RBG-22557, Forwards Weekly Status Rept Re License Conditions & Other Commitments Completed During Previous Wk & Cumulatively Since Issuance of Low Power License,In Response to

From kanterella
Jump to navigation Jump to search
Forwards Weekly Status Rept Re License Conditions & Other Commitments Completed During Previous Wk & Cumulatively Since Issuance of Low Power License,In Response to
ML20209H694
Person / Time
Site: River Bend Entergy icon.png
Issue date: 11/07/1985
From: Booker J
GULF STATES UTILITIES CO.
To: Butler W
Office of Nuclear Reactor Regulation
References
RBG-22557, NUDOCS 8511110193
Download: ML20209H694 (4)


Text

--

GULF ' STATES UTEL1 TEES COMPANY P O S T O F F I C E 8 0 X 2 9 51 e _eEAUMONTTEXAS77704 -j AREACODE 409 838-8631 i

November 7, 1985 l File No. G9.5 RBG-22557 Director.of Nuclear Reactor Regulation

-Attention: Dr. W. R. Butler, Chief Licensing Branch No.'2 Division.of Licensing ' .

U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Dear Mr. Butler:

' River Bend Station - Unit 1 Docket No.~50-458 In response to your letter dated September 25, 1985, this weekly status report-is being provided which identifies those license con-ditions and other commitments that have been completed during the previous week and cumulatively since issuance of the low power license.

Attachment 1 is a cumulative listing of license conditions and Attach-ment 2 covers other important commitments that have been completed.

Should you have any questions please contact W.~ J. Reed of my staff.

Sincerely,

.b 4 J. E. Booker Manager-Engineering, Nuclear Fuels & Licensing River Bend Nuclear Group

-JEB/WJR/LAE/meh Attachments cc: Mr. Robert Martin RIV Mr. Dwight Chamberlain SRI hkg PDR >

> I

ATTACHMENT 1 Noveiber 7, 1985 RBG-COMPLETED LICENSE CONDITIONS License Condition No. Description Comments L/C (1)2.s Modify operating procedures to GSU letter monitor control room HVAC cooling 9/26/85 water (DR-314).

L/C (1)2.f Complete HVAC charcoal loading GSU letter and testing. 9/26/85 L/C (1)3.a.ii Fire-wrap control building GSU letter electrical raceways, 9/26/85 L/C (1)2.b Modify EOP relative to GSU letter Limitorque operators (DR-280). 10/3/85 L/C (1)5.a Fuel building sampling system. GSU letter 10/3/85 L/C (1)7.a Elgar fuse blocks (DR-287). CSU letter 10/3/85 L/C (13) Use advisors until operating GSU letter etaff experience requirements 9/26/85 are met.

L/C 2.D Exemption for operation up to GSU letter five percent from CDC2-Seismic 10/3/85 Qualification of two A0V's (IDFR*144 and 145). "

L/C (1)1.a Test off-gas system and off-gas GSU letter vault refrigeration system. 10/10/85 L/C (1)3.a.1 Test CO2 fire protection for T/G. GSU letter 10/10/85 L/C (1)3.c Complete modifications / qualification GSU letter of 1DFR*A0V 144 and 145 (DR-193). 10/10/85 L/C (16) 3 Submit containment venting information. GSU letter 10/10/85

ATTACHMENT 1 November 7, 1985 RBG-Page 2 License Condition No. Description Commente L/C (1)2.c Verify Plant's air flow GSU letter Characteristics. 10/17/85 L/C (1)2.d Place sample panels in service GSU letter after testing and calibration. 10/17/85 L/C (1)3.s Modifications to. reduce maximum GSU letter emergency service load for 10/24/85 Division I and II diesel generators.

L/C (1)2.e Testing of service water GSU letter modifications and TDI diesel 10/31/85 generator load reduction modifications.

L/C (6) Environmental qualification of GSU letter electrical equipment. 10/31/85 L/C (1)3.b Testing of liquid, gaseous and GSU letter solid radwsste systems. 10/31/85 L/C (1)6.a Load testing of cranes and hoists l

l L_

I ATTACHMENT 2 November 7, 1985 RBG-OTHER COMMITMENTS COMPLETED ,

Reference Description Comments R80-21093 Perform internal sample review of Gsu letter 5/24/85 Seismic Qualification Documentation 10/3/85 before 5% power.

RBG-21378 Replace existing Rosemount 1153 5 CSU letter 6/24/85 devices used for suppression pool 10/3/85 water level measurement with Rosemount 1154 devices before exceeding 55 power.

SSER 3 QA check of implemeating and GSU letter 8.3.1(2.4) procedural documents pertaining 10/3/85 to maintenance and surveillence-of diesels against TDI owner's Group and PNL recommendations.

SSER 3 Incorporate PNL recommendations CSU letter 8.3.1(2.4) into TDI maintenance and 10/3/85 surveillance programs.

TECH SPEC Program to assure detection and CSU letter 6.8.4.d prevention of Asiatic Class. 10/10/85 RBG-21767 Submit Rev. 3 to Offsite Dose GSU 18tt*Y 8/5/85 Calculation Manual. 10/10/85 6/13/85 High energy line. break detection CSU letter Item A.1 and mitigation. 10/31/85 6/13/85 Moderate energy line crack detection GSU letter Item A.2 and mitigation. 10/31/85 6/13/85 Containment atmospherie monitoring. CSU letter ices 3.1 10/31/85 6/13/85 Miscellaneous building floor drains. GSU letter Item B.10 10/31/85 6/13/85 Fire wrapping of electrical raceways Item A.8 (Spent fuel pool cooling system) 6/13/85 Generator H2 and CO2 Item B.9 QW