MONTHYEARML22181B0842022-06-30030 June 2022 2021 Point Beach Nuclear Plant End-of-Cycle Meeting Handout ML21336A7972021-12-0909 December 2021 GL 2004-02 Resolution Update - NextEra Energy Point Beach, LLC - December 9, 2021 (Slides) ML21335A0232021-12-0808 December 2021 Slides - Point Beach Nuclear Plant, Unit Nos. 1 and 2 December 8, 2021 Public Meeting Slides for the Draft Plant-Specific Supplement 23, Second Renewal Dseis Public Meeting ML21285A1212021-08-0505 August 2021 SLRA Public Meeting Discussion Questions August 5 2021 ML21162A2632021-06-11011 June 2021 2020 Point Beach Nuclear Plant End-of-Cycle Meeting Presentation ML21134A0232021-05-18018 May 2021 GL 2004-02 Resolution Update - NextEra Energy Point Beach, LLC (NextEra) ML21042B9452021-02-17017 February 2021 Scoping and Process Meeting - February 17, 2021 ML20240A2702020-08-27027 August 2020 2019 EOC Slide Presentation ML18213A3912018-07-12012 July 2018 Public Meeting ML18179A4032018-06-29029 June 2018 Public Meeting Discussion Points ML18108A0152018-05-0101 May 2018 NextEra Approach to Resolution of Tornado Missile Protection May 1, 2018 ML18121A3392018-05-0101 May 2018 Slides for Point Beach 2017 EOC Open House ML17023A0652017-01-24024 January 2017 Pre-Submittal Call Regarding License Amendment Requests for Prairie Island Nuclear Generating Plant, Units 1 and 2 and Monticello Nuclear Generating Plant Emergency Action Level Scheme Changes ML16291A1772016-10-18018 October 2016 License Amendment Request Pre-Submittal Discussion October 18, 2016 ML16154A6772016-05-25025 May 2016 Annual Assessment Meeting/Open House (Hand Out) ML15112A0672015-04-20020 April 2015 Annual Assessment Meeting Open House - Handout EOC 2014 Mtg ML15091A5172015-04-0606 April 2015 4/6/2015, Meeting Slide for Public Teleconference on Point Beach MCR Abandonment Analysis for Loss of Control Scenarios ML14112A4252014-04-0808 April 2014 Annual Assessment Meeting, 2013 Reactor Oversight Process - Slides ML13162A7902013-06-11011 June 2013 Meeting Slides ML12206A3252012-08-0707 August 2012 G20120513/EDATS: OEDO-2012-0436 - Briefing Book for Meeting with Duke Energy on August 7, 2012 ML1114603332011-05-25025 May 2011 EOC Licensee Presentation Slides ML1107703492011-03-22022 March 2011 3/22/11 PRE-Application Meeting Slides Regarding NFPA 805 License Amendment Request ML1108206992011-03-22022 March 2011 3/22/11 Revised Pre-application Meeting Slides Regarding NFPA 805 License Amendment Request ML1011304452010-04-22022 April 2010 FPL Energy Point Beach Handout from End-Of-Cycle Public Meeting ML0921107842009-07-29029 July 2009 Meeting Slides, Public Meeting with NRC Region III on Point Beach ML0912007212009-04-29029 April 2009 NRC Presentation Handouts for Point Beach 2008 End-of-Cycle Public Meeting ML0912007042009-04-29029 April 2009 Presentation at 2008 End-of-Cycle Public Meeting ML0912007342009-04-29029 April 2009 NRC Slides for Point Beach 2008 End-of-Cycle Public Meeting ML0828905272008-10-14014 October 2008 Meeting with NRC on AST ML0822503302008-10-0606 October 2008 Teleconference Summary Regarding Point Beach Nuclear Plant Supplement to the Auxiliary Feedeater Amendment ML0826819412008-09-24024 September 2008 Meeting Slides, FPL Energy Point Beach Public Meeting with NRC Region III ML0825401402008-09-16016 September 2008 Meeting Slides Point Beach Nuclear Plant Meeting with NRC on Epu. ML0819905262008-07-16016 July 2008 EOC Annual Assessment Meeting Slides ML0705106742007-02-21021 February 2007 NMC Slides for Public Meeting, Conduct of Operations Action Plan Update. ML0632601422006-11-21021 November 2006 11/21/2006 Informational Meeting