PMNS20210610, Public Meeting Regarding Path Forward for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 2
Letter Sequence Request | |
---|---|
EPID:L-2017-LRC-0000, TSTF-567, TSTF-567, TSTF-567, TSTF-567, TSTF-567 (Approved, Closed) | |
Initiation Questions Answers Results Other: ML21161A299, ML21203A314, ML21211A082, ML21214A178, ML21260A161, ML22013A339, ML22019A279, ML22061A056, ML22109A175, ML22164A861, ML22167A170, ML23188A020, ML23193A938, ML23200A183, ML23243A910 | |
MONTHYEARML17310B2322017-11-0707 November 2017
[Table View]Presentation Slides - NextEra Energy/Fpl - GSI-191 Issue Resolution, Pre-submittal Meeting, September 20, 2017 Project stage: Meeting ML17310B2062017-11-20020 November 2017 Summary of September 20, 2017, Meeting with Florida Power & Light Company and NextEra Energy Regarding Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 Project stage: Meeting ML18136A9052018-05-31031 May 2018 Summary of April 25, 2017, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of Exemption Requests to Support Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 Project stage: Meeting L-20-162, Supplemental Response to NRC Generic Letter 2004-022020-11-30030 November 2020 Supplemental Response to NRC Generic Letter 2004-02 Project stage: Request 0CAN122001, Final Response to NRC Generic Letter 2004-022020-12-10010 December 2020 Final Response to NRC Generic Letter 2004-02 Project stage: Request ML21062A0642021-03-0202 March 2021 NRR E-mail Capture - Request for Additional Information for Diablo Canyon Generic Letter 2004-02 Submittal (L-2017-LRC-0000) Project stage: RAI NL-21-0020, Final Supplemental Response to NRC Generic Letter 2004-022021-03-23023 March 2021 Final Supplemental Response to NRC Generic Letter 2004-02 Project stage: Request DCL-21-034, Response to Request for Additional Information on Final Supplemental Response to Generic Letter 20042021-04-15015 April 2021 Response to Request for Additional Information on Final Supplemental Response to Generic Letter 2004 Project stage: Supplement ML21118A0072021-04-28028 April 2021 Final Response and Close-out to Generic Letter 2004-02 Project stage: Request PMNS20210610, Public Meeting Regarding Path Forward for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 22021-05-17017 May 2021 Public Meeting Regarding Path Forward for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 2 Project stage: Request ML21134A0232021-05-18018 May 2021 GL 2004-02 Resolution Update - NextEra Energy Point Beach, LLC (NextEra) Project stage: Request ML21147A1462021-05-27027 May 2021 Response to Request for Additional Information Regarding Generic Letter 2004-02 Project stage: Response to RAI ML21168A2612021-06-17017 June 2021 (Vcsns), Unit 1 - NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-water Reactors - Final Supplemental Response Project stage: Request ML21161A2992021-06-17017 June 2021 Summary of May 18, 2021 Public Webinar with Nextera Energy Point Beach, LLC Regarding Path Forward for Generic Letter 2004-02 Closure Project stage: Other ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 Project stage: RAI ML21203A3142021-07-29029 July 2021 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML21232A0402021-08-20020 August 2021 Notice of Teleconference with Entergy Operations, Inc. Concerning Final Response to Generic Letter 2004-02 at Arkansas Nuclear One, Units 1 and 2 Project stage: Meeting ML21252A3212021-08-20020 August 2021, 30 August 2021, 14 September 2021 ANO Meeting Summary for September 1, 2020 Public Meeting/Teleconference Project stage: Request ML21242A2792021-08-30030 August 2021 ANO Slides Presentation for 9-1-21 Public Meeting Project stage: Meeting ML21252A2662021-09-14014 September 2021 Summary of September 1, 2021, Teleconference Meeting with Entergy Operations, Inc. Concerning the Final Response to Generic Letter 2004-02 for Arkansas Nuclear One, Units 1 and 2 Project stage: Meeting ML21211A0822021-09-24024 September 2021 Closeout of Generic Letter 2004 02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML21260A1612021-09-24024 