|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217F8231999-10-13013 October 1999 Informs That on 990930,NRC Completed mid-cycle PPR of Catawba Nuclear Station.Based on Review,Nrc Did Not Identify Any New Areas That Warranted More than Core Insp Program Over Next Five Months.Historical Listing of Issues,Encl ML20217H0041999-10-13013 October 1999 Forwards MOR for Sept 1999 & Revised MOR for Aug 1999 for Catawba Nuclear Station,Units 1 & 2 ML20217F1301999-10-0707 October 1999 Forwards Rev 1 to Request for Relief 99-03 from Requirements of ASME B&PV Code,In Order to Seek Relief from Performing Individual Valve Testing for Certain Valves in DG Starting (Vg) Sys ML20212J3011999-10-0101 October 1999 Forwards Exemption from Certain Requirements of 10CFR54.17(c) Re Schedule for Submitting Application for Operating License Renewal.Se Also Encl ML20217K2651999-10-0101 October 1999 Forwards Retake Exams Repts 50-413/99-302 & 50-414/99-302 on 990921-23.Two of Three ROs & One SRO Who Received Administrative Section of Exam Passed Retake Exam, Representing 75 Percent Pass Rate 05000414/LER-1999-004, Forwards LER 99-004-01,providing Correction to Info Previously Provided in Rev 0 of Rept.Planned Corrective Actions Contain Commitments1999-09-27027 September 1999 Forwards LER 99-004-01,providing Correction to Info Previously Provided in Rev 0 of Rept.Planned Corrective Actions Contain Commitments 05000413/LER-1999-015, Forwards LER 99-015-00 Re Inoperability of Auxiliary Bldg Ventilation Sys That Exceeded TS Limits Due to Improperly Positioned Vortex Damper.Commitments Are Contained in Corrective Actions Section of Encl Rept1999-09-27027 September 1999 Forwards LER 99-015-00 Re Inoperability of Auxiliary Bldg Ventilation Sys That Exceeded TS Limits Due to Improperly Positioned Vortex Damper.Commitments Are Contained in Corrective Actions Section of Encl Rept ML20217A7911999-09-24024 September 1999 Forwards Insp Repts 50-413/99-05 & 50-414/99-05 on 990718- 0828 at Catawba Facility.Nine NCVs Identified Involving Inadequate Corrective Actions Associated with Degraded Svc Water Supply Piping to Auxiliary Feedwater Sys ML20212E6471999-09-24024 September 1999 Discusses GL 98-01 Issued by NRC on 980511 & DPC Responses for Catawba NPP & 990615.Informs That NRC Reviewed Response for Catawba & Concluded That All Requested Info Provided.Considers GL 98-01 to Be Closed for Catawba ML20212F0941999-09-21021 September 1999 Discusses Closeout of GL 97-06, Degradation of Steam Generator Internals for Cns,Units 1 & 2 ML20212M2001999-09-20020 September 1999 Confirms 990913 Telcon Between M Purser & R Carroll Re Management Meeting to Be Conducted on 991026 in Atlanta,Ga to Discuss Operator Licensing Issues 05000414/LER-1999-005, Forwards LER 99-005-00 Re Missed EDG TS Surveillance Concerning Verification of Availability of Offsite Power Sources Resulted from Defective Procedure.Planned Corrective Actions Stated in Rept Represent Regulatory Commitments1999-09-20020 September 1999 Forwards LER 99-005-00 Re Missed EDG TS Surveillance Concerning Verification of Availability of Offsite Power Sources Resulted from Defective Procedure.Planned Corrective Actions Stated in Rept Represent Regulatory Commitments ML20212D5321999-09-15015 September 1999 Informs That Duke Energy Corp Agrees to Restrict Max Fuel Rod Average Burnup to 60,000 Mwd/Mtu,In Order to Support NRC Final Approval & Issuance of Requested Amend ML20212B4641999-09-14014 September 1999 Forwards Monthly Operating Repts for Aug 1999 & Revised Monthly Operating Rept for Catawba Nuclear Station,Units 1 & 2 ML20212A4131999-09-14014 September 1999 Informs That TR DPC-NE-2009P Submitted in 990817 Affidavit, Marked Proprietary,Will Be Withheld from Public Disclosure, Pursuant to 10CFR2.709(b) & Section 103(b) of Atomic Energy Act of 1954,as Amended ML20212M1931999-09-13013 September 1999 Refers to 990909 Meeting Conducted at Region II Office Re Presentation of Licensee self-assessment of Catawba Nuclear Station Performance.List of Attendees & Licensee Presentation Handout Encl ML20212A3751999-09-10010 September 1999 Informs That Postponing Implementation of New Conditions Improved by RG 1.147,rev 12,acceptable Since Evaluation on Relief Based on Implementation Code Case for Duration of Insp Interval ML20212A5191999-09-0808 September 1999 Requests NRC Approval for Relief from Requirements of ASME Boiler & Pressure Vessel Code,Section XI,1989 Edition,App VI,VI-2430(c) & 2440(b).Approval of 99-GO-002 Is Requested by 000301 05000413/LER-1999-014, Forwards LER 99-014-00, Missed Surveillance & Operation Prohibited by TS Occurred as Result of Defective Procedures or Program & Inappropriate TS Requirements. Planned Corrective Action Stated in Rept Represents Commitment1999-09-0101 September 1999 Forwards LER 99-014-00, Missed Surveillance & Operation Prohibited by TS Occurred as Result of Defective Procedures or Program & Inappropriate TS Requirements. Planned Corrective Action Stated in Rept Represents Commitment 05000414/LER-1999-003, Forwards LER 99-003-01, Unplanned Actuation of ESFAS Due to a SG High Level Caused by Inadequate Procedural Guidance. Suppl Rept Provides Info Re Root Cause & Corrective Actions Associated with Event Developed Subsequent to Rev1999-08-31031 August 1999 Forwards LER 99-003-01, Unplanned Actuation of ESFAS Due to a SG High Level Caused by Inadequate Procedural Guidance. Suppl Rept Provides Info Re Root Cause & Corrective Actions Associated with Event Developed Subsequent to Rev 0 of LER ML20211H1741999-08-30030 August 1999 Forwards Comments on Catawba Nuclear Station Units 1 & 2 & McGuire Nuclear Station,Units 1 & 2 Specific Reactor Vessel Info Contained in Rvid.Ltr Dtd 990107,rept ATI-98-012-T005 & Partial marked-up Rept WCAP-14995 Encl ML20211M4451999-08-30030 August 1999 Forwards Summary of Util Conclusions Re Outstanding Compliance Issue Re Staff