PNO-III-87-080, on 870529,reactor Achieved Initial Criticality.Ol Issued on 861017,authorizing Fuel Load & Subcritical Testing.Preparation for & Achievement of Initial Criticality Monitored by Resident Inspectors

From kanterella
Jump to navigation Jump to search
PNO-III-87-080:on 870529,reactor Achieved Initial Criticality.Ol Issued on 861017,authorizing Fuel Load & Subcritical Testing.Preparation for & Achievement of Initial Criticality Monitored by Resident Inspectors
ML20214S262
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 06/01/1987
From: Little W, Tongue T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
References
PNO-III-87-080, PNO-III-87-80, NUDOCS 8706090201
Download: ML20214S262 (1)


{ PRELIMINARY l'0TIFICATION OF EVENT OR UNUSUAL OCCURRENCE--PNO bm6 i

This preliminary notification constitutes EARLY notice of events of POSSIBLE safety Cr public interest significance. The information is as initially received without verification or evaluation, and is basically all that is known by the Region III (

staff on this date.

Facility: Corraonwealth Edison Company Licensee Emergency Classification:

Braidwood Unit I hotification of an Unusual Event Braceville, IL 60407 Alert Site Area Emergency Docket No. 50-456 General Emergency X Not Applicable

Subject:

INITIAL CRITICALITY The Unit I reactor achieved initial criticality at 10:39 p.m. (CDT) on May 29, 1987.

Conditions at the time of the initial criticality were as expected.

An Operating License was issued on October 17, 1986, authorizing fuel load and subcritical testing. The license authorizing operation up to five percent power was issued on May 21, 1987.

The preparation for and achievement of initial criticality was monitored by the resident inspectors.

The State of Illinois will be notified.

Region III (Chicago) was notified of the initial criticality by the resident inspector May 29, 1987. This information is current as of 9 a.m., June 1,1987.

, b CONTACT: T ' Tongue

//f W. Little (815)458-2852 FTS 388-557C DTSTRIBUTION:

H. St. ED0 NRR E/W Willste Mail: ADM:DMB Chairman Zech PA IE NMSS 00T:Trans only Comm. Roberts ELD OIA RES Conn. Asselstine AE0D NRC Ops Ctr /)dih Comm. Bernthal Conn. Carr SP /.2.NP Regional Offices ACRS SECY INP0/.2.'50 NSAC /)'Sil CA RIII Resident Office PDR Licensee: /g, g7 (Corp. Office - Reactor Lic. Only)