September 2021 Closeout of Generic Letter 2004 02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other RA-21-0230, Duke Energy - Final Supplemental Response to NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors2021-09-30030 September 2021 Duke Energy - Final Supplemental Response to NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Request 0CAN102101, Final Request for Additional Information Concerning Generic Letter 2004-022021-10-0404 October 2021 Final Request for Additional Information Concerning Generic Letter 2004-02 Project stage: Request ML21214A1782021-10-0808 October 2021 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors Project stage: Other PMNS20211455, Pre-Submittal Public Meeting Regarding License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 22021-12-0303 December 2021 Pre-Submittal Public Meeting Regarding License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 2 Project stage: Meeting ML21336A7972021-12-0909 December 2021 GL 2004-02 Resolution Update - NextEra Energy Point Beach, LLC - December 9, 2021 (Slides) Project stage: Request ML22019A2792022-01-20020 January 2022 Summary of Public Webinar with NextEra Energy Point Beach, LLC Regarding Future License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Project stage: Other ML22019A2652022-01-27027 January 2022 Us NRC Staff Review of Documentation Provided by Firstenergy Nuclear Operating Co. for Beaver Valley, Units 1&2 Concerning Resolution of Generic Letter 2004-02 - Potential Impact of Debris Blockage on Emergency Recirculation During Design B Project stage: Approval ML22013A3722022-01-27027 January 2022, 31 January 2022 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Request ML22013A3392022-01-31031 January 2022 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML22053A2402022-02-22022 February 2022 Final Supplemental Response to NRC Generic Letter 2004-02 Project stage: Request ML22061A0562022-03-29029 March 2022 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML22112A1482022-04-22022 April 2022 Correction_H. B. Robinson Steam Electric Plant, Unit 2 - Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-02 Project stage: RAI ML22109A1752022-04-27027 April 2022 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other RA-22-0144, Response to NRC Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-022022-05-19019 May 2022 Response to NRC Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-02 Project stage: Supplement ML22164A8612022-06-24024 June 2022 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML22167A1702022-07-14014 July 2022 Closeout of Generic Letter 2004 02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) Project stage: Draft RAI ML22251A1292022-09-0909 September 2022 Request for Additional Information Related to Response to Generic Letter 2004-04 Project stage: RAI ML22312A4432022-11-0707 November 2022 NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Fleet Response to RAI Project stage: Request ML22335A4142022-12-21021 December 2022 Request for Withholding Information from Public Disclosure for Dominion Fleet Response to Request for Additional Information Regarding NRC Generic Letter 2004-02 Project stage: RAI ML23193A9382023-07-18018 July 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML23188A0202023-07-26026 July 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML23200A1832023-08-0303 August 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML23243A9102023-09-0606 September 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML24012A0492024-01-11011 January 2024 Request for Additional Information Regarding Final Response to Generic Letter 2004-02 Project stage: RAI 2021-09-14 |
ML21137A278 | |
Person / Time | |
---|---|
Site: | Point Beach |
Issue date: | 05/17/2021 |
From: | Office of Nuclear Reactor Regulation |
To: | |
References | |
PMNS20210610 | |
Download: ML21137A278 (3) | |
Similar Documents at Point Beach | |
---|---|
Category:Meeting Notice
MONTHYEARML23171B0912023-06-21021 June 2023