Interpretation of TS SR 3.0.1,per Insp Repts 50-369/99-03 & 50-370/99-03,as Discussed with NRC During 990618 Meeting 05000413/LER-1999-013, Forwards LER 99-013-00,re RHR Heat Exchanger Bypass Valves Not Verified Per TS Surveillance.Surveillance Procedures Have Been Revised & There Are No Further Planned Corrective Actions or Commitments in LER1999-08-25025 August 1999 Forwards LER 99-013-00,re RHR Heat Exchanger Bypass Valves Not Verified Per TS Surveillance.Surveillance Procedures Have Been Revised & There Are No Further Planned Corrective Actions or Commitments in LER ML20211M8191999-08-25025 August 1999 Confirms 990825 Telcon Between G Gilbert & R Carroll Re Mgt Meeting to Be Held on 990909 in Atlanta,Ga,To Allow Licensee to Present self-assessment of Catawba Nuclear Station Performance ML20211A9641999-08-20020 August 1999 Forwards SE Authorizing Licensee 990118 Request for Approval of Proposed Relief from Volumetric Exam Requirements of ASME B&PV Code,Section XI for Plant,Units 2 ML20211C1191999-08-18018 August 1999 Forwards ISI Rept Unit 1 Catawba 1999 RFO 11, Providing Results of ISI Effort Associated with End of Cycle 11 ML20211B9471999-08-18018 August 1999 Forwards Request for Relief 99-02,associated with Limited Exam Results for Welds Which Were Inspected During Unit 1 End of Cycle 11 RFO ML20211C3651999-08-17017 August 1999 Forwards Rev 25 to Catawba Nuclear Station Units 1 & 2 Pump & Valve Inservice Testing Program, Which Includes Reformatting of Manual & Addl Changes as Noted in Attached Summary of Changes ML20211F2971999-08-17017 August 1999 Forwards non-proprietary & Proprietary Updated Pages for DPC-NE-2009,submitted 980722.Pages Modify Fuel Design & thermal-hydraulic Analysis Sections of DPC-NE-2009. Proprietary Page 2-4 Withheld,Per 10CFR2.790 05000413/LER-1999-011, Forwards LER 99-011-00,re Missed Surveillance on Both Trains of CR Area Ventilation Sys Resulting in TS Violation.Planned Corrective Actions Stated in LER Represent Regulatory Commitment1999-08-16016 August 1999 Forwards LER 99-011-00,re Missed Surveillance on Both Trains of CR Area Ventilation Sys Resulting in TS Violation.Planned Corrective Actions Stated in LER Represent Regulatory Commitment ML20211B1121999-08-16016 August 1999 Forwards Topical Rept DPC-NE-2012, Dynamic Rod Worth Measurement Using Casmo/Simulate, Describing Results of Six Drwm Benchmark Cycles at Catawba & McGuire & Discusses Qualification to Use Drwm at Catawba & McGuire ML20210V0321999-08-13013 August 1999 Forwards Insp Repts 50-413/99-04 & 50-414/99-04 on 990606- 0717.Six Violations of NRC Requirements Identified & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML20210S2751999-08-12012 August 1999 Forwards Monthly Operating Repts for July 1999 for Catawba Nuclear Station,Units 1 & 2.Revised Rept for June 1999,encl ML20210Q3751999-08-0505 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Authorized Representative of Facility Must Submit Ltr as Listed,Thirty Days Before Exam Date,In Order to Register Individuals for Exam ML20210N9521999-08-0404 August 1999 Forwards Changes to Catawba Nuclear Station Selected Licensee Commitments Manual.Documents Constitutes Chapter 16 of Ufsar.With List of Effective Pages IR 05000413/19980131999-08-0202 August 1999 Discusses Integrated Insp Repts 50-413/98-13,50-414/98-13, 50-413/98-16,50-414/98-16 & NRC Special Repts 50/413/99-11 & 50-414/99-11 Conducted Between Aug 1998 & May 1999.Six Violations Occurred,Based on OI Investigation & Insp ML20210M6411999-07-29029 July 1999 Forwards Request for Relief 99-03 from Requirements of ASME Boiler & Pressure Vessel Code,In Order to Seek Relief from Performing Individual Valve Testing for Certain Valves in DG Starting Air (Vg) Sys 05000413/LER-1999-010, Forwards LER 99-010-01 Which Replaces LER 99-002.Rept Number Has Been Changed in Order to Conform to Numbering Convention Specified in NUREG-1022,since Primary Event Involved Both Units1999-07-22022 July 1999 Forwards LER 99-010-01 Which Replaces LER 99-002.Rept Number Has Been Changed in Order to Conform to Numbering Convention Specified in NUREG-1022,since Primary Event Involved Both Units IR 05000413/19990101999-07-22022 July 1999 Discusses Insp Rept 50-413/99-10 & 50-414/99-10 on 990314- 0424 & Forwards Notice of Violation Re Failure to Comply with TS 3.7.13,when Misalignment of Two Electrical Breakers Rendered SSS Inoperable from 981216-29 ML20217G5241999-07-20020 July 1999 Forwards Exam Repts 50-413/99-301 & 50-414/99-301 on 990524- 27,0603,07-10 & 16.Of Fourteen SRO & RO Applicants Who Received Written Exams & Operating Tests,Eight Applicants Passed & Six Failed Exam 05000413/LER-1999-009, Forwards LER 99-009-00,re Inoperability of Containment Valve Injection Water Sys Valve in Excess of TS Limits.Root Cause & Corrective Actions Associated with Event Are Being Finalized & Will Be Provided in Supplement to Rept1999-07-19019 July 1999 Forwards LER 99-009-00,re Inoperability of Containment Valve Injection Water Sys Valve in Excess of TS Limits.Root Cause & Corrective Actions Associated with Event Are Being Finalized & Will Be Provided in Supplement to Rept 05000414/LER-1999-001, Forwards LER 99-001-01 Re Unanalyzed Condition Associated with Relay Failure in Auxiliary Feedwater Sys,Due to Inadequate Single Failure Analysis.Rev Is Being Submitted to Include Results of Failure Analysis Which Was Performed1999-07-15015 July 1999 Forwards LER 99-001-01 Re Unanalyzed Condition Associated with Relay Failure in Auxiliary Feedwater Sys,Due to Inadequate Single Failure Analysis.Rev Is Being Submitted to Include Results of Failure Analysis Which Was Performed ML20209H4431999-07-14014 July 1999 Forwards Monthly Operating Repts for June 1999 for Catawba Nuclear Station,Units 1 & 2.Revised Rept for May 1999 on Unit Shutdowns Also Encl ML20210A5771999-07-14014 July 1999 Forwards Revsied Catawba Nuclear Station Selected Licensee