RBG-26995, Responds to NRC Re Violations Noted in Insp Rept 50-458/87-24.Corrective Actions:Work Copies of Incorrect Procedure STP-000-3001 Maintained at Security Compliance Section Immediately Destroyed

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in Insp Rept 50-458/87-24.Corrective Actions:Work Copies of Incorrect Procedure STP-000-3001 Maintained at Security Compliance Section Immediately Destroyed
ML20236Q865
Person / Time
Site: River Bend Entergy icon.png
Issue date: 11/16/1987
From: Deddens J
GULF STATES UTILITIES CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
RBG-26995, NUDOCS 8711200330
Download: ML20236Q865 (4)


Text

_

x;$ '

1 l

)

GULF STATES UTILITIES COMPANY.

a?e 'i i

November 16, 1987 RBG - 26995 {"

File ~Nos. G9.5, G15.4.1 n

U.S. Nuclear Regulatory Commission Document Control Desk Washington. D.C. 20555 Gentlemen:-

River Bend Station - Unit 1 Refer to: . Region IV Docket No. 50-458/ Report 87-24 This letter ' responds to. the Notice of Violation contained in NRC Inspection Report No. 50-458/87-24. .. The inspection was performed by.

Messrs.- Chamberlain, Jones, and Jaudon during the period of September

~ ~

16-30, 1987 on activities authorized by NRC Operating License NPF for River Bend Station Unit No. 1. Notice of Violation 458/8724-01 corrective action was' fully described in the inspection report and no written response was required.

Gulf States Utilities Company's (GSU) response to Notice of Violation 458/8724-02,'" Failure to Utilize Proper Revision of Surveillance Test Procedure," is provided in the enclosed attachment pursuant to 10CFR2.201. This completes GSU's response to this item.

Sincerely, J. C. Deddens Senior Vice President River Bend Nuclear Group i JCD/E h cc: U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76011

- NRC Resident Inspector

i. P.O. Box 1051 St. Francisville, LA 70775 O(

8711200330 871116 i PDR ADOCK 05000458 G PDR 1

l- .'

-UNITED STATES OF AMERICA

. NUCLEAR REGULATORY COMMISSION STATE OF LOUISIANA )

. PARISH OF WEST FELICIANA )

.In the Matter of ) Docket No.-50-458 50-459 GULF STATES UTILITIES. COMPANY )

'(River Bend Station, Unit 1)-

AFFIDAVIT J.. C. Deddens, being duly sworn, states that he is a Senior Vice President of Gulf States Utilities Company; that he is authorized on the part of said company to sign and file with the-Nuclear. Regulatory . Commission the documents attached hereto; .and that all such documents are true and correct to the best of his knowledge, information and belief, h / W J. CfDeddens Subscribed and sworn to before me, a Notary Public in and for the State and Parish above named, this [k b day of O{/6/h be r , 19 h9.

11, / 1, &

f,,doan W. Middlebrooks i Notary Public in and for West Feliciana Parish, Louisiana 1 i

I My Commission is for Life.

I

W ..

ATTACHMENT Response To Notice of Violation 50-458/8724-02 Level IV

REFERENCE:

_ Notice of Violation - letter from L-. J. Callan to J. C. Deddens, dated October 15, 1987.-

VIOLATION:

' Failure to . Utilize Proper' Revision of Surveillance Test Procedure -

Technical Specification 6.8.1.g requires that written procedures be established, implemented and maintained for activities implementing the fire protection program.

Administrative' Procedure-(ADM)-0015, " Station Surveillance Test . Program,"

requires than an ' individual assigned to perform a surveillance test utilize anL official work copy of the. latest test , revision of the surveillance test procedure '(STP) and. any associated temporary change '

notices.

Contrary to the:above, STP-000-3001, " Daily Fire Door Position Check,"'

performed on September 20. 1987, and September 22, 1987, did not utilize-the latest revision of the.STP which was available from station document

" ,ntrol'on August 27, 1987.

. REASON FOR THE VIOLATION:

In ' August. 1987, Security Compliance personnel- picked up several work copies of STP-000-3001, " Daily Fire Door Position Check", from Plant  !

Document Control. On September 20 and .again on September' 22, the individuals failed to verify that they had the latest revision to STP-000-3001, Revision 2, dated August 27,.1987 and proceeded to conduct the surveillance tests using the out-of-date August 26, 1987.STP. Failure to follow procedure was a personnel error which has been isolated and corrected as described.

CORRECTIVE STEPS WHICH HAVE BEEN TAKEN AND THE RESULTS ACHIEVED:

On September 25, 1987, when the use of an incorrect procedure was identified, all work copies of STP-000-3001 maintained at the Security Compliance Section were immediately destroyed. Security Compliance personnel are required to obtain an official work copy of the STP from Plant Document Control on the day the surveillance test is to be performed with no exceptions.

Security personnel have been re-instructed, pursuant to ADM-0015, to verify ~with document control or the Station Operating Manual (SDM) Index maintained in the Control' Room that the documents to be used are current

' prior to performing the work.

L 1-

J i

A review was performed of STP documentation completed within the last six months and no similar occurrences were identified prior to August 27, 1987. GSU has determined'this use of an incorrect revision from August 27

- to September 24, 1987, to be an isolated case.

CORRECTIVE STEPS WHICH WILL BE TAKEN TO AVOID FURTHER VIOLATIONS:

In addition to steps taken as listed above, Plant Security has been placed on Document Control distribution list to receive copies of Temporary Change Notices and Procedure Changes. This along with above mentioned personnel training should prevent recurrence of the oversight.

DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED:

Compliance to Procedure STP-000-3001 has been fully achieved.

)