Text
Exelon.
Exelon Generation Company, LLC www.exeloncorp.com N uc e ar Dresden Nuclear Power Station 6500 North Dresden Road Morris, IL 60450-9765 March 15, 2002 PSLTR: #02-0017 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 Dresden Nuclear Power Station, Units 2 and 3 Facility Operating License Nos. DPR-19 and DPR-25 Docket Nos. 50-237 and 50-249
Subject:
Monthly Operating Report for February 2002 In accordance with Technical Specifications, Section 5.6.4, "Monthly Operating Reports," we are submitting the February 2002 - Monthly Operating Report for Dresden Nuclear Power Station, Units 2 and 3.
Should you have any questions concerning this letter, please contact Mr. Bob Rybak, Regulatory Assurance Manager, at (815) 416 - 2800.
Respectfully, Preston Swafford Site Vice President Dresden Nuclear Power Station Attachment cc:
Regional Administrator - NRC Region III NRC Senior Resident Inspector - Dresden Nuclear Power Station
ATTACHMENT DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 MONTHLY OPERATING REPORT FOR FEBRUARY 2002 EXELON GENERATION COMPANY, LLC FACILITY OPERATING LICENSE NOS. DPR-19 AND DPR-25 NRC DOCKET NOS. 50-237 AND 50-249 I
TABLE OF CONTENTS I.
Introduction I.
Summary of Operating Experience A.
Unit 2 Monthly Operating Experience Summary B.
Unit 3 Monthly Operating Experience Summary III.
Operating Data Statistics A.
Operating Data Report - Dresden Unit 2 B.
Operating Data Report - Dresden Unit 3 IV.
Unit Shutdowns A.
Unit 2 Shutdowns B.
Unit 3 Shutdowns V.
Amendments to Facility Licenses or Technical Specifications No Amendments to Facility Licenses or Technical Specifications were issued in the month of February VI.
Unique Reporting Requirements A.
Main Steam Relief and/or Safety Valve Operations 2
I.
Introduction Dresden Nuclear Power Station (DNPS) is a two reactor generating facility owned and operated by the Exelon Generation Company, LLC. DNPS is located at the confluence of the Kankakee and Des Plaines Rivers, in Grundy County, near Morris, Illinois.
DNPS Unit 2 is a General Electric Boiling Water Reactor. DNPS Unit 2 is licensed at 2957 megawatts thermal. The gross electrical output is 912 megawatts, with design net electrical output ratings of 864 megawatts. The commercial service date for Unit 2 is August 11, 1970.
DNPS Unit 3 is a General Electric Boiling Water Reactor. DNPS Unit 3 is licensed at 2527 megawatts thermal. The gross electrical output of Unit 3 is 834 megawatts, with design net electrical output ratings of 795 megawatts. The commercial service date for Unit 3 is October 30, 1971.
Waste heat is rejected to a man-made cooling lake using the Kankakee River for make up and the Illinois River for blowdown.
The Architect-Engineer for DNPS Units 2 and 3 was Sargent and Lundy of Chicago, Illinois.
3
II.
SUMMARY
OF OPERATING EXPERIENCE FOR FEBRUARY 2002 A.
UNIT 2 MONTHLY OPERATING EXPERIENCE
SUMMARY
From February 25 through February 28, 2002, Unit 2 operated between 725 and 850 MWe, for planned maintenance on Feedwater, Condensate, and Condensate Booster Pumps. Operation at full uprated power requires all of these pumps to be in operation. Therefore periods have been scheduled for power derates in order to perform routine maintenance on these pumps. With the exception of the above description and scheduled surveillances, Unit 2 operated at full power for the remainder of the period.
B.
UNIT 3 MONTHLY OPERATING EXPERIENCE
SUMMARY
Unit 3 operated throughout the period at full power except for short periods for maintenance and surveillances.
4
III.
OPERATING DATA STATISTICS A. Dresden Unit 2 Operating Data Report for February 2002 DOCKET NO.
DATE 050-237 March 04, 2002 COMPLETED BY Don Hamilton TELEPHONE (815) 416-3585 OPERATING STATUS
- 1.
REPORTING PERIOD: February 2002
- 2.
CURRENTLY AUTHORIZED POWER LEVEL (MWth): 2,957 MAXIMUM DEPENDABLE CAPACITY (MWe NET): 850 (estimated)
DESIGN ELECTRICAL RATING (MWe Net): 864
- 3.
POWER LEVEL TO WHICH RESTRICTED (MWe Net): No Restrictions
- 4.
