NPDES Noncompliance Notification Re Unauthorized Leak Noted at Approx 2,300 Gallons on 960111.Caused by Leak in Cooling Basin.Leak Will Be Evaluated for Repair During Plant Outage Scheduled to Begin 960127
ML20096D790
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 01/15/1996
From: Shelton D
CENTERIOR ENERGY
To:
OHIO, STATE OF
References
PY-CEI-OEPA-024, PY-CEI-OEPA-24, NUDOCS 9601190274
Download: ML20096D790 (2)


Text

r- . . . - . . . . _ _ . . - ~ _ . - - . . _- _._,._,__,a.,.

cswrseson ENmRGY PERRY NUCLEAR POWER PLANT Mail Address: Donald C. SheltOn 10 CENTER ROAD SENIOR VICE PRESIDENT R , O 10 44081 PERRY, OHIO 44081 NUCLEAR (216) 259-3737 January 15, 1996 PY-CEI/0 EPA-0241L Ohio Environmental Protection Agency-Northeast District Office 2110 E. Aurora Rd.

Twinsburg, Ohio 44087 Re Perry Nuclear Power Plant OEPA Permit No. 3IB00016DD Gentlemen:

In accordance with Part III, Section 12.C of the Permit, this letter is serving as confirmation of a telephone report of an unauthorized discharge. The discharge is due to a leak in the plant cooling tower basin. The telephone report was made to the State Emergency Response Commission on 1/12/96.

1. The limitation which has been exceeded: Plant circulating water is discharging to the ground at a rate of approximately one gallon per minute through a leaking expansion joint on the cooling tower basin.

This is not the normal flow path'for the water from this system.

2. The extent of the exceedance: Approximately one gallon per minute of plant circulating water is leaking to the ground.
3. The cause of the exceedance: A leaking expansion joint on the cooling tower basin.
4. The period of exceedance: The leak was noted at approximately 2300 on 1/11/96 and is continuing.
5. If uncorrected, the anticipated time the exceedance is expected to continue: The leak cannot be repaired at this time due to safety concerns. The cooling tower basin vill be emptied during a plant outage scheduled to begin January 27, 1996. The leak will be evaluated for repair at that time.

9601190274 960115 PDR ADOCK 05000440 S PDR 190c5s' Operchrg Coc pones g96 jo Cleve ord f(ect c te ec"a ICWM FO W

J 4

PY-CEI/0 EPA-0241L January 15, 1996 Page 2 of 2 6.. Steps being taken to reduce, eliminate and/or prevent recurrence of the exceedance: The cooling tower basin vill be emptied and inspected during an upcoming plant outage scheduled to begin January 27, 1996.

If you have questions or need more information, please contact Louise Barton at (216) 280-5512.

Very truly yours, a b c. SAIfn LD C. SHEL N DCSilkb:vh cc NRC Project Manager NRC Resident Inspector NRC Document Control Desk NRC Region III

- . . - .--