[Table view]Notice of Significant Public Meeting to Discuss NRC End-Of-Cycle Performance Assessment of Point Beach Nuclear Plant for Performance for 2022 Calendar Year ML22160A6602022-06-10010 June 2022 Information Meeting with a Question and Answer Session to Discuss NRC 2021 End of Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML22159A3252022-06-0909 June 2022 2021 Point Beach End of Cycle Public Meeting Notice PMNS20220468, Notice of Meeting with NextEra Energy Llc/Florida Power & Light Company2022-05-0404 May 2022 Notice of Meeting with NextEra Energy Llc/Florida Power & Light Company PMNS20220063, Notice of Meeting with NextEra Energy Llc/Florida Power & Light Company2022-02-0101 February 2022 Notice of Meeting with NextEra Energy Llc/Florida Power & Light Company PMNS20211455, Pre-Submittal Public Meeting Regarding License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 22021-12-0303 December 2021 Pre-Submittal Public Meeting Regarding License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 2 ML21319A2842021-11-15015 November 2021 Draft Supplemental Environmental Impact Statement Meeting Related to the Point Beach Nuclear Plant, Unit Nos. 1 and 2 (Point Beach), Subsequent License Renewal Application PMNS20211108, Public Pre-application Meeting for Proposed License Amendment Request Regarding Technical Specification Task Force (TSTF)- 505, for Point Beach Nuclear Plant Units 1 and 22021-09-13013 September 2021 Public Pre-application Meeting for Proposed License Amendment Request Regarding Technical Specification Task Force (TSTF)- 505, for Point Beach Nuclear Plant Units 1 and 2 ML21144A1632021-05-24024 May 2021 6/10/21 Notice of Significant Public Meeting to Discuss NRC End-of-Cycle Performance Assessment of Point Beach Nuclear Plant for Performance for 2020 Calendar Year ML21141A2322021-05-21021 May 2021 Public Meeting 6/3/21 Point Beach SLRA Fluence Concrete Steel Notice Information PMNS20210610, Public Meeting Regarding Path Forward for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 22021-05-17017 May 2021 Public Meeting Regarding Path Forward for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 2 PMNS20210090, Environmental Scoping Meeting Related to the Point Beach Nuclear Plant, Unit Nos. 1 and 2 (Point Beach), Subsequent License Renewal Application2021-02-0303 February 2021 Environmental Scoping Meeting Related to the Point Beach Nuclear Plant, Unit Nos. 1 and 2 (Point Beach), Subsequent License Renewal Application PMNS20201308, Meeting with NextEra Energy/Florida Power & Light Company to Discuss Generic Safety Issue-191/Generic Letter 2004-02 Closeout Letters2020-11-0505 November 2020 Meeting with NextEra Energy/Florida Power & Light Company to Discuss Generic Safety Issue-191/Generic Letter 2004-02 Closeout Letters ML20192A0622020-07-0909 July 2020 7/30/2020 Notice of Significant Public Meeting to Discuss Nrc'S End of Cycle Assessment of Duane Arnold Energy Center and Point Beach Nuclear Plant Performance for the 2019 Calendar Year ML19071A0472019-03-11011 March 2019 Notice of Significant Public Meeting to Discuss Nrc'S End-Of-Cycle Assessment of the Point Beach Nuclear Plant, Units 1 and 2 ML18071A2912018-03-12012 March 2018 4/10/2018 Notice of Significant Public Meeting to Discuss Nrc'S End-of-Cycle Assessment of the Point Beach Nuclear Plant, Units 1 and 2 Performance for the 2017 Calendar Year ML17257A3762017-09-14014 September 2017 Public Meeting Notice of NRC Region III 2017 Operator Licensing Workshop ML17165A5602017-06-14014 June 2017 6/14/17 Notice of Significant Public Meeting to Discuss Nrc'S End-of-Cycle Assessment of the Point Beach Nuclear Plant Performance for the 2016 Calendar Year ML16112A4002016-04-21021 April 2016 Notice of Significant Public Meeting to Discuss Nrc'S End-of-Cycle Assessment of the Nextera Energy Point Beach Nuclear Plant Performance for the 2015 Calendar Year ML16112A2852016-04-21021 April 2016 Notice of Forthcoming Public Open House to Discuss the 2015 End-of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML15302A1702015-11-0202 November 2015 