ML20213A880

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000282/2020002; 05000306/2020002; and 07200010/2020001
ML20213A880
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 07/30/2020
From: Hironori Peterson
Region 3 Branch 3
To: Sharp S
Northern States Power Company, Minnesota
References
IR 2020001, IR 2020002
Download: ML20213A880 (18)


See also: IR 05000282/2020002

Text

July 30, 2020

Mr. Scott Sharp

Site Vice President

Prairie Island Nuclear Generating Plant

Northern States Power Company, Minnesota

1717 Wakonade Drive East

Welch, MN 55089-9642

SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT - INTEGRATED

INSPECTION REPORT 05000282/2020002; 05000306/2020002; AND

07200010/2020001

Dear Mr. Sharp:

On June 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

Prairie Island Nuclear Generating Plant. On July 8, 2020, the NRC inspectors discussed the

results of this inspection with you and other members of your staff. The results of this

inspection are documented in the enclosed report.

One NRC-identified Severity Level IV violation without an associated finding is documented in

this report. We are treating this violation as a non-cited violation (NCV) consistent with Section

2.3.2 of the Enforcement Policy.

No NRC-identified or self-revealing findings were identified during this inspection.

A licensee-identified violation which was determined to be of very low safety significance is

documented in this report. We are treating this violation as a non-cited violation (NCV)

consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this

inspection report, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional

Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector

at Prairie Island Nuclear Generating Plant.

S. Sharp 2

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Hironori Peterson, Chief

Branch 3

Division of Reactor Projects

Docket Nos. 05000282; 05000306; and

07200010

License Nos. DPR-42; DPR-60; and

SNM-2506

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

ML20213A880

SUNSI Review

Non-Sensitive Publicly Available

Sensitive Non-Publicly Available

OFFICE RIII RIII

NAME NShah:bw via email HPeterson via email

DATE 7/30/2020 7/30/2020

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Numbers: 05000282; 05000306; 07200010

License Numbers: DPR-42, DPR-60, SNM-2506

Report Numbers: 05000282/2020002; 05000306/2020002; 07200010/2020001

Enterprise Identifier: I-2020-002-0041 and I-2020-001-0143

Licensee: Northern States Power Company, Minnesota

Facility: Prairie Island Nuclear Generating Plant

Location: Welch, Minnesota

Inspection Dates: April 01, 2020 to June 30, 2020

Inspectors: J. Dalzell, Health Physicist

R. Edwards, Senior Health Physicist

N. Feliz-Adorno, Branch Chief

L. Haeg, Senior Resident Inspector

K. Pusateri, Resident Inspector

Approved By: Hironori Peterson, Chief

Branch 3

Division of Reactor Projects

Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at Prairie Island Nuclear Generating Plant,

in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the

NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer

to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-

identified non-cited violation is documented in report section: 71152.

List of Findings and Violations

Cask Transport Vehicle Evaluation

Cornerstone Significance Cross-Cutting Report

Aspect Section

Not Applicable NCV 05000282,05000306/2020002-01 Not Applicable 60855.1

Open/Closed

The inspectors identified a Severity Level IV Non-cited violation (NCV) of 10 CFR 72.146,

Design Control for failing to adequately analyze, control deviations, and translate into

procedures the design for the interfacing surfaces of the tracked Cask Transport Vehicle

(CTV) which affected quality. Specifically, the interfacing surfaces that were relied upon to

preclude the new CTV from sliding into a cask loaded with spent fuel was not installed using a

procedure that reflected the design, the design calculation contained inadequacies, and

deviations from the design and installed configuration were not controlled to ensure the

minimum factors of safety to sliding were met.

Additional Tracking Items

None.

2

PLANT STATUS

Units 1 and 2 operated at or near full power for the entirety of the inspection period, with the

exception of brief power reductions to perform surveillance testing or flexible power operations.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors reviewed selected procedures and records,

observed activities, and interviewed personnel to assess licensee performance and compliance

with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President

of the United States on the public health risks of the coronavirus (COVID-19), resident

inspectors were directed to begin telework and to remotely access licensee information using

available technology. During this time the resident inspectors performed periodic site visits

each week and during that time conducted plant status activities as described in IMC 2515,

Appendix D; observed risk significant activities, and completed on-site portions of IPs. In

addition, resident and regional baseline inspections were evaluated to determine if all or a

portion of the objectives and requirements stated in the IP could be performed remotely. If the

inspections could be performed remotely, they were conducted per the applicable IP. In some

cases, portions of an IP were completed remotely and on-site. The inspections documented

below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1) Unit 1 caustic addition system on 04/16/2020