Commitments Manual, Per 10CFR50.71(e),changing Sections 16.7-5,16.8-5,16.9-1,16.9-3,16.9-5 & 16.11-7.Manual Constitute Chapter 16 of UFSAR ML20216D3941999-07-14014 July 1999 Forwards Revs to Catawba Nuclear Station Selected Licensee Commitments Manual NUREG-1431, Forwards SER Agreeing with Util General Interpretation of TS LCO 3.0.6,but Finds No Technical Basis or Guidance That Snubbers Could Be Treated as Exception to General Interpretation1999-07-0909 July 1999 Forwards SER Agreeing with Util General Interpretation of TS LCO 3.0.6,but Finds No Technical Basis or Guidance That Snubbers Could Be Treated as Exception to General Interpretation ML20196L0371999-07-0808 July 1999 Approves Requested Schedule Change of Current two-year Requalification Examinations to non-outage dates.Two-year Cycle Will Start on 991001 & Will End on 020930 05000413/LER-1999-008, Forwards LER 99-008-00,re Operation Prohibited by TS 3.5.2. Rev to LER Will Be Submitted by 990812 Which Will Include All Required Info About Ventilation Sys Pressure Boundry Breach1999-07-0808 July 1999 Forwards LER 99-008-00,re Operation Prohibited by TS 3.5.2. Rev to LER Will Be Submitted by 990812 Which Will Include All Required Info About Ventilation Sys Pressure Boundry Breach ML20196J9001999-07-0606 July 1999 Informs That 990520 Submittal of Rept DPC-NE-3004-PA,Rev 1, Mass & Energy Release & Containment Response Methodology, Marked Proprietary Will Be Withheld Per 10CFR2.790(b)(5) & Section 103(b) of AEA of 1954 IR 05000413/19990031999-07-0101 July 1999 Discusses Insp Repts 50-413/99-03 & 50-414/99-03 Completed on 990605 & Transmitted by Ltr .Results of Delibrations for Violation Re Discovery of Potentially More Limiting Single Failure Affecting SGTS Analysis Provided 1999-09-08
[Table view] Category:NRC TO UTILITY
MONTHYEARML20058J1251990-11-13013 November 1990 Advises That Re Martin Recently Assigned as Project Manager for Facility ML20058F6161990-10-26026 October 1990 Forwards Insp Repts 50-413/90-28 & 50-414/90-28 on 901001-04.Violation Re Corrective Actions Which Appear to Be Ineffective in Preventing Recurrence of Similar Violation Noted.Enforcement Conference Scheduled for 901105 ML20058F0891990-10-22022 October 1990 Confirms 901031-1102 & 12-16 & 26-30 as Dates for Maint Team Insp of Plant Per 901011 Telcon ML20058B4551990-10-17017 October 1990 Forwards Insp Repts 50-413/90-25 & 50-414/90-25 on 900924-28.No Violations or Deviations Noted ML20062B7051990-10-12012 October 1990 Requests Completion of Analysis of Liquid Samples Spiked W/ Radionuclides within 60 Days of Receipt of Ltr ML20062A0951990-10-0303 October 1990 Forwards Insp Repts 50-413/90-24 & 50-414/90-24 on 900803- 0905 & Notice of Violation ML20059L4141990-09-14014 September 1990 Forwards Insp Repts 50-413/90-23 & 50-414/90-23 on 900730-0803.No Violations or Deviations Noted IR 05000413/19900151990-09-0505 September 1990 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-413/90-15 & 50-414/90-15 ML20059L5241990-09-0505 September 1990 Ack Receipt of 900810 Supplemental Response to Violations Noted in Insp Repts 50-413/90-09 & 50-414/90-09 ML20059H0121990-08-31031 August 1990 Forwards Insp Repts 50-413/90-19 & 50-414/90-19 on 900624- 0802 & Notice of Violation.Util Should Detail Measures to Be Taken to Place Addl Emphasis on Compensatory Actions Program ML20059E3121990-08-30030 August 1990 Advises That Util Responses to NRC Bulletin 88-004, Potential Safety-Related Pump Loss, Acceptable.Further NRC Review,If Any,Will Be Performed Either by Insp or Audit ML20059G6171990-08-28028 August 1990 Forwards Insp Repts 50-413/90-20 & 50-414/90-20 on 900724-26.Unresolved Item Identified Re Procedure of Equating self-referral to Employee Assistance Program as First Positive Drug Test ML20056A5571990-08-0202 August 1990 Requests Addl Info Re DPC-NE-2004, Core Thermal-Hydraulic Methodology Using VIPRE-01 for McGuire & Catawba. Requests Response Expeditiously IR 05000413/19900111990-08-0101 August 1990 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-413/90-11 & 50-414/90-11 ML20058P8761990-07-31031 July 1990 Forwards Insp Repts 50-413/90-22 & 50-414/90-22 on 900709-13.No Violations or Deviations Noted ML20055H9131990-07-27027 July 1990 Forwards Safety Evaluation Accepting Actions Taken to Resolve NRC Bulletin 88-002, Rapidly Propagating Fatigue Cracks in Steam Generator Tubes ML20055J2931990-07-23023 July 1990 Forwards Request for Addl Info Re Util 900315 Submittal of General Relief Request for Pumps in Inservice Testing Program.Addl Info Re Certain Areas That Deviate from OM-6, Identified in Encl,Required to Complete NRC Review IR 05000413/19900171990-07-23023 July 1990 Discusses Insp Repts 50-413/90-17 & 50-414/90-17 on 900611- 19 & Forwards Notice of Violation.Insp Included Review of Actions Re 900611 Inadvertent Transfer of Reactor Coolant Water to Refueling Water Storage Tank at Unit 1 ML20056A5071990-07-20020 July 1990 Forwards Insp Repts 50-413/90-15 & 50-414/90-15 on 900527-0623 & Notice of Violation.Violations,Refs Pertinent to Requirements & Elements to Be Included in Response Presented in Encl Notice of Violation ML20055H4191990-07-19019 July 1990 Forwards Insp Repts 50-413/90-21 & 50-414/90-21 on 900627-29.No Violations or Deviations Noted ML20055H4101990-07-18018 July 1990 Forwards Summary of Enforcement Conference on 900712 Re Unit 1 Inadvertent Diversion of Higher Pressure Reactor Coolant Water to Refueling Water Storage Tank on 900611,per Insp Repts 50-413/90-17 & 50-414/90-17.Handouts Also Encl ML20055H5881990-07-13013 July 1990 Forwards Insp Repts 50-413/90-16 & 50-414/90-16 on 900611-15.Violations Noted But Not Cited ML20058M9361990-07-13013 July 1990 Forwards Insp Repts 50-413/90-18 & 50-414/90-18 on 900625-29.No Violations or Deviations Noted ML20055H3601990-07-10010 July 1990 Advises That Reactor Operator & Senior Operator Licensing Exams Scheduled for Wk of 