Regarding Prairie Island License Renewal Application ML0604406422006-02-10010 February 2006 Summary of Public Meeting to Discuss Point Beach Self-Assessments, Summary Letter & Licensee Slides ML0434900602004-11-30030 November 2004 NMC Slides for 11/30/04 Public Meeting ML0413803782004-05-0707 May 2004 NMC New Fuel Supplier Development Initiative ML0412602942004-04-21021 April 2004 Public Meeting Slides, Point Beach 2003 End-of-Cycle Assessment ML0511502282004-04-19019 April 2004 Public Meeting Slides Point Beach EOC Performance Assessment ML0336406072004-01-0505 January 2004 Summary of Meeting with Nuclear Management Company, LLC Potential Repairs That May Overlap Remnant j-groove Welds on the Upper Reactor Vessel Head Penetrations ML0316902142003-06-16016 June 2003 Enclosure 1- NMC Handout Regulatory Conference Concerning Auxiliary Feedwater Orifice Issue for 06/06/2003 Point Beach Regulatory Conference ML0316903022003-06-16016 June 2003 Enclosure 3b - NMC Handout Regu;Atory Conference Concerning Auxiliary Feedwater Orifice Issue for 06/06/2003 Point Beach Regulatory Conference NRC 2003-0056, Submittal of the Auxiliary Feedwater Orifice Issue Regulatory Conference Slide Presentation2003-06-10010 June 2003 Submittal of the Auxiliary Feedwater Orifice Issue Regulatory Conference Slide Presentation ML1122206032003-06-0606 June 2003 Meeting Presentation, Point Beach, Regulatory Conference, EA-03-057 ML0312202182003-04-25025 April 2003 Public Meeting, Point Beach Re EOC, Licensee'S Slides ML0309300732003-04-25025 April 2003 Public Meeting, Point Beach Re EOC, Slides ML0306407162003-02-0606 February 2003 Meeting Slides Regarding Selective Implementation of the AST for the Point Beach Fuel Handling Accident ML0226102762002-09-17017 September 2002 Meeting Handout Materials for Meeting Re Reactor Vessel Evaluation Methodologies for Point Beach, Units 1 & 2 ML0308706512002-04-29029 April 2002 NMC Viewgraphs - Point Beach Nuclear Plant Potential Common Mode Failure Auxiliary Feedwater 2022-06-30
[Table view] Category:Slides and Viewgraphs
MONTHYEARML22181B0842022-06-30030 June 2022 2021 Point Beach Nuclear Plant End-of-Cycle Meeting Handout ML21336A7972021-12-0909 December 2021 GL 2004-02 Resolution Update - NextEra Energy Point Beach, LLC - December 9, 2021 (Slides) ML21335A0232021-12-0808 December 2021 Slides - Point Beach Nuclear Plant, Unit Nos. 1 and 2 December 8, 2021 Public Meeting Slides for the Draft Plant-Specific Supplement 23, Second Renewal Dseis Public Meeting ML21253A0152021-09-16016 September 2021 Pre-Submittal Meeting: LAR to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times -RITSTF Initiative 4b ML21162A2632021-06-11011 June 2021 2020 Point Beach Nuclear Plant End-of-Cycle Meeting Presentation ML21134A0232021-05-18018 May 2021 GL 2004-02 Resolution Update - NextEra Energy Point Beach, LLC (NextEra) ML21042B9452021-02-17017 February 2021 Scoping and Process Meeting - February 17, 2021 ML20240A2702020-08-27027 August 2020 2019 EOC Slide Presentation ML18121A3392018-05-0101 May 2018 Slides for Point Beach 2017 EOC Open House ML18108A0152018-05-0101 May 2018 NextEra Approach to Resolution of Tornado Missile Protection May 1, 2018 ML17310B2322017-11-0707 November 2017 Presentation Slides - NextEra Energy/Fpl - GSI-191 Issue Resolution, Pre-submittal Meeting, September 20, 2017 ML17205A0192017-07-17017 July 2017 Presentation for Point Beach 2016 EOC Open House ML17023A0652017-01-24024 January 2017 Pre-Submittal Call Regarding License Amendment Requests for Prairie Island Nuclear Generating Plant, Units 1 and 2 and Monticello Nuclear Generating Plant Emergency