(2) 12 diesel-driven cooling water pump on 05/4/2020

(3) 121 safeguards travelling screen on 05/20/2020

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

The inspectors evaluated system configurations during a complete walkdown of the

following:

(1) Unit 1 control rod system on 06/19/2020

3

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1) Fire zone 18 relay and cable spreading room on 04/22/2020

(2) Fire zone 58 Unit 1 charging pumps 11, 12, and 13 on 04/22/2020

(3) Fire zone 75 plant screen house elevation 695' on 05/20/2020

(4) Fire zone 74 plant screen house elevation 670' on 06/15/2020

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) 695' elevation turbine building on 04/28/2020

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1) Control room observations during a spent fuel loading campaign on 05/26/2020

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated operator training in the simulator on

05/27/2020

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following

structures, systems, and components (SSCs) remain capable of performing their intended

function:

(1) Component cooling water system on 04/27/2020

(2) AR 501000039958; PMT unsatisfactory due to leak on 4/23/2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the

following planned and emergent work activities to ensure configuration changes and

appropriate work controls were addressed;

4

(1) AR 501000039494; 23 fan coil unit damper did not re-position on 04/09/2020

(2) AR 501000039466; 2A reheater drain level control failure on 04/10/2020

(3) AR 501000039723; CV-31941 had dual indication on the control board on 04/16/2020

(4) 22 diesel-driven cooling water jacket water hose leak availability determination on

05/12/2020

(5) Maintenance risk during 12 residual heat removal pump breaker replacement on

06/23/2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the

following operability determinations and functionality assessments:

(1) 23 containment fan coil unit damper past operability review on 05/04/2020

(2) 22 diesel driven cooling water jacket water hose leak past operability review on

05/06/2020

(3) 22 turbine driven auxiliary feedwater pump bearing temperature in the alert range on

04/21/2020

(4) 11 turbine driven auxiliary feedwater pump past operability review on 06/04/2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the following post maintenance test activities to verify system

operability and functionality:

(1) AR 501000038420; 23 containment fan coil unit damper did not re-position on

04/09/2020

(2) Maintenance on 13 charging pump breaker following instantaneous trip test failure on

04/22/2020

(3) AR 501000039981; PMT planning issues on 2SM-5-4 on 04/23/2020

(4) D5 emergency diesel generator ventilation system testing following damper

maintenance on 06/10/2020

(5) 22 component cooling water heat exchanger temperature control valve failure on

06/02/2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01) (1 Sample)

(1) SP 1856; Bus 26 undervoltage test on 4/28/20

Inservice Testing (IP Section 03.01) (1 Sample)

(1) SP 1089A; RHR quarterly pump and valve test on 05/08/2020

5

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01)

(1 Sample)

(1) Licensed operator re-qualification training with DEP Performance Indicator evaluation

on 06/19/2020

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS07: High Pressure Injection Systems (IP Section 02.06) (1 Sample)

(1) MSPI high pressure injection 2Q19 through 1Q20 on 04/22/2020

MS08: Heat Removal Systems (IP Section 02.07) (1 Sample)

(1) MSPI heat removal 2Q19 through 1Q20 on 04/23/2020

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program during the period of

January 1, 2020, through June 30, 2020, for potential adverse trends in maintenance

practices that might be indicative of a more significant safety issue.

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program

related to the following issues:

(1) RCE 501000036932; Breaker 26-16 undersized on 03/31/2020

OTHER ACTIVITIES - TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

60855.1 - Operation of an Independent Spent Fuel Storage Installation at Operating Plants

Operation of an Independent Spent Fuel Storage Installation at Operating Plants (1 Sample)

(1) Due to the COVID-19 public health emergency, the inspectors remotely evaluated the

licensees Independent Spent Fuel Storage Installation (ISFSI) cask loading through

use of the licensee's in-plant camera system on May 26 - May 29, 2020. To complete

this inspection, the inspectors intend to visit the Prairie Island ISFSI before the end of

2020 to evaluate the material and radiological conditions of the site. This site visit is

pending further reductions in risk associated with travel during the public health

emergency. During the remote portion of the inspection, the inspectors observed the

6

following activities:

  • Fuel selection and fuel loading for the third and final cask in the campaign,

cask number 47

  • Heavy load movement of the cask out of the spent fuel pool to the cask

processing area, and movement of the cask in preparation for transport to the

ISFSI

  • Drying and backfill evolutions
  • Closure operations
  • Cask transport evolutions
  • Radiological field surveys