901015.Encl Ref Matls Requested by 900806 ML20055E3711990-07-0909 July 1990 Ack Receipt of Re Payment of Civil Penalties in Amount of $100,000,per NRC ML20055H4411990-07-0202 July 1990 Ack Receipt of 900607 Response to Violations Noted in Insp Repts 50-413/90-09 & 50-414/90-09.Implementation of Corrective Actions Will Be Examined During Future Insp ML20055C9911990-06-27027 June 1990 Confirms Region II Insp of fitness-for-duty Program on 900724-26.Brief Itinerary to Expedite Util Support of Program Encl ML20055C8421990-06-13013 June 1990 Forwards Insp Repts 50-413/90-14 & 50-414/90-14 on 900521-25.No Violations or Deviations Noted ML20059M9241990-06-13013 June 1990 Forwards NRC Performance Indicators for First Quarter 1990. W/O Encl ML20248J3891989-10-16016 October 1989 Forwards Insp Repts 50-413/89-28 & 50-414/89-28 on 890911-15.Violations Noted ML20248D2921989-09-28028 September 1989 Discusses Util Response to Generic Ltr 88-05, Boric Acid Corrosion of Carbon Steel Reactor Boundary Components in PWR Plants ML20248B6881989-09-25025 September 1989 Forwards Insp Repts 50-413/89-25 & 50-414/89-25 on 890801-28 & 0912-15.No Notice of Violation Issued for Violations Identified.Enforcement Conference to Discuss Violations Scheduled for 890928 ML20248B0921989-09-22022 September 1989 Confirms Arrangements for Enforcement Conference on 890928 to Discuss Failure to Take Adequate Corrective Action in Response to Failed Surveillance Test on Unit 2 Turbine Driven Auxiliary Feedwater Pump.Items to Discuss Encl IR 05000413/19890021989-09-20020 September 1989 Ack Receipt of Util Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-413/89-02 & 50-414/89-02 IR 05000413/19890161989-09-20020 September 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-413/89-16 & 50-414/89-16 ML20248B7431989-09-20020 September 1989 Forwards Insp Repts 50-413/89-26 & 50-414/89-26 on 890821-24.No Violations or Deviations Noted.Attention Invited to Unresolved Items Identified IR 05000413/19890091989-09-20020 September 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-413/89-09 & 50-414/89-09.Extension of Reply Due Date to 891010 for Weaknesses Identified in Insp Approved in 890823 Telcon ML20247G7421989-09-12012 September 1989 Forwards Insp Repts 50-413/89-24 & 50-414/89-24 on 890807-11.No Violations or Deviations Noted ML20246J6491989-08-31031 August 1989 Forwards Order Imposing Civil Penalty in Amount of $75,000, Per Violations Noted in Insp Repts 50-413/88-38 & 50-414/88-38 Re Inoperability of Containment Air Return & Hydrogen Skimmer Sys Due to Electrical Wiring Error IR 05000413/19880381989-08-31031 August 1989 Forwards Order Imposing Civil Penalty in Amount of $75,000, Per Violations Noted in Insp Repts 50-413/88-38 & 50-414/88-38 Re Inoperability of Containment Air Return & Hydrogen Skimmer Sys Due to Electrical Wiring Error IR 05000414/19890191989-08-31031 August 1989 Discusses Insp Rept 50-414/89-19 on 890616-28 & Forwards Notice of Violation.Violation Noted:On 890602,upper-range Pressurizer Transmitter Isolation Valves on Reactor Vessel Level Instrumentation Not Opened Prior to Entering Mode 3 ML20247C5541989-08-30030 August 1989 Advises That 890405 Rev 29 to Crisis Mgt Plan Consistent W/Provisions of 10CFR50.47(b) & Requirements of App E & Acceptable ML20246J9191989-08-29029 August 1989 Requests Addl Info Re Direct Generation Response Spectra & Snubber Reduction Program.Response Requested within 30 Days ML20247A1781989-08-29029 August 1989 Forwards Summary of 890720 & 0815 Enforcement Conferences Re Findings in Insp Repts 50-413/89-19 & 50-414/89-19 on Inoperability of Reactor Vessel Level Instrumentation Sys. List of Attendees & Viewgraphs Also Encl ML20246N1671989-08-28028 August 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-413/89-17 & 50-414/89-17 ML20246M5061989-08-22022 August 1989 Forwards Insp Repts 50-413/89-22 & 50-414/89-22 on 890723-28.No Violations Noted IR 05000413/19890141989-08-16016 August 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-413/89-14 & 50-414/89-14 ML20246C7051989-08-14014 August 1989 Forwards Insp Repts 50-413/89-18 & 50-414/89-18 on 890717-21.Violations Noted in Rept But Not Cited ML20245K4051989-08-11011 August 1989 Forwards Insp Repts 50-413/89-20 & 50-414/89-20 on 890717-21.No Violations or Deviations Noted ML20246A7411989-08-0808 August 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-413/89-13 & 50-414/89-13 1990-09-05
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217F8231999-10-13013 October 1999 Informs That on 990930,NRC Completed mid-cycle PPR of Catawba Nuclear Station.Based on Review,Nrc Did Not Identify Any New Areas That Warranted More than Core Insp Program Over Next Five Months.Historical Listing of Issues,Encl ML20217K2651999-10-0101 October 1999 Forwards Retake Exams Repts 50-413/99-302 & 50-414/99-302 on 990921-23.Two of Three ROs & One SRO Who Received Administrative Section of Exam Passed Retake Exam, Representing 75 Percent Pass Rate ML20212J3011999-10-0101 October 1999 Forwards Exemption from Certain Requirements of 10CFR54.17(c) Re Schedule for Submitting Application for Operating License Renewal.Se Also Encl ML20212E6471999-09-24024 September 1999 Discusses GL 98-01 Issued by NRC on 980511 & DPC Responses for Catawba NPP & 990615.Informs That NRC Reviewed Response for Catawba & Concluded That All Requested Info Provided.Considers GL 98-01 to Be Closed for Catawba ML20217A7911999-09-24024 September 1999 Forwards Insp Repts 50-413/99-05 & 50-414/99-05 on 990718- 0828 at Catawba Facility.Nine NCVs Identified Involving Inadequate Corrective Actions Associated with Degraded Svc Water Supply Piping to Auxiliary Feedwater Sys ML20212F0941999-09-21021 September 1999 Discusses Closeout of GL 97-06, Degradation of Steam Generator Internals for Cns,Units 1 & 2 ML20212M2001999-09-20020 September 1999 Confirms 990913 Telcon Between M Purser & R Carroll