ML20196J120

From kanterella
Jump to navigation Jump to search
Ack Receipt of 971217 & 30 & 980112,0309,0423 & 0630 Ltrs Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-293/97-02,50-293/97-11,50-293/97-13, 50-293/97-80 & 50-293/98-01.Actions Found Acceptable
ML20196J120
Person / Time
Site: Pilgrim
Issue date: 12/04/1998
From: Cowgill C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Ted Sullivan
BOSTON EDISON CO.
References
50-293-97-02, 50-293-97-11, 50-293-97-13, 50-293-97-2, 50-293-97-80, 50-293-98-01, 50-293-98-1, NUDOCS 9812090264
Download: ML20196J120 (3)


See also: IR 05000293/1997002

Text

. ,:

December 4,1998

Mr. Theodore A. Sullivan

Vice President Nuclear and Station Director

BEC Energy

Pilgrim Nuclear Power Station

600 Rocky Hill Road

Plymouth, Massachusetts 02360-5599

SUBJECT: PILGRIM INTEGRATED INSPECTION REPORT (IR) Nos. 50-293/97-02,50-

293/97-11,50-293/97-13,50-293/97-80,and 50-293/98-01

Dear Mr. Sullivan:

This letter refers to your letters dated December 17 and 30,1997, and January,12, March

9, Aprii 23, and June 30,1998 in response to the Notices of Violation forwarded with the

subject inspection Reports.

Thank you for informing us of the corrective and preventive actions documented in your

letters. These actions were reviewed and found acceptable by the NRC during subsequent

inspections of your licensed program, including: IR 50-293/97-13, dated February 6,1998,

IR 50-293/98-01, dated March 24,1998,IR 50-293/98-05, dated July 9,1998, and IR

50-293/98-06, dated August 28,1998.

Your cooperation with us is appreciated. '

Sincerely,

Original Signed By:

Curtis J. Cowgill, Chief

Projects Branch 8

Division of Reactor Projects

Docket No. 50-293

i

. n n f.

D A K 50 293

G PDR DI

.V

,

. . ,-- . . . . . - . . ~ . - . - _ - . - . _ . - . . - - - . . -- - . . - . . . - . - - - . _ - -..

i . ,

I

l

t

Mr. Theodore A. Sullivan 2

cc w/o cv of Licensee Response letter: , i

l R. Ledgett, Executive Vice President - Operations

l J. Alexander, Nuclear Assessment Group Manager

D. Tarantino, Nuclear Information Manager

S. Brennion, Regulatory Affairs Department Manager 1

J. Fulton, Assistant General Counsel

l

l

f cc: w/cv of Licensee Response letter

R. Hallisey, Department of Public Health, Commonwealth of Massachusetts

The Honorable Therese Murray

The Honorable Joseph Gallitano

T. MacGregor, Mass. Dept. of Public Comm. & Energy

'

Chairman, Plymouth Board of Selectmen l

Chairman, Duxbury Board of Selectmen

Chairman, Nuclear Matters Committee

Plymouth Civil Defense Director )

{

P. Gromer, Massachusetts Secretary of Energy Resources  !

J. Miller, Senior issues Manager

J. Fleming

A. Nogee, MASSPIRG

Office of the Commissioner, Massachusetts Department of Environmental Quality

Engineering

Office of the Attorney General, Commonwealth of Massachusetts

l T. Rapone, Massachusetts Executive Office of Public Safety

Chairman, Citizens Urging Responsible Energy

Commonwealth of Massachusetts, SLO Designee

!

!

!

,

i

!

i

l.

!

,

a

f

i

l

1

!

_ . .

,~ __ _._ _ ._ _ _ _ _.. _..._ . _ . . . _. _ __ _ .. .._. _ _ ._._. _

.

. .

i

,

Mr. Theodore A. Sullivan 3

!

Distribution w/ encl: l

Region I Docket Room (with concurrences) '

Nuclear Safety Information Center (NSIC)

i

PUBLIC '

NRC Resident inspector

H. Miller, RA/W. Axelson, DRA '

C. Cowgill, DRP .

R. Summers, DRP '

C. O'Daniell, DRP

B. McCabe, OEDO

C. Thomas, NRR ! COT)

A. Wang, NRR  !

R. Correia, NRFt  ;

DOCDESK

Inspection Program Branch, NRR (IPAS) l

+

F

i

!

,

,

!

!

L

e '

f

!

i

DOCUMENT NAME: g :\ bra nc h 5 \rply-ltr\pitre ply.rj s

Ta receive a copy of this docurnent, indicate in the box: *C" = Copy without attachment / enclosure *E' = Copy with attachment / enclosure *N* = No copy

OFFICE Rl/DRPQ h l Rl/DRPG hl / l [

CCowgill @

'

NAME RSummers,

DATE 12/04/98 12/'//98 f 12/ /98 12/ /98 12/ /98

!

OFFICIAL RECORD COPY

I

!

, . . i

'

l

h

knon Edison

P:Igom Nuclear Power Staton

i Rocky Hdt Road

i

Plymouth. Massachusetts 02360

,

Henry V. Oheim

Genersi uanager .Technicai section December 30,1997

BECo Ltr. 2.97.133

U.S. Nuclear Regulatory Commission

ATTN: Document Control Desk

Washington, D.C. 20555-0001

Docket No. 50-293

License No. DPR-35

SUPPLEMENTARY INFORMATION RELATED TO VENDOR OVERSIGHT V!OLATION

References: (1) Boston Edison Company Letter No. 2.97.065, " Initial Reply to Notice of Violation

97-02-02," dated June 20,1997.

(2) Beco Letter No. 2.97.073, " Supplemental P.eply to Notice of Violation (97-02)",

dated July 11,1997.

f-References 4and1g_onveyed Boston Edison Company's initial and supplemental responses to NRC

LNotice of Violation onceming weaknesses in oversight of vendors. The latter letter

committed to aeveToKng 97-02-02)ia

criIer that identifies categories of vendor interface (e.g., specialty sk!

proprietary information used for analyses or calculations, atypical or prototype design) that will

require additional controls. A checklist or matrix for determining additional controls when special ,

vendor oversight / interface is required will be created from those categories. The committed '

completion date was December 31,1997.

l

Currently, a preliminary effort identifying the categories of vendor interface has been completed.

Additional categories are expected pending completion of other team reviews. However, the

commitment will not be fulfilled by the original target date due to resource challenges presented by

the recent forced outages and other emergent issues. This requires deferral of the target completion

date to March 15,1998.

If you have any questions regarding the information contained in this letter, please contact Walter

Lobo at (508)830-7940. q7

I) 0k: $

H.V. Oheim

JK/Itv297133/ doc

l

l

W N O ] v v.s l 2g

. -. .. -- - . . . - _ . _ . . - . _ - . . . . . _ .. - _. ....- ...

'

- . . .

-

. \

'

cc: Mr. Al:n B. W:ng, Project Mrnig:r

Project Directorate 1-3

Office Of Nuclear Reactor Regulation .

Mail Stop: OWFN 1482  !

1 White Flint North  !

l 11555 Rockville Pike l

l Rockville, MD 20852 1

1

/U.S. Nuclear Regulatory Commission  !

i

Region I i

l 475 Allendalo Road -

King of Prussia, PA 19406  ;

1

l

Senior Resident inspector

l Pilgrim Nuclear Power Station i

!

<

l

l

l

l

l

<

l

l

l

l

I ,.

1

l

l

l

1

1

!

I

l i

i

t

I

_

', i. *

2 #

!

so.== m 77 - y i

' Pilgrim Nuclear Power Station L

Rocky Hill Road i

Plymouth, Massachusetts 02360

Q - Q(

!

LJ. Olivier

!