The inspectors evaluated the following change reviews:

  • Selected corrective action program documents
  • Selected 72.48 screenings and evaluations

INSPECTION RESULTS

Cask Transport Vehicle Evaluation

Cornerstone Severity Cross-Cutting Report

Aspect Section

Not Severity Level IV Not 60855.1

Applicable NCV 05000282,05000306/2020002-01 Applicable

Open/Closed

The inspectors identified a Severity Level IV Non-cited violation (NCV) of 10 CFR 72.146,

Design Control for failing to adequately analyze, control deviations, and translate into

procedures the design for the interfacing surfaces of the tracked Cask Transport Vehicle

(CTV) which affected quality. Specifically, the interfacing surfaces that were relied upon to

preclude the new CTV from sliding into a cask loaded with spent fuel was not installed using

a procedure that reflected the design, the design calculation contained inadequacies, and

deviations from the design and installed configuration were not controlled to ensure the

minimum factors of safety to sliding were met.

Description:

A new CTV was procured by the licensee for transporting TN-40/40HT casks between the

Auxiliary Building and the Independent Spent Fuel Storage Installation (ISFSI) pad.

Calculation No. 2018-03457, "Evaluation of Auxiliary Building Fuel Unloading Area for

Loading Associated with New Cask Transport Vehicle," Revision 0, was a safety related

analysis that included an evaluation of the stability of spent fuel casks (empty and full) and

the CTV (loaded and unloaded). The Prairie Island Nuclear Generating Plant (PINGP) ISFSI

was licensed by the NRC in Renewed License SNM-2506, License for Independent Spent

Nuclear Fuel and High-Level Radioactive Waste, Amendment 10. License Condition 9,

Authorized Use, of SNM-2506, states, in part, that the basis for this license was submitted in

the Safety Analysis Report dated August 31, 1990 and as further supplemented and

amended in accordance with 10 CFR 72.70 and 10 CFR 72.48. Calculation No. 2018-03457

utilized the ISFSI design basis to establish the acceptance criteria for factors of safety against

sliding and tipping. Specifically, section 6.1 of Calculation No. 2018-03457 states the factors

of safety against sliding and overturning shall be 1.1 or greater per Ref[erence]s. 5a and 6a.

Reference 5a is Revision 18 of the PINGP ISFSI Safety Analysis Report which established

1.1 as the minimum factor of safety to sliding in section 4.2.1, Structures, for postulated

7

earthquake loads. The TN-40/40HT cask is safety-related equipment and the Auxiliary

Building slab foundation is considered a safety-related structure.

In Calculation No. 2018-03457, a sliding analysis was performed to assess whether the CTV

will slide during a postulated design basis earthquake. The conclusion that the cask would

not slide was based on an assumed coefficient of friction of 0.5 between the Auxiliary Building

concrete slab and the CTV tracks. This coefficient of friction value was taken from

Calculation No. 8708-320, Spent Fuel Storage Cask Transporter for Xcel Energy Prairie

Island Nuclear Generating Plant," Revision 3. In Calculation No. 8708-320, the coefficient of

friction was specified as coefficient of friction to road; however, the interfacing surfaces for

this value are not described and the CTV travels over multiple surfaces on the haul path

towards the ISFSI, including concrete and gravel. Calculation No. 2018-03457 also permits

SS [stainless steel] deck plates or plywoods may be placed to protect concrete surfaces if

the contact areas between CTV treads and SS deck plates/plywoods are not greater than

8.0 ft2 with maximum thickness of 3/8 in[ch].

Prairie Island Nuclear Generating Plant Maintenance Procedure No. D95.10, "Tracked Cask

Transporter Vehicle Operations," Revision 0, provided the detailed instructions for the

inspection, startup, and operation of the tracked CTV. This procedure did not contain any

limitations or guidance regarding the material, size, or placement of the protective surfaces

between the Auxiliary Building slab and the tracked CTV. The actual configuration, as

remotely observed by the inspectors during ISFSI operations on May 28, 2020, consisted of

1/2-inch-thick high-density plastic sheets placed between the steel CTV treads and the

painted Auxiliary Building concrete slab. Since the design for protective surfaces was not

translated into a procedure, the installed protective surfaces were not as analyzed in

Calculation No. 2018-03457 and deviations to the design were not controlled. Specifically,

there were 3 examples where the interfacing surfaces relied upon to preclude the new CTV

from sliding into a cask loaded with spent fuel was inadequately analyzed, deviations were

not controlled, and the installation of these surfaces was not controlled by a procedure to

ensure the configuration matched the design:

  • The chosen coefficient of friction value of 0.5 for the surface between the Auxiliary

Building floor and tracks of the CTV was taken from a haul path analysis where these

surfaces differed from the interfacing surfaces in the Auxiliary Building (the Auxiliary

Building had relatively smooth, painted, concrete floors).

