021 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request to Adopt a Safety Function Determination Program ML21238A3742021-08-23023 August 2021 RFI Email - Cyber PI&R Inspection (ANO) ML21252A0052021-08-20020 August 2021 NRR E-mail Capture - ANO-1 and 2 Final RAI License Amendment Request to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21202A1662021-07-20020 July 2021 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action Alternative ANO2-PT-003 ML21201A0062021-07-19019 July 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 ML21179A0052021-06-25025 June 2021 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21179A0042021-06-25025 June 2021 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21174A0342021-06-22022 June 2021 NRR E-mail Capture - Entergy Fleet (ANO, Ggulf, Rbend, & Waterford) - Acceptance Review for Relief Request to Use a Provision of a Later Edition of the ASME Code, Section XI for Periodic System Pressure Tests Exemptions ML21116A1092021-04-26026 April 2021 NRR E-mail Capture - ANO-1 and ANO-2: Final Supplemental RAI Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of ECP Supply Piping 2024-08-02
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24143A0632024-05-22022 May 2024 Notification of Inspection (NRC Inspection Report 05000368/2024003) and Request for Information ML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information ML24088A0082024-03-27027 March 2024 NRR E-mail Capture - ANO-2 -- TSTF-505 Post-Audit Final RAI (L-2023-LLA-0052) ML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23104A1052023-03-10010 March 2023 NRR E-mail Capture - ANO-2 Final RAI Alternative Request for Life-of-Repair of RVCH Pen. 46 ML23019A0672023-01-19019 January 2023 Inservice Inspection Request for Information ML22349A0112022-12-14014 December 2022 NRR E-mail Capture - Final RAI Relief Request ANO1-ISI-035 ML22213A1662022-08-0101 August 2022 Information Request, Security IR 2022401 ML22208A0542022-07-26026 July 2022 Request for Information ML22174A1362022-06-23023 June 2022 NRR E-mail Capture - ANO-2 Final RAI Relief Requests ANO2-ISI-023 Through -028 (EPIDs L-2022-LLR-0022 Through -0027) ML22159A3242022-06-0909 June 2022 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000313/2022003 and 05000368/2022003) and Request for Information ML22151A3262022-05-31031 May 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22122A2952022-05-0404 May 2022 Notification of Inspection NRC Inspection Report 05000368/2022003 and Request for Information ML22124A2452022-05-0404 May 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI 2 License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22108A1642022-04-18018 April 2022 NRR E-mail Capture - ANO-1: Final RAI License Amendment Request Concerning TS Changes Due to Revised Dose Calculations (L-2021-LLA-0181) ML22034A5482022-02-0303 February 2022 NRR E-mail Capture - Final RAI License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22020A0822022-01-19019 January 2022 NRR E-mail Capture - ANO-1 and 2 - Final RAI 2 License Amendment Requests to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21312A0382021-11-0505 November 2021 NRR E-mail Capture - ANO-2 RAI Relief Request ANO2-RR-21-002 ML21286A7132021-10-15015 October 2021 ANO2022010 Tfp RFI Stg, Arkansas Nuclear One, Units 1 and 2 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000313/2022010 and 05000368/2022010) and Request for Information ML21273A0672021-09-29029 September 2021 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request to Adopt a Safety Function Determination Program ML21236A3222021-09-19019 September 2021 Request for Information ML21252A0052021-08-20020 August 2021 NRR E-mail Capture - ANO-1 and 2 Final RAI License Amendment Request to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21204A0842021-07-28028 July 2021 ANO Phase 4 2021013 RFI Gap ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 0CAN042105, Supplement to Response to Request for Additional Information Reduction of Commitment to the Entergy Operations Quality Assurance Program Manual Description2021-04-30030 April 2021 Supplement to Response to Request for Additional Information Reduction of Commitment to the Entergy Operations Quality Assurance Program Manual Description ML21116A1092021-04-26026 April 2021 NRR E-mail Capture - ANO-1 and ANO-2: Final Supplemental RAI Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of ECP Supply Piping ML21105A0122021-04-0909 April 2021 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Adopt a Safety Function Determination Program ML21071A2172021-03-10010 March 2021 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Proposed Change to Quality Assurance Program Manual ML21026A2682021-01-26026 January 2021 Request for Information ML21022A0842021-01-22022 January 2021 Request for Additional Information - Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of Emergency Cooling Pond Supply Piping - Arkansas Nuclear