Vice President Nuclear and Station Director i

December 17,1997
l

BECo Ltr. 2.97.132

1

U.S. Nuclear Regulatory Commission

ATTN: Document Control Desk

Washington, D.C. 20555-0001 (

i

>

Docket No. 5, .293

License No. DPR-35

Completion of Reply to Notice of Violation 97-80-01

Boston Edison Company (BECo) provided an initial response to Notice of Violation 97-80-01 I

by letter dated October 17,1997, (BECo 2.97.104). That response provided the reasons for i

the specific procedural violations cited by the NRC and the corrective actions taken and

results achieved. A sixty day extension was requested in order to conduct an in-depth root

cause of the overallissue of procedural compliance at Pilgrim Station and thereby

determine meaningful and effective corrective actions to preclude recurrence. A multi-

discipline root cause team was formed to analyze the procedural compliance data contained l

in the Pilgrim Station corrective action data base, assess root cause, correlate the  !

relationship to the previous and current procedural compliance corrective action activities, i

and recommend comprehensive solutions. A discussion of the team's findings and Pilgrim's l

corrective actions to preclude recurrence are enclosed. )

This letter describes the following corrective actions to preclude recurrence:

I

. A 1998 organization goal for addressing procedure adher,ence will be developed and

individual department tasks for meeting the goal will also be developed.

. Establish a cross functional team for improving procedure structure and content.

. Managers will be updated on the overall broad procedural compliance issues and

with issues that may be unique to their area of oversight.

!

!

!

Nt 1 A l'f_

  • '

, .

L dails of the activities to be undertaken to implement these corrective actions are

ds '.cribed in the enclosure.

[

l

Should you have any questions or require further clarification, please do not hesitaie to

contact me.

.-

L. J. Olivier

Enclosure

Completion of Reply to Notice of Violation 97-80-01

cc w/ encl.

Regional Administrator, Region 1

U.S. Nuclear Regulatory Commission

475 Allendale Road

King of Prussia, PA 19406

Senior Resident inspector

Pilgrim Nuclear Power Station

Mr. Alan B. Wang

Project Manager Project Directorate 1-3

Office of Nuclear Reactor Regulation

Mail Stop: OWF 1482

1 White Flint North

11555 Rockville Pike

Rockville, MD 20852

i

i

l

1

!

l

l

i

. . _ , . _ _ . _ _ . - _ . _ _ _ . _ _ _ . . _ _ . . . _ _ _ _ . _ _ . _ . . _ _

, . .

,

Enclosure

Completion of Reply to Notice of Violation 97-80-01

On September 17,1997, the NRC issued the 40500 team inspection results of the

Pilgrim Station corrective action processes (NRC IR 97-80). The NRC identified three

specific issues relating to procedural compliance at Pilgrim Station that became NRC

Notice of Violation (NOV) 97-80-01. Boston Edison Company (BECo) provided an initial

response by letter dated October 17,1997. In this response, the reasons for each of

the instances of procedural noncompliance were addressed along with the specifh

corrective actions taken or planned for each instance. A sixty day extension to

determine corrective actions to preclude recurrence was requested and granted. The

extension was needed to conduct an in-depth root cause of the broader issue of

procedural usage and why noncompliance with procedures remains an issue at Pilgrim

Station.

A multi discipline root cause team was formed to analyze the procedural compliance

data contained in the Pilgrim Station corrective action data base, assess root cause,

correlate the relationship to the previous and current procedural compliance corrective

action activities, and recommend comprehensive solutions. The root cause analysis

findings and corrective actions to preclude recurrence are presented below.

Findinas

The corrective action program (CAP) information data base was reviewed to determine

the extent of organizational procedure non-adherence. These data show procedure

non-adherence exists in every work unit, at all job levels in the organization.

Administrative tasks are cited three times more frequently than technical tasks.

A defense of quality, barrier matrix was developed to determine the barriers that are in

place to ensure procedure compliance. The potential weaknesses of the barriers and

the probability of failure of any of the barriers were assessed and reconciled to the data

base, it was concluded the barriers that are most likely to be weak or potentially fail are

management expectations and standards, supervisory oversight, procedure complexity

j and construction, and time and resources to implement jobs correctly.

l

A survey of the organization corroborated the barrier analysis conclusions. This survey

i probed for agreement or disagreement on each of the proposed barriers and solicited  ;

! free form feedback. As a feedback question, the survey solicited an opinion on why l

l procedure non-compliance events occur and what management can do to correct the

j prob'em.

,

  • I

i

1

a

i I  ;

,

-- - . - - -

, _ ._ _ ._

,

1, . ,

,

Root Cause

Two primary causes have been identified for procedure non-adherences at Pilgrim.

.

The structure and content of procedures are complex and inhibit performing

tasks in a timely and complete manner. Problem resolutions via procedural

additions and/or repairs over the years have contributed to many of the

cumbersome requirements..

j

e Manager and supervisor oversight efforts to resolve procedure adherence I

issues have been generally ineffective. Although action plans have been

formulated to resolve the problem, they were not effective nor validated to

ensure the actions were solving the problem. Also, the emphasis on

following procedures is not consistently carried through using coaching on

implementation of assigned tasks nor is there sufficient accountability for

procedure non-compliance. This provides an attitude of acceptance toward

procedure non-compliance.

Several ancillary and contributing causes were also identified. These ranged from the

hierarchy of the procedure system, (Policies, Nuclear Organization Procedures (NOPs),

Procedures, and Work Instructions) to training on updates and to perceived time

!

pressure. While these concerns are related to the problem, they are of a contributing l

i nature, generally limited in scope, and not the root of the problem. However, white the

effort to correct the root causes is the major focus of the corrective actions to preclude

recurrence, elements of the contributing causes are included as part of the overall

corrective action plan required to preclude recurrence. The contributing causes are:

. The content of procedures for new and revised versions is sometimes

ineffectively communicated to the users.

.

A time / pressure perception exists in some disciplines when performing tasks.

. End-user input is not universally used in procedure development and

revision.

Corrective Actions to Preclude Recurrence (CATPR) ,

The procedure non-adherence problem is the result of two primary root causes, a

complex and confusing procedure structure, and ineffective oversight and corrective

'

action validation at the manager and supervisory level. The corrective actions to

preclude recurrence, therefore, are structured to address these causes and build on

past corrective actions already taken or that are still in progress.

2

. . -.

, ,

CATPR 1

A 1998 organization goal will be established for improvement in procedure adherence.

The goal will be developed and instituted by February 1,1998.

The following tasks will be required for each department as part of this goal

i implementation:

e include procedure adherence as a required focus for the corrective action

program (CAP) quarterly self-assessment program. A report of department

procedure compliance and improvements experienced during the quarter will

be required. The reports shall provide details of coaching and accountability

actions. The reports will continue until satisfactory performance thresholds

are achieved.

Establish focus themes for procedure adherence and improvement meetings

to be held on a bi-monthly frequency. These meetings will follow the iormat

similar to th6t of department safety meetings with procedural issen selected

for discussion ao case studies based on department-specific ir ues.

.

Department performance matrices will be developed and used in evaluating

long term progress or possible recurrence of procedure non-compliance

problems. The matrices will also be used by the managers to apply

accountability and ownership.

CATPR 2

Some improvements were made from the previous effort to integrate the high level

policies and nuclear organization procedures (NOPs). This work needs to continue.

Therefore, a cross functional and multi-disciplined eam will be established to continue

the effort to improve procedure structure and content. The team shall specify what

content is required in procedures and establish a definition of procedure compliance.

Integral to this effort will be the task to work with department managers to cancel,

combine, consolidate and re-write procedures. The extent of input from the end users

for the revised procedures will be determined by the respective department manager.

Team selection will be from all groups and all levels.

The team will take importance of the procedure relative to safety, reliable plant

operation, and the incidences of procedural non-compliances into account when

establishing the priority of procedures to be worked through this effort.

This effort will complete by June 30,1998.

3

1

1

- . . . _ _ , . _ -- __ _ ,.

_

., _ _ . ._ _

', .

.

CATPR 3

( Because of the varying nature of department roler, and responsibilities, the' type of

procedure non-adherence differs for each departrnent. Therefore, in addition to the

broader organizational corrective actions to be taken, department-specific corrective

actions will need to be determined and implemented at the department level. Therefore,

the root cause team leader will explain to each group and department manager, the

CAP data base trends, the survey results, and the results of the root cause analysis.

This will familiarize the managers with the overall broad procedural compliance issues

and with issues that may be unique to their particular area of oversight. This activity will

be completed by March 10,1998.