Action Level Scheme Changes ML16291A1772016-10-18018 October 2016 License Amendment Request Pre-Submittal Discussion October 18, 2016 ML15203A5072015-07-28028 July 2015 July 28, 2015, Turbine Driven Auxiliary Feedwater Cross-tie License Amendment Request ML15203A4982015-07-22022 July 2015 July 2015, Containment Dome Truss Seismic Analysis Methodology License Amendment Request ML15112A0672015-04-20020 April 2015 Annual Assessment Meeting Open House - Handout EOC 2014 Mtg ML15091A5172015-04-0606 April 2015 4/6/2015, Meeting Slide for Public Teleconference on Point Beach MCR Abandonment Analysis for Loss of Control Scenarios ML14112A4252014-04-0808 April 2014 Annual Assessment Meeting, 2013 Reactor Oversight Process - Slides ML13200A3962013-07-19019 July 2013 EA-13-125, Point Beach, Conference Slides ML13162A7902013-06-11011 June 2013 Meeting Slides ML1114603332011-05-25025 May 2011 EOC Licensee Presentation Slides ML1115400612011-05-25025 May 2011 Licensee Slides from 5/25/11 Public Meeting ML1107703492011-03-22022 March 2011 3/22/11 PRE-Application Meeting Slides Regarding NFPA 805 License Amendment Request ML1108206992011-03-22022 March 2011 3/22/11 Revised Pre-application Meeting Slides Regarding NFPA 805 License Amendment Request ML1013802102010-05-18018 May 2010 5/18/2010 Point Beach Public Meeting Slides ML1011304972010-04-22022 April 2010 NRC Slides for Point Beach End-of-Cycle Public Meeting ML1011304452010-04-22022 April 2010 FPL Energy Point Beach Handout from End-Of-Cycle Public Meeting ML0921107842009-07-29029 July 2009 Meeting Slides, Public Meeting with NRC Region III on Point Beach ML0912007342009-04-29029 April 2009 NRC Slides for Point Beach 2008 End-of-Cycle Public Meeting ML0912007042009-04-29029 April 2009 Presentation at 2008 End-of-Cycle Public Meeting ML0912007212009-04-29029 April 2009 NRC Presentation Handouts for Point Beach 2008 End-of-Cycle Public Meeting ML0828905272008-10-14014 October 2008 Meeting with NRC on AST ML0826819412008-09-24024 September 2008 Meeting Slides, FPL Energy Point Beach Public Meeting with NRC Region III ML0825401402008-09-16016 September 2008 Meeting Slides Point Beach Nuclear Plant Meeting with NRC on Epu. ML0819905262008-07-16016 July 2008 EOC Annual Assessment Meeting Slides ML0709403182007-03-28028 March 2007 EOC Summary Meeting Slides - 2007, Reactor Oversight Program - Cy 2006 ML0705106742007-02-21021 February 2007 NMC Slides for Public Meeting, Conduct of Operations Action Plan Update. ML0632601422006-11-21021 November 2006 11/21/2006 Informational Meeting Regarding Prairie Island License Renewal Application ML0615106012006-05-23023 May 2006 EPRI HRA Users Group Review of Draft NUREG-1842 ML0609307552006-04-0303 April 2006 Public Meeting Summary - Point Beach Safety Culture Meeting (Includes NMC Slides) ML0524903212005-08-25025 August 2005 Slides for Point Beach CAL Public Meeting Summary - August 25, 2005 ML0508304892005-03-14014 March 2005 Confirmatory Action Letter Public Meeting Slides ML0509200092005-03-0303 March 2005 3/3/05 - Preliminary Results of Environmental Review Point Beach Nuclear Plant, Units 1 and 2, Nuclear Regulatory Commission, March 3, 2005 ML0434900602004-11-30030 November 2004 NMC Slides for 11/30/04 Public Meeting ML0425404652004-08-18018 August 2004 Nuclear Management Co Confirmatory Action Letter Public Meeting Presentation Regarding Point Beach Nuclear Plant ML0508303502004-05-11011 May 2004 E-Mail B. Kemp, NMC, to H. Chernoff, NRR, May 11 Rev 2. Ppt W/Att Slides Conference Call, May 11, 2004 ML0508303302004-05-11011 May 2004 Slides: Point Beach Unit 1, Spring 2004 RPV Head Inspection Results Conference Call Tuesday, May 11, 2004 W/Handwritten Notes ML0412602942004-04-21021 April 2004 Public Meeting Slides, Point Beach 2003 End-of-Cycle Assessment ML0412602192004-04-21021 April 2004 Public Meeting Licensee Slides, Point Beach 2003 End - of - Cycle Assessment 2022-06-30