One,Units 1 and 2 -Entergy Operations, Inc. NON-PROPRIETARY Redacted ML21019A5142021-01-14014 January 2021 March 2021 Emergency Preparedness Exercise Inspection - Request for Information ML20324A6412020-11-19019 November 2020 NRR E-mail Capture - ANO-1 - Final RAI Relief Request ANO1-ISI-034 ML20316A0102020-11-0202 November 2020 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Concerning Relief Request EN-20-RR-01 ML20262H0752020-09-17017 September 2020 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request Concerning Proposed Technical Specification Additions, Deletions, and Relocations ML20260H4762020-09-0909 September 2020 NRR E-mail Capture - ANO-1 Final RAI License Amendment Request to Revise Lov Relay Allowable Values ML20154K7622020-06-0101 June 2020 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request Concerning Proposed Technical Specification Additions, Deletions, and Relocations ML20119A0982020-04-28028 April 2020 Notification of Inspection (NRC Inspection Report 05000368/2020003 and Request for Information ML20106E8522020-04-13013 April 2020 Information Request, NRC Inspection Report 05000313/2020410 and 05000368/2020410 IR 05000313/20204102020-04-13013 April 2020 Information Request, NRC Inspection Report 05000313/2020410 and 05000368/2020410 ML20065H7992020-03-0606 March 2020 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request to Revise Loss of Voltage Relay Allowable Values ML20055E9092020-02-24024 February 2020 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Revise Control Element Assembly Drop Time ML20036D3092020-02-0505 February 2020 NRR E-mail Capture - ANO-2 - Final RAI Alternative Request VRR-ANO2-2019-1 ML20013C7472020-01-10010 January 2020 NRR E-mail Capture - ANO-1 and 2 -- Final RAI #2 LAR to Incorporate Tornado Missile Risk Evaluator (TMRE) Into Licensing Basis ML19316A0242019-11-0707 November 2019 NRR E-mail Capture - ANO-1 - - Final RAI Concerning Relief Request ANO1-ISI-033 (L-2019-LLR-0100) ML19280A0402019-10-0707 October 2019 NRR E-mail Capture - ANO-1 and 2 - Final RAI #1 License Amendment Request to Incorporate Tornado Missile Risk Evaluator (TMRE) Into Licensing Basis ML19339F5902019-09-23023 September 2019 Request for Information: Arkansas Nuclear One, IR 05000313/2019-004 Occupational Radiation Safety Inspection ML19281E0032019-08-0505 August 2019 ANO 2019 PIR Request for Information ML19203A0122019-07-16016 July 2019 Request for Information - Inservice Inspection Activities (NRC Inspection Report 05000313/2019004) ML19106A4322019-04-16016 April 2019 NRR E-mail Capture - ANO-2 Final RAI Re LAR to Add TS Actions to Address Inoperability of the Containment Building Sump 2024-05-22
[Table view] |
Text
From:
Wengert, Thomas Sent:
Friday, July 16, 2021 7:56 AM To:
Keele Jr, Riley D Cc:
nmosher@entergy.com; Clark, Robert; REID, MARK; Dixon-Herrity, Jennifer
Subject:
ANO-1 and 2 - Final RAI RE: Final Response to GL 2004-02 (EPID L-2017-LRC-0000)
Attachments:
ANO - Final RAI Concerning GL 2004-02.pdf On July 9, 2021, the U.S. Nuclear Regulatory Commission (NRC) staff sent Entergy Operations, Inc. (the licensee) the draft Request for Additional Information (RAI) identified below. This RAI relates to the licensees final response to Generic Letter 2004-02 for Arkansas Nuclear One, Units 1 and 2, as described below.
The licensee subsequently informed the NRC staff that a clarification conference call was not needed. Attached is the final RAI with draft removed. As agreed, please provide a response to this RAI within 90 days of this correspondence. A publicly available version of this final RAI will be placed in the NRCs Agencywide Documents Access and Management System (ADAMS).
From: Wengert, Thomas Sent: Friday, July 09, 2021 11:44 AM To: Keele Jr, Riley D <rkeele@entergy.com>
Cc: nmosher@entergy.com; Clark, Robert <RCLARK@entergy.com>; REID, MARK
<mreid1@entergy.com>; Dixon-Herrity, Jennifer <Jennifer.Dixon-Herrity@nrc.gov>
Subject:
ANO-1 and 2 - Draft RAI RE: Final Response to GL 2004-02 (EPID L-2017-LRC-0000)
By letter dated December 10, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20353A115), Entergy Operations Inc. (the licensee), submitted a final response to close Generic Letter (GL) 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors, dated September 13, 2004 (ADAMS Accession No. ML042360586), for Arkansas Nuclear One, Units 1 and 2.
The NRC staff has determined that additional information, as described in the attached request for additional information (RAI), is required for the staff to complete its review of this application.
This RAI is identified as draft at this time to confirm your understanding of the information that the NRC staff needs to complete the evaluation. If the request for information is understood, please respond to this RAI within 30 days of the date of this request.
Please contact me if you would like to set up a conference call with the NRC staff to clarify this request for information.