Discussion of Past Corrective Actions

Although previous corrective actions have not resolved the problem of procedure .

compliance, these past activities were correctly focused albeit not in sufficient detail.  !

Our evaluation of these activities concluded most of the actions have been effective in

resolving various aspects of the problem but suffered from a lack of cohesive

programmatic assessment for determining how appropriate and effective the activities

were for problem resolution. Thus, the actlvities were not necessarily ensuring

resolution of the problem in total.

The following is a summary of some of the past and current corrective actions taken.

1

. Management expectations and personal accountability were discussed in small

group meetings (in January and again in September 1997) with all personnel.

. Proceduralimprovements were made on known problem procedures, j

. Management oversight in the field was increased. l

. An error rate performance indicator was developed. l

. QA oversight was increased.  ;

e An error matrix was developed and is maintained by the maintenance department.  !

. A monthly senior managers audit program was established. l

e Root cause assessment improvements were made.

. Performance monitoring and trending improvements were made. j

. Failure Prevention Institute (FPl) training was provided for conducting more j

comprehensive root cause assessments.

  • The worker level self assessment process was strengthened with increased

management participation and oversight.

  • An Independent Oversight Team (IOT) was formed.
  • Monthly human performance reports were developed. *
  • A culture index was conducted.

. The management oversight program was focused on conducting observations of

performance related activities.

. Enhanced problem report coding was established.

i

. A real-time behavior-based human error performance monitoring program was

! developed.

. A procedure change process redesign effort was established. *

4

.

. .

.

,

l

'

1

.

The Mission Organization and Policies (MOPS), Nuclear Organization Procedures

(NOPs), and Administrative procedures were reviewed, revised and consolidated.

.

The QA deficiency report (DR) process was consolidated into the problem report

(PR) process.

.

!

The modification process was redesigned. (Completion of the procedure revisions

and personnel training is expected to be completed on or before December 31,

1997.)

.

Root cause analysis and human error prevention training were expanded.

  • A procedure change team has re-written the procedure change process. The

revised process will provide for a broader class of field changes that allows work

j to continue without waiting for the full procedure change and issue process to be

completed.

Please note, however, current restrictive language in the Administrative Section

of the PNPS Technical Specifications needs to be revised to allow this field

change procedure revision capability to take place. The needed proposed

Technical Specification changes were submitted for NRC review and approval on

September 19,1997, (BECo letter 2.97.096). Based on NRC feedback, this

change is expected to be approved near the end of the first quarter 1998.

The procedure change team reviewed the option of breaking out the change

portion of the process redesign and issuing other portions; however, the team

feels it is best implemented in total. Therefore, this process revision has been

placed on hold until approval of the Technical Specification change request.

Summary

We are committed to the corrective action process enhancements introduced at Pilgrim

in the 1996 timeframe. The problem reporting thresholds have been sufficiently

)

lowered, and the organization is becoming more comfortable in its use for recognizing

and resolving preMems.

However, we recognize that more attention is needed in the oversight of emerging

problem trends highlighted by the corrective action program. In particular, the

effectiveness of corrective actions taken or being taken requires continuous evaluation

to ensure the problem is being resolved. In the case of procedural adherence, although

myriad action plans to resolve the problem were developed, each met with limited

success. The activities were managed at the task level by different individuals but were

not being measured in a total programmatic sense for effectiveness at resolving the

problem of procedural adherence across the station. Therefore, the corrective actions  !

to preclude recurrence are assigned with actions at both the Vice President

Nuclear / Station Director level and department manager / supervisor level. The Vice

l President Nuclear / Station Director will keep the issue highly visible, while the

l

'

department managers / supervisors resolve the problems at the department level. l

Monitoring of the problem will continue at alllevels of management until evidence shows

the problem to be resolved.

5

I

- - --

  • *

l_  ;

\ ~,

-

'

-

0 10 CFR 2.201

Boston Edieon i

Pagrim Nuclear Power Station

Rocky Hill Road f / y g(/

l

Plymouth, Massachusetts 02360 Lp c.[oup 77- p 6

.

i

LJ. Olivkr

W (3 - 0p , &x Q'

March 9,1998

Vice President Nuclear and Station Director

BECo Ltr. #2.98.026

U.S. Nuclear Regulatory Commission -

Attention: Document Control Desk

Washington, DC 20555

Docket No. 50-293

License No. DPR-35 ,

,

REPLY TO NOTICE OF VIOLATIONS 97-13-01 AND 97-13-02 [

NRC INSPECTION REPORT NO. 50-293/97-13. DATED FEBRUARY 6.1998  ;

r

i

Enclosures 1 and 2 provide Boston Edison Company's reply to the Notice of Violations 97-

13-01 and 97-13-02 contained in the subject inspection report. ,

Violation 97-13-02 states the degraded condition due to temperature detector deficiencies i

resulted in an extra plant cooldown and heatup. This is an incorrect statement; Pilgrim did  !

not undergo an extra heatup and cooldown due to temperature detector deficiencies. The  !

heatup and cooldown referenced in the violation was performed as a result of a management i

decision, and it is generally Pilgrim Station policy to place the plant in shutdown cooling j

following shutdowns to perform maintenance and prepare for startup. Also, engineering '

analysis confirmed the vessel flange to shell differential temperatures during heatup and

cooldown did not result in exceeding code stress allowables.

This letter includes the following commitments.

Commitments addressina violation 97-13-01 (Enclosure 1): The effectiveness of the

preparation and implementation of the maintenance work package (MWP) process will be

enhanced by March 27,1998, as follows:

.

. Work control planners will be provided with clear expectations for preparing and reviewing

work packages involving substitution equivalency evaluations (SEES), plant design

changes, and field revision notices.

. The task-ready review process will be enhanced. The expectations for l&C technicians  !

and supervisors on task-ready review walkdowns will be clearly defined with an individual

MWP walkdown review sheet to cover all requirements of a task-ready review in

accordance with procedure 1.5.20, " Work Control Process". These expectations will be

discussed with all I&C Maintenance Department personnel relative to MWP walkdowns

and like-for-like replacements during implementation of MWPs.

. The engineering department managers will hold meetings with their staff to discuss and

review the events associated with ATWS relay replacement problems.

$03)$G.ib3sopp

.. ._ _ .. . _ _ _ _ _ ._ _ _ - _ . _ . . _ _ _ _ __.. _ _ . _ _ _ _ . _ . _ .

t .

-

. .

.

!

Maintenance, I&C, work control, and engineering departments will review the multiple  !

I

human errors caused by indirect communications to promote face-to-face ,

communications to minimize misinterpretations and missed information.  !

.

A standard method for building replacement parts reservations and documenting them will

be established in the planning department's desktop instructions.

Commitments addressino violation 97-13-02 (Enclosure 2): The following corrective actions  !

are planned to avoid further violations of vessel flange temperature indications.

. A technical specification change to remove the requirement for vessel shell to vessel i

flange differential temperature limit of 145T will be submitted by March 27,1998, for

NRC approval.  !

l

. A redesign of the temperature element leads in the drywell will be prepared. This I

modification is currently planned for implementation during RFO 12 or an outage of

sufficient duration that would provide access to the drywell.

.

'

. This violation will be presented as a case study within the existing continuing training

programs. The case study will be prepared and the training schedule will be determined

by April 10,1998.

.

!

Please do not hesitate to contact me if there are any questions regarding the enclosed reply.

r 1

.

l

.  :

.

I

'

L. J. Olivier

WGil vlO97-13-01&O2

Enclosure 1: Reply to Notice of Violation 97-13-01

Enclosure 2: Reply to Notice of Violation 97-13-02

cc: Mr. Alan B. Wang, Project Manager

Project Directorate 1-3

Office of Nuclear Reactor Regulation

USNRC, Mail Stop: OWFN 14B2

1 White Flint North

11555 Rockville Pike

Rockville, MD 20852

Region I, U.S. Nuclear Regulatory Commission

475 Allendale Road

King of Prussia, PA 19406

Senior Resident inspector

Pilgrim Nuclear Power Station

i

.

---

, .

.

