Notification of Readiness for NRC 95001 Inspection
ML15239B289
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 08/25/2015
From: Marik S
Exelon Generation Co
To:
Document Control Desk, NRC/RGN-III
References
IR 2015002, SVPLTR: #15-0055
Download: ML15239B289 (2)


Text

  • * ' Dresden Generating Station Exelon Generat~i onI°*I 6500 North Morris, L05 Dresden Road www.exeloncorp.com August 25, 2015 SVPLTR: #15-0055

%*S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Dresden Nuclear Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-19 and DPR-25 NRC Docket Nos. 50-237 and 50-249

Subject:

Notification of Readiness for NRC 95001 Inspection

References:

1) Letter from Patrick Louden (NRC) to Bryan Hanson, "Final Significance Determination of a White Finding with Assessment Follow-up and Notice of Violation Letter for Dresden Nuclear Power Station Unit 3," dated March 26, 2015.
2) Letter from Anne Boland (NRC) to Bryan Hanson, "Dresden Nuclear Power Station, Unit 2 and 3 Integrated Inspection Report 2015-002 and Preliminary White Finding," for Unit 2, dated August 7, 2015.

In the referenced letters, Exelon Generation Company, LLC (EGC) was informed that based on the failure of the 2C and 3E electromatic relief valves (ERV), the NRC determined that Dresden Nuclear Power Station (DNPS) is in the Regulatory Response (Column Two) of the Reactor Oversight Process Action Matrix.

As a result of the White findings, the NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure 95001, "Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area." Additionally, the NRC requested EGC to provide notification of readiness for a supplemental inspection.

The purpose of this letter is to inform the NRC that EGC is ready for the supplemental inspection in accordance with Inspection Procedure 95001. Based on discussions with the NRC staff, EGC requests that the NRC begin the inspection in September 2015.

There are no regulatory commitments contained in this submittal.

Should you have any questions concerning this letter, please contact Mr. Bruce Franzen, Regulatory Assurance Manager, at 815-416-2800.

Shane Marik Site Vice President Dresden Nuclear Power Station * .__

cc: Regional Administrator - NRC Region IIl NRC Senior Resident Inspector - Dresden Nuclear Power Station NRC Project Manager, NRR - Dresden Nuclear Power Station