Tom Wengert Project Manager - Arkansas Nuclear One NRR/DORL/LPL4 (301) 415-4037
Hearing Identifier:
NRR_DRMA Email Number:
1281 Mail Envelope Properties (MN2PR09MB54492F9CDD6DD556B50820708F119)
Subject:
ANO-1 and 2 - Final RAI RE: Final Response to GL 2004-02 (EPID L-2017-LRC-0000)
Sent Date:
7/16/2021 7:55:59 AM Received Date:
7/16/2021 7:55:00 AM From:
Wengert, Thomas Created By:
Thomas.Wengert@nrc.gov Recipients:
"nmosher@entergy.com" <nmosher@entergy.com>
Tracking Status: None "Clark, Robert" <RCLARK@entergy.com>
Tracking Status: None "REID, MARK" <mreid1@entergy.com>
Tracking Status: None "Dixon-Herrity, Jennifer" <Jennifer.Dixon-Herrity@nrc.gov>
Tracking Status: None "Keele Jr, Riley D" <rkeele@entergy.com>
Tracking Status: None Post Office:
MN2PR09MB5449.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 2188 7/16/2021 7:55:00 AM ANO - Final RAI Concerning GL 2004-02.pdf 118327 Options Priority:
Normal Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
REQUEST FOR ADDITIONAL INFORMATION CONCERNING FINAL RESPONSE TO GENERIC LETTER 2004-02, POTENTIAL IMPACT OF DEBRIS BLOCKAGE ON EMERGENCY CIRCULATION DURING DESIGN BASIS ACCIDENTS AT PRESSURIZED WATER REACTORS ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 DOCKET NOS. 50-313 AND 50-368 By letter dated December 10, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20353A115), Entergy Operations Inc. (the licensee), submitted a final response to close Generic Letter (GL) 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors, dated September 13, 2004 (ADAMS Accession No. ML042360586), for Arkansas Nuclear One, Units 1 (ANO-1) and 2 (ANO-2).
The regulation in Section 50.46 of Title 10 of the Code of Federal Regulations requires that plants must be able to maintain adequate long-term core cooling (LTCC) to ensure that the fuel in the core can be cooled and maintained in a safe and stable configuration following a postulated accident. GL 2004-02 requested that licensees provide information confirming that their plants are in compliance with the regulation. Note that the PDF page numbers below are from the ADAMS accession files. During its review of the licensees submittal dated December 10, 2020, the Nuclear Regulatory Commission (NRC) staff identified additional information required to confirm the licensees evaluation. Provide the following information:
- 1) In Enclosure 1, on pg. 11 of 17 (PDF pg. 14), the second paragraph under test parameters appears to have one-train flow and two-train flow reversed. The velocities for one-train flow is listed as 0.008 feet per second (ft/s) (used for Test 1) and two-train as 0.004 ft/s (used for Test 2). Provide the one and two-train flow rates and state which flow rate was used for each test. State which test resulted in greater penetration.
- 2) Provide additional details on how the penetration models at plant scale were developed.
- a. Describe how the penetration amounts determined from the testing were scaled to the plant condition for each unit.
- b. It appears that the model depicted in Figure 3.n.1-9 (PDF pg. 16) was used for both units. Provide justification that the same model is applicable to both units even though the strainer sizes and fiber amounts are significantly different between the units.
- c. Describe the relevance of the time scale on the x-axis of Figure 3.n.1-9. The NRC staff concluded that the axis implies time at a plant scale. Describe the assumptions used to develop the time scale or justify that it is not important to the calculations.
- d. Describe the application of Figures 3.n.1-10 and 11 to each unit (PDF pgs. 16 and 17).
Explain how the difference in strainer area between units is accounted for in the
analysis, considering that the ANO-2 strainer has approximately 1.8 times the area of the ANO-1 strainer.
- 3) In Enclosure 1, on pg. 15 (PDF pg. 18), the ANO-1 in-vessel fiber calculation credits one Reactor Building Spray System (RBSS) pump at minimum flow. Provide the basis for the assumption that one RBSS pump will start and continue to operate (not be shut off) during the period of interest for fiber accumulation at the core inlet. That is, confirm that the RBSS pumps start for large break scenarios and continue to run.
- 4) In Enclosure 2, on pg. 6 (PDF pg. 27), the ANO-2 in-vessel fiber calculation credits one Containment Spray System (CSS) pump at minimum flow. Provide the basis for the assumption that one CSS pump will start and continue to operate (not be shut off) during the period of interest for fiber accumulation at the core inlet. That is, confirm that the CSS pumps start for large break scenarios and continue to run.
- 5) The NRC staff recognizes that substantial chemical effects information was provided in the licensees letter dated December 10, 2020, Final Response to NRC Generic Letter 2004-
- 02. Please also provide the WCAP-17788, Comprehensive Analysis and Test Program for GSI-191 Closure, Test Group Number(s) that are considered representative of plant conditions for ANO-1 and ANO-2.