Boston Edison Company Docket No. 50-293

Pilgrim Station License No. DPR-35

ENCLOSURE 1

Reolv to Notice of Violation 97-13-01

VIOLATION 97-13-01 (identified as item B in the Notice of Violation)

During an NRC inspection conducted on November 11, 1997, through January 6,1998,

violations of NRC requirements were identified. In accordance with the " General Statement of

Policy and Procedure for NRC Enforcement Actions, NUREG-1600, the violations are listed

below:

A. (see Enclosure 2)

B. Pilgrim Technical Specification (TS) 6.8A, Procedures, requires that procedures be

implemented for activities covered under Appendix "A" of NRC Regulatory Guide 1.33.

Section 9, Procedures For Performing Maintenance, of Appendix "A" requires that

maintenance be properly preplanned, and be performed in accordance with written

procedures or instructions that are appropriate to the circumstances. Additionally,

BECo procedure 1.5.20, Work Control Process, step 7.5, Task Ready Review, specifies

that planners and I&C supervisors shall ensure that parts are in reserve / withdrawn for

the work prior to designating a package as task ready. Step 7.5 also specifies that the

work supervisor or his designee will perform a hands-on parts verification for each job.

Contrary to the above on December 20, 1997, a work control planner and I&C

supervisor classified a work package to replace an ATWS system electrical relay as

task ready when all parts were not available. Additionally, a hands-on parts vetification ,

was not performed prior to the start of work. As a result, a relay of the incorrect voltage

rating was installed which overheated and resulted in an unplanned ATWS system

LCO maintenance outage.

This is a Severity Level IV violation (Supplement 1).

REASON FOR THE VIOLATION

The reason for the violation was non-compliance with procedure 1.5.20, " Work Control

F-rocess". Our assessment (PR 97.9821) of the ATWS relay replacement activity revealed the

following.

The root cause of the installation of the incorrect voltage ATWS relay is the maintenance work

package (MWP) being signed as " task ready" without all the relays reserved. The contributing

causes are (i) a wrong substitution equivalency evaluation (SEE) was used for ATWS relays,

(ii) human errors during MWP preparation and review and parts verification, and (iii)

commun: cation errors by personnel during the preparation and implementation of ATWS relay

j MWP. These errors resulted in violations of the work control process requirements.

l

To replace the aging ATWS relays, a work control planner prepared a MWP to replace four

ATWS relays using the wrong generic SEE No. 797. The ATWS package dealt with three 24

1

1

,

_ _ _ _ _ _ _

i . .

.

i

'

vdc and one 125 vde relays. The SEE was not intended for replacement of ATWS relays. The

planner reserved three 24 vde relays and ordered the 125 vde relay, but did not include a copy

l of the stock material request form (MRF) in the work package. The planner placed the work

l package on a " parts hold" status pending the arrival of the fourth relay. The M'NP did not  !

-

caution the technicians that it differed from the other relay packages that were planned for the

ECCS panel. The MWP steps only required technicians to remove and replace relays per SEE  :

No.797. i

i Two weeks prior to the implementation of the ATWS relays replacement MWP, a second

planner was assigned to make the package task ready. The second planner was not familiar  !

l with the previous history of the package and took shortcuts to arrive at an assumption all parts

were reserved. Since the task ready review on the MWP was already signed by the first  !

planner, the second planner changed the MWP status coding without making an entry in the  !

! " actions tuken" section that he was now the attemato member of the team, in accordance with  !

l

procedure 1.5.20 section 7.4, and without becoming familiar with the work plan and its l

instructions. Accordingly, the second planner changed the status from " parts hold" to " task l

ready" on or about December 10,1997.

l

l

'

Also, the l&C supervisor delegated the maintenance portion of the task ready review for

walkdown review to a lead technician. He had four Agastat relay replacement packages for

review. Each package was written to replace four relays in either the ECCS or the ATWS

panels using SEE No. 797. The MWP for replacement of ATWS relays should have been ,

based upon SEE No.107. The technician reviewed the first package for the ECCS panel and I

had questions that needed to be resolved with the SEE on socket compatibility. Since the i

same SEE was incorrectly referenced in all four relay replacement packages, the technician  ;

i decided not to walk the three other packages down until after the questions about the SEE .

I were resolved. l

The l&C supervisor and his lead technician communicated through a MWP status sheet. The i

MWP status sheet was not intended to go into the details necessary to properly cover all the l

concerns and complete the reviews. The status sheet indicated one MWP had problems and

the other three had similar problems with the SEE. The l&C supervisor mistook the status

sheet to mean that all four packages had been walked down and only one common problem

existed due to the SEE about the socket. The packages were placed on hold until the system

engineer resolved questions on SEE No. 797. Once the SEE questions were resolved, the I&C

supervisor assumed the MWPs were ready to work; accordingly, he approved the task-ready

reviews as being completed and changed the status code for all four MWPs. This assumption

resulted from miscommunications and violated step 7.514] of the Work Control Process.

The final opportunity to detect the incorrect part was missed when one-for-one verification of

the removed relay was not performed. The technicians performed a spot check by only

verifying two of the four relays. The normally energized hot relays required gloves to handle

them which contributed to the technician not obtaining and verifying all information on the {

removed parts. A mindset was created that all relays were the same due to a previous MWP

that replaced all the same 24 volt relays in a ECCS panel.

A review of multiple human performance errors was conducted. Miscommunications during the

i MWP development, review, and implementation were a major contributing cause to barrier 1

breakdowns. i

l

l

l

l

l

- - A

- - - __ _ - .. -

,

1 ,

l

.

l.

! CORRECTIVE STEPS TAKEN AND RJSULTS ACHIEVED

The following corrective steps were taken to resolve the errors included in the Notice of

Violttion:

.

l&C took an immediate corrective action to replace the incorrect voltage ATWS relay.

Operations entered active LCO A97-435 and walkdowns were performed, which revealed

no visual damage to relay sockets or associated wiring. An adjacent relay had signs of

external damage due to localized overheating. A priority 1 maintenance request,

(MR19703150) was written, which later replaced the two damaged relavs with the

l

appropriate relays. Temporary Procedure TP97-084 described the necessary post work

testing. Independent reviews were also conducted of all previous MWPs associated with

l SEE No. 797 to ensure no other problems existed. None were found.

. Individuals involved in the preparation and implementation of the MWP were counseled

concerning the standards and requirements of task ready review, significance of their

signatures in the task ready reviews, and adherence to procedure requirements.

.

1 A critique was held on December 31,1997, at 0730 to gather facts, ensure the plant was in

a safe condition, and determine any further immediate corrective actions. No other

immediate corrective actions were needed.

l

CORRECTIVE STEPS THAT WILL BE TAKEN TO AVOID FURTHER VIOLATIONS

The effectiveness of preparation and implementation of the maintenance work package

, (MWP) process will be improved by March 27,1998, as follows:

.

l Work control planners will be provided with clear expectations for preparing and reviewing

l work packages involving substitution equivalency evaluations (SEES), plant design

l changes, and field revision notices.

1

. The task-ready review process will be enhanced. The expectations for l&C technicians and

'

supervisors on task-ready review walkdowns will be clearly defined with an individual MWP

walkdown review sheet to cover all requi.ements of a task-ready review in accordance with

procedure 1.5.20, " Work Control Process". These expectations will be discussed with all

I&C Maintenance Department personnel relative to MWP walkdowns and like-for-like

replacements during implementation of MWPs.

. Engineering department managers will hold meetings with their staff to discuss and review

the events associated with ATWS relay replacement problems.

. Maintenance, l&C, work control, and engineering departments will review the multiple

human errors caused by indirect communications to promote face-to face communications

l to minimize misinterpretations and missed information.

!

[

. A standard method for building replacement parts reservations and documenting them will

be established in the planning department's desktop instructions.

l

i

4

,

,

.

.

,

DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED

Full compliance was achieved on December 31,1997, when ATWS relays were replaced.

The MWP process improvements will be completed by March 27,1998.

.)

I

!

l

l

l

4

,

l

1

'

. .

.

