Forwards List of Inservice Insp Relief Requests Required for Sixth Refueling Outage,Per NRC Request
ML20235Z426
Person / Time
Site: Farley 
Issue date: 02/08/1989
From: Hairston W
ALABAMA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 8903150439
Download: ML20235Z426 (3)


Text

- _ - _ -

r Alab;m2 Power Company

' 600 North 18th Street Post Office Box 2641 Birmingham, Alabama 352914400 Telephone 2052501837 W. G. Hairston,Ill Senior Vice President Nuclear Operations Alabama Power the southem electrc system 10CFR50.55a(g)

February 8, 1989 I

Docket No. 50-364 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Vashington, D. C.

20555 Gentlemen:

Joseph H. Farley Nuclear Plant - Unit 2 i

Request for Relief From Certain Requirements l

of 10CFR50.55a(g)

By letter dated August 31, 1988, the NRC approved updating the Inservice l

Inspection (ISI) Program for Joseph H. Farley Nuclear Plant, Unit 2 to the J

1983 Edition through the Summer 1983 Addenda of the ASME Code,Section XI.

This letter also stated that these later Code requirements were to be implemented during the Unit 2 sixth refueling outage scheduled for March 1989.

The updated ISI Program was submitted to the NRC by letter dated j

l December 15, 1988.

As a part of the review process for granting specific relief requests, the l

NRC verbally requested a list of the ISI reliefs which vill be required for the Unit 2 sixth refueling outage. A list of these requests is included in l

the attachment.

If there are any questions, please advise.

I f

Respectfully submitted, yjA./L.'t-f V. G. 51airston, III l

VGH/DEH/ CDP-cht:8.37 1

l Attachment l

cc:

Mr. H. L. Ernst Mr. E. A. Reeves Ogry Mr. G. F. Maxwell Il 0$$N$y8ggQ l

PDC

['y,

]

8 i

ATTACHMENT 1'

E Relief Requests Required for the Unit 2 k.*.

Sixth Refueling Outage L

Relief Request No Examination Area RR-l' Material requirements for calibration blocks used

'for ultrasonic examination of. heavy vall vessels.

RR-2' Di nensional requiremen"ts for calibration blocks used for ultrasonic examination of the reactor vessel.

RR-4

' Ultrasonic examination of piping systems and thin vall vessels.

RR-5 Dimensional differences between the' calibration

. blocks used for examination of piping systems and thin vall vessels and the components to be examined.

RR-6 Material' requirements for calibration blocks used for ultrasonic examination of piping systems and thin vall vessels.

RR-7 Dimensional requirements for calibration notches placed on calibration blocks used for ultrasonic examination of piping systems and thin vall vessels.

RR-9 Volumetric examination of nozzle-to-vessel velds in the pressurizer.

RR-10 Volumetric examination of nozzle-to-safe end welds in steam generators.

RR-11 Volumetric examination of nozzle inner radius section for steam generators.

RR-12 Delete VT-4 visual examination method and redefine VT-3 visual examination requirements in accordance with paragraph IVA-2213 of ASME Section XI, 1986 Edition.

RR-16 Visual examination of the internal pressure boundary surfaces of Class 1 valves.

RR-17 Reference system for all velds and areas subject to volumetric and surface examination, i

RR-18 Volumetric examination of pressure retaining velds in the regenerative heat exchanger.

l 1

r

_Y 1

J1 ATTACHMENT 1.h'

,' Relief Requests Requiredffor the Unit 2 l

Sixth Refueling Outage c

RR-24 Hydrostatic testing of the relief-line discharge headers lto the pressurizer relief tank-(line No.

HCB-62).-

RR-28 Volumetric examination of the nozzle inside radius -

section of the steam outlet nozzle on steam generators.

RR-29 Hydrostatic testing of boron injection-recirculation discharge piping.(line No. CCB-62).

RR-31 Visual (VT-2) examination for leakage of Class 3 service' vater pumps.

RR-32 Visual (VT-2) examination for leakage in encased piping in spent fuel pool cooling system.

RR-33, Hydrostatic testing of' portions of Class 3 piping and components which operate continuously during all modes of plant operation.

l RR-35 Hydrostatic testing of Class 3 buried piping in the service water' system.

1 RR-37 Visual (VT-2) examination of condenser coils (tubes) in Class 3 coolers.

RR-38 Hydrostatic testing of Class 3 portions of auxiliary steam piping.

RR-39 Hydrostatic testing of Class 3 auxiliary feedvater pump minimum flow piping.

RR-41 Break away drag test for hydraulic snubbers.

RR-42 Additional sample testing requirements for snubbers.

RR-44 Operational monitoring of the Class 3 spent fuel pool cooling heat exchangers.

l l

/cht:8.38 l