  • To protect the Auxiliary Building floor, Calculation No. 2018-03457 stated up to 8.0 ft2

of 3/8-inch-thick plywood or stainless-steel plates on the Auxiliary Building floor were

permissible, but no analysis was provided about how these multiple surfaces impact

sliding or tipping. That is, the analysis did not analyze the interfacing surfaces

between the floor and plywood/plate, and similarly did not consider the interfacing

surface between the plywood/plate and the tracks on the CTV.

  • The 3/8-inch plywood or stainless-steel plates were not used. Instead, 1/2-inch-thick

high-density plastic sheets were used; however, the change in material and thickness

was not analyzed for how it might impact the sliding and tipping analysis.

Corrective Actions: The inspector identified this concern during the transfer of the last cask in

the loading campaign. Transfer of the loaded cask to the ISFSI was completed safely and

without incident. The concern was placed in the corrective action program, and while

corrective actions were still being developed at the conclusion of the inspection, preliminary

actions include revising Calculation No. 2018-03457.

8

Corrective Action References: AR 501000041132; New Cask Transporter Revise Evaluation;

May 29, 2020

Performance Assessment:

Performance Deficiency: The inspectors concluded that measures were inadequate to

ensure that the design basis was correctly translated into Procedure No. D95.10, the design

calculation was accurate, and deviations to appropriate quality standards specified in design

Calculation No. 2018-03457 were controlled to ensure the minimum factors of safety to

sliding were met which resulted in a performance deficiency.

Screening: The inspectors determined that the violation was of more than minor significance

using IMC 0612, "Power Reactor Inspection Reports," Appendix E, "Example of Minor

Issues." Example 3.e was found to be similar in that the licensee failed to establish

measures to ensure that the procedures for setting up the CTV in the auxiliary building were

in accordance with the design which lead to reasonable doubt whether the seismic sliding

and tipping analysis requirements were met for a CTV loaded with spent fuel. In the 3.e

example, the design was correct; however, the installed configuration was not. In this case,

the design analysis had deficiencies as well as the procedure, which led to a conclusion that

the multiple deficiencies was an issue of more than minor concern.

Significance: In accordance with Section 2.2 of the Enforcement Policy, ISFSIs are not

subject to the SDP and traditional enforcement will be used for these facilities. Traditional

enforcement violations are not assessed for cross-cutting aspects.

Enforcement:

Severity: The inspectors determined that the violation could be evaluated, using Section

6.5.d.1 of the NRC Enforcement Policy, as a violation of very low safety significance (Severity

Level IV) because the licensee failed to meet a regulatory requirement that had a more than

minor safety significance.

Violation: Title 10 CFR 72.146, "Design Control," states, in part, that the licensee shall

establish measures to ensure that applicable regulatory requirements and the design basis,

as specified in the license for those structures, systems, and components to which this

section applies, are correctly translated into specifications, drawings, procedures, and

instructions. These measures must include provisions to ensure that appropriate quality

standards are specified and included in design documents and that deviations from standards

are controlled.

Contrary to the above, on May 28, 2020, measures were inadequate to ensure the design

basis was correctly translated into Procedure No. D95.10, the design calculation was

accurate, and deviations to appropriate quality standards specified in design Calculation No.

2018-03457 were controlled to ensure the minimum factors of safety to sliding were met.

Specifically, the interfacing surfaces that were relied upon to preclude the new CTV from

sliding into a cask loaded with spent fuel was not installed using a procedure that reflected

the design, the design calculation contained inadequacies, and deviations from the design

and installed configuration were not controlled.