Forthcoming Closed Pre-Application Teleconference with NextEra Energy Point Beach, LLC (Nextera), Regarding Steam Generators H* License Amendment Request ML15183A4842015-07-0101 July 2015 Ltr. 07/01/15 Davis-Besse U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4792015-07-0101 July 2015 Ltr. 07/01/15 D.C. Cook U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting)(Drm) ML15183A4782015-07-0101 July 2015 Ltr. 07/01/15 Duane Arnold U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4722015-07-0101 July 2015 Ltr. 07/01/2015 Fermi U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4632015-07-0101 July 2015 Ltr. 07/01/15 Monticello U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4452015-07-0101 July 2015 Ltr. 07/01/15 Perry U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A3862015-07-0101 July 2015 Ltr. 07/01/15 Prairie Island U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15182A4412015-07-0101 July 2015 Notice and Agenda - 2015 Operator Licensing Workshop ML15089A0212015-03-26026 March 2015 Notice of Meeting with Public to Discuss NRC Activities, Nuclear Power Issues, and Point Beach Performance for the 2014 Calendar Year with the Public ML14168A1862014-06-13013 June 2014 07/9-10/2014 Meeting Notice with the Public - 2014 Operator Licensing Workshop ML14169A5782014-06-13013 June 2014 Operator License Workshop Invitation ML14071A5302014-03-11011 March 2014 Notice of Significant NRC Meeting to Discuss Point Beach Nuclear Plant Performance for the 2013 Calendar Year with NextEra Energy Point Beach ML14071A3932014-03-11011 March 2014 Public Meeting to Discuss 2013 End-Of-Cycle Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML13190A2702013-07-0909 July 2013 Notice of Meeting with NextEra Energy Point Beach, LLC to Discuss the Significance Associated with an Apparent Violation of 10 CFR Part 50, Appendix B, Criterion V for the Failure to Have a Procedure Appropriate to the Circumstances to Addr ML13158A0082013-06-0606 June 2013 Public Meeting Notice to Discuss NRC Activities, Nuclear Power Issues, and Point Beach Plant Performance for the 2012 Calendar Year with the Public ML12222A0392012-08-0909 August 2012 8/16/2012 Cancellation Notice of Forthcoming Conference Call with NextEra Energy and Florida Power and Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Proto ML12213A0612012-08-0101 August 2012 8/16/12 Forthcoming Conference Call with NextEra Energy and Florida Power & Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Protocol ML12188A0742012-07-0505 July 2012 7/26/12 Notice of Meeting with NextEra Energy to Present the Licensee the Results of NRC End-of-Cycle Assessment Regarding Point Beach Nuclear Plant ML12138A3312012-05-17017 May 2012 05/31/2012, Notice of Significant Licensee Meeting (non-public) Regarding Operator Licensing Workshop and Meeting ML1111905792011-04-29029 April 2011 Notice of Meeting with NextEra Energy Point Beach to Present the Licensee the Results of NRC End-Of-Cycle Assessment of Point Beach Nuclear Plant ML1106104272011-03-0707 March 2011 Notice of Forthcoming Pre-Application Meeting with Florida Power & Light Company and NextEra Energy Regarding Turkey Point, Units 3 and 4, St. Lucie, Units 1 and 2, Point Beach, Units 1, and 2, and Duane Arnold ML1010503892010-04-15015 April 2010 Notice of Meeting Between FPL Energy Point Beach Management and NRC Region III Management to Discuss General Information ML1008405552010-03-25025 March 2010 Meeting Notice with NextEra Energy Point Beach to Present the Licensee the Results of the NRC End-of-Cycle Assessment ML0921805182009-08-0606 August 2009 Notice of Public Meeting with Florida Power & Light Energy ML0919105832009-07-10010 July 2009 Notice of Public Meeting to Discuss Progress on Actions Taken to Address Substantive Cross-Cutting Issues, and Results of Independent Assessment of Effectiveness of Corrective Actions Taken in Response to Nuclear Safety Culture Surveys ML0919105232009-07-10010 July 2009 Notice of Meeting with NextEra Energy Point Beach, LLC to Discuss Progress of Licensee'S Actions Taken