.

l

Boston Edison Company Docket No. 50 293

l Pilgrim Station License No. DPR-35

l

ENCLOSURE 2

Reolv to Notice of Violation 97-13-02

1

VIOLATION NO. 97-13-02 (identified as item A in the Notice of Violation)

'

During an NRC inspection conducted on November 11, 1997, through January 6,1998,

violations of NRC requirements were identified. In accordance with the " General Statement of

l

Policy and Procedure for NRC Enforcement Actions, NUREG 1600, the violations are listed

below:

A. 10 CFR 50 Appendix B, Criterion XVI, Corrective Action, states, in part, that measures

shall be established to assure that conditions adverse to quality, such as deficiencies,

deviations, and non-conformances are promptly identified and corrected. The measures

.

shall assure that the cause of the condition is determined and corrective actions taken

to preclude repetition.

Procedure 1.3.121, " Problem Report Program," revision 3, section 6.6.3 and 6.6.4

require that corrective actions taken and/or required to correct the deficiency shall be

identified and corrective actions developed are adequate to prevent recurrence. Step

6.1(1) requires that " Hardware and non-hardware (human performance, administrative  ;

controls, procedural deficiencies) related problems shall be documented on a PR. This

includes failures, malfunctions, deficiencies, human errors, abnormal occurances,

defective or degraded material or equipment, and non-conformances."

i Contrary to the above, BECo did not properly evaluate the cause and implement

l corrective actions to preclude repetition of the temporary temperature detectors

deficiencies from the reactor vessel flange. The temperature elements

moved / separated from the reactor vessel flange on three separate occasions <

l (November 27, December 2, and December 7,1997). This degraded condition resulted  !

l in an extra plant cooldown and heatup. In addition, BECo failed to document on a

problem report that two of three temporary temperature detectors, installed per

temporary modification 97-29, had become disengaged from the reactor vessel flange ,

on November 27,1997. l

This is a severity Level IV Violation (Supplement I).

REASON FOR THE VIOLATION

The root cause for the violation was our failure to assign ownership for permanent resolution of

all temperature detector deficiencies following startup from RFO 11. This initial barrier failure

l led to a later non-compliance with procedure 1.3.121, " Problem Report Program" during

l troubleshooting and repair efforts on the temperature elemer: . The assessment (PR97.9747

and 98.0271) conducted in response to the reactor vessel flange temperature indication

problems and notice of violation revealed the following.

The cause of our failure to perform adequate causal investigation and implement

commensurate corrective actions during the forced shutdowns for the temperature detector

5

4

. _. .. .. -. ._

, .

.

j.

deficiencies, as well as our failure to document on a problem report that two of three detectors

became disengaged from the reactor vessel flange on November 27, 1997, is human

performance error. This cause is attributed to our failure to assign ownership for permanent

resolution of all temperature detector deficiencies following startup from RFO 11. At that time,

the condition of the originally installed temperature elements (TE) was known to be degraded

,

resulting in the installation of temporary modification TM 97-29. Since TEs are non safety-

related and there were no knova problems associated with TM 97-29 during heatup from RFO

11, there was no elevated awaieness or urgency to initiate actions to develop a permanent

resolution until the next refueling outage. Accordingly, the problems received low priority for a

permanent resolution. When TE problems again occurred on November 23,1997, with no

l individual owner in place and, consequently, with no established plan in place to permanently

solve the TE problems, all efforts were focused on restoring the temporary modification to

working condition.

The violation states that the degraded condition due to temperature detector deficiencies

resulted in an extra plant cooldown and heatup. This is an incorrect statement; Pilgrim did not

undergo an extra heatup and cooldown due to temperature detector deficiencies. The heatup

and cooldown referenced in the violation was performed as a result of a management

decision, and it is generally Pilgrim Station policy to place the plant in shutdown cooling

following shutdowns to perform maintenance and prepare for startup.

Also, notwithstanding the temperature detectors' failures to provide reliable temperature

l indications, engineering analysis (EE 97-67, Rev. 0) confirmed the vessel flange to shell

differential temperatures during heatup and cooldown did not result in exceeding code stress

allowables.

l

'

BACKGROUND ,

l On February 19,1997, following reactor shutdown for RFO 11, PR 97.9125 reported that TR-

l 263-105 shell temperature was indicating low. I&C Engineering performed a direct cause

analysis that determined the recorder was out of calibration. During the RFO 11 reactor vessel

l hydrostatic test, the vessel flange thermocouples gave inadequate temperature readings.

l

PR97.1487 was issued to document the low readings on the flange temperature elements. TM

. 97-27 was installed to allow operators to read the actual vessel flange temperature during the

i reactor vessel hydrostatic test. On April 5,1997, at the time of the restart from the RFO 11,

l TM 97-27 was changed to provide temperature indications in the control room and was

I

installed on April 7,1997, as TM 97-29 per MR#19700982. There were no known problems

with TM 97-29 during heatup from RFO 11.

On April 30,1997, PR97.1780 was issued stating that vessel flange TEs leading to TR-263-

105 (blue pen, point 2) were not reading correctly. This problem report was dispositioned to a

maintenance request to calibrate the recorder.

On November 24, 1997, at the time of plant cooldown for MSIV repairs, the Operations

!

Department observed TR-263-105 blue pen failed downscale. On November 26, PR97.9731

stated TR-263-105 blue pen failed downscale during plant cooldown. This recorder, as well as

TR-263-104, measures vessel flange temperature, and TR-263-104 is commonly used as the

technical specification reading (point 3). MR#19702899 was issued and PR97.9731 was

closed. MR#19702899 was closed to MR#19700982 and all work was performed under

MR#19700982. Numerous entries into the drywell were performed to ensure magnetic

mounted TEs provide reliable temperature indication. Investigation by maintenance personnel

6

1

. _ _ ._ . _ _ _ _ . . . .. _ - _ _ . . _ _ _ _ _ _ . . . _ - . _ _ _ _ _ . _ _ _ _ _ _ _ _ _ . _

l o ,

~*

f,.

revealed the temperature element for point 3 was found separated from the vessel flange.

Inspection of the other elements revealed point 2 had also separated from the vessel flange.

The terminal screws for these two TEs were loose.. However, no problem report was written to

l document the temperature elements had separated from the reactor vessel flange.

During the December 6,1997, forced outage, l&C Maintenance, System Engineering, and I&C

supervisory and management personnel were involved at different times in performing

investigation and corrective actions for the TE problems. With no single point of contact

l established for ownership, a situation was created in which the coordination of the overall

resolution, including consistent, reliable, accurate communication and evaluation became

ineffective. Additionally, more than one MR was being used to address the TE problems and i

MR log documentation practices were not well implemented for some entries regarding  !

.

conditions found and actions taken. Both of these items added additional confusion. The -

general mindset was these TEs are non safety-related devices, only required for startups and

shutdowns. Important information concerning the as-found condition of the TEs pulled back

.

during the investigative entry on November 26, 1997, was communicated to a system

l engineer, documented in En MR log, but was not documented on a problem report. This

l failure to write problem report and to address cumulative temperature detectors deficiencies

l violated procedure 1.3.121.

,

Once the TEs became an issue for potential technical specification violations on December 2,

1997, concurrent with the issuance of PR97.9747, the l&C Engineering and Maintenance

Managers engaged in direct and prompt work actions for a permanent resolution. Currently,

the adequacy of the design and compliance with technical specification are being addressed to

prevent repeat occurances.

CORRECTIVE STEPS TAKEN AND RESULTS ACHIEVED

The following corrective steps were taken to resolve ineffective corrective actions included in

the Notice of Violation.

.

'

l . An engineering evaluation, EE 97-67, Rev. O, was completed in response to PR97.9747

l

'

which confirmed that vessel flange to shell differential temperatures during heatup and

cooldown did not result in exceeding code stress allowables.

. An I&C night order was issued on December 23,1997, advising I&C technicians to write

problem reports when they discover deficiencies and problems.

CORRECTIVE STEPS THAT WILL BE TAKEN TO AVOID FURTHER VIOLATIONS

Attempts to correct the loss of correct temperature indication on November 26, December 3,

and 7,1997 were unsuccessful. Accordingly, the following corrective actions are planned to

avoid further violations.

