2021 Point Beach Nuclear Plant End-of-Cycle Meeting Handout
ML22181B084
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 06/30/2022
From:
Reactor Projects Region 3 Branch 4
To:
Shared Package
ML21362A689 List:
References
Download: ML22181B084 (12)


Text

Point Beach Nuclear Plant Annual Assessment Summary 2021 Reactor Oversight Process Nuclear Regulatory Commission - Region III 1

Meetings Purpose Public forum for discussion of Point Beach Nuclear Plants performance in 2021 NRC will address the performance issues identified in the annual assessment 2

1

Region III Organization JACK GIESSNER Regional Administrator MOHAMMED SHUAIBI Deputy Regional Administrator JULIO LARA SABRINA ATACK Director, Division of Reactor Director, Division of Reactor Projects Safety (Acting)

JAMIE HEISERER DAVID CURTIS Deputy Director Deputy Director LAURA KOZAK Branch Chief (Acting)

Regional Inspectors Office Assistant Resident Inspectors THERESA RAY THOMAS HARTMAN VANCE PETRELLA 3

What We Do Safety Security Environment 4

2

What We Regulate Reactors Materials Waste 5

What We Dont Regulate Military Radon X-Rays 6

3

Assurance of Plant Safety Continuous Long-Term Training Maintenance Regulation Compliance Defense In-Depth 7

Regulatory Principles Independence Openness Efficiency Clarity Reliability 8

4

How We Regulate 9

Regulatory Framework NRCs Safety Mission Strategic Performance Areas Cornerstones Cross-Cutting Areas Human Performance--Safety Conscious Work Environment--Problem Identification & Resolution 10 5

Performance Indicators 17 Performance Indicators PIs for each cornerstone Licensee submits data to NRC quarterly Inspection program verifies accuracy Data available on NRC website 11 Significance Threshold Performance Indicators Green White Yellow Red Increasing Safety Significance Inspection Findings Green White Yellow Red Increasing Safety Significance 12 6

Action Matrix Columns Multiple/Repetitive Licensee Regulatory Degraded Unacceptable Degraded Response Response Performance Performance Cornerstone Increasing:

  • Safety Significance
  • Inspection
  • Management Involvement
  • Regulatory Action 13 Industry-Wide Performance 100 91 As of 02/23/2022 90 80 70 60 50 0

40 30 20 10 2 0 0 0 0

1 2 3 4 5 6 14 7

Industry-Wide Inspection Findings Finding data current as of 02/23/2022 450 400 Calendar Year 350 289 2021 data 300 250 200 150 100 50 0 1 0 0

0 1 2 3 4

5 15 Industry-Wide Performance Indicators 7000 6314 6000 Calendar Year 2021 data 5000 4000 3000 2000 1000 5

0 0 0 1

2 3

4 16 8

NRC Annual Assessment Summary Point Beach Nuclear Plant, Units 1 and 2 NextEra, the Licensee, operated the plant safely and in a manner that preserved the public health and safety and protected the environment.

Point Beach Nuclear Plant was in the Licensee Response Column of the NRCs ROP Action Matrix for all quarters of 2021.

NRC plans baseline inspections at Point Beach for 2022.

17 NRC Inspection Activities Point Beach Nuclear Plant for 2021 2450 hours0.0284 days <br />0.681 hours <br />0.00405 weeks <br />9.32225e-4 months <br /> of direct inspections 2 resident inspectors on site - residents make four quarterly inspections per year and walk through the plant every day 9 regional inspections 3 major team inspections Contingency Response - Force-on-Force Testing Evaluations of Changes, Tests and Experiments Emergency Preparedness Exercise Evaluation Unit Two Refueling Outage

  • see presentation notes 18 9

Point Beach Nuclear Plant PIs and Findings January 1 through December 31, 2021 All Green Performance Indicators 5 Green / Severity Level IV inspection findings 19 NRC Response to COVID-19 Mission Critical Functions Monitoring plant activities through inspections and oversight.

Maintaining emergency response capabilities within Regional IRCs and HQ.

Risk-informing "eyes on" inspections through residents and regional inspections.

20 10

NRC Response to COVID-19 Additional Actions Expanded use of telework where appropriate Maintaining emergency response capabilities within Regional IRCs and HQ.

Risk-informing "eyes on" inspections through residents and regional inspections.

21 Subsequent License Renewal Review Process and Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)

Subsequent License NRC Renewal Renewal Application Hearings* Decision (SLRA) Accepted 10 CFR 2 (10 CFR 54.29)

Safety ACRS Review Recommendation (10 CFR 54) (10 CFR54.25) 22 22 11

NRC Social Media Channels

23 23 Contacting the NRC Report an emergency

  • (301) 816-5100 (call collect)

Report a safety concern

  • (800) 695-7403
  • Allegation@nrc.gov General information or questions
  • www.nrc.gov Contact Point Beach Resident Inspectors
  • 630-829-9992 24 12