Enforcement Action: This violation is being treated as an non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

9

Licensee-Identified Non-Cited Violation: Safeguards Breaker Racking 71152

Procedure Inappropriate to the Circumstances

This violation of very low safety significance was identified by the licensee and has been

entered into the licensee corrective action program and is being treated as a non-cited

violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Title 10 CFR, Part 50, Appendix B, Criterion V, "Instructions, Procedures, and

Drawings," states, in part, that activities affecting quality shall be prescribed by documented

procedures of a type appropriate to the circumstances and shall be accomplished in

accordance with these procedures. Procedures shall include appropriate quantitative or

qualitative acceptance criteria for determining that important activities have been satisfactorily

accomplished. Contrary to this requirement, on January 24, 2020, the licensee identified that

a 4.16kV safeguards breaker 26-16 (D6 emergency diesel generator supply to Bus 26) with

an incorrect amperage rating had been installed and in service within Bus 26 since

October 11, 2019, due, in part, to insufficient acceptance criteria within Operating Procedure

C20.5-1, "4.16kV Breaker Rack Out/Rack In," Revision 41.

Significance/Severity: Green. The finding was of very low safety significance because it was

a deficiency affecting the qualification of Bus 26 4.16kV safeguards breaker 26-16 (a

mitigating SSC), and the SSC maintained its operability.

Corrective Action References: AR 501000036932

Observation: D6 Emergency Diesel Generator Supply Breaker to Bus 26 71152

Undersized

The inspectors reviewed a past operability review and root cause evaluation following the

January 24, 2020, identification that Breaker 26-16 (D6 EDG Supply to Bus 26) was installed

with an incorrect, undersized amperage since October 11, 2019. This condition was

identified by the licensee during troubleshooting following load sequencer modifications for

which post maintenance testing was not successful. The breaker was promptly replaced with

a correctly-sized breaker prior to restoring operabilty of D6 and Bus 26. Based on the

inspector's review of the licensee's evaluation, the inspectors did not identify any past

operability or reportability concerns; however, a Licensee Identified Non-Cited Violation of

Very Low Safety Significance (Green) was identified and is discussed in this report.

Observation: Semi-Annual Trend Review 71152

Based on the spring of 2020 COVID-19 public health crisis, the inspectors performed a semi-

annual trend review of the licensee's corrective action program during the first and second

calendar quarters of 2020. The inspectors focused on whether any adverse trends existed

related to human performance, equipment performance, and programmatic effectiveness

during this timeframe and did not identify any concerns. For low-level trends that were

identified by the licensee, the inspectors did not identify any concerns with the trend inputs,

level of evaluation, and planned corrective actions.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 8, 2020, the inspectors presented the integrated inspection results to

Mr. S. Sharp, Site Vice President and other members of the licensee staff.

10

  • On June 12, 2020, the inspectors presented interim ISFSI cask loading inspection

results to Mr. S. Sharp, Site Vice President and other members of the licensee staff.

11

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

60855.1 ALARA Plans Radiation Protection Job Plan 2020 Dry Cask 45, 46, 47 Revision 0

Work

Radiation Work Permit 205000 Revision 0

Calculations 12911.54-SC-10 Design of Buried Electrical Ducts Subjected to Cask Revision 1

Transporter Loading

2018-03457 Evaluation of Auxiliary Building Fuel Unloading Area for Revision 0

Loading Associated with New Cask Transporter

Calc. No. 03457 Evaluation of Auxiliary Building Fuel Unloading Area for 12/16/2019

Loading Associated with New Cask Transporter

Corrective Action Selected Corrective Action Documents Created Since

Documents April 2018

Issue ID ISFSI Concrete Strength Greater than ISAR 02/14/2019

501000023147

Issue ID ISFSI Dose Calc Incorrect Berm Height 11/04/2019

501000034318

Corrective Action Issue ID ISFSI INS: Question 21 Response Time 05/28/2020

Documents 501000041017

Resulting from Issue ID Lesson Learned Observation of CASK 47 05/28/2020

Inspection 501000041018

Issue ID NRC ID's Steps Not Signed in PE 05/28/2020

501000041059

Issue ID NRC ID's Signoffs in PM Not Transferred 05/28/2020

501000041074

Issue ID New Cask Transporter Revise Evaluation 05/29/2020

501000041132

Miscellaneous 72.48 Evaluation PINGP ISFSI Expansion Calculation Methodology Revision 0