Re Management Meeting to Be Conducted on 991026 in Atlanta,Ga to Discuss Operator Licensing Issues ML20212A4131999-09-14014 September 1999 Informs That TR DPC-NE-2009P Submitted in 990817 Affidavit, Marked Proprietary,Will Be Withheld from Public Disclosure, Pursuant to 10CFR2.709(b) & Section 103(b) of Atomic Energy Act of 1954,as Amended ML20212M1931999-09-13013 September 1999 Refers to 990909 Meeting Conducted at Region II Office Re Presentation of Licensee self-assessment of Catawba Nuclear Station Performance.List of Attendees & Licensee Presentation Handout Encl ML20212A3751999-09-10010 September 1999 Informs That Postponing Implementation of New Conditions Improved by RG 1.147,rev 12,acceptable Since Evaluation on Relief Based on Implementation Code Case for Duration of Insp Interval ML20211M8191999-08-25025 August 1999 Confirms 990825 Telcon Between G Gilbert & R Carroll Re Mgt Meeting to Be Held on 990909 in Atlanta,Ga,To Allow Licensee to Present self-assessment of Catawba Nuclear Station Performance ML20211A9641999-08-20020 August 1999 Forwards SE Authorizing Licensee 990118 Request for Approval of Proposed Relief from Volumetric Exam Requirements of ASME B&PV Code,Section XI for Plant,Units 2 ML20210V0321999-08-13013 August 1999 Forwards Insp Repts 50-413/99-04 & 50-414/99-04 on 990606- 0717.Six Violations of NRC Requirements Identified & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML20210Q3751999-08-0505 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Authorized Representative of Facility Must Submit Ltr as Listed,Thirty Days Before Exam Date,In Order to Register Individuals for Exam IR 05000413/19980131999-08-0202 August 1999 Discusses Integrated Insp Repts 50-413/98-13,50-414/98-13, 50-413/98-16,50-414/98-16 & NRC Special Repts 50/413/99-11 & 50-414/99-11 Conducted Between Aug 1998 & May 1999.Six Violations Occurred,Based on OI Investigation & Insp IR 05000413/19990101999-07-22022 July 1999 Discusses Insp Rept 50-413/99-10 & 50-414/99-10 on 990314- 0424 & Forwards Notice of Violation Re Failure to Comply with TS 3.7.13,when Misalignment of Two Electrical Breakers Rendered SSS Inoperable from 981216-29 ML20217G5241999-07-20020 July 1999 Forwards Exam Repts 50-413/99-301 & 50-414/99-301 on 990524- 27,0603,07-10 & 16.Of Fourteen SRO & RO Applicants Who Received Written Exams & Operating Tests,Eight Applicants Passed & Six Failed Exam NUREG-1431, Forwards SER Agreeing with Util General Interpretation of TS LCO 3.0.6,but Finds No Technical Basis or Guidance That Snubbers Could Be Treated as Exception to General Interpretation1999-07-0909 July 1999 Forwards SER Agreeing with Util General Interpretation of TS LCO 3.0.6,but Finds No Technical Basis or Guidance That Snubbers Could Be Treated as Exception to General Interpretation ML20196L0371999-07-0808 July 1999 Approves Requested Schedule Change of Current two-year Requalification Examinations to non-outage dates.Two-year Cycle Will Start on 991001 & Will End on 020930 ML20196J9001999-07-0606 July 1999 Informs That 990520 Submittal of Rept DPC-NE-3004-PA,Rev 1, Mass & Energy Release & Containment Response Methodology, Marked Proprietary Will Be Withheld Per 10CFR2.790(b)(5) & Section 103(b) of AEA of 1954 IR 05000413/19990031999-07-0101 July 1999 Discusses Insp Repts 50-413/99-03 & 50-414/99-03 Completed on 990605 & Transmitted by Ltr .Results of Delibrations for Violation Re Discovery of Potentially More Limiting Single Failure Affecting SGTS Analysis Provided ML20209E2701999-07-0101 July 1999 Forwards Insp Repts 50-413/99-03 & 50-414/99-03 on 990425- 0605.Six Violations of NRC Requirements Occurred & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20209E3931999-06-28028 June 1999 Informs of 990618 Meeting Conducted at Facility to Present Results of Most Recent Periodic Plant Performance Review for Plant.List of Attendees Encl ML20196G8861999-06-24024 June 1999 Discusses GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structrual Integrity 950816 & 960729 Responses.Rvid,Version 2 Released as Result of Review.Rvid Should Be Reviewed & Comments Should Be Received by 990901 If Not Acceptable for Plant ML20196G6541999-06-17017 June 1999 Confirms 990614 Telephone Conversation Re Rescheduling of Two Predecisional Enforcement Conferences Originally Scheduled for 990623.SSS Conference Rescheduled for 990712 & Ice Condenser Conference Rescheduled for 990720 ML20196A5781999-06-14014 June 1999 Discusses Notice of Enforcement Discretion for Duke Energy Corp Re Catawba Nuclear Station Unit 1 TSs 3.5.2 & 3.7.12 ML20195E9171999-06-0303 June 1999 Confirms Conversation with Bradshaw on 990526 Re Rescheduling 990607 Predecisional Enforcement Conference to Discuss Apparent Violation in Insp Repts 50-413/99-10 & 50-414/99-10.Conference Will Be on 990623 in Atlanta,Ga ML20195F4141999-06-0202 June 1999 Forwards Insp Repts 50-413/99-11 & 50-414/99-11 on 990422-23 & 0503.Apparent Violation Identified & Being Considered for Escalated Enforcement Action.Violation Involved Failure to Maintain Unit 1 Ice Condenser Lower Inlet Door Operable ML20207D0671999-05-20020 May 1999 Informs That During Meeting on 990512,arrangements Modified for Administration of Licensing Exams at Catawba Nuclear Station During Weeks of 990524 & 0607,respectively ML20207C8721999-05-20020 May 1999 Forwards Insp Repts 50-413/99-02 & 50-414/99-02 on 990314-0424.Three Violations Occurred & Being Treated as non-cited Violations.Activities Generally Characterized by Safety Conscious Operations & Sound Engineering & Maint ML20207C8061999-05-19019 May 1999 Confirms 990510 Telcon with R Jones Re Predecisional Enforcement Conference Requested by NRC & Scheduled for 990607 in Atlanta,Ga to Discuss Apparent Violation Associated with Potential Inoperability of SSS ML20207C7761999-05-19019 May 1999 Informs That on 990618,NRC Will Meet with Mgt of Duke Energy Corp to Discuss Performance