SVPLTR 05-0006, January 2005 Monthly Operating Report for Dresden Nuclear Power Station, Units 2 and 3

From kanterella
Jump to navigation Jump to search
January 2005 Monthly Operating Report for Dresden Nuclear Power Station, Units 2 and 3
ML050420295
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 02/11/2005
From: Bost D
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
SVPLTR # 05-0006
Download: ML050420295 (7)


Text

February 11, 2005 SVPLTR # 05-0006 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Dresden Nuclear Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-19 and DPR-25 NRC Docket Nos. 50-237 and 50-249

Subject:

Monthly Operating Report for January 2005 In accordance with Technical Specifications, Section 5.6.4, Monthly Operating Reports, we are submitting the January 2005 Monthly Operating Report for Dresden Nuclear Power Station (DNPS), Units 2 and 3.

Should you have any questions concerning this letter, please contact Mr. Pedro Salas, Regulatory Assurance Manager, at (815) 416 - 2800.

Respectfully, Original signed by Danny G. Bost Site Vice President Dresden Nuclear Power Station Attachment cc: Regional Administrator - NRC Region III NRC Senior Resident Inspector - Dresden Nuclear Power Station

ATTACHMENT DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 MONTHLY OPERATING REPORT FOR JANUARY 2005 EXELON GENERATION COMPANY, LLC FACILITY OPERATING LICENSE NOS. DPR-19 AND DPR-25 NRC DOCKET NOS. 50-237 AND 50-249 1

TABLE OF CONTENTS I. Summary of Operating Experience A. Unit 2 Monthly Operating Experience Summary B. Unit 3 Monthly Operating Experience Summary II. Operating Data Statistics A. Operating Data Report - Dresden Unit 2 B. Operating Data Report - Dresden Unit 3 III Unit Shutdowns A. Unit 2 Shutdowns B. Unit 3 Shutdowns IV. Challenges to Safety and Relief Valves 2

I.

SUMMARY

OF OPERATING EXPERIENCE FOR JANUARY - 2005 A. UNIT 2 MONTHLY OPERATING EXPERIENCE

SUMMARY

With the exception of short periods for routine maintenance and surveillances, Unit 2 operated at full power throughout the reporting period.

B. UNIT 3 MONTHLY OPERATING EXPERIENCE

SUMMARY

With the exception of short periods for routine maintenance and surveillances, Unit 3 operated at full power throughout the reporting period.

3

II. OPERATING DATA STATISTICS A. Dresden Unit 2 Operating Data Report for January 2005 DOCKET NO. 050-237 DATE February 1, 2005 COMPLETED BY Joseph Reda TELEPHONE (815) 416-3081 OPERATING STATUS

1. REPORTING PERIOD: January 2005
2. CURRENTLY AUTHORIZED POWER LEVEL (MWth): 2,957 MAXIMUM DEPENDABLE CAPACITY (MWe NET): 850 (estimated)

DESIGN ELECTRICAL RATING (MWe Net): 867 Unit 2 Monthly Operating Status This Year to Cumulative Month Date

3. Reactor Critical - Hours 744 744 232,479
4. Hours Generator On-Line 744 744 223,697
5. Unit Reserve Shutdown - Hours 0 0 4
6. Net Electrical Energy Generated -

MWHe 647,066 647,066 151,269,645 4

II. OPERATING DATA STATISTICS B. Dresden Unit 3 Operating Data Report for January 2005 DOCKET NO. 050-249 DATE February 1, 2005 COMPLETED BY Joseph Reda TELEPHONE (815) 416-3081 OPERATING STATUS

1. REPORTING PERIOD: January 2005
2. CURRENTLY AUTHORIZED POWER LEVEL (MWth): 2,957 MAXIMUM DEPENDABLE CAPACITY (MWe NET): 850 (estimated)

DESIGN ELECTRICAL RATING (MWe Net): 867 Unit 3 Monthly Operating Status This Year to Cumulative Month Date

3. Reactor Critical - Hours 744 744 219,718
4. Hours Generator On-Line 744 744 211,570
5. Unit Reserve Shutdown - Hours 0 0 1
6. Net Electrical Energy Generated -

MWHe 649,202 649,202 143,413,408 5

III. UNIT SHUTDOWNS A. Unit 2 Shutdowns for January 2005 NO DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTIONS/

(1) (HOURS) (2) SHUTTING COMMENTS DOWN REACTOR (3)

None B. Unit 3 Shutdowns for January 2005 NO DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTIONS/

(1) (HOURS) (2) SHUTTING COMMENTS DOWN REACTOR (3)

None LEGEND:

(1) Type: (2) Reason (3) Method F - Forced A. Equipment Failure (Explain) 1. Manual S - Scheduled B. Maintenance or Test 2. Manual Trip / Scram C. Refueling 3. Automatic Trip / Scram D. Regulatory Restriction 4. Continuation E. Operator Training & Licensing Exam 5. Other (Explain)

F. Administrative G. Operational Error (Explain)

H. Other (Explain)

IV. Challenges to Safety and Relief Valves Unit 2 None Unit 3 None 6