in Response to Substantive Cross-cutting Issues & Discuss Results of an Independent Assessment of Effectiveness of Corrective Actions... ML0909801332009-04-0606 April 2009 Notice of Meeting with FPL Energy Point Beach, LLC to Discuss the Nrc'S End-of-Cycle Assessment of Point Beach'S Performance for 2008 ML0909703342009-04-0606 April 2009 Notice of Meeting with FPL Energy Point Beach, LLC Regarding the Progress of the Licensee'S Action in Response to Point Beach Nuclear Plant, Units 1 and 2, 2008 Nuclear Safety Culture Survey ML0827307072008-09-29029 September 2008 Pre-application Meeting with FPL Energy Point Beach, LLC to Discuss Their Proposed Alternate Source Term Amendment 2023-06-21 Category:Meeting Agenda MONTHYEARPMNS20220468, Notice of Meeting with NextEra Energy Llc/Florida Power & Light Company2022-05-0404 May 2022
[Table view]Notice of Meeting with NextEra Energy Llc/Florida Power & Light Company PMNS20220063, Notice of Meeting with NextEra Energy Llc/Florida Power & Light Company2022-02-0101 February 2022 Notice of Meeting with NextEra Energy Llc/Florida Power & Light Company PMNS20211455, Pre-Submittal Public Meeting Regarding License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 22021-12-0303 December 2021 Pre-Submittal Public Meeting Regarding License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 2 ML21319A2842021-11-15015 November 2021 Draft Supplemental Environmental Impact Statement Meeting Related to the Point Beach Nuclear Plant, Unit Nos. 1 and 2 (Point Beach), Subsequent License Renewal Application PMNS20211108, Public Pre-application Meeting for Proposed License Amendment Request Regarding Technical Specification Task Force (TSTF)- 505, for Point Beach Nuclear Plant Units 1 and 22021-09-13013 September 2021 Public Pre-application Meeting for Proposed License Amendment Request Regarding Technical Specification Task Force (TSTF)- 505, for Point Beach Nuclear Plant Units 1 and 2 ML21141A2322021-05-21021 May 2021 Public Meeting 6/3/21 Point Beach SLRA Fluence Concrete Steel Notice Information ML21134A0232021-05-18018 May 2021 GL 2004-02 Resolution Update - NextEra Energy Point Beach, LLC (NextEra) PMNS20210610, Public Meeting Regarding Path Forward for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 22021-05-17017 May 2021 Public Meeting Regarding Path Forward for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 2 PMNS20210090, Environmental Scoping Meeting Related to the Point Beach Nuclear Plant, Unit Nos. 1 and 2 (Point Beach), Subsequent License Renewal Application2021-02-0303 February 2021 Environmental Scoping Meeting Related to the Point Beach Nuclear Plant, Unit Nos. 1 and 2 (Point Beach), Subsequent License Renewal Application PMNS20201308, Meeting with NextEra Energy/Florida Power & Light Company to Discuss Generic Safety Issue-191/Generic Letter 2004-02 Closeout Letters2020-11-0505 November 2020 Meeting with NextEra Energy/Florida Power & Light Company to Discuss Generic Safety Issue-191/Generic Letter 2004-02 Closeout Letters ML15302A1702015-11-0202 November 2015 Forthcoming Closed Pre-Application Teleconference with NextEra Energy Point Beach, LLC (Nextera), Regarding Steam Generators H* License Amendment Request ML15183A4842015-07-0101 July 2015 Ltr. 07/01/15 Davis-Besse U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4792015-07-0101 July 2015 Ltr. 07/01/15 D.C. Cook U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting)(Drm) ML15183A4782015-07-0101 July 2015 Ltr. 07/01/15 Duane Arnold U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4722015-07-0101 July 2015 Ltr. 07/01/2015 Fermi U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4632015-07-0101 July 2015 Ltr. 07/01/15 Monticello U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A4452015-07-0101 July 2015 Ltr. 07/01/15 Perry U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A3992015-07-0101 July 2015 Ltr. 07/01/15 Point Beach U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15183A3862015-07-0101 July 2015 Ltr. 07/01/15 Prairie Island U.S. Nuclear Regulatory Commission