  • A technical specification change to remove the requirement for vessel shell to vessel

'

flange differential temperature limit of 145 F will be submitted by March 27,1998, for NRC

approval.

.

'

. A redesign of the temperature element leads in the drywell will be prepared. This ,

'

modification is currently planned for implementation auring RFO 12 or an outage of

sufficient duration that would provide access to the drywell.

,

7

, i

J

. - - - . ._- . . _ - . _ . _ . - . - - - - - . - . - - - . - .

. .

'

'

.,

. This violation involved many different personnel and plant processes and is essentially a

case of missed opportunities. Knowledge-based errors were made, and the application is

broad affecting the entire organization. Accordingly, this violation will be presented as a

case study within the existing continuing training programs. This case study will be

prepared and the schedule for training will be determined by April 10,1998.

DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED

Full compliance resolving allissues related to the vessel flange to shell temperature monitoring

will be completed by RFO 12.

The proposed technical specification changes to remove the vessel flange differential

temperature limit will be submitted to the NRC by March 27,1998.

. The vessel flange temperature corrective action case study and schedule for training will be

set by April 10,1998.

1

i

n

!

!  !

l

l

!

i

i

8

i

I

I

.. ._ - _ _ . i

.. .

.

'

O 10CFR 2.201

Boston Edison

Pilgrim Nuclear Power Station

Rocky Hill Road e

Plymouth, Massachusetts 02360

-

y l

Thos' ,

a

Vice esident Nuclear and Station Director '

gECo tr #2 98.002

I

U.S. Nuclear Regulatory Commission i

Attention: Document Control Desk l

Washington, DC 20555 l

Docket No. 50-293

License No. DPR-35

RErl Y TO NOTICE OF VIOLATION 97-11-01

SUBJECT AC INSPECTION REPORT NO. 50-293/97-11

Enclosed is Boston Edison Company's reply to the Notice of Violation (VIO 97-11-01)

contained in the subject inspection report. j

l

The following commitments are made in this letter to enhance the effectiveness of the tagout

process by June 15,1998:

  • Operations personnel will receive initial or refresher training in human error prevention

techniques.

  • Procedure 1.4.5, "PNPS Tagging Procedure", will be revised to clarify requirements for an

independent technical review of tagout adequacy and correctness of maintenance tasks.

. The standard tagouts retained in the tagout database will be reviewed to ensure entries

for component isolation are correct. Operations management will review the feasibility of

including the standard tagout database in the configuration management program to help

ensure accuracy of " normal" specified positions.

  • Procedure 1.5.20 " Work Control Process", will be evaluated to determine if any

enhancements can be made to provide for earlier work package review and tagout

preparation by operations and maintenance personnel.

. Operations management will establish trending indicators and perform quarterly reviews

of the effectiveness of these corrective actions through department self-assessments

during the first two quarters of 1998. If required, additional quarterly self-assessments

will continue during 1998 and corrective actions will be taken based upon the results of

these self-assessments.

Please do not hesitate to contact me if there are any questions regarding the enclosed reply.

  • '

.

,

. J. Olivier

WGL/ Vio97-11

Enclosure: Reply to Notice of Violation

4 % M 2 A O X 7 4 (cpa

. ,.

.

.

Boston Edison Company

cc: Mr. Alan B. Wang, Project Manager

Project Directorate 1-3

Omce of Nuclear Reactor Regulation

Mail Stop: OWFN 1482

U. S. Nuclear Regulatory Commission

1 White Flint North

11555 Rockville Pike

Rockville, MD 20852

U.S. Nuclear Regulatory Commission

Region i

475 Allendale Road

King of Prussia, PA 19406

Senior Resident inspector

Pilgrim Nuclear Power Station

_ _ _ _ _ _ - _ _

- - . . - - --.--- .. ._. . __ --

. .

~

.

.

I

l

Boston Edinn Company Docket No. 50-293 ,

Pilgrim Station License No. DPR-35 l

ENCLOSURE

1

l Repiv to Notice of Violation 97-11-01 <

VIOLATION ,

As a result of an inspection conducted September 14,1997, through November 10,1997, the ,

following violation of NRC requirements was identified. In accordance with the NRC :

Enforcement Policy (60 FR ?A381; June 30,1995), the violation is described below:

Pilgrim technical specifications, section 6.8, Procedures, requires that written procedures be

established and implemented for activities covered in NRC Regulatory Guide 1.33, Appendix

A. Appendix A, Section 1.c, Equipment Control, requires procedures to be established and  ;

implemented for equipment tagging. BECo Procedure No.1.4.5, "PNPS Tagging Procedure", i

steps 3.0, 6.2 and 6.7 require that tagouts be properly prepared, implemented and I

independently verified. l

Contrary to the above,

A. On October 1,1997, the licensee identified that, tagout T97-46-162 was incorrectly

prepared and applied; breaker 1021 was placed in the closed vice open position as

required by the tagout. This resulted from redundant errors in implementing the tagout

process by their licensed operators.

B. On October 7,1997, the NRC identified that tagout T97-61-44 was inadequate for

maintenance work on K-103A, air start compres.sor for the " A" emergency diesel

generator. The tagout did not require that the boundary valve in the sensing line

between the air compressor and the air start receivers was isolated.

This is a Severity Level IV Violation (Supplement 1).

REASON FOR THE VIOLATION

The reason for the violation was non-compliance with procedure 1.4.5, "PNPS Tagging

Procedure". The assessment conducted in response to the above tagout problems revealed

the following:

The cause of the first example (Problem Report 97.2909) was licensed operator error. The

tagout was prepared by a Senior Reactor Operator (SRO) using the tagout computer. The

tagout computer incorrectly listed the " normal" position for breaker 52-1021 as " closed" verses

normally "open". Therefore, the tagout sheet was incorrect for the normal position of this

breaker. The SRO did not verify that the normal positions listed on the tagout sheet were i

correct as required by procedure 1.4.5. Although the " normal" position was not correct, the  ;

'

tagged position on the tagout sheet was correct.

Subsequently, Operator A tagged breaker 52-1021 in an incorrect position. The operator did

not use the proper self checking technique of reading the tagged position on the tagout sheet

1

_ _ . _. _

- .

.

.

and comparing it to the actual position specified in the tagout. Contributing to the error was the

operator's mind-set about the position of this breaker. He knew its normal position was open;

however, when he read the tagout sheet to position the break open with a normal position of

closed, he was mentally prompted to change the state of the creaker. This action was incorrect

for the isolation portion of the tagout. The tagout was independently verified by Operator B,

but the operator failed to execute the intended purpose of an independent verification. This

was apparently caused by a mind-set that he expected to see breaker 52-1021 open and

visualized it in that condition. Thus the positioning error was not discovered by either the

person hanging the tagout or by the verifier of the tagout.

The cause of the second example (Problem Report 97.2997) was licensed SRO error. This

was due to inadequate review of the maintenance work plan for the "A" emergency diesel

generator (EDG) air start compressor. An SRO solicited information on the maintenance

activities from the work week manager and the system engineer. The standard tagout for work

on the "A" EDG air compressors normally requires the air receiver drain valves to be tagged

open to depressurize the tank. In order to reduce the EDG out-of-service time (72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> LCO),

he decided to keep the air receiver pressurized. However, when the standard tagout was ,

modified, the tagout preparer did not identify that the pressure sensing tubing connected to the l

compressor unloader needed to be isolated from the receiver. A second SRC performed a

'

field walk-down and maintenance request review but also failed to recognize the omission of

the isolation in the compressor unloader pressure sensing line. The review by the Nuclear

Watch Engineer authorizing the tagout was not to a level of detail that would have identified

this omission. The Nuclear Watch Engineer's review was focused more on equipment

availability with respect to the technical specification requirements. The maintenance

technicians proceeded with maintenance on the compressor with minor air leakage present.

When it was identified that further isolation was needed, operations was notified. A tag

change was initiated by the Nuclear Operations supervisor to add danger tags to the sensing

line isolating valves.