No. 1146 Departures

72.48 Evaluation PINGP ISFSI Expansion: AB-5 Procedure and Dose Scaling Revision 0

No. 1150 Approach Evaluation

72.48 Screening PINGP ISFSI Expansion Revision 0

No. 5565

72.48 Screening EC60100001234; PINGP ISFSI New CTV Revision 0

12

Inspection Type Designation Description or Title Revision or

Procedure Date

No. 5640

72.48 Screening EC 60100001234; PINGP ISFSI New CTV Revision 0

No. 5641

72.48 Screening EC601000002176; Sensitivity Analysis for Drop Eval of Revision 0

No. 5652 TN40HT

72.48 Screening EC 601000002232 - Revise Calculation TN40HT-0512 Revision 0

No. 5659

Cask No. 47 Cask Inventory Verification 05/26/2020

D95.1 Cask Inventory Verification 05/26/2020

D95.1 Appendix A Cask Loading Report 05/26/2020

FP-MA-COM-02 Supplemental Worker Oversight Plan 01/17/2020

OP-2014-002 Prairie Island Dry Fuel Storage Project Oversight Plan Revision 5

Sample ID: SFP Spent Fuel Pool Boric Acid 05/26/2020

0706 and 0715

NDE Reports BOP-PT-20-015 TN-40 Special Lift Fixture 04/23/2020

and BOP-MT-20-

2008

Procedures AB-5 Buried Cask Revision 3

D95.1 TN-40 Cask Loading Procedure Revision 32

D95.10 Tracked Cast Transporter Vehicle Operation Revision 0

D95.3 TN-40 Cask Removal and Storage Procedure Revision 39

SP 1075.HT TN-40HT Fuel Selection and Identification Revision 4

Radiation Survey PI-M- Cask 46 Transferred To ISFSI Pad #41 05/21/2020

Surveys 20200521-9

Self-Assessments 2019 Nuclear Oversight Prairie Island Nuclear Generating 10/01/2019

Plant Audit of Programs

Master Lessons Learned Cask 41-44 05/03/2018

600000598736 Snapshot 2020 NRC Inspection 02/28/2020

CR No. Fleet Cask Loading Challenge Board 04/09/2020

603000004605

QF0406 2020 ISFSI NRC Inspection Snapshot 02/28/2020

Work Orders WO 7000059192 SP1077 Special Lift Fixture TN-40 Cask 04/17/2020

WO 700056472 AUX Building Crane Mechanical/Electrical Inspection 02/25/2020

13

Inspection Type Designation Description or Title Revision or

Procedure Date

WO 700059191 SP 1057 TN-40 Fuel Selection & Identification 03/17/2020

WO 700061687 SP1076 ISFSI Qtr Sfty Status 03/16/2020

71111.04 Drawings NF-39252 Flow Diagram, Caustic Addition System, Units 1 and 2 Revision 83

Procedures C1.1.7-1 Unit 1 Reactor Control Checklist Revision 10

71111.05 Procedures C5-1 Rod Control System Checklist Revision 10

C6-1 System Prestart Checklist Rod Position Indication System Revision6

71111.06 Calculations ENG-ME-732 Determination of HELB/Flooding Interactions in the Turbine Revision 1

Building

ENG-ME-759 GOTHIC Internal Flooding Calculation for the Turbine Revision 1

Building

Procedures TP 1398 Internal Flooding Walkdown Revision 10

71111.12 Miscellaneous Prairie Island Maintenance Rule Basis Document 04/20/2020

Procedures FP-E-MR-03 Maintenance Rule Monitoring Revision 8

FP-E-MR-05 Maintenance Rule Expert Panel Revision 8

MSIP 5015 Swagelok Compression Tubing Fittings Revision 4

RPIP 3655 Sampling Unit 2 Pressurizer Revision 9

WO Replace Valve and Fittings as Needed Revision 0

  1. 70000942010

71111.15 Corrective Action AR 23 CFCU Damper Past Operability Review 05/04/2020

Documents 501000039494

AR 23 FCU Damper Did Not Reposition 04/08/2020

501000039494

AR PMT Planning Issues on 2SM-5-4 04/23/2020

501000039981

AR 22 DDCLP Jacket Water Hose Leak POR 05/06/2020

501000040177

14

Inspection Type Designation Description or Title Revision or

Procedure Date

AR Coolant Leak of 22 DDCLP Jacket Cooling 05/01/2020

501000040177

71111.19 Corrective Action AR PMT Planning Issues on 2SM-5-4 04/23/2020

Documents 501000039981

71111.22 Procedures SP 1089A RHR Quarterly Pump and Valve Test 05/08/2020

SP 1089A Train A RHR Pump and Suction Valve From RWST Quarterly Revision 32

Test

SP 1856 Bus 26 Undervoltage Test 04/28/2020

SP 1856 Monthly 4kV Bus 16 Undervoltage Relay Test (OMICRON) Revision 9

71151 Procedures MSPI High Pressure Injection Data 2Q19 through 1Q20 04/22/2020

FP-E-MSPI-01 Mitigating System Performance Index (MSPI) Revision 10

15