of Catawba Facility & Extends Invitation to Attend Meeting as Observer ML20206P4911999-05-14014 May 1999 Forwards Safety Evaluation Accepting GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML20206M4201999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation (NRR) Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt (DLPM) Created.Reorganization Chart Encl ML20206U4091999-05-10010 May 1999 Forwards Insp Repts 50-413/99-10 & 50-414/99-10 on 990314-0424.One Violation Occurred & Being Considered for Escalated Enforcement Action Involving Inoperability of Standby Shutdown Sys from 981216-29 ML20206N4191999-05-0606 May 1999 Informs That Team Will Inspect Dam at Standby Nuclear Service Water Pond on 990609.Purpose of Insp Will Be to Confirm That Structure Conforms with Design Documents & Capability of Performing Design Functions ML20205S5491999-04-21021 April 1999 Forwards SE Discussing DPC Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions. Response Acceptable ML20206B7941999-04-16016 April 1999 Confirms 990331 Telcon Between M Purser of Util & R Franovich of NRC Re Public Meeting Scheduled for 990618 in York,Sc to Discuss Results of NRC Recent Plant Performance Review for Catawba Nuclear Station ML20205N3471999-04-12012 April 1999 Forwards Safety Evaluation & Eri/Nrc 95-506, Technical Evaluation Rept on Submittal Only Review of IPE of External Events at Catawba Nuclear Station,Units 1 & 2 ML20205T3491999-04-0909 April 1999 Informs That on 990317,T Beedle & Ho Christensen Confirmed Initial Operator Licensing Exam Schedule for Catawba Nuclear Station for Y2K.No Y2K Exam Scheduled.Initial Exam Requested for Apr 2001 for Approx 18 Candidates ML20205N0531999-04-0606 April 1999 Forwards Insp Repts 50-413/99-01 & 50-414/99-01 on 990124-0313.DPC Conduct of Activities at Catawba Facility Generally Characterized by Safety Conscious Operations & Sound Engineering.Five Violations Noted & Treated as NCVs ML20196K9961999-03-30030 March 1999 Forwards Synopsis of NRC OI Completed Rept Re Alleged Compromise of Initial Licensed Operator Exam at Cns.Oi Did Not Substantiate Allegation That Initial Operator Exam Compromised.Plans No Further Action Re Matter ML20205M2651999-03-25025 March 1999 Discusses PPR Completed 990201.Advises of Planned Insp Effort Resulting from Catawba PPR Review.Forwards Plant Issues Matrix & Insp Plan ML20207L7741999-03-15015 March 1999 Requests That NRC Exercise Discretion Not to Enforce Compliance with Actions Required by Plant,Units 1 & 2 Re TS Limiting Conditions for Operation 3.3.7 & 3.3.8 ML20207M9091999-03-0505 March 1999 Informs That Info Submitted by Application, Marked as Proprietary Will Be Withheld from Public Disclosure Per 10CFR2.790(b)(5) & Section 103(b) of AEA of 1954,as Amended ML20207A5821999-02-17017 February 1999 Forwards Insp Repts 50-413/98-12 & 50-414/98-12 & Notice of Violation.One Violation Being Considered for Escalated Enforcement Action ML20203G5161999-02-0505 February 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 990407. Representative of Facility Must Submit Either Ltr Indicating No Candidates or Listing of Candidates for Exam ML20203A2421999-02-0505 February 1999 Forwards SE Accepting Proposal to Revise Methodology in TR DPC-NE-3002-A,to Permit Use of single-node Model,Instead of multi-node Model,To Represent SG Secondary Sys for post-trip Phase of Loss of Normal Feedwater Analysis for Plant,Unit 2 ML20202J4751999-01-29029 January 1999 Responds to Concern Raised on 981020 Re Appropriateness of Interaction of NRC Headquarters Operations Officer with on-shift Operations Staff During Event ML20202C2511999-01-27027 January 1999 Forwards Request for Addl Info Re Util 980331 Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, for Catawba Nuclear Station. Response Requested within 60 Days of Date of Ltr 1999-09-24
[Table view] |
Text
E May 10, 1988 Duke Power Company ATTN: Mr. H. B. Tucker, Vice President Nuclear Production Department
'422 South Church Street Charlotte, NC 28242 Gentlemen:
SUBJECT:
REACTOR OPERATOR AND SENIOR OPERATOR LICENSING EXAMINATIONS In a telephone conversation between Mr. W. Barron, Operations Training Superintendent, and Mr. R. Baldwin, NRC Region !!-Operator Licensing Section 2, arrangements were made for administration of the Reactor Operator examinations et the Duke Power Company, Catawba Nuclear Station.
The written examinations are scheduled for September 26, 1988. The simulator /
operating examinations are scheduled for the week of September 26, 1988, at the Catawba simulation facility. The plant oral examinations are scheduled for the week of SeptemMr ?6,1988.
In order for us to meet the 'above schedule, it will be necessary for the facility to furnish the approved reference material listed in Enclosure 1, "Reference Material Requirements for Reactor / Senior Reactor Operator Licensing Examinations," ,
by June 15, 1988. Any delay in receiving properly bound and-indexed reference '
material will result in a delay in administering the examinations. Our examinations ,
are scheduled far in advance with considerable planning to utilize our present :
limited examiner manpower and to meet the examination dates requested by the ;
various facilities. Therefore, missing the June 15, 1988 deadline, even by a !
few days, will likely result in a long delay, because it may not be possible to i reschedule examinations at other facilities. Mr. Barron has been advised of our reference material sets that are required, and the examiners' names and addresses l where each set is to be mailed. !
l The facility management is responsible for providing adequate space and accom-modations in order to properly conduct the written examinations. Enclosure 2, "Requirements for Administration of Written Examinations," describes our requirements for conducting these examinations. Mr. Barron has also been informed of these requirements.