A review of errors associated with operations tagout preparation and execution was

conducted. Additionally, an independent review of the corrective action data base by the

independent oversight team did not indicate that significant problems existed. However, an

adverse short term trend has been noted by the two examples identified in the violation and i

another tagging error (PR97.9734) identified by our staff subsequent to the end of the I

inspection 97-11.

CORRECTIVE STEPS TAKEN AND RESULTS ACHIEVED

l

The following corrective steps were taken to resolve the tagout errors included in the Notice of

Violation:

. The operator who hung tagout T97-46-162 did not have any recent performance problems.

The operator who did the independent verification had one recent performance problem.

He was removed from shift duties for one week and provided training for remediation.

Senior plant management conducted interviews with the operator to verify the

effectiveness of the remediation training. Both operators received quality venfication and

validation training. The SRO that prepared the tagout had no previous performance

issues; however, his performance was addressed by operations management. The SROs'

and operators' performance is routinely trended. ,

2

,

  • -

. ,

l -

.

.

l

l

. Tagout T97-61-44 was moo;fied to include isolation of the air compressor unloader from

the air receivers. An operations night order was issued clearly delineating second person

review of tagout preparation, and a second night order was issued for senior reactor

operators to emphasize that the review for normal component position in accordance with

procedure 1.4.5 must be done during tagout preparation. These actions were completed

by December 30,1997.

l . A samp!e population of in-place tagouts was inspected to verify proper positions and

l tagg;ng. No other examples of non-compliance were identified.

l . A maintenance night order was issued to reinforce the job walkdown requirements for

maintenance personnel. This order stressed ensuring isolation is adequate for safe work

performance and to immediately notify operations if there is a problem with the isolation.

. The operations and maintenance departmeni managers briefed their respective crews on

the importance of proper tagging and verification methods.

. Operations management has begun the process of having limnsed reactor operators

preparing tagouts. The intent is to have more worker level involvement in the initial

preparation using the extensive field ' hands on' experience.

CORRECTIVE STEPS THAT WILL BE TAKEN TO AVOID FURTHER VIOLATIONS

The effectiveness of preparation and implementation of tagout process will be improved by

June 15,1998, as follows:

. Operations personnel will receive initial or refresher training in human error prevention

techniques. This training covers various human error reduction techniques to reduce the

impact of time pressure, distractions, high workload, over confidence inducers, stress and

imprecise communications. Also included ir, this training will be an overview of these

tagging errors and the issues surrounding them.

. Procedure 1.4.5, "PNPS Tagging Procedure", will be revised to clarify requirements for an

independent technical review of tagout adequacy and correctness of maintenance tasks.

In the past, the second person review was done by the Nuclear Watch Engineer. As

specified in the operations night order identified above, the expectatior; is that each tagout

receives an independent review for adequacy by an operator or SRO.

. The standard tagouts retained in the tagout database will be reviewed to ensure

correctness of entries for component isolation. Unneeded or infrequently used standard

tagouts will be reviewed for deletion from the database. Operations management will

review the feasibility of including the standard tagout database in the configuration

management program to help ensure accuracy of " normal" specified positions.

  • Procedure 1.5.20, " Work Control Process", will be evaluated to determine if any

enhancements can be made to provide for earlier work package review and tagout

preparation by operations and maintenance personnel.

  • Considering the potential r.onsequences of a tagging error on plant and personnel safety,

management reviews wil'. focus on early identification and correction of adverse trends in

! 3

l

- - . - . . . . . ~ . - . - - . .

,

  • = i

..

l

4 4

.

I

this area. Operations management will establish trending indicators and perform quarterly l

reviews of the effectiveness of these corrective actions through department self- i

assessments during the first two quarters of 1998. If required, additional quarterly self- l

assessments will continue during 1998 and corrective actions will be taken based upon the j

results of these self-assessments,  ;

DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED l

l

Full compliance resolving all the tagout issues was achieved by January 7,1998. I

I

The tagout process improvements will be completed by June 15,1998. .

!

!

i

f

1

r

!

I

'

1

i

i

l

I

l

!

i

l

> ,

!  !

1

.

4

, _. - -

_ , _ .- _ -

_ _ _ . . . . - _ . . _ _ _ . _ _ _ , .

_ __ - . . _ -. _ _ _ _ . . _ _ . . __ . _ _. -

! - ,. .

!

'-

0 10 CFR 2.201

mm W-of- 07:

f Pilgrim Nuclear Power Station

Rocky Hill Road

Plymouth, Massachusetts 02360

3 ^O "MM.

, _ / 4 f

_

,qfiv3g

t I

f W&

$ 0l-08: . Y Y6

i

L.J. olivier

Vice President Nuclear and Station Director April 23,1998

BECo Ltr. #2.98.054

M$%  ;

'

i

i

l U.S. Nuclear Regulatory Commission ,

l Attention: Document Control Desk  ;

Washirigton, DC 20555  :

i

Docket No. 50-293

License No. DPR-35 i

REPLY TO NOTICE OF VIOLATIONS 98-01-07 AND 98-01-08 -

NRC INSPECTION REPORT NO. 50-293/98-01. DATED MARCH 24.1998

.

Enclosures 1 and 2 provide Boston Edison Company's reply to Notice of Violations 98-01-07 $

and 98-01-08 contained in the subject inspection report.

This letter includes the following commitment addressing violation 98-01-07 (Enclosure 1):

.

The circumstances surrounding this late 10 CFR 50.72 reporting will be communicated to

all nuclear engineering personnel in the 2nd quarter engineering support personnel

training session. This will be completed by July 30,1998.

Violation 98-01-08 was resolved and full compliance achieved in October 1997.

l Please do not hesitate to contact me if there are any questions regarding the enclosed reply.

I

L. . Olivier

WGU298054'Itrs

Enclosure 1: Reply to Notice of Violation 98-01-07

Enclosure 2: Reply to Notice of Violation 98-01-08

cc: Mr. Alan B. Wang, Project Manager Region I, U.S. Nuclear

l Project Directorate 1-3 Regulatory Commission

Office of Nuclear Reactor Regulation 475 Allendale Road l

l USNRC, Mail Stop: OWFN 14B2 King of Prussia, PA 19406 l

1 White Flint North

!

11555 Rockville Pike

, Rockville, MD 20852 Senior Resident inspector l

Pilgrim Nuclear Power Station

,

!

!

l

0 ?O S O $ Q Q b-% C ff.

_ ___ _. _-

l

. . ,.

!

l.

'

Boston Edison Company Docket No. 50-293

Pilgrim Station License No. DPR-35

l

'

l

ENCLOSURE 1 i

!

Reply to Notice of Violation 98-01-07 '

l VIOLATION 98-01-07

During an NRC inspection (investigation) conducted January 7 - February 24,1998, two

violations of NRC requiremer.ts were identified. In accordance with the " General Statement of

,

l

Policy and Procedure for NRC Enforcement Actions," NUREG-1600, violation, VIO 97-01-07, '

is listed below

!

A.

reported to the NRC i w)thm one hour.10 CFR 50.72(b)(ii)(B requires that a cond

l Contrary to the above, ue NRC identified that a condition outside the design basis of the

l plant involving the emergency diesel generator fuel oil storage system was not reported

to the NRC within I hour. The condition was initially identified by the licensee on  ;

January 21,1998, but not reported to the NRC until January 27,1998.

~

This is a Severity Level IV violation (Supplement I). '

REASON FOR THE VIOLATION

i

The reason for the violation was non-compliance with PNPS Procedure 1.3.121, " Problem

Report Program," Rev. 3. Our assessment (PR 98.0646) of the violation revealed the following.

The cause for a condition outside the design basis of the plant not being reported within one

hour was a human error. The individuals involved with the evaluation of the emergency diesel

generator (EDG) fuel requirement did not submit PR 98.9052 to the Nuclear Watch Engineer

(NWE) in a timely manner in accordance with procedure 1.3.121.

During an engineering review of calculation S&SA 55 (Rev. 5), " Minimum On-Site Diesel Fuel

Requirement" an inconsistency in an assumption was identified. A problem report (PR 98.9052)

was written to document the inconsistency. An engineering evaluation (EE 98-011) dated

i

January 21,1998, was drafted to document the minimum fuel oil capacity was adequate. The

PR 98.9052 and EE 98-011 were submitted to the NWE concurrently on January 27,1998.