[Table view] |
Text
Point Beach Nuclear Plant Annual Assessment Meeting Reactor Oversight Program - 2007 Nuclear Regulatory Commission - Region III Lisle, IL July 16, 2008
Purpose of Todays Meeting
- A public forum to discuss Point Beach performance in 2007
- NRC will address the performance issues identified in the annual assessment letter
- Licensee will be given the opportunity to respond and inform the NRC of new or existing programs to maintain or improve performance 2
Agenda
- Review of Reactor Oversight Process
- National Summary of Plant Performance
- Discussion of Plant Performance Results
- Licensee Response and Remarks
- NRC available to address public questions 3
Region III Organization James Caldwell Regional Administrator Mark Satorius Deputy Regional Administrator Cynthia Pederson Steven West Director Division of Reactor Projects Director Division of Reactor Safety Gary Shear Anne Boland Deputy Director Deputy Director Michael Kunowski Regional Specialists Branch Chief KPS Resident Inspectors Project Engineer Robert Krsek John Jandovitz Robert Ruiz 4
Our Mission
- To license and regulate the nations civilian use of byproduct, source, and special nuclear materials to ensure adequate protection of public health and safety, promote the common defense and security, and protect the environment.
5
Some Nuclear Facts
- More than 100 nuclear power plants supply about 20 percent of the electricity in the U.S.
- Nuclear materials are used in medicine for diagnosis and cancer treatment.
- Nuclear materials are widely used in industry, such as in density gauges, flow measurement devices, radiography devices, and irradiators.
6
The NRC Regulates
- Nuclear reactors - commercial power reactors, research and test reactors, new reactor designs
- Nuclear materials - nuclear reactor fuel, radioactive materials for medical, industrial, and academic use
- Nuclear waste - transportation, storage and disposal of nuclear material and waste, decommissioning of nuclear facilities
- Nuclear security - physical security of nuclear facilities and materials from sabotage or attacks 7
What We Dont Do
- Regulate nuclear weapons, military reactors, or space vehicle reactors
- Own or operate nuclear power plants
- Regulate some radioactive materials, such as X-rays and naturally occurring radon 8
How We Regulate
- Establish rules and regulations
- Provide oversight through inspection, enforcement, and evaluation of operational experience
- Conduct research to provide support for regulatory decisions
- Respond to events and emergencies 9
Assurance of Plant Safety
- Require long-term maintenance of equipment
- Require continual training of operators
- Verify compliance with regulations 10
What We Do - Nuclear Waste
- Storage of spent reactor fuel in fuel pools or dry storage casks, and
- A national spent fuel storage site--Yucca Mountain.
11
What We Do - Nuclear Security
- Well-armed and well-trained security forces,
- Surveillance and perimeter patrols,
- State-of-the-art site access equipment and controls,
- Physical barriers and detection zones, and
- Intrusion detection systems and alarm stations.
12
NRC Performance Goals
- Safety: Ensure adequate protection of public health and safety and the environment.
- Security: Ensure adequate protection in the secure use and management of radioactive materials.