Region III 2015 Operator Licensing Workshop (Public Meeting) (Drm) ML15182A4412015-07-0101 July 2015 Notice and Agenda - 2015 Operator Licensing Workshop ML14169A5782014-06-13013 June 2014 Operator License Workshop Invitation ML12222A0392012-08-0909 August 2012 8/16/2012 Cancellation Notice of Forthcoming Conference Call with NextEra Energy and Florida Power and Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Proto ML12213A0612012-08-0101 August 2012 8/16/12 Forthcoming Conference Call with NextEra Energy and Florida Power & Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Protocol ML12138A3312012-05-17017 May 2012 05/31/2012, Notice of Significant Licensee Meeting (non-public) Regarding Operator Licensing Workshop and Meeting ML1107703492011-03-22022 March 2011 3/22/11 PRE-Application Meeting Slides Regarding NFPA 805 License Amendment Request ML1108206992011-03-22022 March 2011 3/22/11 Revised Pre-application Meeting Slides Regarding NFPA 805 License Amendment Request ML1106104272011-03-0707 March 2011 Notice of Forthcoming Pre-Application Meeting with Florida Power & Light Company and NextEra Energy Regarding Turkey Point, Units 3 and 4, St. Lucie, Units 1 and 2, Point Beach, Units 1, and 2, and Duane Arnold ML1012502352010-05-0505 May 2010 Summary of the April 22, 2010, Public Meeting to Discuss the 2009 Point Beach End-of-Cycle Performance Assessment ML1011304452010-04-22022 April 2010 FPL Energy Point Beach Handout from End-Of-Cycle Public Meeting ML0921805182009-08-0606 August 2009 Notice of Public Meeting with Florida Power & Light Energy ML0921107842009-07-29029 July 2009 Meeting Slides, Public Meeting with NRC Region III on Point Beach ML0912007212009-04-29029 April 2009 NRC Presentation Handouts for Point Beach 2008 End-of-Cycle Public Meeting ML0912007342009-04-29029 April 2009 NRC Slides for Point Beach 2008 End-of-Cycle Public Meeting ML0822503302008-10-0606 October 2008 Teleconference Summary Regarding Point Beach Nuclear Plant Supplement to the Auxiliary Feedeater Amendment ML0827307072008-09-29029 September 2008 Pre-application Meeting with FPL Energy Point Beach, LLC to Discuss Their Proposed Alternate Source Term Amendment ML0825401402008-09-16016 September 2008 Meeting Slides Point Beach Nuclear Plant Meeting with NRC on Epu. ML0821707042008-08-0606 August 2008 Notice of Meeting with FPL Energy Point Beach, LLC to Discuss the Auxiliary Feedwater License Amendment ML0634003252006-12-0707 December 2006 Notice of Presubmittal Conference for Proposed Emergency Plan Changes ML0604406422006-02-10010 February 2006 Summary of Public Meeting to Discuss Point Beach Self-Assessments, Summary Letter & Licensee Slides ML0602502942006-01-25025 January 2006 Canceled Notice of Meeting with Nuclear Management Company Regarding Fleet Transition to NFPA Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants ML0518203592005-07-0808 July 2005 Notice of Meeting with Nuclear Management Company Regarding the Planned Amendment to the Point Beach Nuclear Plant, Unit 1, Updated Safety Analysis Report Relating to Movement of the Reactor Vessel Head ML0520305052005-06-0303 June 2005 U1R28 OCC Interactive Turnover Meeting Agenda ML0508400622005-03-21021 March 2005 S/G Nozzle Dam Removal Pre-Job Brief Agenda ML0423600372004-08-26026 August 2004 Notice of Meeting with Industry on Risk Management Technical Specifications ML0520305002004-06-0909 June 2004 U1R28 OCC Interactive Turnover Meeting Agenda ML0508701682004-06-0505 June 2004 U1R28 OCC Interactive Turnover Meeting Agenda ML0508701652004-06-0505 June 2004 U1R28 OCC Interactive Turnover Meeting Agenda ML0508701612004-06-0404 June 2004 U1R28 OCC Interactive Turnover Meeting Agenda ML0508701632004-06-0404 June 2004 U1R28 OCC Interactive Turnover Meeting Agenda ML0520305082004-06-0303 June 2004 U1R28 OCC Interactive Turnover Meeting Agenda 2022-05-04 |
Text
Meeting Update : Meeting Slides are available at ADAMS Accession # ML21134A023 May 05, 2021
Title:
Public Meeting Regarding Path Forward for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 2.
