ML20093F665

From kanterella
Jump to navigation Jump to search

Requests Extension Be Granted for Existing Unit 1 Hydrogen & Oxygen Analyzers.Replacement of Existing Analyzers Scheduled for Fall 1985 Refueling Outage.Qualification Deadline Extension to 850331 Requested for Unit 2 Analyzers
ML20093F665
Person / Time
Site: Hatch  
Issue date: 07/17/1984
From: Gucwa L
GEORGIA POWER CO.
To: Stolz J
Office of Nuclear Reactor Regulation
References
NED-84-383, TAC-55488, TAC-55489, NUDOCS 8407230062
Download: ML20093F665 (4)


Text

Georgia Power Company 333 P;edmont Avenue m

Atlanta, Georgia 30308 Telephone 404 526-6526 Maing Address.

Post Office Box 4545 Atlanta, Georgia 30302 h

Georgia Power L T. Gucwa the southem erectnc system Manager Nuclear Engineenng and Chief Nuclear Engineer NED-84-383 July 17, 1984 Director of Nuclear Res.ctor Regulation Attention: Mr. John F. Stolz, Chief Operating Reactors Branch No. 4 Division of Licensing U. S. Nuclear Regulatory Ccanission Washington, D. C.

20555 NRC DOCKETS 50-321, 50-366 OPEPATING LICEFSIE DPR-57, NPF-5 ENIN I. HMCH NUCLEAR PIANT UNITS 1, 2 EQUIINENT QUALIFICATION PROGRAM DEADLINE SXTENSION REQUEST FOR HYDROGEN / OXYGEN ANALYZERS Genticoen:

Recently, Georgia Power Ccepany (GPC) determined that the upcming refueling outage for Plant Hatch Unit 1 will last approximately ten weeks, beginning around October 1, 1984. The details of this decision are outlined in two previous GPC subnittals to the NRC dated May 31 and July 6, 1984 (NED-81-280 and NED-84-369, respectively).

GPC is in the process of installing new Cmsip-Delphi drywell rfydrogen (H ) and Oxygen (0 ) Analyzers on Hatch-2 as part of the effort to meet 2

2 the requirements of 10 CFR 50.49.

It is currently estimated that this work will have required 25 weeks of outage time (and 16,300 craft man-hours) when

't is empleted prior to unit startup.

Since installation of this new sluipnent rquires emplete removal of the existing analyzers, this work must be performed while the unit is shutdown and cmpleted during the outage in which it was begun.

GPC had originally intended to install new H2 and 02 analyzers on Unit 1 during the upcming outage, in order to meet the deadline requirenents of 10 CER 50.49(g).

However, since this installation would not be feasible during a ten week outage, the latest planning calls for replacanent of the existing Unit 1 analyzers during the refueling outage scheduled for the Fall of

1985, h refore, GPC requests that a

qualification deadline extension to Novenber 30, 1985 be granted, under the provisions of 10 CFR 50.49 (g),

for the existing Hatch-l H2 and O2 analyzers.

8407230062 840717 PDRADOCK05000g g

44' eM i 1

i Georgia Power A 4

i Director of Nuclear Reactor Regulation Attention: Mr. John F. Stolz, Chief Operating Reactors Branch No. 4 July 17, 1984 Page Two GK has been proceeding with the installation of the Hatch-2 analyzers, even though the qualification testing for this new equipent is far fra cmplete, with the expectation that the analyzers will be found suitable for use at Plant Hatch.

Casip, Inc.- recently informed GPC that the qualification testing program schedule had been delayed due to procurement problens.

%e current schedule for qualification testing and analysis for the H2 and 02 analyzers for both Hatch units (see analyzer models will be used on both units) is outlined in Enclosure 1.

GPC expects to be able to declare these analyzers as fully qualified for use at Plant Hatch by the end of 1984, using the results of the Capsip 30-day interim test report.

%e final 180-day IDCA test will be performed only as an additional j

confirmation of qualification..

i Hatch-2 is currently scheduled to restart in late July 1984.

Since the H2 and 02 analyzers will probably not be qualified until the end of 1984, GPC requests that a qualification deadline extension to March 31, 1985 be granted, under the provisions of 10 CFR 50.49(g), for the new Hatch-2 H2 and O2 analyzers.

%e additional time requested beyond the end of 1984 would allow for any unforeseen delays which could occur during the q'ualification testing process.

GPC has made a diligent effort to meet the requirenents of 10 CFR-50.49 within the time prescribed in paragraph (g) of that rule.

Plant Hatch has

' enbarked on an extensive progran of backfitting and equipent replacanent to e

ensure that all applicable equipnent meets the intent of 10 CFR 50.49.

In many ' cases GE has performed costly and time-consuning replacements of sluipnent rather than relying on marginally-acceptable engineering analyses to prove that necessary equipnent would perform its intended function during or after an accident.

GPC believes that the superiority of the new Cmpsip-Delphi H2 and O2 analyzers over the equipnent which tney replace in terms of expected instrunent ' reliability, as well as qualification assurance, outweighs the problems and delays experienced during installation and testing.

%e long-term gain in overall plant safety and performance expected fra these new devices justifies the requested short-term ' extensions of the qualification deadlines; also GPC has subnitted

" Justifications for Continued Operation" for the plant using' the instrunents which these new analyzers will replace.

I 1

_.,. S.

.~.. ~........ - -,., -

GeorgiaPower d Director of Nuclear Reactor Regulation Attention: Mr. John F. Stolz, Chief Operating Reactors Branch No. 4 July 17, 1984 Page 'Itiree GPC is prepared to meet with the NIC staff regarding this extension request on a mutually agreeable date as soon as possible, should you desire such a meeting.

Very truly yours, gr# C & c L. T. Gucwa CBSAnb xc:

J. T. Beckhan, Jr.

H. C. Nix, Jr.

J. P. O'Reilly (NRC-Region II)

Senior Resident Inspector l

j rwns

EPCIOSURE 1 NRC DOCKE7S 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5 EDWIN I. HATCH NUCLEAR PLANT UNI 7S 1, 2 EQUIENEMP CUALIFICATION PROGRAM DEADLINE EXTENSION REQUF.ST FOR HYDROGEN / OXYGEN ANALYZERS The following is the Casip, Inc.

schedule for empletion of qualification testing for the H2 and O2 analyzers procured for use in Plant Hatch Units 1 and 2 as of June 12, 1984:

Testing / Reporting Phase Predicted Completion Date Thermal Aging August 16, 1984 Radiation Aging August 20, 1984 Seismic Aging August 27, 1984 Initiation of IOCA Test Septenber 7, 1984 30 Day IOCA Test October 7, 1984 30 Day Interim Twst Report October 19, 1984 180 Day IOCA Test March 5, 1985 Final Test Report April 16, 1985 t

n

.