13
Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Performance Indicator Baseline Inspection Results Results Significance Significance Threshold Threshold Action Matrix Regulatory Response 14
Examples of Baseline Inspections
- Equipment Alignment ~80 hrs/yr
- Triennial Fire Protection ~250 hrs every 3 yrs
- Operator Response ~125 hrs/yr
- Rad Release Controls ~110 hrs every 2 yrs
- Worker Radiation Protection ~95 hrs/yr
- Corrective Action Program ~250 hrs every 2 yrs
- Corrective Action Case Reviews ~60 hrs/yr 15
Significance Threshold Performance Indicators Green: Only Baseline Inspection White: May increase NRC oversight Yellow: Requires more NRC oversight Red: Requires more NRC oversight Inspection Findings Green: Very low safety issue White: Low to moderate safety issue Yellow: Substantial safety issue Red: High safety issue 16
Action Matrix Concept Licensee Regulatory Degraded Multiple/R ep. Unacceptable Response Response Cornerstone Degraded Perform ance Cornerstone Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions 17
National Summary of Plant Performance Status at End of 2007 Licensee Response 87 Regulatory Response 8 Degraded Cornerstone 8 Multiple/Repetitive Degraded Cornerstone 1 Unacceptable 0 Total 104 18
National Summary
- Performance Indicator Results (for 2007)
- Green 1942
- White 8
- Yellow 1
- Red 0
- Total Inspection Findings (for 2007)
- Green 759
- White 9
- Yellow 2
- Red 0 19
Point Beach Assessment Results (January 1 - December 31, 2007)
- Plant performance for the most recent quarter was within the Licensee Response column of the NRCs Action Matrix based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight.
20
Inspection Activities (January 1 - December 31, 2007)
- The inspections were performed by the Resident Inspectors and Regional Inspectors, including specialists in engineering, security, emergency preparedness, and radiation protection
- There were 29 Green or SL-IV Inspection Findings identified during 2007 and one SL-III violation issued relating to the reactor vessel head drop analysis.
- There was a Refueling Outage on Unit 1 during the 2nd Quarter of 2007.
21
Point Beach Inspection Activities (January 1 - December 31, 2007)
- Major team inspections included the Tri-Annual Fire Protection Inspection; Evaluation of Changes, Tests, or Experiments and Permanent Plant Modifications Inspection; and the June Special Inspection related to the Unit 1 Turbine-Driven Auxiliary Feedwater Pump.
22
Annual Assessment Summary (January 1 - December 31, 2007)
- FPL Energy Point Beach, LLC operated PBNP in a manner that preserved public health and safety.
- NRC plans baseline inspections at PBNP for the remainder of the assessment period.
23
Annual Assessment Summary (January 1 - December 31, 2007)
- Substantive cross-cutting issuesone in problem identification and resolution and one in human performance
- NRC plans baseline inspections at Point Beach for 2008 24
Licensee Response and Remarks Mr. Larry Meyer Site Vice-President Point Beach Nuclear Plant 25
Open to the Public
- The NRC places a high priority on keeping the public and stakeholders informed of its activities.
- Find public meeting dates and transcripts;
- Read NRC testimony, speeches, press releases, and policy decisions; and
- Access the agencys Electronic Reading Room to find NRC publications and documents.
26
Contacting the NRC
- (301) 816-5100 (call collect)
- (800) 695-7403
- Allegation@nrc.gov
- General information or questions
- www.nrc.gov
- Select What We Do for Public Affairs 27
NRC Representatives
- Cynthia Pederson, Director, Division of Reactor Projects
- (630) 829-9600
- Gary Shear, Deputy Division Director, DRP
- (630) 829-9601
- (301) 415-1424
- Rob Krsek, Senior Resident Inspector - Point Beach
- (920) 755-2309
- Rob Ruiz, Resident Inspector - Point Beach
- (920) 755-2309
- John Jandovitz, Senior Project Engineer
- (630) 829-9763
- (630) 829-9618 28
NRC Representatives
- Patrick Louden, Chief, Decommissioning Branch (ISFSI)
- (630) 829-9627
- (630) 829-9662
- (630) 829-9663
- Steve Burton, Senior Resident Inspector - Kewaunee
- (920) 388-3156
- Patrick Higgins, Resident Inspector - Kewaunee
- (920) 388-3156
- NRC Region III Office Switchboard
- (630) 829-9500 (800) 522-3025 29
Reference Sources
- Reactor Oversight Process
- http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.h tml
- Public Electronic Reading Room
- http://www.nrc.gov/reading-rm.html
- Public Document Room 800-397-4209 (Toll Free) 30