    C olina Power and Light Company
      TTF: Mr. E. E. Utley
            Senior Executive Vice President
            Power Supply and Engineering
              and Construction
      P. O. Box 1551
      Raleigh, NC 27602
      Gentlemen:
      SUBJECT: REPORT NOS. 50-325/86-11 AND 50-324/86-12
      On March 1-31, 1986, NRC inspected activities authorized by NRC Operating License
      Nos. DPR-71 and DPR-62 for your Brunswick . Steam Electric Plant. At the
      conclusion of the inspection, the findings were discussed with those members of
      your staff identified in the enclosed inspection report.
      Areas examined during the inspection are identified in the report. Within these
      arecs, the inspection consisted of selective examinations of procedures and
      representative records, interviews with personnel, and observation of activities
      in progress.
      The inspection findings indicate that certain activities violated NRC require-
      ments. The violations with pertinent references and elements to be included in
      your response, are presented in the enclosed Notice.
      Your attention is invited to an unresolved item identified in the inspection
      report. This matter will be pursued during future inspections.
      The responses directed by this letter and the enclosures. are not subject to the
      clearance procedures of the Office of Management and Budget issued under the
      Paperwork Reduction Act of 1980, PL 96-511.
      Should you have any questions concerning this letter, please contact us.
                                                Sincerely,
                                                Original Signed by
                                                Luis A. Reyes
                                                Roger D. Walker, Director
                                                Division of Reactor Projects
      Enclosures:  (See page 2)
                                  _g-
                                  ,
      06osogy{            p
      PDR
      O
                                                                              / I
                                                                                      rec)
 
,
  .        .
    .        .
      Carolina Power and Light Company          2 APR 2 2 Egg
      Enclosures:
      1.  Notice of Violation
      2.  Inspection Reports Nos. 50-325/86-11
                and 50-324/86-12
      fcw/encis:
    wP.  W. Howe, Vice President
        , Brunswick Nuclear Project
      J. R. Dietz, Plant General Manager
      bcc w/encls:
      Document Control Desk
      State of North Carolina
        NRC Resident Inspector
              k
  @ ' Fredrickson:bhg hv4Panciera
      ~4/2t/86
                              4///86
                                2
                                                              l
}}
}}

Latest revision as of 05:02, 31 December 2020

Forwards Insp Repts 50-324/86-12 & 50-325/86-11 on 860301-31 & Notice of Violation
ML20203N445
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 04/22/1986
From: Walker R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Utley E
CAROLINA POWER & LIGHT CO.
Shared Package
ML20203N447 List:
References
NUDOCS 8605050419
Download: ML20203N445 (2)


See also: IR 05000324/1986012

Text

G- ,. ,

t'

,

APR 2 21966

C olina Power and Light Company

TTF: Mr. E. E. Utley

Senior Executive Vice President

Power Supply and Engineering

and Construction

P. O. Box 1551

Raleigh, NC 27602

Gentlemen:

SUBJECT: REPORT NOS. 50-325/86-11 AND 50-324/86-12

On March 1-31, 1986, NRC inspected activities authorized by NRC Operating License

Nos. DPR-71 and DPR-62 for your Brunswick . Steam Electric Plant. At the

conclusion of the inspection, the findings were discussed with those members of

your staff identified in the enclosed inspection report.

Areas examined during the inspection are identified in the report. Within these

arecs, the inspection consisted of selective examinations of procedures and

representative records, interviews with personnel, and observation of activities

in progress.

The inspection findings indicate that certain activities violated NRC require-

ments. The violations with pertinent references and elements to be included in

your response, are presented in the enclosed Notice.

Your attention is invited to an unresolved item identified in the inspection

report. This matter will be pursued during future inspections.

The responses directed by this letter and the enclosures. are not subject to the

clearance procedures of the Office of Management and Budget issued under the

Paperwork Reduction Act of 1980, PL 96-511.

Should you have any questions concerning this letter, please contact us.

Sincerely,

Original Signed by

Luis A. Reyes

Roger D. Walker, Director

Division of Reactor Projects

Enclosures: (See page 2)

_g-

,

06osogy{ p

PDR

O

/ I

rec)

,

. .

. .

Carolina Power and Light Company 2 APR 2 2 Egg

Enclosures:

1. Notice of Violation

2. Inspection Reports Nos. 50-325/86-11

and 50-324/86-12

fcw/encis:

wP. W. Howe, Vice President

, Brunswick Nuclear Project

J. R. Dietz, Plant General Manager

bcc w/encls:

Document Control Desk

State of North Carolina

NRC Resident Inspector

k

@ ' Fredrickson:bhg hv4Panciera

~4/2t/86

4///86

2

l