Proposes Listed Schedule for Completion of NRC Review of Util 881216 Updated Inservice Insp Program for ASME Code Class 1,2 & 3 Components.Approx 2 Yrs Left to Complete Remaining Exam Requirements
ML20244B799
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 06/08/1989
From: Hairston W
ALABAMA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
TAC-71578, NUDOCS 8906130298
Download: ML20244B799 (2)


Text

. _ _ . . _ . _ _ , _ .

  • Alabama Power Company 600 North 18th Street Post Oflice Box 2641 Birmingham. Alabama 352910400 Telephone 205 250-1837 W. G. Hairston, lit Senior Vice President Nuclear Operations the southem electrc system 10CFR50.55a(g)

-June 8, 1989 Docket No. 50-364 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C. 20555 Gentlemen:

Joseph M. Farley Nuclear Plant - Unit 2 Updated Inservice Inspection Program for ASME Code Class 1, 2 and 3 Components (TAC No. 71578)

By letter dated December 16, 1988, Alabama Power Company (APCo) submitted an updated Inservice Inspection (ISI) Program for ASME Code Class 1, 2 and 3 Components for Farley Nuclear Plant - Unit 2. The NRC subsequently requested a list of only those reliefs which were necessary to support completion of the Unit 2 sixth refueling outage. This list was provided by letter dated February 8, 1989 and was later modified by letter dated March 23, 1989. On March 31, 1989 the NRC granted the ISI Program reliefs requested for the Unit 2 outage.

The ISI Program was updated based on the 1983 Edition through the Summer 1983 Addenda of the ASME Code,Section XI. This program, now in effect, governs completion of the examination requirements for the third forty-month period of the first ten-year interval, which ends on July 30, 1991. Approximately two ars, including one refueling outage tentatively scheduled for September 1990, are left in . Ich to complete the remaining examination requirements. Alabama Power Company respectfully proposes the following schedule for completion of the NRC's review process and interim or final approval of the relief requests which vere not granted by the NRC's March 31, 1989 letter:

August 31, 1989 NRC submits a formal request for additional information (RAI), if necessary, on the remaining reliefs. Schedule a review meeting between APCo and the NRC as needed to resolve open issues on the RAI and NRC's review of the ISI Program.

December 1, 1989 APCo submits a revised ISI Program reflecting agreements from the resolution of the RAI and meeting issues.

[DN 6906130296 890608

{DR ADOCK 05000364 I I FDC

a.

D q.; ..-

U. S. Nuclear Regulatory Commission _

Page 2 1 June 1, 1990- NRC grants interim relief on remaining' relief' requests or issues SER with final; granting of all reliefs.

, Resolution of the open issues on the. remaining' relief. requests in accordance with the proposed schedule vill provide approximately one year (not including the Code allowed'one-year extension) for-Alabama Power Company to complete the required examinations. =This will-also:permitL

~

proper planning of examinations to'be performed during~the remaining refueling. outage.

. If therelare any questions or if this schedule cannot be accommodated,u

~

please advise.

Respectfully submitted,

. ALABAMA = POWER COMPANYi

  1. Y

[h_ ~

V. G. Hairston, III

- VGH/DEM/ STB:cht-8.43 cc: Mr. S..D. Ebneter Mr. E. A. Reeves Mr. G. F. Maxwell-1 i