The individuals involved did not believe the issues presented in PR 98.9052 were reportable.

During the review of the problem report and as a result of discussion between the NWE and the

engineer, a potential single failure vulnerability in the EDG fuel oil supply system was identified.

Specifically, it was discovered that failure of either main storage tank suction check valve (38-

CK-101 A/B) could eliminate the ability to cross-connect the tanks. This new potential single

l

'

failure vulnerability in the EDG fuel oil cross-connect line was added to the PR 98.9052 on

January 27, 1998. The NRC Operations Center was notified in accordance with 10 CFR

50.72(b)(ii)(B) on January 27, 1998, due to the belief that a condition was identified to be

potentially outside the design basis of the plant. Licensee Event Report, LER 98-001-00,

describing the event, was submitted to the NRC on March 3,1998.

,

,

_ _ _ _ . _ _ _ . _ _ _ _ _ _ _ . _ _ _ _ . . _ _ _ _ _ _ _ _ _ _ _ . __

.. ,

, e j

!

'

I

i

PNPS procedure 1.3.121, steps 6.1[4] and [5], require the originator of the problem report fill  ;

out the entire problem report form to the extent practical, and if the conditions on the back of l

the problem report exist or if the originator is uncenain, the PR shall be hand carried to the

l

NWE. Also, step 6.1[5] requires an individual to write a problem report at the end of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> .

if there is insufficient information to validate the need for a problem report and the concern

-

!

relates to the potential operability of safety-related systems, structures and components. The i

'

procedure specifically requires the problem report be submitted if, at the end of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, the

need for a problem repon cannot be mied out. PR 98.9052 was not submitted to the NWE in a

timely manner as specified in step 6.1[4] of procedure 1.3.121. This led to delayed reporting of

the potential condition outside the design basis of the plant.

CORRECTIVE STEPS TAKEN AND RESULTS ACHIEVED

e- The NESG Group Manager held a group meeting where he reiterated his expectation that l'

' individuals must prepare a problem report and bring it to the NWE when the engineer

becomes aware of the problem. The engineer cannot wait until an engineering evaluation is  ;

completed.  :

!

. - Individuals involved in the EDG fuel oil requirement assessment were counseled on their  !

failure to submit the PR 98.9052 to the NWE in a timely manner.  !

  • '

Training was provided to all NESG engineers on the requirements of PNPS procedure

l.3.121. Emphasis was placed on the expectation and requirement to write a problem report

per Section 6.1[4]. It was also explained, that though a problem may not pose a threat to

operability, it may still be reportable as being outside the design basis. T u,s training was '

given by the S&SA depanment manager during the weeks ofMarch 2 and March 9,1998.

e Engineers on the design basis information project have been made aware they must follow

l

!

PNP,S 1.3121 when design basis issues'are discoveredc They were'also given the above

.

l tranung.

CORRECTIVE STEPS THAT WILL BE TAKEN TO AVOID FURTHER VIOLATIONS

. The circumstances surrounding this PR will be communicated to all NESG engineers in the

L 2nd quaner ESP training session. This will be completed by July 30,1998.

l DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED

!

Full compliance was achieved on January 27,1998, when the NRC was notified in accordance

I with 10CFR 50.72.

!

!

l

l

'

,

.

!

l

l

l

.

!

l

, . , . -. . - -

_ _ - - --

. .

., .

.

Boston Edison Company Docket No. 50 293

Pilgrim Station License No. DPR-35

ENCLOSURE 2

Reply to Notice of Violation 98-01-08

VIOLATION NO. 98-01-08 (identified as item B in the Notice of Violation)

During an NRC inspection (investigation) conducted January 7 - Febmary 24,1998, two

violations of NRC requirements were identified. In accordance with " General Statement of

Policy and Procedure for NRC Enforcement Actions," NUREG-1600, violation, VIO 98-01-08,

is listed below:

B. 10 CFR 50.71(e) requires periodic updates be submitted to the UFSAR to assure

information included in the UFSAR contains the latest information available. Revisions

must be filed annually or six months aner each refueling outage provided the interval

between updates does not exceed 24 months.

Contrary to the above, prior to October 1997, FSAR updates submitted to the NRC, per

BECo procedure NOP 83A17, "10 CFR 50.71(e) Update," did not include all relevant

changes made to information in the UFSAR within the prescribed time limits. Instead of

updating the UFSAR during the operational turnover phase of changes, the UFSAR was

only updated after completion of modification close-out. This onen times exceeded the

time limits set forth in 10 CFR 50.71(e).

This is a Severity Level IV violation. (Supplement I).

REASON FOR THE VIOLATION

The reason for the violation was Pilgrim Nuclear Organization Procedure, NOP83 A17, "10 CFR

50.71(e) FSAR Update," did not conform to specific requirements set forth in 10 CFR 50.71(e)

for updating the Final Safety Analysis Report (FSAR). Also, our assessment (PR 97.0426)

showed NOP83E4, "t SAR Change Request", NOP83El, " Control of Modifications at Pilgrim

Station", and ineffective quality defense barriers in the areas of management and independent

oversight created delays in FSAR updating timeliness. As such, FSAR updates submitted to the

NRC did not include all relevant changes made to information in the FSAR within the prescribed

time limits.

The first FSAR update took place in 1982 for compliance with the new requirements of 10 CFR

50.71(e). 10 CFR 50.71(e) required implementing a periodic update to the FSAR to assure

information included in the FSAR reflects the changes made to the facility or procedures as

described in the FSAR, all safety evaluations performed by the licensee either in support of

l requested license amendments or in support of conclusions that changes did not involve an

! unreviewed safety question, and all analysis of new safety issues performed by or on behalf of

the licensee at Commission request. NOP83El and NOP83E4 provided procedural steps to

make changes to the information contained in the FSAR afler the update of drawings and close-

out of modifications.

A PNPS regulatory relations self assessment (96-4) identified the PNPS FSAR update process

did not provide timely FSAR updates. Specifically, after a plant design change (PDC) was

performed, an FSAR change request was only submitted after final PDC close-out.

'

l

,

F

l

,-

l '.: ' s , ,, e

l.

l In some cases, even though modifications were put into operation, the PDC final close-out

j occurred after all drawings and other papenvork were updated, which resulted in UFSAR

! updates exceeding the time limit prescribed in 10 CFR 50.71(e).

l

'

NRC Inspection Report No. 50-293/96-10, dated February 7,1997, documented the FSAR l

change process weakness initially identified by BECo was potentially a nonconformance with the

{

requirements of 10 CFR 50.71(e). In response, BECo initiated problem report (PR) 97.9133,  !

dated February 21,1997, which was classified as a significant condition adverse to quality. The '

PR root cause analysis, dated September 22,1997, concluded that procedures for updating the  !

FSAR did not meet the intent of 10 CFR 50.71(e).  !

!  !

L CORRECTIVE STEPS TAKEN AND RESULTS ACHIEVED I

( Several corrective actions were developed and implemented as part of the resolution of

PR97.9133, more specifically, the following actions were implemented. I

! *

NOP83A17, "10 CFR 50.71(e) FSAR Update," was revised to initiate UFSAR- change  !

requests at the same time modifications were considered ready for operational turnover.  ;

t

. Changes to NOP83El, "FSAR Change Request" and NOP83El, " Control of Modifications i

at Pilgrim Station", were also implemented to make changes to the information in the FSAR i

in a timely manner.  !

\

e NOP83 A3, " Regulatory Correspondence Control" was revised to include, in part, guidance  !

l

on the identification of commitments that affect the Pilgrim station licensing basis.  !;

l . All fully implemented plant modification changes affecting the FSAR as of April 21,1997, l

l were submitted to the NRC in revision 21 of the FSAR in October 1997, in full compliance  !

l with 10 CFR 50.71(e).  !

! DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED  !

!

l A full comphance with 10 CFR 50.71(e) was achieved in October 1997.

i

!

'

l

1

l

l

l

,

a

i

a

! 1

. .. . --

- - -. - .1