Date(s) and Time(s): May 18, 2021, 01:00 PM to 03:00 PM EST Location: Webinar Category: This is an Observation Meeting. This is a meeting in which attendees will have an opportunity to observe the NRC performing its regulatory function or discussing regulatory issues. Attendees will have an opportunity to ask questions of the NRC staff or make comments about the issues discussed following the business portion of the meeting; however, the NRC is not actively soliciting comments towards regulatory decisions at this meeting.
Purpose:
The purpose of this meeting is for the U.S. Nuclear Regulatory Commission (NRC) staff to discuss with NextEra Point Beach, LLC (NextEra) the path forward for Generic Letter (GL) 2004-02 closure for the Point Beach Nuclear Plant, Units 1 and 2 (Point Beach).
Specifically, NextEra would discuss its overall methodology, results from preliminary assessment, its proposed risk-informed approach to GL 2004-02 closure and its planned submittal schedule. In addition, NextEra would briefly discuss with the NRC staff the status of the Point Beach Probabilistic Risk Assessment (PRA) in the context of a risk-informed approach to GL 2004-02 closure.
Contact:
Booma Venkataraman Justin Poole 301-415-2934 301-415-2048 booma.venkataraman@nrc.gov justin.poole@nrc.gov
Participants:
NRC External Booma Venkataraman, Office of Nuclear Steve Catron, NextEra Reactor Regulation Robert Hess, NextEra Justin Poole, Office of Nuclear Reactor Regulation Lloyd Hawki, NextEra Steve Smith, Office of Nuclear Reactor Haifeng Li, NextEra Regulation Andrea Russell, Office of Nuclear Reactor Regulation Matthew Yoder, Office of Nuclear Reactor Regulation Robert Vettori, Office of Nuclear Reactor Regulation URL Meeting Number Password Webinar:
https://teams.microsoft.com/l/meetup- 1-301-576-2978 615397661#
join/19%
3ameeting_ZWZlY2VjOGEtMGI2Ni00NjVhL Tk3MDgtMjNhZDRhOWYyOWM5%
40thread.v2/0?context=%7b%22Tid%22%
3a%22e8d01475-c3b5-436a-a065-5def4c64f52e%22%2c%22Oid%22%3a%
2297cfe98b-6467-4da5-b17c-6d0c8a02305f%22%7d Docket No: 05000266 05000301
PUBLIC MEETING AGENDA
Public Meeting Regarding Path Forward for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant Units 1 and 2.
May 18, 2021, 01:00 PM to 03:00 PM EST Webinar
The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If reasonable accommodation is needed to participate in this meeting, or if a meeting notice, transcript, or other information from this meeting is needed in another format (e.g., Braille, large print), please notify the NRC meeting contact.
Determinations on requests for reasonable accommodation will be made on a case-by-case basis.
ADAMS Accession Number: ML21137A278 Distribution:
Office NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DORL/LPL3/BC Name BVenkataraman SRohrer NSalgado (RKuntz for)
Date 05/04/2021 05/04/2021 05/05/2021 OFFICIAL RECORD COPY Link to meeting details: https://www.nrc.gov/pmns/mtg?do=details&Code=20210610 Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings" 67 Federal Register 36920, May 28, 2002 The policy statement may be found on the NRC website http://www.nrc.gov/reading-rm/doc-collections/commission/policy/67fr36920.html