REASONS FOR RESTRICTIONS (IF ANY): See Section II.A of this report.
Unit Two Monthly Operating Status This Month Year to Date Cumulative
- 5. Hours in Period 672 1,416 276,576
- 6. Reactor Critical - Hours 672 1,416 209,054
- 7. Reactor Reserve Shutdown - Hours 0
0 0
- 8. Hours Generator On-Line 672 1,416 200,565
- 9. Unit Reserve Shutdown - Hours 0
0 4
1 0.Thermal Energy Generated - MWHt Gross 1,877,185 3,977,925 433,362,589
- 11. Electrical Energy Generated - MWHe Gross 602,460 1,278,761 138,958,269
- 12. Electrical Energy Generated - MWHe Net 574,432 1,219,247 131,701,928
- 13. Reactor Service Factor - Percent 100.0%
100.0%
75.6%
- 14. Reactor Availability Factor - Percent 100.0%
100.0%
75.6%
- 15. Generator Service Factor - Percent 100.0%
100.0%
72.5%
- 16. Generator Availability Factor - Percent 100.0%
100.0%
72.5%
- 17. Capacity Factor - (Using MDC Net) Percent 100.6%
101.3%
56.0%
- 18. Capacity Factor - (Using DER Net) Percent 98.9%
99.7%
55.1%
5
III.
OPERATING DATA STATISTICS B. Dresden Unit 3 Operating Data Report for February 2002 DOCKET NO.
DATE COMPLETED BY TELEPHONE 050-249 March 04, 2002 Don Hamilton (815) 416-3585 OPERATING STATUS
- 1.
- 2.
- 3.
4.
REPORTING PERIOD: February 2002 CURRENTLY AUTHORIZED POWER LEVEL (MWth): 2,527 MAXIMUM DEPENDABLE CAPACITY (MWe Net): 773 DESIGN ELECTRICAL RATING (MWe Net): 795 POWER LEVEL TO WHICH RESTRICTED: No Restrictions REASONS FOR RESTRICTIONS (IF ANY): See Section II.B of this report.
Unit Three Monthly Operating Status This Month Year to Cumulative Date
- 5. Hours in Period 672 1,416 265,896
- 6. Reactor Critical - Hours 672 1,416 196,434
- 7. Reactor Reserve Shutdown - Hours 0
0 0
- 8. Hours Generator On-Line 672 1,416 188,577
- 9. Unit Reserve Shutdown - Hours 0
0 1
10.Thermal Energy Generated - MWHt Gross 1,696,141 3,567,705 407,744,052
- 11. Electrical Energy Generated - MWHe Gross 552,673 1,163,013 130,864,455
- 12. Electrical Energy Generated-MWHe Net 534,558 1,124,585 124,427,120
- 13. Reactor Service Factor - Percent 100.0%
100.0%
73.9%
- 14. Reactor Availability Factor - Percent 100.0%
100.0%
73.9%
- 15. Generator Service Factor - Percent 100.0%
100.0%
70.9%
- 16. Generator Availability Factor - Percent 100.0%
100.0%
70.9%
- 17. Capacity Factor- (Using MDC Net) Percent 102.9%
102.7%
60.5%
- 18. Capacity Factor- (Using DER Net) Percent 100.1%
99.9%
58.9%
6
IV. UNIT SHUTDOWNS A. Unit 2 Shutdowns for February 2002 NO DATE TYPE DURATION REASON (2)
METHOD OF CORRECTIVE ACTIONS/
(1)
(HOURS)
SHUTTING DOWN COMMENTS REACTOR(3)
None B. Unit 3 Shutdowns for February 2002 NO DATE TYPE DURATION REASON (2)
METHOD OF CORRECTIVE ACTIONS/
(1)
(HOURS)
SHUTTING DOWN COMMENTS REACTOR(3)
None LEGEND:
(1) Type:
(2) Reason (3) Method F - Forced A. Equipment Failure (Explain)
- 1. Manual S - Scheduled B. Maintenance or Test
- 2. Manual Scram C. Refueling
- 3. Automatic Scram D. Regulatory Restriction
- 4. Other (Explain)
E. Operator Training & Licensing Exam
- 5. Load Reduction F. Administrative G. Operational Error H. Other (Explain)
V. Amendments to Facility Licenses or Technical Specifications During the month of February there were no Facility Licenses or Technical Specification changes.
VI. UniQue Reporting ReQuirements A. Main Steam Relief and/or Safety Valve Operations Unit 2 - None Unit 3 - None 7