In addition, to better document simulator examinations, the chief examiner will have the facility simulator operator record prespecified plant conditions (i.e., plant pressure, temperature, pressurizer level, etc.), for each simulator scenario. The candidate will be responsible for providing this information, along with any appeal of his simulator operating examination. Therefore, the facility training staff should retain the simulator examination scenario infonnation until all candidates taking the examination have either passed the operating examination or all appeals filed by the candidates who failed the operating examination have been completed.
8805230290 880510' i DR ADOCK0500g43 }
it ,
__ Y
(
Duke Power Company 2 May 10, 1988 Enclosure 2 also contains the Rules and Guidelines that will be in effect during the administration of the written examination. The facility management is responsible for ensuring that all candidates are aware of these Rules.
All reactor operator and senior reactor operator license application information should normally be submitted at least 60 days before the first examination dates so that we will be able to review the training and experience of the candidates, process the medical certifications, and prepare final examiner assignments after candidate eligibility has been determined. If the application information is not received at least 30 days before the examination dates, it is possible that a postponement will be necessary.
This request for information was approved by the Office of Management and Badget under Clearance Number 3150-0101 which expires on May 31, 1989. Comments on burden and duplication may be directed to the Office of Management and Budget, Reports Management, Room 3208, New Executive Office Building Washington, DC 20503.
The facility staff review of the written examination will be conducted in accordance with requirements specified in Enclosure 3, "Requirements for Facility Review of Written Examination." Mr. Barron has been informed of these requirements.
Thank you for your consideration in this matter. If you have any questions regarding the examination procedures and requirements, please contact Mr. Kenneth E. Brockman, Chief, Operator Licensing Section 2, at 404/331-5594.
Sincerely, j (ORIGINAL SIGNED BY G. A. BELISLE FOR)
Caudie A. Julian, Chief j Operations Branch q Division of Reactor Safety
Enclosures:
- 1. Reference Material Requirements
- 2. Requirements for Administration of I Written Exams I
- 3. Facility Review Requirements I
cc w/encis:
G. Barrett, Catawba Training Supervisor T. B. Owen, Catawba Plant Manager J
r Duke Power Company 3 May 10, 1988 bec w/encis:
K. Jabbour Projects Manager, NRR T. Peebles, Section Chief, DRP R. Baldwin, OL Examiner Senior Resident inspector (Actument Control Desk State of South Carolina R , Ri l. Ril R11 f
Rfhaw:cbw b h'^, . G!?> }v Rlaldwin KBroc kda?'.
n CAJulian 05/y/88 05/[/88 05/[/88 05/;c /88 I
- c. _ _ _
t i
i a
ENCLOSURE 1 L
REFERENCE MATERIAL REQUIREMENTS FOR REACTOR / SENIOR REACTOR OPERATOR LICENSING EXAMINATIONS
- 1. Existing learning objectives and lesson plans (including training manuals, plant orientation manual, system descriptions, reactor theory, thermo-dynamics,etc.)
Training materials should include all substantive written material used for preparing candidates for initial R0 and SRO licensing. The written material should be inclusive of learning objectives and the details presented during ,
lecture, rather than outlines. Training materials should be identified by :
plant and unit, bound, and indexed. Failure to provide complete, properly l bound and indexed plant reference material will result in canceling or ,
rescheduling of the examinations. Training materials which include the '
following should be provided: ,
t
- a. System descriptions including descriptions of all operationally i relevant flow paths, components, controls and instrumentation.
System training material should draw parallels to the actual procedures used for operating the applicable system. j
- b. Complete and operationally useful descriptions of all safety-system !
interactions and, where available, B0P system interactions under !
emergency and abnormal conditions, including' consequences of anticipated operator error, maintenance error, and equipment failure. l F
- c. Training material used to clarify and strengthen understanding of l emergency operating procedures. '
- d. Comprehensive theory material that includes fundamentals in the area of theory of reactor operation, thermodynamics, heat transfer and fluid flow, as well as specific application to actual in-plant components. For example, mechanical theory material on pumps should include pump theory as well as descriptions of how these principles actually apply to major plant pumps and the systems in which they are installed (i.e., Reactor Coolant pumps, all ECCS pumps, Recirculation pumps, Feedwater pumps and Emergency Feedwater pumps). Reactor theory material should include descriptions that draw explicit ties between the fundamentals and the actual operating limits followed in the plant (i.e., reactor theory material should contain explanations of how principles relate to the actual curves used by operators to ]
verify shutdown margin or calculate an ECP). l i
l 1
- _ ~ _ . . - _ _ . _ - __ _
1 l
1 Enclosure 1 2 ;
r i
l
- 2. Procedure Index (alphabetical by subject) '
- 3. All administrative procedures (as applicable to reactor operation or safety)
- 4. All integrated plant procedures (normal or general operating procedures) '
i 5. Emergency procedures (emergency instructions, abnormal or special l procedures)
- 6. Standing orders (important orders that are safety-related and may supersede
- the regular procedures)
- 7. Fuel-handling and core-loading procedures, (initial core-loading procedure, j whenappropriate)
- 8. Annunciatorprocedures(alarmprocedures,includingsetpoints) !
j 9. Radiation protection manual (radiation control manual or procedures) l J 10. Emergency plan implementing procedures [
- 11. Technical Specifications ,
- 12. System operating procedures l
) 13. Piping and instrumentation diagrams, electrical single-line diagrams, or l flow diagrams :
f 14. Technical Data Book, and/or plant curve information as used by operators and [
facility precautions, limitations, and set points (PLS) for the facility l 15. Questions and answers that the facility licensee has prepared (voluntary j by facility licensee)
- 16. The following on the plant reference simulation facility
- a. List of all readily available initialization points i
- b. List of all preset malfutetions with a clear identification number. l l The list should include cause and effect information. Specifically, for each malfunction, a concise description of the expected result, r
- or range of results, that will occur upon implementation should be
! provided. Additionally, an indication of which annunciators are to j be initially expected should be given.
j c. A description of simulator failure capabilities for valves, breakers, indicators and alams.
0 i
i__________________________________
r-Enclosure 1 3
- d. Where the capability exists, an explanation of the saility to vary the severity of a particular malfunction should be provided, i.e., ability to vary the size of a given LOCA or steam leak, or the ability to cause a slow failure of a component such as a feed pump, turbine generator or major valve (e.g., drifting shut of a main feedwater control valve)
- e. An identification of modeling conditions / problems that may impact the examination
- f. Identification of any known Performance Test Failures not yet completed
- g. Identification of significant differences between the simulator and the reference plant's control room
- h. Copies of facility generated scenarios that expose the candidates to situations of degraded pressure control (PWR), degraded heat removal capability (PWR and BWR), and containment challenges (BWR) may be provided (voluntary by licensee)
- 1. Simulator instructors manual (voluntary by licensee)
- j. Description of the scenarios used for the training class (voluntary by_
licensee)
- 17. All material different from that listed in items 1-16 that is specific to the Operator Requalification Training Program
- 18. Additional material required by the examiners to develop examinations that meet the requirements of these standards and the regulations.
The above reference material should be approved, final issues and should be so marked. If a plant has not finalized some of the material, the chief examiner shall verify with the facility that the most complete, up-to-date material is available and that agreement has been reached with the licensee for limiting changes before the administration of the examination. All procedures and reference material should be bound with appropriate indexes or tables of contents so that they can be used efficiently.
l
-- -. - . . . = . - . - .. .
4 I ENCLOSURE 2 REQUIREMENTS FOR ADMINISTRATION OF j
- WRITTEN EXAMINATIONS i
- 1. A single room shall be provided for completing the written examination. !
) The location of this room and supporting restroom facilities ~ shall be such as to prevent contact with all other facility and/or contractor personnel during-the duration of the written examination. If necessary, the facility should make arrangements for the use of a suitable room at a ;
local school, motel, or other building. Obtaining this room is the !
. responsibility of the licensee.
4
- 2. Minimum spacing is required to ensure examination integrity as determined l
, by the chief examiner. Minimum spacing should be one candidate per table, ;
j with a 3-ft. space between tables. No wall charts, models, and/or other i training materials shall be present in the examination room. ;
..1
- 3. Suitable arrangements shall be made by the facility if the candidates are to have lunch, coffee, or other refreshments. These arrangements shall comply with item 1 above. These arrangements shall be reviewed by the examiner and/or proctor.
l 4. The facility staff shall be provided a copy of the written examination and answer key after the last candidate has completed and handed in his ,
l written examination. The facility staff shall then have five working '
4 days to provide formal written comments with supporting documentation on the examination and answer key to the chief examiner or to the regional office section chief.
- 5. The facility licensee shall provide pads of 8-1/2 by 11 inch lined paper in unopened packages for each candidate's use in completing the examination.
'. The examiner shall distribute these pads to the candidates. All reference material needed to complete the examination shall be furnished by the examiner. Candidates can bring pens, pencils, calculators, or slide rules into the examination room, and no other equipment or reference material shall be allowed.
- 6. Only black ink or dark pencils should be used for writing answers to questions.
Enclosure 2 2 NRC RULES AND GUIDELINES FOR LICENSE EXAMINATIONS Ouring the administration of this examination the following rules apply:
- 1. Cheating on the examination means an automatic denial of your application and could result in more severe penalties.
- 2. Restroom trips are to be limited and only one candidate at a time may leave. You must avoid all contacts with anyone outside the examination room to avoid even the appearance or possibility of cheating.
- 3. Use black ink or dark pencil only to facilitate legible reproductions.
4 Print your name in the blank provided on the cover sheet of the examination.
- 5. Fill in the date on the cover sheet of the examination (if necessary).
- 6. Use only the paper provided for answers.
- 7. Print your name in the upper right-hand corner of the first page of each section of the answer sheet.
- 8. Consecutively number each answer sheet, write "End of Category " as appropriate, start each category on a new page, write on only one side of the paper, and write "Last Page" on the last answer sheet. "
- 9. Number each answer as to category and number, for example,1.4, 6.3.
- 10. Skip at least three lines between each answer.
- 11. Separate answer sheets from pad and place finished answer sheets face down on your desk or table.
- 12. Use abbreviations only if they are commonly used in facility literature.
- 13. The point value for each question is indicated in parentheses after the question and can be used as a guide for the depth of answer required.
- 14. Show all calculations, methods, or assumptions used to obtain an answer to mathematical problems, whether indicated in the question or not.
- 15. Partial credit may be given. Therefore, ANSWER ALL PARTS OF THE QUESTION AND DO NOT LEAVE ANY ANSWER BLANK.
Enclosure 2 3
- 16. If parts of the examination are not clear as to intent, ask questions of the examiner only.
- 17. You must sign the statement on the cover sheet that indicates that the work is your own and you have not received or been given assistance in completing the examination. This must be done after the examination has been completed.
- 18. When you ccmplete your examination, you shall:
- a. Assemble your examination as follows: j (1) Exam questions on top.
(2) Exam aids - figures, tables, etc. l l
(3) Answer pages including figures which are a part of the answer. I
- b. Turn in your copy of the examination and all pages used to answer the examination questions,
- c. Turn in all scrap paper and the balance of the paper that you did not use for answering the questions,
- d. Leave the examination area, as defined by the examiner. If after leaving, ycu are found in this area while the examination is still in progress, your license may be denied or revoked.
I s'
4 J
i
- -- y ,_ . __ ._ - - -._,.--m
ENCLOSURE 3 REQUIREMENTS FOR FACILITY REVIEW OF WRITTEN EXAMINATION
- 1. There shall be no review of the written examination by the facility staff before or during the administration of the examination. Folicwing the administration of the written examination, the facility staff shall be provided a marked-up copy of the examination and the answer key.
- 2. The facility will have five (5) working days from the day the written examination is given to provide formal comment submittal. The submittal will be made to the responsible regional office by the highest level of coporate management for plant operations, e.g., Vice President for Nuclear Operatione. A copy of the submittal will be forwarded to the chief examiner, as appropriate. Comments not submitted within five (5) working days will be considered for inclusion in the grading process on a case by case basis by the regional office section chief. Should the comment submittal deadline not be met, a long delay for finalization of the examination results may occur, a
- 3. The following format shoul ' be adhered to for submittal of specific 1 comments:
- a. Listing of NRC question, answer and reference
- b. Facility comment i
- c. Supporting documentation NOTES: 1. No change to the examination will be made without submittal of complete, current, and approved reference material.
- 2. Conments made without a concise facility recommendation will not be addressed.
b l
4 i
l 1 l I
1